Public Act 093-1020
Public Act 1020 93RD GENERAL ASSEMBLY
|
Public Act 093-1020 |
SB3013 Enrolled |
LRB093 15087 MKM 40676 b |
|
| AN ACT concerning water safety.
| Be it enacted by the People of the State of Illinois,
| represented in the General Assembly:
| Section 5. The Counties Code is amended by adding Section | 5-15025 as follows: | (55 ILCS 5/5-15025 new)
| Sec. 5-15025. Boil order; notification of certified local | public health department required. If a county, or any | department or agency of the county, issues a boil order, then | the county must notify any certified local public health | department that serves an area subject to the boil order as | soon as is practical, but no later than 2 hours after issuing | the order. In addition to the initial notice, the county must | provide, to any affected certified local public health | department, a written notification within 24 hours after | issuing the boil order. The written notification must include | the estimated duration of the order or warning and the | geographic area covered by the order or warning. | Section 7. The Township Code is amended by adding Section | 205-12 as follows: | (60 ILCS 1/205-12 new)
| Sec. 205-12. Boil order; notification of certified local | public health department required. If a township, or any | department or agency of the township, issues a boil order, then | the township must notify any certified local public health | department that serves an area subject to the boil order as | soon as is practical, but no later than 2 hours after issuing | the order. In addition to the initial notice, the township must | provide, to any affected certified local public health | department, a written notification within 24 hours after |
| issuing the boil order. The written notification must include | the estimated duration of the order or warning and the | geographic area covered by the order or warning. | Section 10. The Illinois Municipal Code is amended by | adding Section 11-20-10.5 as follows: | (65 ILCS 5/11-20-10.5 new)
| Sec. 11-20-10.5. Boil order; notification of certified | local public health department required. If a municipality, or | any department or agency of the municipality, issues a boil | order, then the municipality must notify any certified local | public health department that serves an area subject to the | boil order as soon as is practical, but no later than 2 hours | after issuing the order. In addition to the initial notice, the | municipality must provide, to any affected certified local | public health department, a written notification within 24 | hours after issuing the boil order. The written notification | must include the estimated duration of the order or warning and | the geographic area covered by the order or warning. | Section 15. The Public Water District Act is amended by | adding Section 7.3 as follows: | (70 ILCS 3705/7.3 new) | Sec. 7.3. Boil order; notification of certified local | public health department required. If a public water district | issues a boil order, then the district must notify any | certified local public health department that serves an area | subject to the boil order as soon as is practical, but no later | than 2 hours after issuing the order. In addition to the | initial notice, the district must provide, to any affected | certified local public health department, a written | notification within 24 hours after issuing the boil order. The | written notification must include the estimated duration of the | order or warning and the geographic area covered by the order |
| or warning. | Section 20. The Water Service District Act is amended by | adding Section 5.2 as follows: | (70 ILCS 3710/5.2 new) | Sec. 5.2. Boil order; notification of certified local | health department required. If a water service district issues | a boil order, then the district must notify any certified local | public health department that serves an area subject to the | boil order as soon as is practical, but no later than 2 hours | after issuing the order. In addition to the initial notice, the | district must provide, to any affected certified local public | health department, a written notification within 24 hours after | issuing the boil order. The written notification must include | the estimated duration of the order or warning and the | geographic area covered by the order or warning. | Section 25. The Water Authorities Act is amended by adding | Section 6c as follows: | (70 ILCS 3715/6c new) | Sec. 6c. Boil order; notification of certified local health | department required. If a water authority issues a boil order, | then the authority must notify any certified local public | health department that serves an area subject to the boil order | as soon as is practical, but no later than 2 hours after | issuing the order. In addition to the initial notice, the | authority must provide, to any affected certified local public | health department, a written notification within 24 hours after | issuing the boil order. The written notification must include | the estimated duration of the order or warning and the | geographic area covered by the order or warning. | Section 30. The Water Commission Act of 1985 is amended by | adding Section 2.5 as follows: |
| (70 ILCS 3720/2.5 new) | Sec. 2.5. Boil order; notification of certified local | public health department required. If a water commission issues | a boil order, then the commission must notify any certified | local public health department that serves an area subject to | the boil order as soon as is practical, but no later than 2 | hours after issuing the order. In addition to the initial | notice, the commission must provide, to any affected certified | local public health department, a written notification within | 24 hours after issuing the boil order. The written notification | must include the estimated duration of the order or warning and | the geographic area covered by the order or warning.
| Section 99. Effective date. This Act takes effect upon | becoming law.
|
Effective Date: 8/24/2004
|