Illinois General Assembly

  Bills & Resolutions  
  Compiled Statutes  
  Public Acts  
  Legislative Reports  
  IL Constitution  
  Legislative Guide  
  Legislative Glossary  

 Search By Number
 (example: HB0001)
Search Tips

Search By Keyword

Illinois Compiled Statutes

 ILCS Listing   Public Acts  Search   Guide   Disclaimer

Information maintained by the Legislative Reference Bureau
Updating the database of the Illinois Compiled Statutes (ILCS) is an ongoing process. Recent laws may not yet be included in the ILCS database, but they are found on this site as Public Acts soon after they become law. For information concerning the relationship between statutes and Public Acts, refer to the Guide.

Because the statute database is maintained primarily for legislative drafting purposes, statutory changes are sometimes included in the statute database before they take effect. If the source note at the end of a Section of the statutes includes a Public Act that has not yet taken effect, the version of the law that is currently in effect may have already been removed from the database and you should refer to that Public Act to see the changes made to the current law.

220 ILCS 50/5.2

    (220 ILCS 50/5.2)
    (This Section may contain text from a Public Act with a delayed effective date)
    Sec. 5.2. Planning design request.
    (a) An underground utility facility owner or operator shall have the following responsibilities:
        (1) respond to a valid planning design request within
    
10 days after receiving the request or by such other date as shall be mutually agreed upon between the underground utility facility owner or operator and the designer or planner. The underground utility facility owner or operator shall provide information regarding the location, size, if greater than 1.5 inches in diameter, which shall be generically listed as communication, electric, gas, water, sewer, streetlight, or traffic control and if direct buried or in conduit or a duct package, of facilities based on the best information available to the underground utility facility owner or operator within the scope of the proposed project;
        (2) respond to a planning design request in one of
    
the following methods:
            (A) provide the most current digital, KMZ file or
        
shapefile, or paper drawings or prints, that are drawn to scale, when available, and include visible utility structures, including measurements from back of curb, sidewalk, edge of pavement, centerline of ditch, property lines, and other similar items;
            (B) request the proposed plans or drawings from
        
the designer or planner and illustrate the location of the underground utility facility owner's or operator's facilities, drawn to scale, and, if available, provide the type and size, as described in paragraph (1), of the facilities, including visible structures on the plans;
            (C) locate and mark the underground utility
        
facility owner's or operator's facilities within the scope of the proposed project, as agreed to with the planner or designer;
            (D) if the responding underground utility
        
facility owner or operator is unable to comply with paragraph (A) or (B), then the underground utility facility owner or operator shall mark the facilities within the scope of the proposed project, as agreed to with the planner or designer; or
            (E) if marking of infrastructure is the preferred
        
or required response of the underground utility facility owner or operator, the underground utility facility owner or operator need only mark main line facilities or any service lines that would otherwise be considered main line due to size or type, as described in paragraph (1); and
        (3) may charge a nominal fee to locate and mark the
    
proposed project, as described in subparagraph (C) or (D) of paragraph (2).
    (b) The planner or designer shall have the following responsibilities:
        (1) follow the guidelines set forth in CI/ASCE 38-02
    
Standard Guidelines for the Collection and Depiction of Existing Subsurface Utility Data, as from time to time amended, when preparing plans or drawings;
        (2) illustrate on all appropriate documents the
    
position, size, and type, as described in paragraph (1) of subsection (a), of all known facilities obtained in the planning design request process and include the valid planning design request number provided by JULIE on any plans or drawings; and
        (3) make all reasonable efforts to prepare the plans
    
or drawings to minimize interference with known existing and proposed facilities in the proposed project area.
    (c) A planning design request shall include the following information:
        (1) name, address, telephone number, office and cell
    
phone, and, if available, email address of the designated contact requesting the information;
        (2) name, address, telephone number, office and cell
    
phone, and, if available, email address of the project owner;
        (3) the approximate date when the facility
    
information is required; and
        (4) the specific area requiring facility information
    
by one or more of the following means:
            (A) the county and place or places involved in
        
the proposed project;
            (B) street names involved in the proposed project
        
or the north, south, east, and west boundaries of the proposed project or the section number or numbers involved in the proposed project;
            (C) latitude and longitude coordinates of the
        
outside edges of the proposed project;
            (D) digital data such as, but not limited to,
        
shapefiles when technology and software allow; and
            (E) the type of work projected to take place
        
within the proposed project.
    Any known site-specific facility information shall be made available to the project owner to be delivered to qualified bidders of the proposed project.
(Source: P.A. 103-614, eff. 1-1-25.)