Public Act 094-0972
Public Act 0972 94TH GENERAL ASSEMBLY
|
Public Act 094-0972 |
HB5260 Enrolled |
LRB094 16231 RSP 51475 b |
|
| AN ACT concerning finance.
| Be it enacted by the People of the State of Illinois,
| represented in the General Assembly:
| Section 5. The State Prompt Payment Act is amended by | changing Sections 3-2 and 7 as follows:
| (30 ILCS 540/3-2) (from Ch. 127, par. 132.403-2)
| Sec. 3-2. Beginning July 1, 1993, in any instance where a | State official or
agency is late in payment of a vendor's bill | or invoice for goods or services
furnished to the State, as | defined in Section 1, properly approved in
accordance with | rules promulgated under Section 3-3, the State official or
| agency shall pay interest to the vendor in accordance with the | following:
| (1) Any bill approved for payment under this Section | must be paid
or the payment issued to the payee within 60 | days of receipt
of a proper bill or invoice.
If payment is | not issued to the payee within this 60 day
period, an
| interest penalty of 1.0% of any amount approved and unpaid | shall be added
for each month or fraction thereof after the | end of this 60 day period,
until final payment is made.
| (1.1) A State agency shall review in a timely manner | each bill or
invoice after its receipt. If the
State agency | determines that the bill or invoice contains a defect | making it
unable to process the payment request, the agency
| shall notify the vendor requesting payment as soon as | possible after
discovering the
defect pursuant to rules | promulgated under Section 3-3 ; provided, however, that the | notice for construction related bills or invoices must be | given not later than 30 days after the bill or invoice was | first submitted . The notice shall
identify the defect and | any additional information
necessary to correct the | defect. If one or more items on a construction related bill |
| or invoice are disapproved, but not the entire bill or | invoice, then the portion that is not disapproved shall be | paid.
| (2) Where a State official or agency is late in payment | of a
vendor's bill or invoice properly approved in | accordance with this Act, and
different late payment terms | are not reduced to writing as a contractual
agreement, the | State official or agency shall automatically pay interest
| penalties required by this Section amounting to $50 or more | to the appropriate
vendor. Each agency shall be responsible | for determining whether an interest
penalty
is
owed and
for | paying the interest to the vendor.
For interest of at least | $5 but less than $50, the vendor must
initiate a written | request for the interest penalty when such interest is due
| and payable. The Department of Central Management Services | and the State
Comptroller shall jointly promulgate rules | establishing the conditions under
which interest of less | than $5 may be claimed and paid. In the event an
individual | has paid a vendor for services in advance, the provisions | of this
Section shall apply until payment is made to that | individual.
| (Source: P.A. 92-384, eff. 7-1-02.)
| (30 ILCS 540/7)
(from Ch. 127, par. 132.407)
| Sec. 7. Payments to subcontractors and material suppliers. | (a) When a State official or agency responsible for | administering a
contract submits a voucher to the Comptroller | for
payment to a contractor, that State official or agency | shall promptly make
available electronically
the voucher | number, the date of the voucher, and
the amount of the voucher.
| The State official or agency responsible for administering the | contract shall
provide subcontractors and material suppliers, | known to the State official or
agency, with instructions on how | to access the electronic information. When a
contractor | receives any payment, the contractor shall
pay each | subcontractor and material supplier in proportion to the work
|
| completed by each subcontractor and material supplier their | application , plus interest received under this Act,
less any | retention. If the contractor receives less than the full | payment
due under the public construction contract, the | contractor shall be
obligated to disburse on a pro rata basis | those funds received, plus interest received under this Act, | with the
contractor, subcontractors and material suppliers | each receiving a prorated
portion based on the amount of | payment. When, however, the public owner
does not release the | full payment due under the contract because there are
specific | areas of work or materials the contractor is rejecting or | because
the contractor has otherwise determined such areas are | not suitable for
payment, then those specific subcontractors or | suppliers involved shall not
be paid for that portion of work | rejected or deemed not suitable for
payment and all other | subcontractors and suppliers shall be paid in full , plus | interest received under this Act .
| (b) If the contractor, without reasonable cause, fails to | make full payment of amounts due under subsection (a) to
his | subcontractors and material suppliers within 15 days after
| receipt of
payment under the public construction contract, the | contractor shall pay to
his subcontractors and material | suppliers, in addition to the payment due
them, interest in the | amount of
2% per month, calculated from the
expiration of the | 15-day period until fully paid. This subsection shall
also | apply to any payments made by subcontractors and material | suppliers to
their subcontractors and material suppliers and to | all payments made to
lower tier subcontractors and material | suppliers throughout the contracting
chain.
| (1) If a contractor, without reasonable cause, fails to | make payment in
full as
provided in subsection (a) within | 15 days after receipt of payment under the
public
| construction contract, any subcontractor or material | supplier to whom payments
are owed
may file a written | notice with the State official or agency setting forth the
| amount owed by
the contractor and the contractor's failure |
| to timely pay the amount owed.
| (2) The State official or agency, within 15 days after | receipt of a
subcontractor's
or material supplier's | written notice of the failure to receive payment from
the | contractor,
shall hold a hearing convened by an | administrative law judge to determine whether the | contractor withheld payment,
without
reasonable cause, | from the subcontractors and material suppliers and what
| amount, if any,
is due to the subcontractors and material | suppliers. The State official or
agency shall
provide | appropriate notice to the parties of the date, time, and | location of
the hearing. Each contractor, subcontractor, | and material supplier has the right to be represented by | counsel at the hearing and to cross-examine witnesses and | challenge documents.
| (3) If there is a finding by the administrative law | judge that the contractor failed
to make
payment in full, | without reasonable cause, as provided in subsection (a), | then
the administrative law judge shall, in writing, direct | the contractor to pay the amount
owed to the
subcontractors | and material suppliers plus interest within 15 days after | the
finding.
| (4) If a contractor fails to make full payment within | 15 days after the
administrative law judge's finding, then | the contractor shall be barred from
entering into a State
| public construction contract for a period of one year | beginning on the date of
the administrative law judge's | finding.
| (Source: P.A. 94-672, eff. 1-1-06.)
| Section 10. The Local Government Prompt Payment Act is | amended by changing Sections 3 and 9 as follows:
| (50 ILCS 505/3) (from Ch. 85, par. 5603)
| Sec. 3. The appropriate local governmental official or | agency
receiving goods or services must approve or disapprove a |
| bill from a vendor
or contractor for goods or services | furnished the local governmental agency
within 30 days after | the receipt of such bill or within 30 days after the
date on | which the goods or services were received, whichever is later.
| If one or more items on a construction related bill or invoice | are disapproved, but not the entire bill or invoice, then the | portion that is not disapproved shall be paid. When safety or | quality assurance testing of goods by the local governmental
| agency is necessary before the approval or disapproval of a | bill and such
testing cannot be completed within 30 days after | receipt of the goods,
approval or disapproval of the bill must | be made immediately upon
completion of the testing or within 60 | days after receipt of the goods,
whichever occurs first. | Written notice shall be mailed to the vendor or
contractor | immediately if a bill is disapproved.
| (Source: P.A. 87-773.)
| (50 ILCS 505/9) (from Ch. 85, par. 5609)
| Sec. 9. Payments to subcontractors and material suppliers; | failure to make timely payments; additional amount due.
When a | contractor receives any payment, the contractor shall
pay each | subcontractor and material supplier in proportion to the work
| completed by each subcontractor and material supplier their | application
less any retention. If the contractor receives less | than the full payment
due under the public construction | contract, the contractor shall be
obligated to disburse on a | pro rata basis those funds received, with the
contractor, | subcontractors and material suppliers each receiving a | prorated
portion based on the amount of payment. All interest | payments received pursuant to Section 4 also shall be disbursed | to subcontractors and material suppliers to whom payment has | been delayed, on a pro rata basis. When, however, the public | owner
does not release the full payment due under the contract | because there are
specific areas of work or materials the | contractor is rejecting or because
the contractor has otherwise | determined such areas are not suitable for
payment, then those |
| specific subcontractors or suppliers involved shall not
be paid | for that portion of the work rejected or deemed not suitable | for
payment and all other subcontractors and suppliers shall be | paid in full.
| If the contractor, without reasonable cause, fails to make | any payment to
his subcontractors and material suppliers within | 15 days after receipt of
payment under the public construction | contract, the contractor shall pay to
his subcontractors and | material suppliers, in addition to the payment due
them, | interest in the amount of 2% per month, calculated from the
| expiration of the 15-day period until fully paid. This Section
| subsection shall
also apply to any payments made by | subcontractors and material suppliers to
their subcontractors | and material suppliers and to all payments made to
lower tier | subcontractors and material suppliers throughout the | contracting
chain.
| (Source: P.A. 87-773.)
| Section 99. Effective date. This Act takes effect July 1, | 2007.
|
Effective Date: 7/1/2007
|
|
|