Full Text of HB4545 95th General Assembly
HB4545ham001 95TH GENERAL ASSEMBLY
|
Local Government Committee
Filed: 3/5/2008
|
|
09500HB4545ham001 |
|
LRB095 17331 HLH 46946 a |
|
| 1 |
| AMENDMENT TO HOUSE BILL 4545
| 2 |
| AMENDMENT NO. ______. Amend House Bill 4545 by replacing | 3 |
| everything after the enacting clause with the following:
| 4 |
| "Section 5. The Counties Code is amended by adding Section | 5 |
| 5-1062.3 as follows: | 6 |
| (55 ILCS 5/5-1062.3 new) | 7 |
| Sec. 5-1062.3. Stormwater management; Peoria. | 8 |
| (a) The purpose of this Section is to allow management and | 9 |
| mitigation of the effects of urbanization on stormwater | 10 |
| drainage in Peoria County and references to "county" in this | 11 |
| Section apply only to that county. The purpose of this Section | 12 |
| shall be achieved by: | 13 |
| (1) Consolidating the existing stormwater management
| 14 |
| framework into a united, countywide structure. | 15 |
| (2) Setting minimum standards for floodplain and
| 16 |
| stormwater management. |
|
|
|
09500HB4545ham001 |
- 2 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| (3) Preparing a countywide plan for the management
of | 2 |
| stormwater runoff, including the management of natural and | 3 |
| man-made drainageways. The countywide plan may incorporate | 4 |
| watershed plans. | 5 |
| (b) A stormwater management planning committee may be | 6 |
| established by county board resolution, with its membership | 7 |
| consisting of equal numbers of county board and municipal | 8 |
| representatives from each county board district, and such other | 9 |
| members as may be determined by the county and municipal | 10 |
| members. The county board may by ordinance divide the county | 11 |
| into not less than 6 areas of approximately equal population, | 12 |
| to be used instead of county board districts for the purpose of | 13 |
| determining representation on the stormwater management | 14 |
| planning committee. | 15 |
| The county board members shall be appointed by the chairman | 16 |
| of the county board. Municipal members from each county board | 17 |
| district or other represented area shall be appointed by a | 18 |
| majority vote of the mayors of those municipalities that have | 19 |
| the greatest percentage of their respective populations | 20 |
| residing in that county board district or other represented | 21 |
| area. All municipal and county board representatives shall be | 22 |
| entitled to a vote; the other members shall be nonvoting | 23 |
| members, unless authorized to vote by the unanimous consent of | 24 |
| the municipal and county board representatives. A municipality | 25 |
| that is located in more than one county may choose, at the time | 26 |
| of formation of the stormwater management planning committee |
|
|
|
09500HB4545ham001 |
- 3 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| and based on watershed boundaries, to participate in the | 2 |
| stormwater management planning program of either or both of the | 3 |
| counties. Subcommittees of the stormwater management planning | 4 |
| committee may be established to serve a portion of the county | 5 |
| or a particular drainage basin that has similar stormwater | 6 |
| management needs. The stormwater management planning committee | 7 |
| shall adopt bylaws, by a majority vote of the county and | 8 |
| municipal members, to govern the functions of the committee and | 9 |
| its subcommittees. Officers of the committee shall include a | 10 |
| chair and vice chair, one of whom shall be a county | 11 |
| representative and one a municipal representative. | 12 |
| The principal duties of the committee shall be to develop a | 13 |
| stormwater management plan for presentation to and approval by | 14 |
| the county board, and to direct the plan's implementation and | 15 |
| revision. The committee may retain engineering, legal, and | 16 |
| financial advisors and inspection personnel. The committee | 17 |
| shall meet at least quarterly and shall hold at least one | 18 |
| public meeting during the preparation of the plan and prior to | 19 |
| its submittal to the county board. The committee may make | 20 |
| grants to units of local government that have adopted an | 21 |
| ordinance requiring actions consistent with the stormwater | 22 |
| management plan and to landowners for the purposes of | 23 |
| stormwater management, including special projects; use of the | 24 |
| grant money must be consistent with the stormwater management | 25 |
| plan. | 26 |
| The committee shall not have or exercise any power of |
|
|
|
09500HB4545ham001 |
- 4 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| eminent domain. | 2 |
| (c) In the preparation of a stormwater management plan, a | 3 |
| county stormwater management planning committee shall | 4 |
| coordinate the planning process with each adjoining county to | 5 |
| ensure that recommended stormwater projects will have no | 6 |
| significant impact on the levels or flows of stormwaters in | 7 |
| inter-county watersheds or on the capacity of existing and | 8 |
| planned stormwater retention facilities. An adopted stormwater | 9 |
| management plan shall identify steps taken by the county to | 10 |
| coordinate the development of plan recommendations with | 11 |
| adjoining counties. | 12 |
| (d) The stormwater management committee may not enforce any | 13 |
| rules or regulations that would interfere with (i) any power | 14 |
| granted by the Illinois Drainage Code (70 ILCS 605/) to | 15 |
| operate, construct, maintain, or improve drainage systems or | 16 |
| (ii) the ability to operate, maintain, or improve the drainage | 17 |
| systems used on or by land or a facility used for production | 18 |
| agriculture purposes, as defined in the Use Tax Act (35 ILCS | 19 |
| 105/), except newly constructed buildings and newly installed | 20 |
| impervious paved surfaces. Disputes regarding an exception | 21 |
| shall be determined by a mutually agreed upon arbitrator paid | 22 |
| by the disputing party or parties. | 23 |
| (e) Before the stormwater management planning committee | 24 |
| recommends to the county board a stormwater management plan for | 25 |
| the county or a portion thereof, it shall submit the plan to | 26 |
| the Office of Water Resources of the Department of Natural |
|
|
|
09500HB4545ham001 |
- 5 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| Resources for review and recommendations. The Office, in | 2 |
| reviewing the plan, shall consider such factors as impacts on | 3 |
| the levels or flows in rivers and streams and the cumulative | 4 |
| effects of stormwater discharges on flood levels. The Office of | 5 |
| Water Resources shall determine whether the plan or ordinances | 6 |
| enacted to implement the plan complies with the requirements of | 7 |
| subsection (f). Within a period not to exceed 60 days, the | 8 |
| review comments and recommendations shall be submitted to the | 9 |
| stormwater management planning committee for consideration. | 10 |
| Any amendments to the plan shall be submitted to the Office for | 11 |
| review. | 12 |
| (f) Prior to recommending the plan to the county board, the | 13 |
| stormwater management planning committee shall hold at least | 14 |
| one public hearing thereon and shall afford interested persons | 15 |
| an opportunity to be heard. The hearing shall be held in the | 16 |
| county seat. Notice of the hearing shall be published at least | 17 |
| once no less than 15 days in advance of the hearing in a | 18 |
| newspaper of general circulation published in the county. The | 19 |
| notice shall state the time and place of the hearing and the | 20 |
| place where copies of the proposed plan will be accessible for | 21 |
| examination by interested parties. If an affected municipality | 22 |
| having a stormwater management plan adopted by ordinance wishes | 23 |
| to protest the proposed county plan provisions, it shall appear | 24 |
| at the hearing and submit in writing specific proposals to the | 25 |
| stormwater management planning committee. After consideration | 26 |
| of the matters raised at the hearing, the committee may amend |
|
|
|
09500HB4545ham001 |
- 6 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| or approve the plan and recommend it to the county board for | 2 |
| adoption. | 3 |
| The county board may enact the proposed plan by ordinance. | 4 |
| If the proposals for modification of the plan made by an | 5 |
| affected municipality having a stormwater management plan are | 6 |
| not included in the proposed county plan, and the municipality | 7 |
| affected by the plan opposes adoption of the county plan by | 8 |
| resolution of its corporate authorities, approval of the county | 9 |
| plan shall require an affirmative vote of at least two-thirds | 10 |
| of the county board members present and voting. If the county | 11 |
| board wishes to amend the county plan, it shall submit in | 12 |
| writing specific proposals to the stormwater management | 13 |
| planning committee. If the proposals are not approved by the | 14 |
| committee, or are opposed by resolution of the corporate | 15 |
| authorities of an affected municipality having a municipal | 16 |
| stormwater management plan, amendment of the plan shall require | 17 |
| an affirmative vote of at least two-thirds of the county board | 18 |
| members present and voting. | 19 |
| (g) The county board may prescribe by ordinance reasonable | 20 |
| rules and regulations for floodplain management and for | 21 |
| governing the location, width, course, and release rate of all | 22 |
| stormwater runoff channels, streams, and basins in the county, | 23 |
| in accordance with the adopted stormwater management plan. | 24 |
| Land, facilities, and drainage district facilities used for | 25 |
| production agriculture as defined in subsection (d) shall not | 26 |
| be subjected to regulation by the county board or stormwater |
|
|
|
09500HB4545ham001 |
- 7 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| management committee under this Section for floodplain | 2 |
| management and for governing location, width, course, | 3 |
| maintenance, and release rate of stormwater runoff channels, | 4 |
| streams and basins, or water discharged from a drainage | 5 |
| district. These rules and regulations shall, at a minimum, meet | 6 |
| the standards for floodplain management established by the | 7 |
| Office of Water Resources and the requirements of the Federal | 8 |
| Emergency Management Agency for participation in the National | 9 |
| Flood Insurance Program. The Commission may not impose more | 10 |
| stringent regulations regarding water quality on entities | 11 |
| discharging in accordance with a valid National Pollution | 12 |
| Discharge Elimination System permit issued under the | 13 |
| Environmental Protection Act. | 14 |
| (h) In accordance with, and if recommended in, the adopted | 15 |
| stormwater management plan, the county board may adopt a | 16 |
| schedule of fees as may be necessary to mitigate the effects of | 17 |
| stormwater runoff based on actual costs. The fees shall not | 18 |
| exceed the cost of satisfying the onsite stormwater retention | 19 |
| or detention requirements of the adopted stormwater management | 20 |
| plan. The fees shall be used to finance activities undertaken | 21 |
| by the county or its included municipalities to mitigate the | 22 |
| effects of urban stormwater runoff by providing regional | 23 |
| stormwater retention or detention facilities, as identified in | 24 |
| the county plan. The county board shall provide for a credit or | 25 |
| reduction in fees for any onsite retention, detention, drainage | 26 |
| district assessments, or other similar stormwater facility |
|
|
|
09500HB4545ham001 |
- 8 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| consistent with the stormwater management ordinance. | 2 |
| Developers are exempt from any fees under this Section if the | 3 |
| new development satisfies onsite retention or detention | 4 |
| pursuant to any other local ordinance addressing erosion, | 5 |
| sediment, or stormwater control and Illinois Environmental | 6 |
| Protection Agency regulations that place the development into | 7 |
| compliance with the National Pollutant Discharge Elimination | 8 |
| System (NPDES) permit program at the time of the dedication of | 9 |
| public infrastructure. All these fees collected by the county | 10 |
| shall be held in a separate fund, and shall be expended only in | 11 |
| the watershed within which they were collected. | 12 |
| (i) For the purpose of implementing this Section and for | 13 |
| the development, design, planning, construction, operation, | 14 |
| and maintenance of stormwater facilities provided for in the | 15 |
| stormwater management plan, a county board that has established | 16 |
| a stormwater management planning committee pursuant to this | 17 |
| Section may cause an annual tax of not to exceed 0.20% of the | 18 |
| value, as equalized or assessed by the Department of Revenue, | 19 |
| of all taxable property in the county to be levied upon all the | 20 |
| taxable property in the county or occupation and use taxes of | 21 |
| 1/10 of one cent. The property tax shall be in addition to all | 22 |
| other taxes authorized by law to be levied and collected in the | 23 |
| county and shall be in addition to the maximum tax rate | 24 |
| authorized by law for general county purposes. The 0.20% | 25 |
| limitation provided in this Section may be increased or | 26 |
| decreased by referendum in accordance with the provisions of |
|
|
|
09500HB4545ham001 |
- 9 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| Sections 18-120, 18-125, and 18-130 of the Property Tax Code | 2 |
| (35 ILCS 200/). | 3 |
| Any revenues generated as a result of ownership or | 4 |
| operation of facilities or land acquired with the tax funds | 5 |
| collected pursuant to this subsection shall be held in a | 6 |
| separate fund and be used either to abate such property tax or | 7 |
| for implementing this Section. | 8 |
| However, the tax authorized by this subsection shall not be | 9 |
| levied until the question of its adoption, either for a | 10 |
| specified period or indefinitely, has been submitted to the | 11 |
| electors thereof and approved by a majority of those voting on | 12 |
| the question. This question may be submitted at any election | 13 |
| held in the county after the adoption of a resolution by the | 14 |
| county board providing for the submission of the question to | 15 |
| the electors of the county. The county board shall certify the | 16 |
| resolution and proposition to the proper election officials, | 17 |
| who shall submit the proposition at an election in accordance | 18 |
| with the general election law. If a majority of the votes cast | 19 |
| on the question is in favor of the levy of the tax, it may | 20 |
| thereafter be levied in the county for the specified period or | 21 |
| indefinitely, as provided in the proposition. The question | 22 |
| shall be put in substantially the following form: | 23 |
| Shall an annual tax be levied
for stormwater management | 24 |
| purposes (for a period of not more than ..... years) at a | 25 |
| rate not exceeding
.....% of the equalized assessed
value | 26 |
| of the taxable property of Peoria County? |
|
|
|
09500HB4545ham001 |
- 10 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| Or this question may be submitted at any election held in the | 2 |
| county after the adoption of a resolution by the county board | 3 |
| providing for the submission of the question to the electors of | 4 |
| the county to authorize use and occupation taxes of 1/10 of one | 5 |
| cent: | 6 |
| Shall use and occupation taxes be raised for stormwater | 7 |
| management purposes (for a period of not more than ..... | 8 |
| years) at a rate of 1/10 of one cent for taxable goods in | 9 |
| Peoria County? | 10 |
| Votes shall be recorded as Yes or No. | 11 |
| (j) If the county adopts a property tax in accordance with | 12 |
| the provisions in this Section, the stormwater management | 13 |
| committee shall offer property tax abatements or incentive | 14 |
| payments to property owners who construct, maintain, and use | 15 |
| approved stormwater management devices. If the county adopts | 16 |
| use and occupation taxes in accordance with the provisions of | 17 |
| this Section, the stormwater management committee may offer tax | 18 |
| rebates or incentive payments to property owners who construct, | 19 |
| maintain, and use approved stormwater management devices.
The | 20 |
| stormwater management committee is authorized to offer credits | 21 |
| to the property tax, if applicable, based on authorized | 22 |
| practices consistent with the stormwater management plan and | 23 |
| approved by the committee. Expenses of staff of a stormwater | 24 |
| management committee that are expended on regulatory project | 25 |
| review may be no more than 20% of the annual budget of the | 26 |
| committee, including funds raised under subsections (h) and |
|
|
|
09500HB4545ham001 |
- 11 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| (i). | 2 |
| (k) If the county has adopted a county stormwater | 3 |
| management plan under this Section it may, after 10 days | 4 |
| written notice receiving consent of the owner or occupant, | 5 |
| enter upon any lands or waters within the county for the | 6 |
| purpose of inspecting stormwater facilities or causing the | 7 |
| removal of any obstruction to an affected watercourse. If | 8 |
| consent is denied or cannot be reasonably obtained, the county | 9 |
| ordinance shall provide a process or procedure for an | 10 |
| administrative warrant to be obtained. The county shall be | 11 |
| responsible for any damages occasioned thereby. | 12 |
| (l) Upon petition of the municipality, and based on a | 13 |
| finding of the stormwater management planning committee, the | 14 |
| county shall not enforce rules and regulations adopted by the | 15 |
| county in any municipality located wholly or partly within the | 16 |
| county that has a municipal stormwater management ordinance | 17 |
| that is consistent with and at least as stringent as the county | 18 |
| plan and ordinance, and is being enforced by the municipal | 19 |
| authorities. On issues that the county ordinance is more | 20 |
| stringent as deemed by the committee, the county shall only | 21 |
| enforce rules and regulations adopted by the county on the more | 22 |
| stringent issues and accept municipal permits. The county shall | 23 |
| have no more than 60 days to review permits or the permits | 24 |
| shall be deemed approved. | 25 |
| (m) The county may issue general obligation bonds for | 26 |
| implementing any stormwater plan adopted under this Section in |
|
|
|
09500HB4545ham001 |
- 12 - |
LRB095 17331 HLH 46946 a |
|
| 1 |
| the manner prescribed in Section 5-1012; except that the | 2 |
| referendum requirement of Section 5-1012 does not apply to | 3 |
| bonds issued pursuant to this Section on which the principal | 4 |
| and interest are to be paid entirely out of funds generated by | 5 |
| the taxes and fees authorized by this Section. | 6 |
| (n) The powers authorized by this Section may be | 7 |
| implemented by the county board for a portion of the county | 8 |
| subject to similar stormwater management needs. | 9 |
| (o) The powers and taxes authorized by this Section are in | 10 |
| addition to the powers and taxes authorized by Division 5-15; | 11 |
| in exercising its powers under this Section, a county shall not | 12 |
| be subject to the restrictions and requirements of that | 13 |
| Division.
| 14 |
| Section 99. Effective date. This Act takes effect upon | 15 |
| becoming law.".
|
|