Illinois General Assembly - Full Text of HB4384
Illinois General Assembly

Previous General Assemblies

Full Text of HB4384  102nd General Assembly

HB4384ham001 102ND GENERAL ASSEMBLY

Rep. Eva Dina Delgado

Filed: 2/23/2022

 

 


 

 


 
10200HB4384ham001LRB102 22727 RJF 36733 a

1
AMENDMENT TO HOUSE BILL 4384

2    AMENDMENT NO. ______. Amend House Bill 4384 by replacing
3everything after the enacting clause with the following:
 
4    "Section 5. The Illinois Procurement Code is amended by
5adding Section 30-60 as follows:
 
6    (30 ILCS 500/30-60 new)
7    Sec. 30-60. Request for change orders.
8    (a) Within 45 days after the date that a written request
9for a change order is submitted by a contractor to a State
10agency or within 45 days after the date that authorization for
11extra work is issued by a State agency to a contractor, the
12State agency shall: (i) issue the change order with an
13agreement on price; (ii) agree on price for the authorization
14for extra work; (iii) counter on price in writing; (iv) give
15written notice to the contractor of the reasons why the change
16order is unreasonable; (v) accept a partial agreement on price

 

 

10200HB4384ham001- 2 -LRB102 22727 RJF 36733 a

1on some of the terms of the change order or extra work; or (vi)
2explain in writing that an additional 30 days are necessary to
3make a determination.
4    (b) If an additional 30 days is requested under subsection
5(a), then, after the 30 additional days have elapsed, the
6State agency shall: (i) issue the change order with an
7agreement on price; (ii) agree on price for the authorization
8for extra work; (iii) counter on price in writing; (iv) give
9written notice to the contractor of the reasons why the change
10order is unreasonable; (v) accept a partial agreement on price
11on some of the terms of the change order or extra work; or (vi)
12explain in writing that an additional 15 days are necessary to
13make a determination. If an additional 15 days is requested
14under this subsection (b), then, after every 15 additional
15days that elapse, as necessary, the State agency shall perform
16one of the actions specified in items (i) through (vi) of this
17subsection (b).
18    (c) The State agency shall report quarterly on its website
19the total number of times the State agency requested
20additional time to make a determination under this Section and
21the total number of times the State agency requested
22additional time for such determination for each contract.
 
23    Section 99. Effective date. This Act takes effect upon