94TH GENERAL ASSEMBLY

 

State of Illinois

 

2005 and 2006

HB2688

 

Introduced 2/18/2005, by Rep. Michael J. Madigan - Gary Hannig - Lovana Jones

 

SYNOPSIS AS INTRODUCED:

 

Makes appropriations for capital expenditures for the following agencies:  Department of Agriculture, Department of Commerce and Economic Opportunity, Department of Natural Resources, Department of Military Affairs, Department of State Police, Department of Transportation, Capital Development Board, Illinois Commerce Commission, Environmental Protection Agency, Historic Preservation Agency, Illinois Finance Authority, Medical District Commission, Illinois Emergency Management Agency, Eastern Illinois University, Northeastern Illinois University, Northern Illinois University, Southern Illinois University, University of Illinois, Illinois Community College Board, State Board of Education, and State Board of Elections.

 

 

OMB094 00078 SAT 30078 b

 

 

 

 

 

$OCE-DPT AGR

 

 

 


    AN ACT making appropriations.

 

        Be it enacted by the People of the State of Illinois, represented in the General Assembly:

 

 

ARTICLE 1

DEPARTMENT OF AGRICULTURE

 

    Section 5.  The following named amounts, or so much thereof as may be necessary are appropriated to the Department of Agriculture for repairs, maintenance, and capital improvements including construction, reconstruction, improvement, repair and installation of capital facilities, cost of planning, supplies, materials, equipment, services and all other expenses required to complete the work:

Payable from Agricultural Premium Fund:

  For various projects at the State

   Fairgrounds................................... $600,000

  For various projects at the DuQuoin State

   Fairgrounds.................................... 225,000

    Total                                          $825,000

 

    Section 10.  The amount of $2,612,500, or so much thereof as may be necessary, is appropriated from the Capital Development Fund to the Department of Agriculture for deposit into the Conservation 2000 Projects Fund.

 

    Section 15.  The amount of $2,612,500, or so much thereof as may be necessary, is appropriated from the Conservation 2000 Projects Fund to the Department of Agriculture for the following project at the approximate cost set forth below:

  Conservation Practices Cost-Share Program..... $2,612,500

 

Total, Article 1                                 $6,050,000

 

ARTICLE 2

DEPARTMENT OF COMMERCE AND ECONOMIC OPPORTUNITY

 

    Section 5.  The sum of $4,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to the Illinois Institute of Technology for the Biomedical Research Center.

 

    Section 10.  The sum of $1,500,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to Argonne National Laboratory for the Advanced Protein Crystallization Facility.

 

    Section 15.  The sum of $3,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to Argonne National Laboratory for the Rare Isotope Accelerator Science Center.

 

    Section 20.  The sum of $6,700,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to Argonne National Laboratory for the Ricketts Regional Biocontainment Laboratory.

 

    Section 25.  The sum of $1,600,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for the Applied Manufacturing Research and Technology Center in Rockford.

 

    Section 45. The sum of $4,000,000, or so much thereof as may be necessary, is appropriated from the Port Development Revolving Loan Fund to the Department of Commerce and Economic Opportunity for grants and loans associated with the Port Development Revolving Loan Program pursuant to 30 ILCS 750-9-11.

 

    Section 50.  The sum of $5,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to Northwestern University for the Nanoscale Science and Engineering Center.

 

    Section 55.  The sum of $4,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for redevelopment of a corporate biotechnology park in Skokie.

 

    Section 60.  The sum of $3,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to the Board of Trustees of the University of Illinois to plan and construct an electrical and computer engineering facility at the Urbana-Champaign campus and related utilities systems, including planning, land acquisition, demolition, construction, remodeling, landscaping, site improvements, equipment, extension or modification of campus utility systems, and such expenses as may be necessary to complete this facility.

 

    Section 65.  The sum of $3,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to the City of Marion for design and construction of a multi-use regional recreational facility.

 

    Section 70.  The sum of $2,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to the Chicago Academy for conversion of a former community college facility into a magnet high school.

 

    Section 75.  The sum of $2,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to the City of Rockford for development of the Center of Excellence.

 

    Section 80.  The sum of $120,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to Parkview Foundation for a window renovation project.

 

    Section 85.  The sum of $25,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for grants and loans pursuant, but not limited to Article 8, Article 9, and Article 10 of the Build Illinois Act.

 

    Section 90.  The sum of $15,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for grants to companies to expand or construct ethanol plants in Illinois.

 

    Section 95.  The sum of $10,000,000, or so much thereof as may be necessary, is appropriated from the Illinois Capital Revolving Loan Fund to the Department of Commerce and Economic Opportunity for the Manufacturing Modernization Program.

 

Total, Article 2                                $89,920,000

 

ARTICLE 3

DEPARTMENT OF COMMERCE AND ECONOMIC OPPORTUNITY

 

    Section 5.  The amount of $8,940,147, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 5 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Department of Commerce and Economic Opportunity for a grant to the DuPage Airport Authority for planning, design, construction and access infrastructure related to the hi-tech business campus.

 

    Section 10.  The amount of $6,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 10 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Department of Commerce and Economic Opportunity for a grant for planning, design, construction, and all other costs associated with a new Ford Technical Training Center.

 

    Section 15.  The sum of $500,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 15 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Department of Commerce and Economic Opportunity for a grant to Argonne National Laboratory for the "TRUE GRID I WIRE" Program.

 

    Section 20.  The amounts of $22,000,000 and $551,947, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 91, Section 20 of Public Act 93-0842, are reappropriated from the Coal Development Fund to the Department of Commerce and Economic Opportunity for the purpose of providing partial funds for planning, design, engineering and testing, and construction of a low emissions boiler system for Illinois high-sulfur coals.

 

    No contract shall be entered into or obligation incurred for any expenditure made in this Section of this Article until after the purpose and amounts have been approved in writing by the Governor.

 

    Section 25.  The sum of $6,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 25 of Public Act 93-0842, is reappropriated from the Coal Development Fund to the Department of Commerce and Economic Opportunity for the Coal Demonstration Program.

 

    Section 30.  The sum of $6,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 30 of Public Act 93-0842, is reappropriated from the Coal Development Fund to the Department of Commerce and Economic Opportunity for Coal Development Programs.

 

    Section 35.  The sum of $50,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 35 of Public Act 93-0842, is reappropriated from the Coal Development Fund to the Department of Commerce and Economic Opportunity for grants pursuant to 20 ILCS 605/605-332 – Coal Revival Program.

 

    Section 40.  The amount of $1,039,300, or so much thereof as may be necessary, and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 40 of Public Act 93-0842, is reappropriated from the Coal Development Fund to the Department of Commerce and Economic Opportunity for the development of other forms of energy.

  No contract shall be entered into or obligation incurred for any expenditure made in this Section of this Article until after the purpose and amounts have been approved in writing by the Governor.

 

    Section 45.  The sum of $13,815,797, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 45 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for grants and loans pursuant but not limited to Article 8, Article 9 or Article 10 of the Build Illinois Act.

 

    Section 50.  The sum of $5,420,856, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 91, Section 50 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for grants and loans pursuant but not limited to Article 8 or Article 10 of the Build Illinois Act.

 

    Section 55.  The sum of $4,778,039, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 55 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for grants and loans pursuant but not limited to Article 8, Article 9 or Article 10 of the Build Illinois Act.

 

    Section 60.  The sum of $15,533,803, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 60 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for grants and loans pursuant but not limited to Article 8, Article 9 or Article 10 of the Build Illinois Act.

 

    Section 65.  The sum of $11,025,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 65 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for grants and loans pursuant but not limited to Article 8, Article 9 or Article 10 of the Build Illinois Act.

 

    Section 70.  The sum of $10,480,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 70 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for grants to companies to expand or construct ethanol plants in Illinois.

 

    Section 75.  The sum of $13,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 75 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to the Argonne National Laboratory for the Rare Isotope Accelerator for bondable infrastructure improvements.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 80.  The sum of $17,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 80 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to Argonne National Laboratory for the Nanotechnology Institute for bondable infrastructure improvements.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 85.  The sum of $6,403,051, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 91, Section 85 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Commerce and Economic Opportunity for a grant to Argonne National Laboratory for the Nanotechnology.

 

Total, Article 3                               $198,487,940

 

ARTICLE 4

DEPARTMENT OF NATURAL RESOURCES

 

GRANTS AND REIMBURSEMENTS - GENERAL OFFICE

 

    Section 10. The sum of $725,000, or so much thereof as may be necessary, is appropriated from the State Boating Act Fund to the Department of Natural Resources for the administration and payment of grants to local governmental units for the construction, maintenance, and improvement of boat access areas.

 

    Section 15.  The sum of $120,000, or so much thereof as may be necessary, is appropriated from the State Boating Act Fund to the Department of Natural Resources for the purposes of the Snowmobile Registration and Safety Act and for the administration and payment of grants to local governmental units for the construction, land acquisition, lease, maintenance and improvement of snowmobile trails and access areas.

 

    Section 20.  To the extent federal funds including reimbursements are available for such purposes, the sum of $75,000, or so much thereof as may be necessary, is appropriated from the State Boating Act Fund to the Department of Natural Resources for all costs for construction and development of facilities for transient, non-trailerable recreational boats, including grants for such purposes and authorized under the Boating Infrastructure Grant Program.

 

    Section 25.  The following named sums, new appropriations, or so much thereof as may be necessary, respectively, for the objects and purposes hereinafter named, are appropriated to the Department of Natural Resources:

Payable from State Boating Act Fund:

  For multiple use facilities and

   programs for boating purposes

   provided by the Department of Natural

   Resources, including construction

   and development, all costs for supplies,

   materials, labor, land acquisition,

   services, studies and all other

   expenses required to comply with the

   intent of this appropriation.................. 1,200,000

Payable from State Parks Fund:

  For multiple use facilities and programs

   for park and trail purposes provided by

   the Department of Natural Resources, including

   construction and development, all costs

   for supplies, materials, labor, land

   acquisition, services, studies, and

   all other expenses required to comply with

   the intent of this appropriation................ 150,000

 

    Section 30.  The sum of $100,000, or so much thereof as may be necessary, is appropriated from the Wildlife and Fish Fund to the Department of Natural Resources for acquisition and development, including grants, for the implementation of the North American Waterfowl Management Plan within the Dominion of Canada or the United States which specifically provides waterfowl for the Mississippi Flyway.

 

    Section 35. To the extent federal funds including reimbursements are available for such purposes, the sum of $100,000, or so much thereof as may be necessary, is appropriated from the Wildlife and Fish Fund to the Department of Natural Resources for construction and renovation of waste reception facilities for recreational boaters, including grants for such purposes authorized under the Clean Vessel Act.

 

    Section 40.  The sum of $2,000,000, or so much thereof as may be necessary, is appropriated from the Wildlife and Fish Fund to the Department of Natural Resources for wildlife conservation and restoration plans and programs from federal funds provided for such purposes.

 

    Section 45.  The following named sums, or so much thereof as may be necessary, respectively, herein made either independently or in cooperation with the Federal Government or any agency thereof, any municipal corporation, or political subdivision of the State, or with any public or private corporation, organization, or individual, are appropriated to the Department of Natural Resources for refunds and the purposes stated:

Payable from Forest Reserve Fund:

  For U.S. Forest Service Program.................. 500,000

 

    Section 50.  The sum of $110,000, or so much thereof as may be necessary, is appropriated from the Plugging and Restoration Fund to the Department of Natural Resources, Office of Mines and Minerals for the Landowner Grant Program authorized under the Oil and Gas Act, as amended by Public Act 90-0260.

 

    Section 55.  The sum of $1,500,000, or so much thereof as may be necessary, is appropriated to the Department of Natural Resources from the Abandoned Mined Lands Set Aside Fund for grants and contracts to conduct research, planning and construction to eliminate hazards created by abandoned mines and any other expenses necessary for emergency response.

 

    Section 60.  The sum of $110,000, or so much thereof as may be necessary, is appropriated to the Department of Natural Resources from the State Furbearer Fund for the conservation of fur bearing mammals in accordance with the provisions of Section 5/1.32 of the "Wildlife Code", as now or hereafter amended.

 

    Section 65.  The following named sums, new appropriations, or so much thereof as may be necessary, respectively, for the objects and purposes hereinafter named, are appropriated to the Department of Natural Resources:

Payable from Natural Areas Acquisition Fund:

  For the acquisition, preservation and

   stewardship of natural areas, including habitats

   for endangered and threatened species, high

   quality natural communities, wetlands

   and other areas with unique or unusual

   natural heritage qualities.................... 6,000,000

 

    Section 70.  The sum of $20,000,000, or so much thereof as may be necessary, is appropriated from the Open Space Lands Acquisition and Development Fund to the Department of Natural Resources for expenses connected with and to make grants to local governments as provided in the "Open Space Lands Acquisition and Development Act".

 

    Section 75.  The sum of $550,000, or so much thereof as may be necessary, is appropriated from the State Pheasant Fund to the Department of Natural Resources for the conservation of pheasants in accordance with the provisions of Section 5/1.31 of the "Wildlife Code", as now or hereafter amended.

 

FOR ILLINOIS HABITAT FUND PROGRAM

 

    Section 80.  The sum of $1,150,000, or so much thereof as may be necessary, is appropriated from the Illinois Habitat Fund to the Department of Natural Resources for the preservation and maintenance of high quality habitat lands in accordance with the provisions of the "Habitat Endowment Act", as now or hereafter amended.

 

    Section 85.  The sum of $250,000, or so much thereof as may be necessary, is appropriated from the Illinois Habitat Fund to the Department of Natural Resources for the preservation and maintenance of a high quality fish and wildlife habitat and to promote the heritage of outdoor sports in Illinois from revenue derived from the sale of Sportsmen Series license plates.

 

    Section 90.  The sum of $600,000, or so much thereof as may be necessary, is appropriated to the Department of Natural Resources for expenditure by the Office of Water Resources from the Flood Control Land Lease Fund for disbursement of monies received pursuant to Act of Congress dated September 3, 1954 (68 Statutes 1266, same as appears in Section 701c-3, Title 33, United States Code Annotated), provided such disbursement shall be in compliance with 15 ILCS 515/1 Illinois Compiled Statutes.

 

    Section 95.  The following named sums, or so much thereof as may be necessary, respectively, herein made either independently or in cooperation with the Federal Government or any agency thereof, any municipal corporation, or political subdivision of the State, or with any public or private corporation, organization, or individual, are appropriated to the Department of Natural Resources for refunds and the purposes stated:

Payable from Land and Water Recreation Fund:

  For Outdoor Recreation Programs................ 6,200,000

 

    Section 100.  The sum of $600,000, or so much thereof as may be necessary, is appropriated from the Off Highway Vehicle Trails Fund to the Department of Natural Resources for grants to units of local governments, not-for-profit organizations, and other groups to operate, maintain and acquire land for off-highway vehicle trails and parks as provided for in the Recreational Trails of Illinois Act, including administration, enforcement, planning and implementation of this Act.

 

    Section 105.  The sum of $4,500,000 or so much thereof as may be necessary, is appropriated from the Conservation 2000 Projects Fund to the Department of Natural Resources for the acquisition, planning and development of land and long-term Easements, and cost-shared natural resource management practices for ecosystem-based management of Illinois' natural resources, including grants for such purposes.

 

    Section 110.  The following named sums, or so much thereof as may be necessary, respectively, herein made either independently or in cooperation with the Federal Government or any agency thereof, any municipal corporation, or political subdivision of the State, or with any public or private corporation, organization, or individual, are appropriated to the Department of Natural Resources for refunds and the purposes stated:

Payable from Federal Title IV Fire

 Protection Assistance Fund:

  For Rural Community Fire Protection

   Programs........................................ 325,000

 

    Section 115.  The sum of $80,000, or so much thereof as may be necessary, is appropriated from the Snowmobile Trail Establishment Fund to the Department of Natural Resources for the administration and payment of grants to nonprofit snowmobile clubs and organizations for construction, maintenance, and rehabilitation of snowmobile trails and areas for the use of snowmobiles.

 

    Section 120.  The sum of $625,000, or so much thereof as may be necessary, is appropriated from the Illinois Forestry Development Fund to the Department of Natural Resources for the payment of grants to timber growers for implementation of acceptable forestry management practices as provided in the "Illinois Forestry Development Act" as now or hereafter amended.

 

    Section 125.  To the extent Federal Funds including reimbursements are made available for such purposes, the sum of $300,000, is appropriated from the Illinois Forestry Development Fund to the Department of Natural Resources for Forest Stewardship Technical Assistance.

 

    Section 130.  The sum of $160,000, or so much thereof as may be necessary, is appropriated from the State Migratory Waterfowl Stamp Fund to the Department of Natural Resources for the payment of grants for the implementation of the North American Waterfowl Management Plan within the Dominion of Canada or the United States which specifically provides waterfowl to the Mississippi Flyway as provided in the "Wildlife Code", as amended.

 

    Section 135.  The sum of $160,000, or so much thereof as may be necessary, is appropriated from the State Migratory Waterfowl Stamp Fund to the Department of Natural Resources for the payment of grants for the development of waterfowl propagation areas within the Dominion of Canada or the United States which specifically provide waterfowl for the Mississippi Flyway as provided in the "Wildlife Code", as amended.

 

    Section 140.  The sum of $500,000, or so much thereof as may be necessary, is appropriated from the State Migratory Waterfowl Stamp Fund to the Department of Natural Resources for the purpose of attracting waterfowl and improving public migratory waterfowl areas within the State.

 

    Section 145.  The sum of $2,500,000, or so much thereof as may be necessary, is appropriated from the Park and Conservation Fund to the Department of Natural Resources for grants to units of local government for the acquisition and development of bike paths.

 

    Section 150.  The sum of $500,000, or so much thereof as may be necessary, is appropriated from the Park and Conservation Fund to the Department of Natural Resources for land acquisition, development and maintenance of bike paths and all other related expenses connected with the acquisition, development and maintenance of bike paths.

 

    Section 155.  The sum of $1,500,000, or so much thereof as may be necessary, is appropriated from the Park and Conservation Fund to the Department of Natural Resources for the development and maintenance of recreational trails and trail-related projects authorized under the Intermodal Surface Transportation Efficiency Act of 1991, provided such amount shall not exceed funds to be made available for such purposes from state or federal sources.

 

    Section 160.  The following named sums, new appropriations, or so much thereof as may be necessary, respectively, for the objects and purposes hereinafter named, are appropriated to the Department of Natural Resources:

Payable from the Illinois Beach Marina Fund:

  For rehabilitation, reconstruction, repair,

   replacing, fixed assets, and improvement

   of facilities at North Point Marina at

   Winthrop Harbor................................. 375,000

 

    Section 165.  The sum of $6,000,000, or so much thereof as may be necessary, is appropriated to the Department of Natural Resources from the Abandoned Mined Lands Reclamation Council Federal Trust Fund for grants and contracts to conduct research, planning and construction to eliminate hazards created by abandoned mines, and any other expenses necessary for emergency response.

 

    Section 170.  The sum of $5,000,000, or so much thereof as may be necessary, is appropriated from the State Parks Fund to the Department of Natural Resources, in coordination with the Capital Development Board, for the development of the World Shooting and Recreation Complex including all construction expenses required to comply with this appropriation.  Provided further, to the extent that revenues are received for such purposes, said revenues must come from non-State sources.

 

    Section 175.  No contract shall be entered into or obligation incurred or any expenditure made from an appropriation herein made in Section 170 until after the purpose and amount of such expenditure has been approved in writing by the Governor.

 

    Section 185.  The sum of $150,000, new appropriation, is appropriated from the State Boating Act Fund to the Department of Natural Resources for a grant to the Chain O’Lakes – Fox River Waterway Management Agency for the Agency’s operational expenses.

 

    Section 195.  The sum of $10,000,000 is appropriated from

the Capital Development Fund to the Department of Natural Resources for the non-federal cost share of a Conservation Reserve Enhancement Program to establish long-term contracts and permanent conservation easements in the Illinois River Basin; to fund cost-share assistance to landowners to encourage approved conservation practices in environmentally sensitive and highly erodible areas of the Illinois River Basin; and to fund the monitoring of long term improvements of these conservation practices as required in the Memorandum of Agreement between the State of Illinos and the United States Department of Agriculture.

 

    Section 200. The sum of $3,000,000 is appropriated from the Capital Development Fund to the Department of Natural Resources for planning, design and construction of ecosystem rehabilitation, habitat restoration and associated development in cooperation with the U.S. Army Corps of Engineers.

 

    Section 205. The sum of $12,000,000, or so much thereof may be necessary is appropriated from the Capital Development Fund to the Department of Natural Resources for expenditure by the Office of Water Resources for water development projects at the approximate cost set forth below:

 

Des Plaines River I&M Canal Draines –

  Will County - for land rights and

  construction of replacing drainage,

  flood control, and related

  improvements in the Lower Des

  Plaines River and south edge

  of the I&M Canal................................ $500,000

Fox Chain of Lakes - Lake and

  McHenry Counties - For the

  State cost share in the

  implementation of the

  comprehensive Dredging and

  Disposal Plan, including beneficial

  use of dredge material and

  island creation, for the Fox

  River and Chain of Lakes...................... $1,000,000

Fox River Dams - Kane County –

  for rehabilitation, modification,

  and reconstruction of Batavia and

  Yorkville dams................................ $1,100,000

Hickory/Spring Creek - Will County –

  For implementation of

  State IIIb of channel construction

  of Hickory/Spring Creeks

  flood control project in cooperation

  with the City of Joliet....................... $3,000,000

Prairie/Farmers Creeks - Cook County –

  For costs associated with the

  implementation of flood damage

  reduction measures along Prairie/

  Farmers Creeks and the Des Plaines

  River, including partial payment

  of the non-federal cost requirements

  of the U.S. Army Corps of Engineers'

  Upper Des Plaines River Flood

  Control Project............................... $6,300,000

Small Drainage and Flood

  Control Projects - For implementation

  of small drainage and flood

  control improvements in accordance

  with plans developed in cooperation

  with local governments and school

  districts not to exceed $100,000

  at any single locality.......................... $100,000

  Total                                         $12,000,000

 

    Section 210. The sum of $10,000,000, or so much thereof as may be necessary, is appropriated from the Capital Development Fund to the Department of Natural Resources for grants to public museums for permanent improvements.

 

    Section 215. The sum of $5,000,000, or so much thereof as may be necessary, is appropriated from the Capital Development Fund to the Department of Natural Resources for natural resource conservation and public recreation including, but not limited to, acquisition, protection and preservation of lands.

 

    Section 230. The sum of $6,700,000 or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Natural Resources for the office of Water Resources to pay for a portion of the non-federal cost requirements associated with the Corps of Engineers' project for the repair of Lake Michigan shoreline in Chicago in cooperation with the City of Chicago and the Chicago Park District.

 

    Section 235.  The sum of $325,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Department of Natural Resources for capital expenses related to the Sahara Woods.

 

    Section 240.  No contract shall be entered into or obligation incurred or any expenditure made from a reappropriation herein made in Sections:

  95,

  105,

  145, 150, 155,

  170,

  190-235

until after the purpose and amount of such expenditure has been approved in writing by the Governor.

 

Total, Article 4                               $111,740,000

 

ARTICLE 5

DEPARTMENT OF NATURAL RESOURCES

 

    Section 5.  The sum of $725,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 5, page 573, line 25 of Public Act 93-0842, as amended, is reappropriated from the State Boating Act Fund to the Department of Natural Resources for the administration and payment of grants to local governmental units for the construction, maintenance, and improvement of boat access areas.

 

    Section 7.  The sum of $725,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 10, page 565, line 2 of Public Act 93-0842, as amended, is reappropriated from the State Boating Act Fund to the Department of Natural Resources for the administration and payment of grants to local governmental units for the construction, maintenance, and improvement of boat access areas.

 

    Section 10.  The sum of $1,542,612, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 10, page 574, line 6 of Public Act 93-0842, as amended, is reappropriated from the State Boating Act Fund to the Department of Natural Resources for the administration and payment of grants to local governmental units for the construction, maintenance, and improvement of boat access areas.

 

    Section 15.  The sum of $100,863, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 15, page 574, line 15 of Public Act 93-0842, as amended, is reappropriated from the State Boating Act Fund to the Department of Natural Resources for the purposes of the Snowmobile Registration and Safety Act and for the administration and payment of grants to local governmental units for the construction, land acquisition, lease, maintenance and improvement of snowmobile trails and access areas.

 

    Section 20.  The sum of $160,603, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 20, page 574, line 26 of Public Act 93-0842, as amended, is reappropriated from the State Boating Act Fund to the Department of Natural Resources for the purposes of the Snowmobile Registration and Safety Act and for the administration and payment of grants to local governmental units for the construction, land acquisition, lease, maintenance and improvement of snowmobile trails and access areas.

 

    Section 22.  The sum of $120,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 15, page 565, line 8 of Public Act 93-0842, as amended, is reappropriated from the State Boating Act Fund to the Department of Natural Resources for the purposes of the Snowmobile Registration and Safety Act and for the administration and payment of grants to local governmental units for the construction, land acquisition, lease, maintenance and improvement of snowmobile trails and access areas.

 

    Section 30.  To the extent federal funds including reimbursements are available for such purposes, the sum of $1,554,184, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 30 of Public Act 93-0842, as amended, is reappropriated from the State Boating Act Fund to the Department of Natural Resources for all costs for construction and development of facilities for transient, non-trailerable recreational boats, including grants for such purposes and authorized under the Boating Infrastructure Grant Program.

 

    Section 32.  To the extent federal funds including reimbursements are available for such purposes, the sum of $1,075,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 20 of Public Act 93-0842, as amended, is reappropriated from the State Boating Act Fund to the Department of Natural Resources for all costs for construction and development of facilities for transient, non-trailerable recreational boats, including grants for such purposes and authorized under the Boating Infrastructure Grant Program.

 

    Section 35.  The following named sum, or so much thereof as may be necessary, respectively, and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purposes, is reappropriated to the Department of Natural Resources for the objects and purposes set forth below:

Payable from State Boating Act Fund:

    (From Article 93, Section 35, on

    page 575, lines 27-32 and on page 576,

    lines 1-2, of Public Act 93-0842,

    as amended)

  For multiple use facilities and programs

   for boating purposes provided by the

   Department of Natural Resources including

   construction and development, all costs

   for supplies, materials, labor, land

   acquisition, services, studies and all

   other expenses required to comply with

   the intent of this appropriation.............. 1,351,400

 

    Section 37.  The following named sum, or so much thereof as may be necessary, respectively, and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made for such purposes, is reappropriated to the Department of Natural Resources for the objects and purposes set forth below:

Payable from State Boating Act Fund:

    (From Article 92, Section 25, on

    page 565, lines 25-30 and on page 566,

    lines 1-8, of Public Act 93-0842,

    as amended)

  For multiple use facilities and programs

   for boating purposes provided by the

   Department of Natural Resources including

   construction and development, all costs

   for supplies, materials, labor, land

   acquisition, services, studies and all

   other expenses required to comply with

   the intent of this appropriation.............. 1,200,000

 

    Section 40.  The following named sum, or so much thereof as may be necessary, respectively, and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made for such purposes, is reappropriated to the Department of Natural Resources for the objects and purposes set forth below:

Payable from State Boating Act Fund:

(From Article 93, Section 40 on page 576,

    lines 14-21 of Public Act 93-0842,

     as amended)

  For multiple use facilities and programs

   for boating purposes provided by the

   Department of Natural Resources including

   construction and development, all costs

   for supplies, materials, labor, land

   acquisition, services, studies and all

   other expenses required to comply with

   the intent of this appropriation.............. 1,200,000

 

 

    Section 45.  The following named sums, or so much thereof as may be necessary, respectively, and as remain unexpended at the close of business on June 30, 2005, from appropriations heretofore made for such purposes, are reappropriated to the Department of Natural Resources for the objects and purposes set forth below:

Payable from the State Parks Fund:

    (From Article 93, Section 45

    on page 576, line 32 and on page

    577, lines 1-7 of Public

    Act 93-0842, as amended)

  For multiple use facilities and programs

   for park and trail purposes provided

   by the Department of Natural Resources, including

   construction and development, all costs

   for supplies, materials, labor, land

   acquisition, services, studies, and

   all other expenses required to comply with

   the intent of this appropriation............... 150,000

Payable from the State Parks Fund:

(From Article 93, Section 45 on

    page 577, lines 12-19, of Public

    Act 93-0842, as amended)

For multiple use facilities and programs

   for park and trail purposes provided

   by the Department of Natural Resources, including

   construction and development, all costs

   for supplies, materials, labor, land

   acquisition, services, studies, and

   all other expenses required to comply with

   the intent of this appropriation................ 477,920

 

    Section 47.  The following named sums, or so much thereof as may be necessary, respectively, and as remain unexpended at the close of business on June 30, 2005, from appropriations heretofore made for such purposes, are reappropriated to the Department of Natural Resources for the objects and purposes set forth below:

Payable from State Parks Fund:

(From Article 92, Section 25 on

    page 566, lines 9-13, of Public

    Act 93-0842, as amended)

  For multiple use facilities and programs

   for park and trail purposes provided by

   the Department of Natural Resources, including

   construction and development, all costs

   for supplies, materials, labor, land

   acquisition, services, studies, and

   all other expenses required to comply with

   the intent of this appropriation................ 150,000

 

    Section 48.  The sum of $5,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 170 of Public Act 93-0842, as amended, is reappropriated from the State Park Fund to the Department of Natural Resources, in coordination with the Capital Development Board, for the development of the World Shooting and Recreation Complex including all construction expenses required to comply with this appropriation.  Provided further, to the extent that revenues are received for such purposes, said revenues must come from non-State sources.

 

    Section 50.  The sum of $1,619,622 or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 50, page 577, line 20 of Public Act 93-0842, as amended, is reappropriated from the Wildlife and Fish Fund to the Department of Natural Resources for wildlife conservation and restoration plans and programs from federal funds provided for such purposes.

 

    Section 52.  The sum of $2,000,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 40, page 567, line 1 of Public Act 93-0842, as amended, is reappropriated from the Wildlife and Fish Fund to the Department of Natural Resources for wildlife conservation and restoration plans and programs from federal funds provided for such purposes.

 

    Section 55. The sum of $2,923,780, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 55, page 577, line 28 of Public Act 93-0842, as amended, is reappropriated from the Wildlife and Fish Fund to the Department of Natural Resources for wildlife conservation and restoration plans and programs from federal funds provided for such purposes.

 

    Section 60.  To the extent federal funds including reimbursements are available for such purposes, the sum of $100,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 60, page 578, line 6 of Public Act 93-0842, as amended, is reappropriated from the Wildlife and Fish Fund to the Department of Natural Resources for construction and renovation of waste reception facilities for recreational boaters, including grants for such purposes authorized under the Clean Vessel Act.

 

    Section 62.  To the extent federal funds including reimbursements are available for such purposes, the sum of $100,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 35, page 566, line 27 of Public Act 93-0842, as amended, is reappropriated from the Wildlife and Fish Fund to the Department of Natural Resources for construction and renovation of waste reception facilities for recreational boaters, including grants for such purposes authorized under the Clean Vessel Act.

 

    Section 65. To the extent federal funds including reimbursements are available for such purposes, the sum of $205,997, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 65, page 578, line 17 of Public Act 93-0842, as amended, is reappropriated from the Wildlife and Fish Fund to the Department of Natural Resources for construction and renovation of waste reception facilities for recreational boaters, including grants for such purposes authorized under the Clean Vessel Act.

 

    Section 70.  The sum of $1,433,426, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 70, page 578, line 26 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Department of Natural Resources for planning, design and construction of ecosystem rehabilitation, habitat restoration and associated development in cooperation with the U.S. Army Corps of Engineers.

 

    Section 75.  The sum of $3,237,550, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 75, page 579, line 4 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Department of Natural Resources for planning, design and construction of ecosystem rehabilitation, habitat restoration and associated development in cooperation with the U.S. Army Corps of Engineers.

 

    Section 80.  The sum of $27,931,232, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 80, page 579, line 13 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources to acquire, protect and preserve open space and natural lands.

 

    Section 85.  The sum of $3,940,311, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 85, page 579, line 21 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources for the non-federal cost share of a Conservation Reserve Enhancement Program to establish long-term contracts and permanent conservation easements in the Illinois River Basin; to fund cost-share assistance to landowners to encourage approved conservation practices in environmentally sensitive and highly erodible areas of the Illinois River Basin; and to fund the monitoring of long term improvements of these conservation practices as required in the Memorandum of Agreement between the State of Illinois and the United State Department of Agriculture.

 

    Section 90. The sum of $871,846, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 90, page 580, line 6 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources for the non-federal cost share of a Conservation Reserve Enhancement Program to establish long-term contracts and permanent conservation easements in the Illinois River Basin; to fund cost-share assistance to landowners to encourage approved conservation practices in environmentally sensitive and highly erodible areas of the Illinois River Basin; and to fund the monitoring of long term improvements of these conservation practices as required in the Memorandum of Agreement between the State of Illinois and the United State Department of Agriculture.

 

    Section 95.  The sum of $1,631,310, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 95 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources for expenditure by the Office of Water Resources for the acquisition of lands, buildings, and structures, including easements and other property interests, located in the 100-year floodplain in counties or portions of counties authorized to prepare stormwater management plans and for removing such buildings and structures and preparing the site for open space use.

 

    Section 100.  The sum of $11,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 100 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources for expenditure by the Office of Water Resources for water development projects at the approximate cost set forth below:

Union - McHenry County - for flood control

 and drainage improvement of unnamed

 Kishwaukee River tributary........................ 200,000

Wood River - Madison County - for partial

 payment of the non-federal cost requirements

 to construct Grassy Lake Pump Station Project

 in cooperation with the Wood River Drainage

 and Levee District................................ 200,000

Flood Hazard Mitigation - For implementation

 of flood hazard mitigation plans, and

 acquisition of wetland and tree mitigation

 sites for state and local joint

 flood control projects in

 cooperation with federal agencies, state

 agencies, and units of local government,

 in various counties............................. 3,300,000

Fox Chain of Lakes - Lake and McHenry

 Counties - For the state cost share in

 implementation of the comprehensive

 Dredging and Disposal Plan, including

 beneficial use of dredge material and

 island creation, for the Fox River and

 Chain of Lakes.................................. 2,000,000

Fox River Dams - Kane County - For

 rehabilitation, modification, and

 reconstruction of Batavia

 and Yorkville Dams.............................. 2,600,000

Field Service Facility - Sangamon County -

 For site development and construction

 of a field survey service building

 and storage facility.............................. 200,000

East St. Louis & Vicinity Flood Control -

 Madison and St. Clair Counties - For

 partial payment of the non-federal cost

 requirement of an interior flood protection

 project and ecosystem restoration at East

 St. Louis and Vicinity area..................... 1,800,000

Prairie/Farmers Creeks - Cook County -

 For costs associated with the implementation

 of flood damage reduction measures along

 Prairie/Farmers Creeks and the Des Plaines

 River, including for partial payment of the

 non-federal cost requirements of the U.S.

 Army Corps of Engineers' Upper Des Plaines

 River Flood Control Project....................... 600,000

Small Drainage and Flood Control Projects -

 For implementation of

 small drainage and flood control

 improvements in accordance with plans

 developed in cooperation with local

 governments and school districts, not

 to exceed $100,000 at any single

 locality.......................................... 100,000

    Total                                       $11,000,000

 

FOR WATERWAY IMPROVEMENTS

 

    Section 105.  The sum of $28,497,163, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 93, Section 105 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources for expenditure by the Office of Water Resources for the following projects at the approximate costs set forth below:

Addison Creek Watershed - Cook

 and DuPage Counties............................... 214,935

Chandlerville/Panther Creek -

 Cass County........................................ 24,294

Chicago Harbor Leakage Control -

 Cook County - For implementation

 of a project to identify, measure,

 control, and eliminate leakage

 flows through controlling structures at

 the mouth of the Chicago River in

 cooperation with federal agencies and

 units of local government......................... 990,416

Crisenberry Dam - Jackson County:

 For complete rehabilitation of the

 dam and spillway, including the

 required geotechnical investigation,

 the preparation of plans and

 specifications, and the construction

 of the proposed rehabilitation.................... 522,964

Crystal Creek - Cook County...................... 2,866,704

East Chicago (Ford Heights) - Cook

 County - For partial payment of the

 non-federal cost requirements of the

 Deer Creek federal flood control and

 ecosystem restoration project in

 cooperation with the Village of East

 Chicago........................................... 925,600

East Peoria - Tazewell County.................... 1,878,499

East St. Louis and Vicinity Flood Control -

 Madison and St. Clair Counties - For

 partial payment of the non-federal cost

 requirements of an interior flood protection

 project and ecosystem restoration at

 East St. Louis and Vicinity area.................. 500,000

Floor Service Facility – Sangamon County........... 200,000

Flood Mitigation - Disaster

 Declaration Areas............................... 2,678,372

Fox Chain O'Lakes - Lake and McHenry

 Counties  ...................................... 1,599,312

Fox River Dams - Kane, Kendall

 and McHenry Counties............................ 5,481,776

Granite City - Area  Groundwater-

 Madison County.................................... 300,000

Havana Facilities - Mason County................... 293,344

Hickory Hills - Cook County........................ 158,410

Hickory/Spring Creeks Watershed -

 Cook and Will Counties.......................... 2,595,779

Illinois River Mitigation - Calhoun,

 Jersey, Peoria and Woodford

 Counties........................................... 80,908

Indian Creek - Kane County.......................... 87,025

Kaskaskia River System - Randolph,

 Monroe and St. Clair Counties...................... 33,916

Kyte River - Rochelle, Ogle County............... 1,450,863

Lake Michigan Artificial Reef -

 Cook County........................................ 28,040

Little Calumet Watershed -

 Cook County........................................ 14,154

Loves Park - Winnebago County...................... 489,745

Lower Des Plaines River Watershed -

 Cook and Lake Counties............................ 975,000

Metro-East Sanitary District -

 Madison and St. Clair Counties..................... 60,578

North Branch Chicago River Watershed -

 Cook and Lake Counties............................. 25,690

Prairie du Rocher - Randolph County:

  For partial payment to implement the

  federal flood protection project for

  the Village of Prairie du Rocher in

  cooperation with local units of

  government........................................ 10,000

Prairie/Farmers Creek - Cook County.............. 2,756,259

Asian Carp Barrier - Cook County.................... 10,000

Rock River Dams - Rock Island and

 Whiteside Counties................................ 151,081

Small Drainage and Flood Control

 Projects - Statewide (not to exceed

 $100,000 at any locality)......................... 413,499

Union - McHenry County.............................. 30,000

Village of Justice - Cook County................... 100,000

W. B. Stratton (McHenry) Lock

 and Dam - McHenry County.......................... 750,000

    Total                                       $28,497,163

 

    Section 110.  The sum of $213,812, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 110 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources for expenditure by the Office of Water Resources in cooperation with federal agencies, state agencies and units of local government in the implementation of flood hazard mitigation plans in counties that received a Presidential Disaster Declaration as a result of flooding in calendar years 1993 and thereafter, in accordance with reports filed under Section 5 of the "Flood Control Act of 1945".

 

    Section 115.  The sum of $5,000,000, or so much thereof as may be necessary, and as remains unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 93, Section 115, page 586, line 3 of Public Act 93-0842, and Article   , Section    of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources for grants to public museums for permanent improvements.

 

    Section 120.  The sum of $10,023,728, less $300,000 to be lapsed from the unexpended appropriation, or so much thereof as may be necessary, and as remains unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 93, Section 120, page 586, line 11 of Public Act 93-0842, and Article  , Section    of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources for grants to public museums for permanent improvements.

 

    Section 125.  The amount of $30,115, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 125 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources for grants to public museums for permanent improvements.

 

    Section 130.  The amount of $4,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 130 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources for grants to public museums for permanent improvements.

 

    Section 135.  The sum of $61,418, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 135, page 587, line 3 of Public Act 93-0842, as amended, is reappropriated to the Department of Natural Resources from the State Furbearer Fund for the conservation of fur bearing mammals in accordance with the provisions of Section 5/1.32 of the "Wildlife Code", as now or hereafter amended.

 

    Section 137.  The sum of $104,200, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 60, page 567, line 29 of Public Act 93-0842, as amended, is reappropriated to the Department of Natural Resources from the State Furbearer Fund for the conservation of fur bearing mammals in accordance with the provisions of Section 5/1.32 of the "Wildlife Code", as now or hereafter amended.

 

    Section 140. The sum of $81,394, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 140, page 587, line 12 of Public Act 93-0842, as amended, is reappropriated to the Department of Natural Resources from the State Furbearer Fund for the conservation of fur bearing mammals in accordance with the provisions of Section 5/1.32 of the "Wildlife Code", as now or hereafter amended.

 

    Section 145.  The following named sums, or so much thereof as may be necessary, respectively, and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made for such purposes, are reappropriated to the Department of Natural Resources for the objects and purposes set forth below:

Payable from Natural Areas Acquisition Fund:

    (From Article 93, Section

    145 on page 587, line 31, and page

    588, lines 1-6, of Public

    Act 93-0842, as amended)

  For the acquisition, preservation and

   stewardship of natural areas,

   including habitats for endangered and

   threatened species, high quality natural

   communities, wetlands and other areas

   with unique or unusual natural

   heritage qualities............................ 3,193,368

Payable from Natural Areas Acquisition Fund:

(From Article 93, Section 145 on

    page 588, lines 11-17, of Public

    Act 93-0842, as amended)

For the acquisition, preservation and

   stewardship of natural areas,

   including habitats for endangered and

   threatened species, high quality natural

   communities, wetlands and other areas

   with unique or unusual natural

   heritage qualities............................ 2,412,844

 

    Section 147.  The following named sums, or so much thereof as may be necessary, respectively, and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made for such purposes, are reappropriated to the Department of Natural Resources for the objects and purposes set forth below:

Payable from Natural Areas Acquisition Fund:

(From Article 92, Section 65 on

    page 568, lines 16, of Public

    Act 93-0842, as amended)

For the acquisition, preservation and

   stewardship of natural areas,

   including habitats for endangered and

   threatened species, high quality natural

   communities, wetlands and other areas

   with unique or unusual natural

   heritage qualities............................ 4,499,200

 

    Section 150.  The sum of $18,138,458, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 150, page 588, line 18 of Public Act 93-0842, as amended, is reappropriated from the Open Space Lands Acquisition and Development Fund to the Department of Natural Resources for expenses connected with and to make grants to local governments as provided in the "Open Space Lands Acquisition and Development Act".

 

    Section 155.  The sum of $27,303,854, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 155, page 588, line 27 of Public Act 93-0842, as amended, is reappropriated from the Open Space Lands Acquisition and Development Fund to the Department of Natural Resources for expenses connected with and to make grants to local governments as provided in the "Open Space Lands Acquisition and Development Act".

 

    Section 157.  The sum of $20,000,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 70, page 568, line 17 of Public Act 93-0842, as amended, is reappropriated from the Open Space Lands Acquisition and Development Fund to the Department of Natural Resources for expenses connected with and to make grants to local governments as provided in the "Open Space Lands Acquisition and Development Act".

 

FOR STATE PHEASANT PROGRAM

    Section 160.  The sum of $305,546, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 160, page 589, line 5 of Public Act 93-0842, as amended, is reappropriated from the State Pheasant Fund to the Department of Natural Resources for the conservation of pheasants in accordance with the provisions of Section 5/1.31 of the "Wildlife Code", as now or hereafter amended.

 

    Section 165.  The sum of $179,377, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 165, page 589, line 14 of Public Act 93-0842, as amended, is reappropriated from the State Pheasant Fund to the Department of Natural Resources for the conservation of pheasants in accordance with the provisions of Section 5/1.31 of the "Wildlife Code", as now or hereafter amended.

 

    Section 167.  The sum of $550,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 75, page 568, line 23 of Public Act 93-0842, as amended, is reappropriated from the State Pheasant Fund to the Department of Natural Resources for the conservation of pheasants in accordance with the provisions of Section 5/1.31 of the "Wildlife Code", as now or hereafter amended.

 

    Section 170.  The sum of $644,654, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 170, page 589, line 23 of Public Act 93-0842, as amended, is reappropriated from the Illinois Habitat Fund to the Department of Natural Resources for the preservation and maintenance of high quality habitat lands in accordance with the provisions of the "Habitat Endowment Act", as now or hereafter amended.

 

    Section 175.  The sum of $163,308, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 175, page 590, line 1 of Public Act 93-0842, as amended, is reappropriated from the Illinois Habitat Fund to the Department of Natural Resources for the preservation and maintenance of high quality habitat lands in accordance with the provisions of the "Habitat Endowment Act", as now or hereafter amended.

 

    Section 177.  The sum of $1,150,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 80, page 569, line 1 of Public Act 93-0842, as amended, is reappropriated from the Illinois Habitat Fund to the Department of Natural Resources for the preservation and maintenance of high quality habitat lands in accordance with the provisions of the "Habitat Endowment Act", as now or hereafter amended.

 

    Section 180.  The sum of $142,533, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 180, page 590, line 10 of Public Act 93-0842, as amended, is reappropriated from the Illinois Habitat Fund to the Department of Natural Resources for the preservation and maintenance of a high quality fish and wildlife habitat and to promote the heritage of outdoor sports in Illinois from revenue derived from the sale of Sportsmen Series license plates.

 

    Section 185.  The sum of $1,623, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 185, page 590, line 20 of Public Act 93-0842, as amended, is reappropriated from the Illinois Habitat Fund to the Department of Natural Resources for the preservation and maintenance of a high quality fish and wildlife habitat and to promote the heritage of outdoor sports in Illinois from revenue derived from the sale of Sportsmen Series license plates.

 

    Section 187.  The sum of $250,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 85, page 569, line 7 of Public Act 93-0842, as amended, is reappropriated from the Illinois Habitat Fund to the Department of Natural Resources for the preservation and maintenance of a high quality fish and wildlife habitat and to promote the heritage of outdoor sports in Illinois from revenue derived from the sale of Sportsmen Series license plates.

 

    Section 190.  The following named sums, or so much thereof as may be necessary and as remain unexpended at the close of business on June 30, 2005, from appropriations heretofore made in Article 93, Section 190 of Public Act 93-0842, as amended, made either independently or in cooperation with the Federal Government or any agency thereof, any municipal corporation, or political subdivision of the State, or with any public or private corporation, organization, or individual, are reappropriated to the Department of Natural Resources for refunds and the purposes stated:

Payable from Land and Water Recreation Fund:

    (From Article 93, Section

    190, page 591, line 15 of Public

    Act 93-0842, as amended)

  For Outdoor Recreation Programs................ 6,200,000

Payable from Land and Water Recreation Fund:

    (From Article 93, Section 190

    on page 591, line 20, of Public

    Act 93-0842, as amended)

  For Outdoor Recreation Programs................ 7,800,777

 

    Section 192.  The following named sums, or so much thereof as may be necessary and as remain unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 95 of Public Act 93-0842, as amended, made either independently or in cooperation with the Federal Government or any agency thereof, any municipal corporation, or political subdivision of the State, or with any public or private corporation, organization, or individual, are reappropriated to the Department of Natural Resources for refunds and the purposes stated:

Payable from Land and Water Recreation Fund:

    (From Article 92, Section 95

    on page 570, line 1, of Public

    Act 93-0842, as amended)

  For Outdoor Recreation Programs................ 6,200,000

 

    Section 195.  The sum of $597,437, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 195, page 591, line 21 of Public Act 93-0842, as amended, is reappropriated from the Off Highway Vehicle Trails Fund to the Department of Natural Resources for grants to units of local governments, not-for-profit organizations, and other groups to operate, maintain and acquire land for off-highway vehicle trails and parks as provided for in the Recreational Trails of Illinois Act, including administration, enforcement, planning and implementation of this Act.

 

    Section 197.  The sum of $600,000 or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 100, page 570, line 2 of Public Act 93-0842, as amended, is reappropriated from the Off Highway Vehicle Trails Fund to the Department of Natural Resources for grants to units of local governments, not-for-profit organizations, and other groups to operate, maintain and acquire land for off-highway vehicle trails and parks as provided for in the Recreational Trails of Illinois Act, including administration, enforcement, planning and implementation of this Act.

 

    Section 200.  The sum of $910,741, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made in Article 93, Section 200, page 592, line 1 of Public Act 93-0842, as amended, is reappropriated from the Off Highway Vehicle Trails Fund to the Department of Natural Resources for grants to units of local governments, not-for-profit organizations, and other groups to operate, maintain and acquire land for off-highway vehicle trails and parks as provided for in the Recreational Trails of Illinois Act, including administration, enforcement, planning and implementation of this Act.

 

    Section 205.  The sum of $2,652,734, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made for such purposes in Article 93, Section 205 of Public Act 93-0842, as amended, is reappropriated from the Conservation 2000 Projects Fund to the Department of Natural Resources for the acquisition, planning and development of land and long-term easements, and cost-shared natural resource management practices for ecosystem-based management of Illinois' natural resources, including grants for such purposes.

 

    Section 210.  The sum of $7,194,314, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made for such purposes in Article 93, Section 210 of Public Act 93-0842, as amended, is reappropriated from the Conservation 2000 Projects Fund to the Department of Natural Resources for the acquisition, planning and development of land and long-term easements, and cost-shared natural resource management practices for ecosystem-based management of Illinois' natural resources, including grants for such purposes.

 

    Section 215.  The following named sums, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made in Article 93, Sections 215 and     of Public Act 93-0842, as amended, made either independently or in cooperation with the Federal Government or any agency thereof, any municipal corporation, or political subdivision of the State, or with any public or private corporation, organization, or individual, are reappropriated to the Department of Natural Resources for refunds and the purposes stated:

Payable from Federal Title IV Fire Protection Assistance Fund:

(From Article 93, Section 215

    on page 593, lines 17-18 of Public

    Act 93-0842, as amended)

For Rural Community Fire

 Protection Program............................... 194,419

 

    Section 217.  The following named sums, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 110 of Public Act 93-0842, as amended, made either independently or in cooperation with the Federal Government or any agency thereof, any municipal corporation, or political subdivision of the State, or with any public or private corporation, organization, or individual, are reappropriated to the Department of Natural Resources for refunds and the purposes stated:

Payable from Federal Title IV Fire Protection Assistance Fund:

(From Article 92, Section 110

    on page 570, lines 21-22 of Public

    Act 93-0842, as amended)

For Rural Community Fire

 Protection Program............................... 307,532

(From Article 93, Section 220 on

    page 593, lines 24-25, of Public

    Act 93-0842, as amended)

For Rural Community Fire

 Protection Program................................. 21,252

 

    Section 225.  The sum of $46,515, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 225, page 593, line 26 of Public Act 93-0842, as amended, is reappropriated from the Snowmobile Trail Establishment Fund to the Department of Natural Resources for the administration and payment of grants to nonprofit snowmobile clubs and organizations for construction, maintenance, and rehabilitation of snowmobile trails and areas for the use of snowmobiles.

 

    Section 227.  The sum of $80,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 115, page 570, line 23 of Public Act 93-0842, as amended, is reappropriated from the Snowmobile Trail Establishment Fund to the Department of Natural Resources for the administration and payment of grants to nonprofit snowmobile clubs and organizations for construction, maintenance, and rehabilitation of snowmobile trails and areas for the use of snowmobiles.

 

    Section 230.  The sum of $48,683, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made in Article 93, Section 230, page 594, line 5 of Public Act 93-0842, as amended, is reappropriated from the Snowmobile Trail Establishment Fund to the Department of Natural Resources for the administration and payment of grants to nonprofit snowmobile clubs and organizations for construction, maintenance, and rehabilitation of snowmobile trails and areas for the use of snowmobiles.

 

    Section 235.  The sum of $605,658, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 235, page 594, line 15 of Public Act 93-0842, as amended, is reappropriated from the Illinois Forestry Development Fund to the Department of Natural Resources for the payment of grants to timber growers for implementation of acceptable forestry management practices as provided in the "Illinois Forestry Development Act" as now or hereafter amended.

 

    Section 237.  The sum of $625,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 120, page 570, line 30 of Public Act 93-0842, as amended, is reappropriated from the Illinois Forestry Development Fund to the Department of Natural Resources for the payment of grants to timber growers for implementation of acceptable forestry management practices as provided in the "Illinois Forestry Development Act" as now or hereafter amended.

 

    Section 240.  The sum of $15,911, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 240, page 594, line 25 of Public Act 93-0842, as amended, is reappropriated from the Illinois Forestry Development Fund to the Department of Natural Resources for the payment of grants to timber growers for implementation of acceptable forestry management practices as provided in the "Illinois Forestry Development Act" as now or hereafter amended.

 

    Section 245.  To the extent Federal Funds including reimbursements are made available for such purposes, the sum of $113,880, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 245, page 595, line 6 of Public Act 93-0842, as amended, is reappropriated from the Illinois Forestry Development Fund to the Department of Natural Resources for Forest Stewardship Technical Assistance.

 

    Section 247.  To the extent Federal Funds including reimbursements are made available for such purposes, the sum of $208,942, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 125, page 571, line 9 of Public Act 93-0842, as amended, is reappropriated from the Illinois Forestry Development Fund to the Department of Natural Resources for Forest Stewardship Technical Assistance.

 

    Section 250. To the extent Federal Funds including reimbursements are made available for such purposes, the sum of $15,520, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 250, page 595, line 15 of Public Act 93-0842, as amended, is reappropriated from the Illinois Forestry Development Fund to the Department of Natural Resources for Forest Stewardship Technical Assistance.

 

    Section 255.  To the extent federal funds including reimbursements are made available for such purposes, the sum of $206, or so much thereof as may be necessary and as remains unexpended, at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 255 of Public Act 93-0842, as amended, is reappropriated from the Illinois Forestry Development Fund to the Department of Natural Resources for Urban Forestry programs, including technical assistance, education and grants.

 

    Section 260.  The sum of $428,359, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 260, page 596, line 1 of Public Act 93-0842, as amended, is reappropriated from the State Migratory Waterfowl Stamp Fund to the Department of Natural Resources for the purpose of attracting waterfowl and improving public migratory waterfowl areas within the State.

 

    Section 262.  The sum of $500,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section140, page 571, line 28 of Public Act 93-0842, as amended, is reappropriated from the State Migratory Waterfowl Stamp Fund to the Department of Natural Resources for the purpose of attracting waterfowl and improving public migratory waterfowl areas within the State.

 

    Section 265.  The sum of $1,629,108, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 265, page 596, line 9 of Public Act 93-0842, as amended, is reappropriated from the State Migratory Waterfowl Stamp Fund to the Department of Natural Resources for the purpose of attracting waterfowl and improving public migratory waterfowl areas within the State.

 

FOR BIKEWAYS PROGRAMS

 

    Section 270.  The following named sums, or so much thereof as may be necessary, and is available for expenditure as provided herein, are appropriated from the Park and Conservation Fund to the Department of Natural Resources for the following purposes:

 

  Section 275.  The sum of $10,886 or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 275, on page 597, lines 1-6 of Public Act 93-0842, as amended, is reappropriated for land acquisition, development and grants, for the following bike paths at the approximate costs set forth below:

  Great River Road/Vadalabene Bikeway

   through Grafton................................... 5,300

  Super Trail between the Quad Cities

   and Savannah.......................................... 0

  Illinois Prairie Path in

   Cook County....................................... 5,600

 

    Section 280.  The sum of $2,328,876, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 280, on page 597, line 7 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for grants to units of local government for the acquisition and development of bike paths.

 

    Section 282.  The sum of $2,500,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 145, on page 572, line 3 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for grants to units of local government for the acquisition and development of bike paths.

 

    Section 285. The sum of $9,866,987, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 285, on page 597, lines 15-22 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for grants to units of local government for the acquisition and development of bike paths.

 

    Section 290.  The sum of $56,700, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 290, on page 597, lines 23-31 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for land acquisition, development, grants and all other related expenses connected with the acquisition and development of bike paths.

    No funds in this Section may be expended in excess of the revenues deposited in the Park and Conservation Fund as provided for in Section 2-119 of the Illinois Vehicle Code.

 

    Section 300.  The sum of $843,389, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 300 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for multiple use facilities and programs for conservation purposes provided by the Department of Natural Resources, including repairing, maintaining, reconstructing, rehabilitating, replacing fixed assets, construction and development, marketing and promotions, all costs for supplies, materials, labor, land acquisition and its related costs, services, studies, and all other expenses required to comply with the intent of this appropriation.

 

    Section 305.  The sum of $500,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 305, page 598, line 18 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for land acquisition, development and maintenance of bike paths and all other related expenses connected with the acquisition, development and maintenance of bike paths.

 

    Section 307.  The sum of $500,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 150, page 572, line 8 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for land acquisition, development and maintenance of bike paths and all other related expenses connected with the acquisition, development and maintenance of bike paths.

 

    Section 310.  The sum of $1,792,880, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 310 of Public Act 93-0842, as amended, is reappropriated to the Department of Natural Resources from the Park and Conservation Fund for multiple use facilities and programs for conservation purposes provided by the Department of Natural Resources, including repairing, maintaining, reconstructing, rehabilitating, replacing fixed assets, construction and development, marketing and promotions, all costs for supplies, materials, labor, land acquisition and its related costs, services, studies, and all other expenses required to comply with the intent of this appropriation.

 

    Section 315.  The sum of $3,788,194, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 315 on page 599, line 10 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for land acquisition, development and maintenance of bike paths and all other related expenses connected with the acquisition, development and maintenance of bike paths.

 

    Section 320.  The sum of $1,474,400, less $500,000 to be lapsed from the unexpended appropriation, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 320, page 599, line 19 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for the development and maintenance of recreational trails and trail-related projects authorized under the Intermodal Surface Transportation Efficiency Act of 1991, provided such amount shall not exceed funds to be made available for such purposes from state or federal sources.

 

    Section 322.  The sum of $1,500,000, less $500,000 to be lapsed from the unexpended appropriation, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 155, page 572, line 14 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for the development and maintenance of recreational trails and trail-related projects authorized under the Intermodal Surface Transportation Efficiency Act of 1991, provided such amount shall not exceed funds to be made available for such purposes from state or federal sources.

 

    Section 325.  The sum of $4,311,328, less $460,000 to be lapsed from the unexpended appropriation, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 325, page 599, line 30 of Public Act 93-0842, as amended, is reappropriated from the Park and Conservation Fund to the Department of Natural Resources for the development and maintenance of recreational trails and trail-related projects authorized under the Intermodal Surface Transportation Efficiency Act of 1991, provided such amount shall not exceed funds to be made available for such purposes from state or federal sources.

 

    Section 330.  The sum of $2,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 330 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Natural Resources for grants and contracts for well plugging and restoration projects.  The appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 335.  The sum of $12,882,638, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 335 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Natural Resources for grants to museums for permanent improvements.

 

    Section 340.  The sum of $7,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 340 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Natural Resources for the Division of Water Resources for costs associated with the repair of the Lake Michigan shoreline in Chicago.  The appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 345.  The sum of $110,969, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 345 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Natural Resources for grants and contracts for well plugging and restoration projects. The appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 350.  The sum of $583,423, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 350 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Natural Resources for grants and contracts for well plugging and restoration projects.  The appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 360.  The sum of $76,789, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 360 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Department of Natural Resources for the Division of Water Resources for costs associated with the repair of the Lake Michigan shoreline in Chicago.  The appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 375.  The amount of $189,520, or so much thereof as may be necessary and remains unexpended on June 30, 2005, from appropriations heretofore made for such purposes in Article 93, Section 375 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Department of Natural Resources for the completion of the following projects at the approximate costs set forth below:

Lower Des Plaines River at Tributaries Watershed -

   Cook and DuPage Counties - for

   construction of drainage, flood control,

   recreation and related improvements and

   facilities in the Lower Des Plaines

   Watershed; and for necessary land

   acquisition, relocation, and related

   expenses, all in general conformance with

   the Lower Des Plaines River and Tributaries

   Watershed Work plan in cooperation with the

   U.S. Soil Conservation Service and local

   governments sponsoring this Federal

   Flood Control project........................... 189,520

 

    Section 380.  The amount of $32,507, or so much thereof as may be necessary and remains unexpended on June 30, 2005, from appropriations heretofore made for such purposes in Article 93, Section 380 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Department of Natural Resources for the following projects at the approximate costs set forth below:

Indian Creek - Kane County - For implementation

   of the Indian Creek flood control project

   in Kane County in cooperation with the City

   of Aurora ....................................... 18,656

Midlothian Creek - Cook County - Improvement of

   Midlothian Creek channel to provide flood

   damage reduction for Fernway Subdivision in

   cooperation with the Villages of Orland

   Park and Tinley Park...........................   13,851

    Total                                           $32,507

 

    Section 385.  The following named sums, or so much thereof as may be necessary, respectively, and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made for such purposes, are reappropriated to the Department of Natural Resources for the objects and purposes set forth below:

Payable from the Illinois Beach Marina Fund:

    (From Article 93, Section 385 on

    page 604, lines 21-25, of Public Act

    93-0842, as amended)

  For rehabilitation, reconstruction,

   repair, replacing, fixed assets,

   and improvement of facilities at

   North Point Marina at Winthrop

   Harbor........................................... 37,500

 

    Section 390.  The following named sums, or so much thereof as may be necessary, respectively, and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purposes, are reappropriated to the Department of Natural Resources for the objects and purposes set forth below:

Payable from the Illinois Beach Marina Fund:

    (From Article 93, Section 390

    on page 605, lines 4-8 of Public Act

    93-0842, as amended)

  For rehabilitation, reconstruction,

   repair, replacing, fixed assets,

   and improvement of facilities at

   North Point Marina at Winthrop

   Harbor.......................................... 177,895

 

    Section 392.  The following named sums, or so much thereof as may be necessary, respectively, and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made for such purposes, are reappropriated to the Department of Natural Resources for the objects and purposes set forth below:

Payable from the Illinois Beach Marina Fund:

    (From Article 92, Section 165

    on page 572, line 30 of Public Act

    93-0842, as amended)

  For rehabilitation, reconstruction,

   repair, replacing, fixed assets,

   and improvement of facilities at

   North Point Marina at Winthrop

   Harbor.......................................... 375,000

 

    Section 395.  The sum of $4,052,450, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 395, page 605, line 9 of Public Act 93-0842, as amended, is reappropriated to the Department of Natural Resources from the Abandoned Mined Lands Reclamation Council Federal Trust Fund for grants and contracts to conduct research, planning and construction to eliminate hazards created by abandoned mines, and any other expenses necessary for emergency response.

 

    Section 397.  The sum of $6,000,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 92, Section 165, page 573, line 1 of Public Act 93-0842, as amended, is reappropriated to the Department of Natural Resources from the Abandoned Mined Lands Reclamation Council Federal Trust Fund for grants and contracts to conduct research, planning and construction to eliminate hazards created by abandoned mines, and any other expenses necessary for emergency response.

 

    Section 400.  The sum of $7,128,842, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 93, Section 400, page 605, line 19 of Public Act 93-0842, as amended, is reappropriated to the Department of Natural Resources from the Abandoned Mined Lands Reclamation Council Federal Trust Fund for grants and contracts to conduct research, planning and construction to eliminate hazards created by abandoned mines, and any other expenses necessary for emergency response.

 

    Section 405.  The sum of $4,535,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 93, Section 405, page 605, line 29 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Natural Resources to acquire, protect and preserve open space and natural lands.

 

    Section 410.  The sum of $9,966, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 93, Section 410 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Department of Natural Resources for grants and contracts for well plugging and restoration projects.

 

    Section 420.  No contract shall be entered into or obligation incurred or any expenditure made from a reappropriation herein made in Sections:

  70 through 130,

  190, 192,

  205, 210

  270 through 380, and

  405, 410

until after the purpose and amount of such expenditure has been approved in writing by the Governor.

 

Total, Article 5                               $311,709,063

 

ARTICLE 6

DEPARTMENT OF MILITARY AFFAIRS

 

    Section 5.  The sum of $243,700, or so much thereof as may be necessary, is appropriated from the Illinois National Guard Armory Construction Fund to the Department of Military Affairs for land acquisition and construction of parking facilities at armories.

 

Total, Article 6                                   $243,700

 

ARTICLE 7

DEPARTMENT OF STATE POLICE

 

    Section 10.  The sum of $23,666,518, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made for such purposes in Article 96, Section 10 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of State Police for the cost associated with a statewide voice communication system.

 

Total, Article 7                                $23,666,518

 

ARTICLE 8

DEPARTMENT OF TRANSPORTATION

 

    Section 5.  The sum of $9,000,000, or so much thereof as may be necessary, is appropriated from the Road Fund to the Department of Transportation for Permanent Improvements to Illinois Department of Transportation facilities, including but not limited to the purchase of land, construction, repair, alterations and improvements to maintenance and traffic facilities, district and central headquarters facilities, storage facilities, grounds, parking areas and facilities, fencing and underground drainage, including plans, specifications, utilities and fixed equipment installed and all costs and charges incident to the completion thereof at various locations.

 

    Section 10.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Road Fund to the Department of Transportation for the objects and purposes hereinafter named:

  For costs associated with the

   identification and disposal of hazardous

   materials at storage facilities............... 1,158,600

  For Maintenance, Traffic and Physical

   Research Purposes (A)........................ 26,129,100

  For repair of damages by motorists

   to highway guardrails, fencing,

   lighting units, bridges, underpasses,

   signs, traffic signals, crash

   attenuators, landscaping, roadside

   shelters, rest areas, fringe parking

   facilities, sanitary facilities,

   maintenance facilities including salt

   storage buildings, vehicle weight

   enforcement facilities including scale

   houses, and other highway appurtenances,

   provided such amount shall not exceed

   funds to be made available from collections

   from claims filed by the Department

   to recover the costs of such

   damages....................................... 5,500,000

  For Maintenance, Traffic and Physical

   Research Purposes (B)........................ 12,207,100

    Total                                       $44,994,800

 

    Section 15.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Road Fund to the Department of Transportation for the objects and purposes hereinafter named:

  For apportionment to counties for

   construction of township bridges 20

   feet or more in length as provided

   in Section 6-901 through 6-906 of the

   "Illinois Highway Code"...................... 15,000,000

  For apportionment to needy Townships and

   Road Districts, as determined by the

   Department in consultation with the County

   Superintendents of Highways, Township

   Highway Commissioners, or Road District

   Highway Commissioners........................ 10,014,300

  For apportionment to high-growth cities over

   5,000 in population, as determined by the

   Department in consultation with the Illinois

   Municipal League.............................. 4,000,000

  For apportionment to counties

   under 1,000,000 in population,

   $8,000,000 of the total apportioned

   in equal amounts to each eligible

   county, and $13,800,000 apportioned

   to each eligible county in proportion

   to the amount of motor vehicle license

   fees received from the residents of

   eligible counties............................ 21,800,000

    Total                                       $50,814,300

 

    Section 20.  The following sums, or so much thereof as may be necessary, are appropriated from the Road Fund to the Department of Transportation for preliminary engineering and construction engineering and contract costs of construction, including reconstruction, extension and improvement of State highways, arterial highways, roads, access areas, roadside shelters, rest areas, fringe parking facilities and sanitary facilities, and such other purposes as provided by the "Illinois Highway Code"; for purposes allowed or required by Title 23 of the U.S. Code; for bikeways as provided by Public Act 78-0850; and for land acquisition and signboard removal and control, junkyard removal and control and preservation of natural beauty; and for capital improvements which directly facilitate an effective vehicle weight enforcement program, such as scales (fixed and portable), scale pits and scale installations, and scale houses, in accordance with applicable laws and regulations as follows:

 District 1, Schaumburg.................................. 0

 District 2, Dixon....................................... 0

 District 3, Ottawa...................................... 0

 District 4, Peoria...................................... 0

 District 5, Paris....................................... 0

 District 6, Springfield................................. 0

 District 7, Effingham................................... 0

 District 8, Collinsville................................ 0

 District 9, Carbondale.................................. 0

 Statewide..................................... 909,185,700

 Engineering.....................................         0

    Total                                      $909,185,700

 

    Section 25.  The sum of $26,250,000, or so much thereof as may be necessary, is appropriated from the Grade Crossing Protection Fund to the Department of Transportation for the installation of grade crossing protection or grade separations at places where a public highway crosses a railroad at grade, as ordered by the Illinois Commerce Commission, as provided by law.

 

    Section 30.  The sum of $152,000,000 or so much thereof as may be necessary, is appropriated from the Federal/Local Airport Fund to the Department of Transportation for funding the local or federal share of airport improvement projects, including reimbursements and/or refunds, undertaken pursuant to pertinent state or federal laws, provided such amounts shall not exceed funds available from federal and/or local sources.

 

    Section 35.  The sum of $3,325,000, or so much thereof as may be necessary, is appropriated from the State Rail Freight Loan Repayment Fund for funding the State Rail Freight Loan Repayment Program created by Section 49.25g-1 of the Civil Administrative Code of Illinois.

 

    Section 40.  The sum of $5,000,000, or so much thereof as may be necessary, is appropriated from the Federal High Speed Rail Trust Fund to the Department of Transportation for the federal share of the High Speed Rail Project.

 

    Section 45.  The sum of $16,000,000, or so much thereof as may be necessary, is appropriated from the Federal Mass Transit Trust Fund to the Department of Transportation for the federal share of capital, operating, consultant services, and technical assistance grants, as well as state administration and interagency agreements, provided such amounts shall not exceed funds to be made available from the Federal Government.

 

    Section 50.  The following sums, or so much thereof as may be necessary,  are appropriated from the State Construction Account Fund to the Department of Transportation for preliminary engineering and construction engineering and contract costs of construction, including reconstruction, extension and improvement of State highways, arterial highways, roads, access areas, roadside shelters, rest areas, fringe parking facilities and sanitary facilities, and such other purposes as provided by the "Illinois Highway Code"; for purposes allowed or required by Title 23 of the U.S. Code; for bikeways as provided by Public Act 78-0850; and for land acquisition and signboard removal and control, junkyard removal and control and preservation of natural beauty; and for capital improvements which directly facilitate an effective vehicle weight enforcement program, such as scales (fixed and portable), scale pits and scale installations, and scale houses, in accordance with applicable laws and regulations as follows:

 District 1, Schaumburg.................................. 0

 District 2, Dixon....................................... 0

 District 3, Ottawa...................................... 0

 District 4, Peoria...................................... 0

 District 5, Paris....................................... 0

 District 6, Springfield................................. 0

 District 7, Effingham................................... 0

 District 8, Collinsville................................ 0

 District 9, Carbondale.................................. 0

 Statewide..................................... 765,000,000

 Engineering......................................        0

    Total                                      $765,000,000

 

    Section 55.  The sum of $350,000,000, or so much thereof as may be necessary, for statewide use pursuant to Section 4(a)(1) of the General Obligation Bond Act, is appropriated from the Transportation Bond Series A Fund to the Department of Transportation for land acquisition, engineering (including environmental studies and archaeological activities and other studies and activities necessary or appropriate to secure federal participation in the project), and construction, including reconstruction, extension and improvement of State highways, arterial highways, roads, structures separating highways and railroads and bridges and for purposes allowed or required by Title 23 of the U.S. Code as provided by law in order to implement a portion of the road improvements program.

 

    Section 60.  The sum of $1,045,000, or so much thereof as may be necessary, is appropriated from the Rail Freight Loan Repayment Fund to the Department of Transportation for the Rail Freight Service Assistance Program, created by Section 49.25a through 49.25g-1 of the Civil Administrative Code of Illinois.

 

    Section 65.  No contract shall be entered into or obligation incurred or any expenditure made from an appropriation herein made in

Section 5        Permanent Improvements

Section 35       State Rail Freight Loan Repayment

Section 40       Fed High Speed Rail Trust

Section 60       Federal Rail Freight Loan Repayment

of this Article until after the purpose and the amount of such expenditure has been approved in writing by the Governor.

 

Total, Article 8                             $2,300,985,700

 

ARTICLE 9

DEPARTMENT OF TRANSPORTATION

PERMANENT IMPROVEMENTS

 

    Section 5.  The sum of $11,334,116, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation concerning Permanent Improvements heretofore made in Article 98, Section 5 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 10.  The sum of $5,854,610, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation concerning Permanent Improvements heretofore made in Article 98, Section 10 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 15.  The sum of $9,000,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation concerning Permanent Improvements heretofore made in Article 97, Section 5 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

CENTRAL OFFICE, DIVISION OF HIGHWAYS

AWARDS AND GRANTS

 

    Section 20.  The sum of $5,386,658, or so much thereof as may be necessary and remains unexpended, less $5,224,479 to be lapsed from the unexpended balance at the close of business on June 30, 2005, from the reappropriation concerning railroad relocation demonstration projects heretofore made in Article 98, Section 15 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes, provided such amount does not exceed funds to be made available from the federal government.

 

    Section 25.  The sum of $155,595, or so much thereof as may be necessary and remains unexpended, less $151,229 to be lapsed from the unexpended balance at the close of business on June 30, 2005, from the reappropriation concerning the State share of railroad relocation demonstration projects heretofore made in Article 98, Section 20 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

CONSTRUCTION

 

    Section 30.  The sum of $5,143,981, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made for “Engineering and Consultant Contracts” in Article 98, Section 40 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 35.  The sum of $10,128,508, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 25 of Public Act 93-0842, as amended, for Engineering and Consultant Contracts only, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 40.  The sum of $22,565,305, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 30 of Public Act 93-0842, as amended, for Engineering and Consultant Contracts only, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 45.  The sum of $49,434,130, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 35 of Public Act 93-0842, as amended, for Engineering and Consultant Contracts only, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 55.  The sum of $4,623,569, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation concerning hazardous materials made in Article 98, Section 50 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 60.  The sum of $1,014,499, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation concerning hazardous materials made in Article 98, Section 55 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 65.  The sum of $1,158,600, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation concerning hazardous materials made in Article 97, Section 10 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 70.  The sum of $1,617,976, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made for Formal Contracts in the line item, “For Maintenance, Traffic and Physical Research Purposes (A)” for the Central Offices, Division of Highways, in Article 98, Section 60 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 75.  The sum of $2,709,789, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation made for Formal Contracts in the line item, “For Maintenance, Traffic and Physical Research Purposes (A)” for the Central Offices, Division of Highways, in Article 98, Section 65 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 80.  The sum of $20,669,517, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation made for Formal Contracts in the line item, “For Maintenance, Traffic and Physical Research Purposes (A)” for the Central Offices, Division of Highways, in Article 97, Section 10 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 85.  The sum of $1,944,287, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation concerning Highway Damage Claims heretofore made in Article 98, Section 70 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 90.  The sum of $1,012,991, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation concerning Highway Damage Claims heretofore made in Article 98, Section 75 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 95.  The sum of $4,999,781, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation concerning Highway Damage Claims heretofore made in Article 97, Section 10 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 100. The sum of $115,562,606, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 275 of Public Act 93-0842, as amended, for Engineering and Consultant Contracts only, is reappropriated from the State Construction Fund to the Department of Transportation for the same purposes.

 

    Section 105. The sum of $106,636,304, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation heretofore made in Article 97, Section 50 of Public Act 93-0842, as amended, for Engineering and Consultant Contracts only, is reappropriated from the State Construction Fund to the Department of Transportation for the same purposes.

 

HIGHWAY CONSTRUCTION AND LAND ACQUISITION

AWARDS AND GRANTS

 

    Section 110.  The sum of $1,787,247, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made for township bridges in Article 98, Section 80 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 115.  The sum of $4,682,350, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made for township bridges in Article 98, Section 85 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 120.  The sum of $11,838,754, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation heretofore made for township bridges in Article 97, Section 15 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

CONSTRUCTION

 

    Section 125.  The sum of $84,344,126, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made  in Article 98, Section 105 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 130.  The sum of $15,327,842, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made  in Article 98, Section 110 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 135.  The sum of $37,190,337, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 90 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 140.  The sum of $105,652,814, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 95 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 145.  The sum of $84,121,379, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 100 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 150.  The following named sums, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriations heretofore made in Article 98, Section 115 of Public Act 93-0842, as amended, are reappropriated from the Road Fund to the Department of Transportation for preliminary engineering and construction engineering and contract costs of construction, including reconstruction, extension and improvement of State highways, arterial highways, roads, access areas, roadside shelters, rest areas, fringe parking facilities and sanitary facilities, and such other purposes as provided by the “Illinois Highway Code”; for purposes allowed or required by Title 23 of the U.S. Code, for bikeways as provided by Public Act 78-850; and for land acquisition and signboard removal and control, junkyard removal and control and preservation of natural beauty; and for capital improvements which directly facilitate an effective vehicle weight enforcement program; such as scales (fixed and portable), scale pits and scale installations and scale houses, in accordance with applicable laws and regulations as follows:

   District 1, Schaumburg .................... $200,932,200

   District 2, Dixon............................ $1,957,521

   District 3, Ottawa........................... $4,792,101

   District 4, Peoria........................... $2,609,730

   District 5, Paris............................ $3,037,678

   District 6, Springfield...................... $4,533,803

   District 7, Effingham....................... $19,032,878

   District 8, Collinsville.................... $24,009,551

   District 9, Carbondale....................... $1,197,513

   Statewide   ................................ $24,771,241

  Total                                        $286,874,216

 

    Section 155.  The following named sums, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriations heretofore made in Article 98, Section 120 of Public Act 93-0842, as amended, are reappropriated from the Road Fund to the Department of Transportation for preliminary engineering and construction engineering and contract costs of construction, including reconstruction, extension and improvement of State highways, arterial highways, roads, access areas, roadside shelters, rest areas, fringe parking facilities and sanitary facilities, and such other purposes as provided by the “Illinois Highway Code”; for purposes allowed or required by Title 23 of the U.S. Code, for bikeways as provided by Public Act 78-850; and for land acquisition and signboard removal and control, junkyard removal and control and preservation of natural beauty; and for capital improvements which directly facilitate an effective vehicle weight enforcement program; such as scales (fixed and portable), scale pits and scale installations and scale houses, in accordance with applicable laws and regulations as follows:

   District 1, Schaumburg..................... $189,992,755

   District 2, Dixon............................ $9,428,867

   District 3, Ottawa .......................... $4,236,876

   District 4, Peoria........................... $2,249,157

   District 5, Paris............................ $2,881,965

   District 6, Springfield...................... $8,922,091

   District 7, Effingham........................ $2,624,939

   District 8, Collinsville..................... $5,094,159

   District 9, Carbondale....................... $7,153,837

   Statewide   ................................ $15,545,452

    Total                                      $248,130,098

 

    Section 160.  The sum of $307,718,845, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation heretofore made in Article 97, Section 20 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for preliminary engineering and construction engineering and contract costs of construction, including reconstruction, extension and improvement of State highways, arterial highways, roads, access areas, roadside shelters, rest areas, fringe parking facilities and sanitary facilities, and such other purposes as provided by the “Illinois Highway Code”; for purposes allowed or required by Title 23 of the U.S. Code, for bikeways as provided by Public Act 78-850; and for land acquisition and signboard removal and control, junkyard removal and control and preservation of natural beauty; and for capital improvements which directly facilitate an effective vehicle weight enforcement program; such as scales (fixed and portable), scale pits and scale installations and scale houses, in accordance with applicable laws and regulations.

 

    Section 165.  The sum of $963,018, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 125 of Public Act 93-0842, is reappropriated from the Road Fund to the Department of Transportation for the same purposes.

 

    Section 170.  The sum of $82,888,328, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation heretofore made in Article 98, Section 195 of Public Act 93-0842, as amended, is reappropriated from the Road Fund to the Department of Transportation for highway construction expenditures on projects consistent with the purposes of the Road Fund.

 

    Section 175.  The sum of $155,802, or so much thereof as may be necessary, and remains unexpended, less $91,777 to be lapsed from the unexpended balance at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 150 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Transportation for use as matching funds for the Illinois Transportation Enhancement program for the Historic Preservation Agency.

 

    Section 180.  The sum of $27,151, or so much thereof as may be necessary, and remains unexpended, less $14,783 to be lapsed from the unexpended balance at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 155 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Department of Transportation for use as matching funds for the Illinois Transportation Enhancement program for the Department of Natural Resources.

 

    Section 185.  The sum of $10,426,906, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 300 of Public Act 93-0842, as amended, is reappropriated from the State Construction Account Fund to the Department of Transportation for the same purposes.

 

    Section 190.  The sum of $1,720,966, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 305 of Public Act 93-0842, as amended, is reappropriated from the State Construction Account Fund to the Department of Transportation for the same purposes.

 

    Section 195. The sum of $4,053,691, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 280 of Public Act 93-0842, as amended, is reappropriated from the State Construction Account Fund to the Department of Transportation for the same purposes.

 

    Section 200.  The sum of $20,264,570, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 285 of Public Act 93-0842, as amended, is reappropriated from the State Construction Account Fund to the Department of Transportation for the same purposes.

 

    Section 205.  The sum of $26,521,044, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 290 of Public Act 93-0842, as amended, is reappropriated from the State Construction Account Fund to the Department of Transportation for the same purposes.

 

    Section 210.  The following named sums, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriations heretofore made in Article 98, Section 295 of Public Act 93-0842, as amended, are reappropriated from the State Construction Account Fund to the Department of Transportation for preliminary engineering and construction engineering and contract costs of construction, including reconstruction, extension and improvement of state highways, arterial highways, roads, access areas, roadside shelters, rest areas, fringe parking facilities and sanitary facilities, and such other purposes as provided by the “Illinois Highway Code”; for purposes allowed or required by Title 23 of the U.S. Code; for bikeways as provided by Public Act 78-0850; and for land acquisition and signboard removal and control, junkyard removal and control and preservation of natural beauty; and for capital improvements which directly facilitate an effective vehicle weight enforcement program, such as scales (fixed and portable), scale pits and scale installations, and scale houses, in accordance with applicable laws and regulations as follows:

 

   District 1, Schaumburg...................... $14,599,303

   District 2, Dixon............................ $1,055,807

   District 3, Ottawa............................. $562,607

   District 4, Peoria........................... $2,083,744

   District 5, Paris.............................. $345,534

   District 6, Springfield........................ $147,944

   District 7, Effingham........................ $1,651,750

   District 8, Collinsville..................... $3,149,376

   District 9, Carbondale......................... $298,425

   Statewide................................... $12,721,660

    Total                                       $36,616,150

 

    Section 215.  The following named sums, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriations heretofore made in Article 98, Section 310 of Public Act 93-0842, as amended, are reappropriated from the State Construction Account Fund to the Department of Transportation for preliminary engineering and construction engineering and contract costs of construction, including reconstruction, extension and improvement of state highways, arterial highways, roads, access areas, roadside shelters, rest areas, fringe parking facilities and sanitary facilities, and such other purposes as provided by the “Illinois Highway Code”; for purposes allowed or required by Title 23 of the U.S. Code; for bikeways as provided by Public Act 78-0850; and for land acquisition and signboard removal and control, junkyard removal and control and preservation of natural beauty; and for capital improvements which directly facilitate an effective vehicle weight enforcement program, such as scales (fixed and portable), scale pits and scale installations, and scale houses, in accordance with applicable laws and regulations as follows:

 

   District 1, Schaumburg ..................... $21,017,113

   District 2, Dixon........................... $22,191,602

   District 3, Ottawa........................... $8,273,466

   District 4, Peoria........................... $4,491,447

   District 5, Paris............................ $7,276,480

   District 6, Springfield..................... $15,160,109

   District 7, Effingham....................... $11,368,442

   District 8, Collinsville.................... $24,972,306

   District 9, Carbondale...................... $15,341,046

   Statewide................................... $45,912,173

    Total                                      $176,004,184

 

    Section 220.  The following named sums, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriations heretofore made in Article 97, Section 50 of Public Act 93-0842, as amended, are reappropriated from the State Construction Account Fund to the Department of Transportation for preliminary engineering and construction engineering and contract costs of construction, including reconstruction, extension and improvement of state highways, arterial highways, roads, access areas, roadside shelters, rest areas, fringe parking facilities and sanitary facilities, and such other purposes as provided by the “Illinois Highway Code”; for purposes allowed or required by Title 23 of the U.S. Code; for bikeways as provided by Public Act 78-0850; and for land acquisition and signboard removal and control, junkyard removal and control and preservation of natural beauty; and for capital improvements which directly facilitate an effective vehicle weight enforcement program, such as scales (fixed and portable), scale pits and scale installations, and scale houses, in accordance with applicable laws and regulations as follows:

 

   District 1, Schaumburg..................... $412,790,159

   District 2, Dixon........................... $59,036,358

   District 3, Ottawa.......................... $34,943,254

   District 4, Peoria......................... $165,675,709

   District 5, Paris........................... $41,651,464

   District 6, Springfield..................... $45,771,863

   District 7, Effingham....................... $26,603,879

   District 8, Collinsville.................... $83,920,745

   District 9, Carbondale...................... $28,378,481

   Statewide................................... $60,527,613

    Total                                      $959,299,525

 

    Section 225.  The sum of $12,575,772, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation heretofore made in Article 98, Section 200 of Public Act 93-0842, as amended, is reappropriated from the State Construction Account Fund to the Department of Transportation for highway construction expenditures on projects consistent with the purposes of the State Construction Account Fund.

 

BOND FUND CONSTRUCTION

CONSTRUCTION

 

    Section 230.  The sum of $5,117,609, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 180 of Public Act 93-0842, for statewide purposes, is reappropriated from the Transportation Bond Series A Fund to the Department of Transportation for the same purposes.

 

    Section 235.  The sum of $20,621,985, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 185 of Public Act 93-0842, for statewide purposes, is reappropriated from the Transportation Bond Series A Fund to the Department of Transportation for the same purposes.

 

    Section 240.  The sum of $59,360,449, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 190 of Public Act 93-0842, for statewide purposes, is reappropriated from the Transportation Bond Series A Fund to the Department of Transportation for the same purposes.

 

    Section 245.  The sum of $273,438,795, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 205 of Public Act 93-0842, as amended, for statewide purposes, is reappropriated from the Transportation Bond Series A Fund to the Department of Transportation for the same purposes.

 

    Section 250.  The sum of $100,000,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 210 of Public Act 93-0842, as amended, for statewide purposes, is reappropriated from the Transportation Bond Series A Fund to the Department of Transportation for the same purposes.

 

GRADE CROSSING PROTECTION

CONSTRUCTION

 

    Section 255.  The sum of $31,150,068, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made for grade crossing protection or grade separation in Article 98, Section 130 of Public Act 93-0842, as amended, is reappropriated from the Grade Crossing Protection Fund to the Department of Transportation for the same purpose.

 

    Section 260.  The sum of $21,897,668, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made for grade crossing protection or grade separation in Article 98, Section 135 of Public Act 93-0842, as amended, is reappropriated from the Grade Crossing Protection Fund to the Department of Transportation for the same purpose.

 

    Section 265.  The sum of $26,250,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation heretofore made for grade crossing protection or grade separation in Article 97, Section 25 of Public Act 93-0842, as amended, is reappropriated from the Grade Crossing Protection Fund to the Department of Transportation for the same purpose.

 

DIVISION OF AERONAUTICS

AWARDS AND GRANTS

 

    Section 270.  The sum of $71,483,115, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 140 of Public Act 93-0842, as amended, is reappropriated from the Federal/Local Airport Fund to the Department of Transportation for funding the local or federal share of airport improvement projects, including reimbursements and/or refunds, undertaken pursuant to pertinent state or federal laws, provided such amounts shall not exceed funds available from federal and/or local sources.

 

    Section 275.  The sum of $55,703,205, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 145 of Public Act 93-0842, as amended, is reappropriated from the Federal/Local Airport Fund to the Department of Transportation for funding the local or federal share of airport improvement projects, including reimbursements and/or refunds, undertaken pursuant to pertinent state or federal laws, provided such amounts shall not exceed funds available from federal and/or local sources.

 

    Section 280.  The sum of $204,042,900, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation heretofore made in Article 97, Section 30 of Public Act 93-0842, as amended, is reappropriated from the Federal/Local Airport Fund to the Department of Transportation for funding the local or federal share of airport improvement projects, including reimbursements and/or refunds, undertaken pursuant to pertinent state or federal laws, provided such amounts shall not exceed funds available from federal and/or local sources.

 

    Section 285.  The sum of $25,845,235, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation concerning airport improvements heretofore made in Article 98, Section 215 of Public Act 93-0842, as amended, is reappropriated from the Transportation Bond Series B Fund to the Department of Transportation for the same purposes.

 

    Section 290.  The sum of $13,740,100, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation concerning airport improvements heretofore made in Article 98, Section 220 of Public Act 93-0842, as amended, is reappropriated from the Transportation Bond Series B Fund to the Department of Transportation for the same purposes.

 

CONSTRUCTION

 

    Section 295.  The sum of $25,610,250, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 225 of Public Act 93-0842, as amended, is reappropriated from the Transportation Bond Series B Fund to the Department of Transportation for the same purposes.

 

    Section 300.  The sum of $5,000,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 230 of Public Act 93-0842, as amended, is reappropriated from the Transportation Bond Series B Fund to the Department of Transportation for the same purposes.

 

DIVISION OF PUBLIC AND INTERMODAL TRANSPORTATION

AWARDS AND GRANTS

 

    Section 310.  The following named sums, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriations heretofore made in Article 98, Section 250 of Public Act 93-0842, as amended, are reappropriated from the Transportation Bond Series B Fund to the Department of Transportation for the same purposes as follows:

  Pursuant to Section 4(b)(1) of the General

    Obligation Bond Act, as amended,

    less $2,736,726 to be lapsed

    from the unexpended balance................. $2,987,085

  For the counties of Cook, DuPage,

    Kane, Lake, McHenry and Will,

    pursuant to Section 4(b)(2) of

    the General Obligation Bond Act,

    as amended, less $1,899,084

    to be lapsed from the unexpended balance.... $3,027,296

  For the counties of the State

    outside the counties of Cook,

    DuPage, Kane, Lake, McHenry and

    Will, pursuant to Section

    4(b)(3) of the General Obligation

    Bond Act, as amended, less $843,745

    to be lapsed from the unexpended balance...... $871,759

    Total                                        $1,406,585

 

    Section 315.  The following named sums, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriations heretofore made in Article 98, Section 235 of Public Act 93-0842, as amended, are reappropriated from the Transportation Bond Series B Fund to the Department of Transportation for the same purposes as follows:

 

  Pursuant to Section 4(b)(1) of

    the General Obligation Bond Act,

    as amended, less $12,665,654

    to be lapsed from the unexpended balance.. $143,002,139

  For the counties of the State

    outside the counties of Cook,

    DuPage, Kane, McHenry, and Will,

    pursuant to Section 4(b)(1)

    of the General Obligation Bond

    Act, as amended, less $8,762,953

    to be lapsed from the unexpended balance... $15,275,028

  For the Department of Transportation's

    Greenlight Program pursuant to

    Section 4(b)(1) of the General

    Obligation Bond Act, as amended,

    less $4,757,461 to be lapsed from

the unexpended balance ........................ $46,602,722

  To extend the metrolink rail line

  to Mid-America Airport........................ $5,000,002

    Total                                      $183,693,823

 

    Section 320.  The following named sums, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriations heretofore made in Article 98, Section 240 of Public Act 93-0842, as amended, are reappropriated from the Transportation Bond Series B Fund to the Department of Transportation for the same purposes as follows:

 

  Pursuant to Section 4(b)(1) of

    the General Obligation Bond Act,

    as amended, less $43,703,400

    to be lapsed from the unexpended balance... $75,977,478

  For the counties of the State

    outside the counties of Cook,

    DuPage, Kane, McHenry, and Will,

    pursuant to Section 4(b)(1)

    of the General Obligation Bond

     Act, as amended.................................... $0

  For the Department of Transportation's

    Greenlight Program pursuant to

    Section 4(b)(1) of the General

    Obligation Bond Act, as amended................       0

    Total                                       $75,977,478

 

    Section 325. The sum of $33,742,989, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 265 of Public Act 93-0842, as amended, is reappropriated from the Federal Mass Transit Trust Fund to the Department of Transportation for the federal share of capital, operating, consultant services, and technical assistance grants, as well as state administration and interagency agreements, provided such amounts shall not exceed funds to be made available from the Federal Government.

 

    Section 330. The sum of $15,000,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 270 of Public Act 93-0842, as amended, is reappropriated from the Federal Mass Transit Trust Fund to the Department of Transportation for the federal share of capital, operating, consultant services, and technical assistance grants, as well as state administration and interagency agreements, provided such amounts shall not exceed funds to be made available from the Federal Government.

 

    Section 335. The sum of $15,039,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation heretofore made in Article 97, Section 45 of Public Act 93-0842, as amended, is reappropriated from the Federal Mass Transit Trust Fund to the Department of Transportation for the federal share of capital, operating, consultant services, and technical assistance grants, as well as state administration and interagency agreements, provided such amounts shall not exceed funds to be made available from the Federal Government.

 

RAIL PASSENGER AND RAIL FREIGHT

AWARDS AND GRANTS

 

    Section 340.  The sum of $9,603,756, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 160 of Public Act 93-0842, as amended, is reappropriated from the State Rail Freight Loan Repayment Fund to the Department of Transportation for the same purposes.

 

    Section 345.  The sum of $2,575,333, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 165 of Public Act 93-0842, as amended, is reappropriated from the State Rail Freight Loan Repayment Fund to the Department of Transportation for the same purposes.

 

    Section 350.  The sum of $3,500,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation heretofore made in Article 97, Section 35 of Public Act 93-0842, as amended, is reappropriated from the State Rail Freight Loan Repayment Fund to the Department of Transportation for the same purposes.

 

    Section 355.  The sum of $7,840,403, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 170 of Public Act 93-0842, as amended, is reappropriated from the Federal High Speed Rail Trust Fund to the Department of Transportation for the federal share of the High Speed Rail Project.

 

    Section 360.  The sum of $2,713,714, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 175 of Public Act 93-0842, as amended, is reappropriated from the Federal High Speed Rail Trust Fund to the Department of Transportation for the federal share of the High Speed Rail Project.

 

    Section 365.  The sum of $5,000,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation heretofore made in Article 97, Section 40 of Public Act 93-0842, as amended, is reappropriated from the Federal High Speed Rail Trust Fund to the Department of Transportation for the federal share of the High Speed Rail Project.

 

    Section 370.  The sum of $20,889,926, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 255 of Public Act 93-0842, as amended, is reappropriated from the Transportation Bond Series B Fund to the Department of Transportation for the same purposes.

 

    Section 375.  The sum of $20,000,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation heretofore made in Article 98, Section 260 of Public Act 93-0842, as amended, is reappropriated from the Transportation Bond Series B Fund to the Department of Transportation for the same purposes.

 

    Section 380.  The sum of $2,609,597, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation concerning the federal share of the Rail Freight Loan Repayment Program heretofore made in Article 98, Section 315 of Public Act 93-0842, as amended, is reappropriated from the Rail Freight Loan Repayment Fund to the Department of Transportation for the same purposes.

 

    Section 385.  The sum of $1,100,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the reappropriation concerning the federal share of the Rail Freight Loan Repayment Program heretofore made in Article 98, Section 320 of Public Act 93-0842, as amended, is reappropriated from the Rail Freight Loan Repayment Fund to the Department of Transportation for the same purposes.

 

    Section 390.  The sum of $1,100,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from the appropriation concerning the federal share of the Rail Freight Loan Repayment Program heretofore made in Article 97, Section 55 of Public Act 93-0842, as amended, is reappropriated from the Rail Freight Loan Repayment Fund to the Department of Transportation for the same purposes.

 

    Section 395. No contract shall be entered into or obligation incurred or any expenditure made from a reappropriation herein made in:

 

Section 5    Permanent Improvements

Section 10   Permanent Improvements

Section 15   Permanent Improvements

Section 20   Rail Relocation – Federal

Section 25   Rail Relocation - State

Section 175  CDB – Enhancement

Section 180  CDB - Enhancement

Section 230  Series A - (Road Program)

Section 235  Series A - (Road Program)

Section 240  Series A - (Road Program)

Section 245  Series A - (Road Program)

Section 250  Series A - (Road Program)

Section 285  Series B - (Aeronautics)

Section 290  Series B - (Aeronautics)

Section 295  Series B - (Land Acquisition 3rd Airport)

Section 300  Series B - (Land Acquisition 3rd Airport)

Section 310  Series B - (Transit)

Section 315  Series B - (Transit)

Section 320  Series B - (Transit)

Section 340  State Rail Freight Loan Repayment

Section 345  State Rail Freight Loan Repayment

Section 350  State Rail Freight Loan Repayment

Section 355  FHSRTF High Speed Rail-Federal

Section 360  FHSRTF High Speed Rail-Federal

Section 365  FHSRTF High Speed Rail-Federal

Section 370  Series B - (Rail)

Section 375  Series B - (Rail)

Section 380  Federal Rail Freight Loan Repayment

Section 385  Federal Rail Freight Loan Repayment

Section 390  Federal Rail Freight Loan Repayment

 

of this Article until after the purpose and the amount of such expenditure has been approved in writing by the Governor.

 

Total, Article 9                             $4,192,006,252

 

ARTICLE 10

CAPITAL DEVELOPMENT BOARD

 

    Section 5.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the projects hereinafter enumerated:

 

STATEWIDE

For surveys and modifications to buildings

   to meet requirements of the federal Americans

   with Disabilities Act (ADA)................... 4,000,000

For surveys and abating hazardous materials........ 250,000

For repairing minor problems and emergencies..... 2,000,000

    Total                                        $6,250,000

 

    Section 10.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Department of Agriculture for the projects hereinafter enumerated:

 

ILLINOIS STATE FAIRGROUNDS - SPRINGFIELD

For replacing fire suppression systems in

   various buildings............................. 1,107,000

For replacing roofing systems...................... 375,000

    Total                                        $1,482,000

 

    Section 15.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Department of Natural Resources for the projects hereinafter enumerated:

 

CAVE-IN-ROCK STATE PARK – HARDIN COUNTY

For replacing the site residence roof............... 22,200

GIANT CITY STATE PARK – JACKSON COUNTY

For replacing roofing systems...................... 102,000

HORSESHOE LAKE CONSERVATION AREA – ALEXANDER COUNTY

For replacing roofing systems...................... 105,000

I & M CANAL – CHANNAHON STATE PARK – WILL COUNTY

For improving DuPage River Spillway, in addition

   to funds previously appropriated................ 475,000

JUBILEE COLLEGE STATE PARK – PEORIA COUNTY

For replacing the dump station sewage system....... 409,000

PERE MARQUETTE STATE PARK – JERSEY COUNTY

For repairing sewage and water plant............... 621,000

SNAKEDEN HOLLOW FISH & WILDLIFE AREA – KNOX COUNTY

For rehabilitating the Spillway, in addition

   to funds previously appropriated.............. 1,215,000

    Total                                        $2,949,200

 

    Section 20.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Department of Veterans’ Affairs for the projects hereinafter enumerated:

 

LASALLE VETERANS’ HOME

For constructing an 80-bed expansion, in addition

   to funds previously appropriated............. 11,600,000

MANTENO VETERANS’ HOME – KANKAKEE COUNTY

For installing nurse call stations................. 454,000

For replacing water mains........................ 1,040,000

For installing humidifiers and

   dehumidifers, in addition to

   funds previously appropriated................... 855,000

QUINCY VETERANS’ HOME – ADAMS COUNTY

For replacing the fire alarm system................ 373,000

STATEWIDE

For planning and beginning a 200-bed facility.... 2,000,000

... Total...................................... $16,322,000

 

    Section 25.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Illinois Medical District Commission for the projects hereinafter enumerated:

 

ILLINOIS MEDICAL DISTRICT COMMISSION – CHICAGO

For repairing structural deficiencies.............. 300,000

For redeveloping site and code compliance........ 1,000,000

    Total                                        $1,300,000

 

    Section 30.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Department of Corrections for the projects hereinafter enumerated:

 

DIXON CORRECTIONAL CENTER – LEE COUNTY

For planning and beginning the upgrade of the

   fire alarm system............................... 300,000

HARDIN COUNTY WORK CAMP

For upgrading the sewage treatment plant........... 350,000

ILLINOIS YOUTH CENTER – PERE MARQUETTE

For replacing roofing systems....................... 96,000

For replacing boilers in two buildings.............. 91,000

JACKSONVILLE CORRECTIONAL CENTER – MORGAN COUNTY

For upgrading underground utilities................ 189,000

MENARD CORRECTIONAL CENTER – RANDOLPH COUNTY

For rehabilitating the north cellhouse........... 4,769,000

ROBINSON CORRECTIONAL CENTER – CRAWFORD COUNTY

For expanding the warehouse freezer................ 728,000

SHAWNEE CORRECTIONAL CENTER – JOHNSON COUNTY

For replacing windows in housing units in addition

   to funds previously appropriated.............. 4,000,000

SHERIDAN CORRECTIONAL CENTER – LASALLE COUNTY

For replacing the door and lock control system..... 400,000

For moveable equipment for the 200-bed

   housing unit.................................... 300,000

    Total                                       $11,223,000

 

    Section 35.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Department of State Police for the projects hereinafter enumerated:

 

DISTRICT 12 - EFFINGHAM

For upgrading the firing range................... 1,995,000

METRO-EAST

For the acquisition of land, planning

   and beginning of a new forensic lab........... 2,500,000

    Total                                        $4,495,000

 

    Section 40.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Courts of Illinois for the projects hereinafter enumerated:

 

APPELLATE COURT BUILDING AT MT. VERNON – JEFFERSON COUNTY

For replacing roofing systems....................... 59,000

SUPREME COURT BUILDING AT SPRINGFIELD – SANGAMON COUNTY

For replacing roofing systems...................... 293,000

For renovating former 4th district

   appellate court space......................... 1,820,000

    Total                                        $2,172,000

 

    Section 45.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Historic Preservation Agency for the projects hereinafter enumerated:

 

BLACKHAWK HISTORICAL AREA – ROCK ISLAND

For renovating retaining walls and shelters........ 528,000

CAHOKIA MOUNDS HISTORIC SITE – ST. CLAIR COUNTY

For replacing entry doors.......................... 588,000

LINCOLN’S TOMB HISTORIC SITE – SANGAMON COUNTY

For rehabilitating Lincoln’s Tomb.................. 426,000

    Total                                        $1,542,000

 

    Section 50.  The sum of $150,000, or so much thereof as may be necessary, is appropriated from the Capital Development Fund to the Capital Development Board for the Historic Preservation Agency for planning and beginning renovation of the Crenshaw House.

 

    Section 55.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Department of Central Management Services for the projects hereinafter enumerated:

 

ILLINOIS CENTER FOR REHABILITATION AND EDUCATION –

ROOSEVELT – CHICAGO

For upgrading the fire alarm system................ 135,000

KENNETH HALL REGIONAL OFFICE BUILDING – EAST ST. LOUIS

For replacing roofing systems...................... 221,000

For upgrading the HVAC system.................... 1,145,000

MARION REGIONAL OFFICE BUILDING – WILLIAMSON COUNTY

For replacing roofing systems...................... 615,000

MEDICAL CENTER ( EDWARDS CENTER) – CHICAGO

For renovating for office space.................. 3,149,000

SINGER MENTAL HEALTH CENTER – ROCKFORD

For renovating for office space.................. 3,500,000

SUBURBAN NORTH REGIONAL OFFICE FACILITY – DES PLAINES

For renovating for office space.................. 1,601,000

... Total...................................... $10,366,000

 

    Section 60.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Department of Human Services for the projects hereinafter enumerated:

 

CHOATE MENTAL HEALTH AND DEVELOPMENTAL CENTER – ANNA

For installing an emergency generator.............. 547,000

ILLINOIS SCHOOL FOR THE DEAF – JACKSONVILLE

For replacing water valves throughout the campus... 403,000

JACKSONVILLE DEVELOPMENTAL CENTER – MORGAN COUNTY

For upgrading coal conveying equipment............. 530,000

KILEY DEVELOPMENTAL CENTER – WAUKEGAN

For repairing/replacing roofing systems.......... 1,481,000

MADDEN MENTAL HEALTH CENTER – HINES

For upgrading pavilions for safety and security.... 525,000

SHAPIRO DEVELOPMENTAL CENTER – WAUKEGAN

For planning and beginning

  replacement of the HVAC system................. 1,500,000

SINGER MENTAL HEALTH AND DEVELOPMENTAL CENTER – ROCKFORD

For upgrading the fire alarm system, in addition

   to funds previously appropriated................ 300,000

    Total                                        $5,286,000

 

    Section 65.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Office of the Secretary of State for the projects hereinafter enumerated:

 

CAPITOL COMPLEX

For upgrading emergency egress systems........... 1,128,000

HERNDON BUILDING – SPRINGFIELD

For correcting the water infiltration problems..... 897,000

SPRINGFIELD

For upgrading the high voltage system

   at the capitol complexand the Dirksen

   Parkway motor vehicle services facility......... 535,000

    Total                                        $2,560,000

 

    Section 70.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Department of Military Affairs for the projects hereinafter enumerated:

 

GALESBURG ARMORY

For the construction of a new armory............. 1,800,000

AURORA ARMORY

For planning and beginning construction

   of an Army aviation support facility............ 250,000

    Total                                         2,050,000

 

    Section 75.  The following named amounts, or so much thereof as may be necessary, are appropriated from the School Construction Fund to the Capital Development Board for the School Construction Program for the projects hereinafter enumerated:

 

STATEWIDE

Grants for facility construction............... 500,000,000

 

    Section 80.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Office of the Attorney General for the projects hereinafter enumerated:

 

ATTORNEY GENERAL – SPRINGFIELD

For upgrading the snow melt system................. 134,000

For replacing the roof and stone joints............ 121,000

    Total                                          $255,000

 

    Section 85.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Illinois Community College Board/Illinois Board of Higher Education for the projects hereinafter enumerated:

 

STATEWIDE

For miscellaneous capital improvements including construction, capital facilities, cost of planning, supplies, equipment, materials, services and all other expenses required to complete the work at the various universities and community colleges.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.................................. 30,000,000

Chicago State University............... 483,100

Eastern Illinois University............ 773,300

Governors State University............. 284,600

Illinois State University............ 1,532,000

Northeastern Illinois University....... 575,500

Northern Illinois University......... 1,738,500

Western Illinois University.......... 1,188,300

Southern Illinois University-

  Carbondale......................... 2,437,500

Southern Illinois University-

  Edwardsville....................... 1,144,600

University of Illinois-Chicago....... 4,165,900

University of Illinois-Springfield..... 343,700

University of Illinois-Urbana-

  Champaign.......................... 6,225,400

Illinois Community College Board..... 9,107,600

 

    Section 90.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Board of Trustees of the University of Illinois for the projects hereinafter enumerated:

UNIVERSITY OF ILLINOIS-URBANA-CHAMPAIGN

For the planning, analysis and design

   of Lincoln Hall.  Design cannot

   proceed beyond program analysis/

   preliminary design unless

   approved in writing by the Governor........... 3,000,000

For planning and beginning construction

   of the Integrated-Post-Harvest

   Processing Center............................. 2,990,000

    Total                                        $5,990,000

 

    Section 95.  The following named amount, or so much thereof as may be necessary, is appropriated from the Capital Development Fund to the Capital Development Board for the Board of Trustees of Western Illinois University for the project hereinafter enumerated:

WESTERN ILLINOIS UNIVERSITY

For planning and beginning the Phase

   One construction of the riverfront

   campus development............................ 2,399,000

 

    Section 100.  The following named amounts, or so much thereof as may be necessary, are appropriated from the Capital Development Fund to the Capital Development Board for the Board of Trustees of Southern Illinois University for the projects hereinafter enumerated:

SOUTHERN ILLINOIS UNIVERSITY – CARBONDALE

For planning and beginning the construction

   of a Transportation Education Center.......... 3,902,900

SOUTHERN ILLINOIS UNIVERSITY – EDWARDSVILLE

For planning and beginning the renovation

   and expansion of the Science

   Laboratory Building........................... 2,906,400

    Total                                        $6,809,300

 

    Section 105.  The following named amount, or so much thereof as may be necessary, is appropriated from the Capital Development Fund to the Capital Development Board for the Illinois Math and Science Academy for the project hereinafter enumerated:

ILLINOIS MATH AND SCIENCE ACADEMY - AURORA

For replacing the fire alarm system............... $200,000

 

    Section 110.  The amount of $377,533, or so much thereof as may be necessary, is appropriated from the Capital Development Fund to the Capital Development Board for the Illinois Board of Higher Education for the projects hereinafter enumerated for land, planning, remodeling, construction and all costs necessary to construct a facility at the University Center of Lake County, in addition to funds previously appropriated.

 

    Section 115.  The amount of $1,887,550, or so much thereof as may be necessary, is appropriated from the Capital Development Fund to the Capital Development Board for the Illinois Board of Higher Education to plan and begin construction of a space for the delivery of a teacher training and development and student enrichment program at the Illinois Math and Science Academy, in addition to funds previously appropriated.

 

    Section 120.  The sum of $50,000,000, or so much there of as may be necessary, is appropriated from the Build Illinois Bond Fund to the Capital Development Board for the Illinois Community College Board for miscellaneous capital improvements including construction, capital facilities, cost of planning, supplies, equipment, materials and all other expenses required to complete the work at the various community colleges.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

Total, Article 10                              $666,065,583

 

ARTICLE 11

CAPITAL DEVELOPMENT BOARD

 

    Section 5.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 5 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Department of Agriculture for the projects hereinafter enumerated:

 

ILLINOIS STATE FAIRGROUNDS - DUQUOIN

(From Article 99, Section 5 of Public Act 93-0842)

For completing the upgrade of the

  electrical distribution system, in

  addition to funds previously

  appropriated................................... 1,510,411

For upgrading the telecommunications

  system........................................... 400,000

For upgrading the HVAC system...................... 180,208

For constructing a multi-purpose

  building......................................... 297,084

ILLINOIS STATE FAIRGROUNDS - SPRINGFIELD

For renovating comfort stations, in addition

  to funds previously appropriated................. 982,190

For renovating the grandstand area.................. 92,189

For renovating the Emmerson Building................ 93,813

For renovating or replacing #26 Barn............... 133,169

For renovating the Junior Home Economics

  Building.......................................... 61,424

For installing HVAC system and

  restrooms in the Orr Building.................... 228,211

    Total                                        $3,978,699

 

    Section 15.  The following named amount, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 15 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Department of Agriculture for the project hereinafter enumerated:

ILLINOIS STATE FAIRGROUNDS - SPRINGFIELD

(From Article 99, Section 15 of Public Act 93-0842)

For replacing and upgrading roofs, in addition

  to funds previously appropriated................. 106,968

 

    Section 20.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 20 of Public Act 93-0842, as amended, are reappropriated from the Capital Development Fund to the Capital Development Board for the Courts of Illinois for the projects hereinafter enumerated:

 

MT. VERNON APPELLATE COURT BUILDING

(From Article 99, Section 20 of Public Act 93-0842)

For expanding the courthouse, in

  addition to funds previously

  appropriated...................................... 33,519

SPRINGFIELD - SUPREME COURT BUILDING

For replacing the roofing system, in addition

  to funds previously appropriated.................. 16,570

For replacing the roof.............................. 23,575

For renovating the HVAC system on

  the 3rd Floor.................................... 140,000

For installing humidifier and water

  filtration systems............................. 1,527,950

APPELLATE COURT SECOND DISTRICT - ELGIN

For miscellaneous improvements...................... 61,779

    Total                                        $1,803,393

 

    Section 30.  The following named amount, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 30 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Courts of Illinois for the projects hereinafter enumerated:

SUPREME COURT BUILDING - SPRINGFIELD

(From Article 99, Section 30 of Public Act 93-0842)

For renovating the Library and

  completing HVAC, in addition to funds

  previously appropriated.......................... 235,000

 

    Section 35.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 35 of Public Act 93-0842, as amended, are reappropriated from the Capital Development Fund to the Capital Development Board for the Office of the Architect of the Capitol for the projects hereinafter enumerated:

 

CAPITOL BUILDING - SPRINGFIELD

(From Article 99, Section 35 of Public Act 93-0842)

For equipment, remodeling and all other

  costs related to the maintenance, renovation

  or restoration of areas located in the

  Capitol Building............................... 2,500,000

For all costs related to asbestos and

  environmental abatement in the

  Capitol Building............................... 7,500,000

    Total                                       $10,000,000

 

    Section 40.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 99, Section 40, of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Office of the Secretary of State for the projects hereinafter enumerated:

CAPITOL BUILDING - SPRINGFIELD

(From Article 99, Section 40 of Public Act 93-0842)

For planning and design, providing a study,

  historical analysis, asbestos abatement

  and all other costs associated with the

  upgrade of the HVAC system in the Capitol

  building....................................... 2,650,000

For all costs related to the planning

  and design of life safety and fire

  protection system improvements, hazardous

  material abatement, historical restoration

  and construction in the Capitol Building....... 1,000,000

For upgrading the HVAC systems, in

  addition to funds previously

  appropriated................................... 2,329,972

CAPITOL COMPLEX - SPRINGFIELD

For completing the stone restoration, in

  addition to funds previously appropriated...... 1,393,643

For demolition of 222 S. College,

  and landscaping of Capitol Complex

  in addition to funds previously

  appropriated................................... 1,200,000

For demolition of 222 South College

  Building and landscaping of

  Capitol Complex................................ 2,387,894

DRIVER'S FACILITY WEST - CHICAGO

For renovating the building........................ 832,578

MOTOR VEHICLE SERVICES FACILITY - SPRINGFIELD

For upgrading the fire alarm and

  security systems................................. 420,640

STATE POWER PLANT - SPRINGFIELD

For installing new water service and

  repairing power plant systems..................... 72,377

WILLIAM G. STRATTON BUILDING - SPRINGFIELD

For the planning, design, reconstruction,

  and construction to renovate or replace

  the Stratton Office Building, in addition

  to funds previously appropriated.............. 11,582,631

    Total                                       $23,869,735

 

    Section 45.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 99, Section 45 of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Office of the Secretary of State for the projects hereinafter enumerated:

CAPITOL COMPLEX – SPRINGFIELD

(From Article 99, Section 45 of Public Act 93-0842)

For upgrading fire alarm systems in

  two buildings................................... 150,642

For expanding the shipping and

  receiving dock................................... 161,389

    Total                                          $312,031

 

    Section 50.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 50 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Department of Central Management Services for the projects hereinafter enumerated:

STATEWIDE

(From Article 99, Section 50 of Public Act 93-0842)

For upgrading the building security

  system at the James R. Thompson Center

  and the State of Illinois building

  in addition to funds previously

  appropriated..................................... 655,000

OFFICE AND LAB BUILDING, CHICAGO MEDICAL CENTER

For planning and beginning the renovation

  of the facility................................ 1,608,958

DIXON STATE GARAGE - LEE COUNTY

For upgrading the lighting and

  replacing the roof............................... 240,981

JAMES R. THOMPSON CENTER - CHICAGO

For installing an emergency generator............ 3,545,000

For rehabilitating exterior columns, in

  addition to funds previously appropriated...... 1,000,000

For upgrading mechanical systems, in

  addition to funds previously appropriated........ 813,472

MEDICAL CENTER (DCFS DISTRICT OFFICE) - CHICAGO

For replacing roof and upgrading

  mechanical and electrical systems................ 325,656

ROCKFORD REGIONAL OFFICE BUILDING

For replacing Halon and upgrading

  the air conditioning............................. 424,590

ILLINOIS CENTER FOR REHABILITATION AND EDUCATION

ROOSEVELT ROAD - CHICAGO

For upgrading electrical systems................... 436,295

For upgrading the HVAC system....................... 45,237

ILLINOIS CENTER FOR REHABILITATION AND

EDUCATION (WOOD) - CHICAGO

For upgrading fire and safety systems.............. 118,253

SPRINGFIELD - RESEARCH AND COLLECTION CENTER

For expanding surplus warehouse.................... 594,445

SPRINGFIELD STATE GARAGE

For renovating the interior of the

  central garage................................... 120,033

SPRINGFIELD - COMPUTER FACILITY

For upgrading the computer room and the

  electrical system................................ 594,241

For installing a cooling tower and fire alarm

  system and various other improvements............ 162,911

STATE OF ILLINOIS BUILDING - CHICAGO

For restoring exterior and rebuilding

  foundation....................................... 611,248

    Total                                       $11,296,320

 

    Section 60.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 60, of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Department of Central Management Services for the projects hereinafter enumerated:

STATEWIDE

(From Article 99, Section 60 of Public Act 93-0842)

Telecommunications Building - Springfield

  Roof Replacement.................................. 91,229

ILLINOIS CENTER FOR REHABILITATION AND EDUCATION

(ROOSEVELT) – CHICAGO

For replacing the roofing system................... 91,567

For upgrading the kitchen and plumbing............. 219,513

JAMES R. THOMPSON CENTER - CHICAGO

For rehabilitating exterior columns, in

  addition to funds previously appropriated........ 48,157

    Total                                          $450,466

 

    Section 65.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 65 and Article 28, Section 95 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Department of Natural Resources for the projects hereinafter enumerated:

ARGYLE LAKE STATE PARK - MCDONOUGH COUNTY

(From Article 99, Section 65 of Public Act 93-0842)

For upgrading the sewage treatment system.......... 259,700

BABE WOODYARD STATE NATURAL AREA -

VERMILION COUNTY

For developing the site and associated

  land acquisition............................... 2,610,485

BEAVER DAM STATE PARK - MACOUPIN COUNTY

For replacing the sewage system..................... 61,779

CARLYLE LAKE STATE PARKS

For road and site improvements at

  Carlyle Lake................................... 1,477,424

For infrastructure and site

  improvements at Carlyle Lake..................... 821,110

EAGLE CREEK STATE PARK - SHELBY COUNTY

For constructing lake access boat

  docks at resort.................................. 326,934

FERNE CLYFFE STATE PARK - JOHNSON COUNTY

For replacing the campground

  sewage treatment system.......................... 391,843

FOX RIDGE STATE PARK - COLES COUNTY

For replacing spillway............................. 127,161

GOOSE LAKE PRAIRIE NATURAL AREA - GRUNDY COUNTY

For replacing floating boardwalk.................... 40,980

HENNEPIN CANAL PARKWAY STATE PARK AND ACCESS AREA

For rehabilitating/repairing railroad

  bridges, in addition to funds

  previously appropriated.......................... 859,185

For rehabilitating aqueducts

  #3, #4 and #8.................................... 104,452

HORSESHOE LAKE CONSERVATION AREA - ALEXANDER COUNTY

For dam rehabilitation and the State's share

  to implement the ecological restoration

  plan in cooperation with the U.S.

  Army Corps of Engineers, and

  land acquisition................................. 842,605

I & M Canal - CHANNAHON STATE PARK - WILL COUNTY

For improving DuPage River Spillway................ 101,600

ILLINOIS BEACH STATE PARK - LAKE COUNTY

For replacing sanitary sewer line................... 79,748

For replacing sanitary sewer lines................. 362,372

KANKAKEE RIVER STATE PARK - KANKAKEE/WILL COUNTIES

For constructing sanitary sewer system, in

  addition to funds previously appropriated...... 5,000,000

KICKAPOO STATE PARK - VERMILION COUNTY

For replacing stairway to Long Pond................. 39,018

For rehabilitating the water

  system and day-use areas......................... 108,424

MASON STATE FOREST TREE NURSERY

For expanding the cold storage facility............. 33,004

For expanding the seed cleaning facility........... 210,659

MORAINE HILLS STATE PARK - MCHENRY COUNTY

For replacement of restrooms and upgrading

  the water system.................................. 82,922

MORAINE VIEW STATE PARK - MCLEAN COUNTY

For upgrading the water plant....................... 30,008

RED HILLS STATE PARK - LAWRENCE COUNTY

For miscellaneous improvements...................... 44,740

RESEARCH & COLLECTIONS CENTER - SPRINGFIELD

For renovating the interior........................ 113,771

ROCK CUT STATE PARK - WINNEBAGO COUNTY

For upgrading the sewage system.................. 1,936,593

NEW OFFICE BUILDING - SPRINGFIELD

For completing construction of an

  office building, in addition to funds

  previously appropriated........................... 21,411

SAM PARR STATE PARK - JASPER COUNTY

For renovating recreational facilities............. 819,757

SILOAM SPRINGS STATE PARK - ADAMS COUNTY

For rehabilitating office/service

  area........................................... 1,142,972

SNAKEDEN HOLLOW FISH AND WILDLIFE AREA - KNOX COUNTY

For rehabilitating the Spillway, in

  addition to funds previously

  appropriated...................................... 47,504

WORLD SHOOTING COMPLEX – SPARTA

(From Article 28, Section 95 of Public Act 93-0842)

For construction of the World Shooting

  Complex in Sparta............................. 27,956,233

SPRING GROVE FISHERIES CENTER - MCHENRY COUNTY

(From Article 99, Section 65 of Public Act 93-0842)

For planning and beginning renovation

  of hatchery...................................... 144,480

SPRINGFIELD

For constructing an office building and

  interpretive center.............................. 234,875

SPRING LAKE CONSERVATION AREA - TAZEWELL COUNTY

For stabilizing levee and

  shoreline........................................ 400,256

STARVED ROCK STATE PARK AND LODGE - LASALLE COUNTY

For upgrading water and sewer systems.............. 119,645

WASTE MANAGEMENT & RESEARCH CENTER

For constructing a garage and

  storage area..................................... 368,009

WELDON SPRINGS STATE PARK - DE WITT COUNTY

For upgrading residence utilities................... 40,000

WHITE PINES FOREST STATE PARK - OGLE COUNTY

For completing the replacement of the

  sewer system, in addition to funds

  previously appropriated........................... 34,506

For planning and beginning sewer system

  replacement....................................... 57,278

For planning and beginning lodge and cabin

  restoration........................................ 8,512

WILDLIFE PRAIRIE PARK

For rehabilitating the sewage

  treatment plant.................................. 768,125

For planning and beginning the upgrade

  of the park...................................... 131,648

WILLIAM W. POWERS FISH AND WILDLIFE AREA – COOK COUNTY

For replacing sanitary sewer lines and

  lift station..................................... 466,816

TUNNEL HILL-CACHE RIVER STATE NATURAL AREA

For constructing a visitor center and

  purchasing land.................................. 329,689

STATE MUSEUM - SPRINGFIELD

Plan, begin construction of Illinois

  State Museum................................... 3,573,090

For renovating or replacing exhibits, in

  addition to funds previously appropriated......... 48,357

STATEWIDE

For replacing/repairing the roofing systems

  at the following locations at the approximate

  cost set forth below............................ 245,000

  Clinton Lake Recreational

   Area - DeWitt County................. 65,000

  Ferne Clyffe State Park-

   Johnson County....................... 20,000

  Hennepin Canal Parkway

   State Park........................... 26,000

  Lake Le-Aqua-Na State Park-

   Stephenson County.................... 39,000

  Mermet Lake Conservation Area-

   Massac County........................ 95,000

For replacing/repairing the roofing systems

  at the following locations at the approximate

  costs set forth below........................... 183,179

  Starved Rock State Park &

   Lodge-LaSalle County................. 60,000

  Kaskaskia River Fish & Wildlife

   Area-Randolph County................. 25,000

  Pyramid State Park-

   Perry County.......................... 4,109

  Region V Office (Benton)

   Franklin County...................... 94,070

For rehabilitating dams and bridges................ 767,542

For constructing, replacing and

  renovating lodges and concession

  buildings...................................... 3,616,471

For replacing roofs at the following locations,

  at the approximate cost set forth below.......... 167,660

  Shabbona Lake State

   Park................................. 40,850

  Hennepin Canal Parkway

   State Park........................... 15,750

  Randolph Fish &

   Wildlife Area........................ 65,000

  Dixon Springs State

   Park................................. 46,060

For replacing and constructing vault

  toilets at the following locations,

  at the approximate cost set forth

  below............................................ 629,937

   Wayne Fitzgerrell State Park........ 106,348

   Hennepin Canal Parkway

   State Trail......................... 294,567

   Kaskaskia River Fish &

   Wildlife Area....................... 229,022

For rehabilitating dams at the

  following locations, at the

  approximate cost set forth below................. 662,604

   Rock Cut State Park................. 450,000

   Snakeden Hollow State Park.......... 212,604

For replacing roofs at the following

  locations, at the approximate

  cost set forth below............................. 206,926

   Southern IL Arts &

    Crafts Center.......................... 412

   Frank Holten State Park................. 412

   DNR Geological Survey-

    Champaign.............................. 413

   Sangchris Lake State

    Park................................. 5,291

   Illini State Park..................... 1,692

   Shelbyville Fish &

    Wildlife Area....................... 79,480

   Trail of Tears State

    Forest............................... 3,685

   Sanganois Conservation Area............. 413

   Rice Lake State Park................. 28,090

   Hidden Spring State Park............. 53,740

   Siloam Springs State Park............. 2,417

   Mississippi Palisades

    State Park.......................... 30,880

For replacing roofing systems at the

  following locations, at the approximate

  cost set forth below............................. 325,528

    Beall Woods Conservation Area -

     Wabash County....................... 2,500

    Eldon Hazlet State Park -

     Clinton County...................... 2,475

    Fox Ridge State Park -

     Coles County....................... 21,532

    Giant City State Park -

     Jackson/Union Counties.................. 1

    Goose Lake Prairie State Park -

     Grundy County....................... 9,450

    Hennepin Canal Parkway State Trail . 41,303

    Illinois Beach State Park -

     Lake County....................... 146,682

    Illinois Caverns Natural Area -

     Monroe County...................... 21,000

    Kankakee River State Park -

     Kankakee/Will Counties............. 38,647

    Moraine Hills State Park -

     McHenry County..................... 23,387

    Moraine View State Park -

     McLean County....................... 3,601

    Ramsey Lake State Park -

     Fayette County...................... 1,000

    Randolph County Conservation Area...... 160

    Stephen A. Forbes State Park -

     Marion County....................... 6,857

    Ten Mile Creek State Fish &

     Wildlife Area - Jefferson/

     Hamilton Counties...................... 63

    Union County Conservation Area.......... 23

    Washington County Conservation Area . 3,453

    William W. Powers Conservation Area -

     Cook County......................... 2,394

    Wolf Creek State Park -

     Shelby County....................... 1,000

For replacing vault toilets at the following

  locations, at the approximate cost set forth

  below............................................ 333,369

    Anderson Lake Conservation Area -

     Fulton/Schuyler Counties........... 86,928

    Giant City State Park -

     Jackson/Union Counties............ 179,162

    Randolph County Conservation Area... 38,158

    Silver Springs State Park -

      Kendall County.................... 29,121

For constructing hazardous material storage

  buildings......................................... 11,535

For constructing vault toilets at the

  following locations at the approximate

  cost set forth below:............................ 137,897

   Apple River Canyon State Park........ 19,699

   Des Plaines Conservation Area........ 19,700

   Kankakee River State Park............ 19,700

   Lake Le-Aqua-Na State Park........... 19,699

   Marshall County Conservation Area.... 19,700

   Morrison-Rockwood State Park......... 19,699

   Rice Lake Conservation Area.......... 19,700

For land acquisition............................... 274,539

For planning, construction, reconstruction,

  land acquisition and related costs,

  utilities, site improvements, and all other

  expenses necessary for various capital

  improvements at parks, conservation areas,

  and other facilities under the jurisdiction

  of the Department of Natural Resources......... 1,307,244

    Total                                       $61,816,770

 

    Section 70.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 70 of Public Act 93-0842, are reappropriated from the Tobacco Settlement Recovery Fund to the Capital Development Board for the Department of Natural Resources for the projects hereinafter enumerated:

STATEWIDE PROGRAM

(From Article 99, Section 70 of Public Act 93-0842)

For maintaining lodge and concession

  facilities........................................ 13,722

For maintaining lodge

  and concession facilities......................... 20,018

For rehabilitating or

  replacing playground equipment.................... 74,649

ILLINOIS BEACH STATE PARK - LAKE COUNTY

For stabilizing the shoreline...................... 390,055

    Total                                          $498,444

 

    Section 75.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 99, Section 75 of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Department of Natural Resources for the project hereinafter enumerated:

GOOSE LAKE PRAIRIE NATURAL AREA - GRUNDY COUNTY

(From Article 99, Section 75 of Public Act 93-0842)

For rehabilitating visitor's center

  exterior.......................................... 26,605

STATEWIDE PROGRAM

For replacing roofs at the following

 locations, at the approximate costs set

 forth below....................................... 63,077

  Castle Rock State Park................ 29,414

  Morrison-Rockwood State Park.......... 33,663

WELDON SPRINGS STATE PARK - DEWITT COUNTY

For improving the campgrounds....................... 47,232

    Total                                          $136,914

 

    Section 80.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 80, of Public Act 93-0842, as amended, are reappropriated from the Capital Development Fund to the Capital Development Board for the Department of Corrections for the projects hereinafter enumerated:

CENTRALIA CORRECTIONAL CENTER

(From Article 99, Section 80 of Public Act 93-0842)

For replacing the cooling tower.................... 624,276

For upgrading the electrical system, in

  addition to funds previously appropriated........ 718,989

For upgrading building automation system........... 114,452

DANVILLE CORRECTIONAL CENTER

For upgrading the power plant, in

  addition to funds previously appropriated...... 1,045,888

DECATUR CORRECTIONAL CENTER

For upgrading smoke and fire doors................. 140,000

DIXON CORRECTIONAL CENTER

For planning the upgrade and expansion

  of the medical care facility..................... 190,913

For constructing a gun range and

  classroom building................................ 21,350

DWIGHT CORRECTIONAL CENTER

For renovating Housing Unit C8, in

  addition to funds previously

  appropriated..................................... 270,000

For renovating buildings, in addition

  to funds previously appropriated................. 274,847

For renovation of buildings......................... 30,261

EAST MOLINE CORRECTIONAL CENTER

For completing replacement of the

  absorption chiller, in addition to

  funds previously appropriated.................... 400,000

For upgrading the roofing system................... 687,807

For replacing windows, in addition to

  funds previously appropriated.................. 1,604,422

For replacing the chiller/absorber................. 354,410

For upgrading the electrical

  system........................................... 664,359

GRAHAM CORRECTIONAL CENTER

For upgrading the cooling tower.................... 269,881

For upgrading the mechanical system................ 385,955

For upgrading the building automation

  system, in addition to funds previously

  appropriated..................................... 900,000

For planning upgrade of building automation

  system and fire alarm system..................... 128,020

For upgrading electrical system.................... 425,628

HOPKINS PARK

For infrastructure improvements

  in connection with the Hopkins Park

  Correctional Center............................ 6,398,238

ILLINOIS YOUTH CENTER - HARRISBURG

For utility upgrade, including gas

  and sewer...................................... 5,475,300

For constructing a multi-purpose medical,

  vocational and confinement building............ 9,757,548

ILLINOIS YOUTH CENTER - RUSHVILLE

For planning, design, construction, equipment

  and all other necessary costs to add

  a cellhouse.................................... 4,674,988

ILLINOIS YOUTH CENTER - ST. CHARLES

For constructing an R & C building 

  and other improvements........................ 27,191,194

For rehabilitation of the administration

  building......................................... 200,668

JOLIET CORRECTIONAL CENTER

For replacing the transfer switch and

  emergency generator.............................. 948,968

KANKAKEE MSU - KANKAKEE COUNTY

For fencing improvements............................ 34,878

LAWRENCE COUNTY CORRECTIONAL CENTER - LAWRENCEVILLE

For constructing two cellhouses, in

  addition to funds previously appropriated........ 158,637

LINCOLN CORRECTIONAL CENTER

For replacing doors and locks...................... 899,618

For upgrading the dietary freezers............... 1,812,420

LOGAN CORRECTIONAL CENTER

For planning and beginning the upgrade

  of the power plant............................... 620,609

For renovating the electrical

  distribution system............................ 1,653,627

For constructing a medical building

  and dietary building........................... 2,405,027

MENARD CORRECTIONAL CENTER - CHESTER

For replacing the administration building,

  in addition to funds previously

  appropriated.................................. 12,300,000

For replacing the Administration

  Building....................................... 1,000,000

For correcting slope failure & MSU

  improvements...................................... 45,526

For improving ventilation and dehumidification

  systems in the kitchen and dining rooms........... 75,183

For completing upgrade of North Cellhouse

  plumbing system, in addition to funds

  previously appropriated........................... 35,051

For replacing toilets and waste lines

  at E/W Cellhouse and upgrade

  North Cellhouse plumbing......................... 374,675

For renovation or replacement of the

  Old Hospital Building, in addition to

  funds previously appropriated.................... 153,586

For planning and construction of the

  Administration Building.......................... 890,215

PONTIAC CORRECTIONAL CENTER

For replacing doors and frames................... 1,620,000

For replacing the roof on the Training

  Center and Industry.............................. 368,939

SHAWNEE CORRECTIONAL CENTER

For replacing the emergency generator............ 1,018,257

STATEVILLE CORRECTIONAL CENTER - JOLIET

For replacing doors and locks...................... 580,000

For planning and beginning renovation of

  H & I houses..................................... 390,775

For replacing the water line....................... 215,294

For constructing a housing unit, cellhouse,

  vehicle maintenance building and

  warehouse for the reception and

  classification center, in addition to

  funds previously appropriated.................... 121,050

For replacing windows in B House................... 126,480

For replacing power plant and

  utility distribution system.................... 1,508,463

For planning, design, construction,

  equipment and all other necessary costs

  for an Adult Reception and Classification

  Center......................................... 1,406,145

For upgrading electrical system and elevator

  and installing HVAC system..................... 1,156,777

TAMMS CORRECTIONAL CENTER

Construct bar screen............................... 150,905

VANDALIA CORRECTIONAL CENTER

For constructing a multi-purpose program

  building.......................................... 90,656

For converting Administration Building and

  planning construction of an Administration/

  Health Care Unit................................. 308,406

For planning and beginning construction

  for a slaughter house and meat plant............. 127,978

VIENNA CORRECTIONAL CENTER

For replacing the cooler and freezer............. 2,170,087

For upgrading the power plant.................... 4,670,000

For upgrading the HVAC system and replacing

  water lines in six housing units................. 555,999

STATEWIDE

For upgrading roofing systems at the

 following locations at the approximate

 costs set forth below............................. 220,833

  Hardin County Work

     Camp................................. 8,808

   Illinois Youth Center

     Joliet.............................. 44,151

   Pontiac Correctional

    Center............................. 167,874

For replacing windows at the following

 locations at the approximate costs

 set forth below, in addition to funds

 previously appropriated......................... 1,008,110

  Dixon Correctional Center.......... 1,008,110

For replacing doors and locks

  at the following locations at the

  approximate costs set forth below.............. 1,758,247

   Dixon Correctional Center......... 1,224,587

   Hill Correctional Center............ 472,616

   Vienna Correctional Center........... 61,044

For replacing roofing systems at

  the following locations at the

  approximate cost set forth below................. 236,373

   Illinois Youth Center -

    St. Charles......................... 87,434

   Illinois Youth Center -

   Warrenville......................... 117,522

   Logan Correctional Center............ 31,417

For upgrading showers at the following

  locations at the approximate

  cost set forth below............................. 545,110

   Hill Correctional

    Center............................. 545,110

For upgrading water distribution systems at

  the following locations at the approximate

  cost set forth below............................. 336,500

   Dixon Correctional Center............ 30,806

   Joliet Correctional

    Center............................. 305,694

For upgrading water towers at the following

  locations at the approximate

  cost set forth below........................... 1,729,245

   Dixon Correctional

    Center............................. 490,862

   Illinois Youth Center -

    St. Charles...................... 1,228,853

   Illinois Youth Center -

    Valley View.......................... 9,530

For planning, design, construction, equipment

  and all other necessary costs for a

  maximum security facility..................... 95,869,558

For planning a medium security facility

  and land acquisition........................... 2,629,428

For replacing locks and control panels

  at the following locations at the

  approximate costs set forth below................ 849,512

   Illinois River

    Correctional Center................ 283,171

   Western Illinois

    Correctional Center................ 283,171

   Danville Correctional

    Center............................. 283,170

For replacing roofing systems at

  the following locations at the

  approximate cost set forth below................. 155,768

   Menard Correctional Center............ 7,353

   Vienna Correctional Center........... 81,100

   Illinois Youth Center -

    Harrisburg........................... 4,138

   Pontiac Correctional Center.............. 10

   Illinois Youth Center - Joliet....... 63,167

For replacing or upgrading security and

  monitoring systems at the following

  locations at the approximate cost set

  forth below...................................... 373,156

   Vienna Correctional

    Center............................. 250,000

   Pontiac Correctional

    Center.............................. 94,450

   Joliet Correctional

    Center.............................. 28,706

For planning and replacing windows at the

  following locations at the approximate cost

  set forth below................................ 2,246,305

   Vienna Correctional

    Center........................... 1,780,000

   Sheridan Correctional

    Center............................. 314,454

   Illinois Youth Center -

    Valley View.......................... 8,310

   Illinois Youth Center -

    Joliet.............................. 74,875

   Dixon Correctional

    Center.............................. 65,436

   Shawnee Correctional

    Center............................... 3,230

For upgrading and renovating showers at

  the following locations at the approximate

  cost set forth below.............................. 32,189

   Shawnee Correctional

    Center.............................. 21,345

   Danville Correctional

    Center............................... 1,017

   Graham Correctional

    Center............................... 9,827

For replacing security fencing at the

  following locations at the approximate

  cost set forth below............................. 358,250

   Hill Correctional

    Center............................... 3,547

   Western IL Correctional

    Center.............................. 31,427

   Joliet Correctional

    Center.............................. 49,119

   Logan Correctional

    Center............................. 200,000

   Dixon Correctional

    Center............................... 8,752

   Shawnee Correctional

    Center............................... 5,269

   Graham Correctional

    Center.............................. 24,369

   Danville Correctional

    Center.............................. 35,767

For planning, design, construction, equipment

  and all other necessary costs for a

  female multi-security level

  correctional center........................... 61,781,817

For replacing roofing systems at the

  following locations at the approximate

  cost set forth below............................. 189,284

    Vienna Correctional Center......... 150,261

    Sheridan Correctional Center........ 17,785

    Western Illinois Correctional

     Center - Mt. Sterling.............. 21,238

For upgrading security control systems and

  panels in housing units at the following

  locations at the approximate cost set

  forth below....................................... 26,463

    Danville Correctional Center......... 5,292

    Hill Correctional Center -

     Galesburg........................... 5,293

    Western Illinois Correctional

     Center - Mt. Sterling............... 5,292

    Illinois River Correctional

     Center - Canton..................... 5,293

    Shawnee Correctional Center -

     Vienna.............................. 5,293

For planning, design, construction,

  equipment and all other necessary costs

  for a juvenile facility........................ 1,260,525

For replacing roofing systems at the following

  locations at the approximate cost set forth

  below............................................. 53,645

    Dixon Correctional Center,

     four buildings...................... 3,762

    IYC - St. Charles, two buildings.... 27,316

    Joliet Correctional Center,

     six buildings...................... 11,441

    Logan Correctional Center - Lincoln

     three buildings..................... 5,584

    Pontiac Correctional Center,

     one building........................ 5,542

For inspecting and upgrading water towers

  at the following locations at the approximate

  costs set forth below............................ 230,266

    Dixon Correctional Center,

     Upgrade Water Tower................ 24,238

    Graham Correctional Center - Hillsboro

     Upgrade Water Tower  .............. 30,990

    Joliet Correctional Center,

     Upgrade Water Tower................ 17,044

    Logan Correctional Center - Lincoln

     Complete Water Tower Upgrade  ..... 13,111

    Menard Correctional Center - Chester

     Upgrade Water Tower  .............. 22,443

    Stateville Correctional Center - Joliet

     Upgrade Water Tower  .............. 36,112

    Statewide, Inspect and Upgrade

     Water Towers....................... 86,328

For upgrading fire and safety systems at

  the following locations at the approximate

  costs set forth below, in addition to

  funds previously appropriated.................. 2,037,256

    Menard Correctional Center -

     Chester......................... 1,854,559

    Sheridan Correctional Center....... 110,620

    Vienna Correctional Center.......... 72,077

For upgrading fire safety systems at the

  following locations at the approximate

  costs set forth below, in addition to

  funds previously appropriated:................... 917,626

   Menard Correctional Center............ 1,370

   Pontiac Correctional Center......... 696,383

   Stateville Correctional Center...... 219,873

For upgrading water and wastewater

  systems at the following locations

  at the approximate costs set forth below:........ 437,821

   Big Muddy Correctional Center

    for installing mechanical

    bar screen........................... 7,348

   Centralia Correctional Center

    for upgrading water

    treatment plant........................ 946

   Ed Jenison Work Camp (Paris)

    for installing mechanical

    bar screen........................... 2,530

   IYC - Harrisburg for upgrading

    water distribution system........... 59,198

   Kankakee MSU for constructing

    well #2............................ 288,550

   IYC - St. Charles for upgrading

    sewage/storm system................. 67,475

   IYC - Valley View for installing

    mechanical bar screen............... 11,774

For planning, design, construction,

  equipment and other necessary costs

  for a Medium Security Correctional

  Facility.......................................... 83,625

    Total                                      $278,310,537

 

    Section 85.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purpose in Article 99, Section 85, of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Department of Corrections for the projects hereinafter enumerated:

BIG MUDDY CORRECTIONAL FACILITY

(From Article 99, Section 85 of Public Act 93-0842)

For replacing door locking controls

  and intercom systems........................... 2,701,892

STATEVILLE CORRECTIONAL CENTER

For installing fire alarm systems................ 1,600,000

STATEWIDE

For upgrading the water towers at the

 following locations at the approximate

 costs set forth below............................ 362,058

  Joliet Correctional Center........... 334,902

  Vienna Correctional Center............ 27,156

HILL CORRECTIONAL CENTER - GALESBURG

For upgrading building automation................... 66,433

VANDALIA CORRECTIONAL CENTER

For upgrading the water distribution system

  and replacing the water tower, in addition

  to funds previously appropriated................. 103,914

    Total                                        $4,834,297

 

    Section 90.  The sum of $3,108,095, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 99, Section 90 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Capital Development Board for the Illinois Emergency Management Agency for costs associated with a new State Emergency Operations Center.

 

    Section 95.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 95 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Historic Preservation Agency for the projects hereinafter enumerated:

BISHOP HILL HISTORIC SITE - HENRY COUNTY

(From Article 99, Section 95 of Public Act 93-0842)

For restoring interior and exterior................. 72,197

For rehabilitating Bjorkland Hotel................. 584,757

BRYANT COTTAGE STATE MEMORIAL - BEMENT

For rehabilitating interior and exterior............ 42,862

CAHOKIA COURTHOUSE STATE MEMORIAL - CAHOKIA

For providing structural stabilization............. 269,978

For renovation of the Cahokia Courthouse

  and the Jarrot House.............................. 31,183

CAHOKIA MOUNDS HISTORIC SITE - COLLINSVILLE

For replacement of Monk's Mounds stairs............ 339,695

For restoration of Monk's Mound.................. 1,009,932

For purchasing private land within historic

  site boundary.................................... 189,979

DAVID DAVIS HOME

To acquire a residence to be

  converted to a Visitors Center................... 249,400

JARROT MANSION STATE HISTORICAL SITE

For restoring the mansion, site improvements

  and land acquisition, in addition

  to funds previously appropriated............... 1,528,993

LINCOLN'S TOMB/VIETNAM MEMORIAL - SPRINGFIELD

For rehabilitating site and providing

  irrigation system................................ 201,760

LINCOLN-HERNDON LAW OFFICE - SPRINGFIELD

For rehabilitating interior and exterior............ 16,205

LINCOLN'S NEW SALEM HISTORIC SITE - MENARD COUNTY

For providing electrical at

  campgrounds...................................... 115,376

LINCOLN PRESIDENTIAL CENTER - SPRINGFIELD

For constructing library and museum complex, in

  addition to funds previously appropriated..... 17,099,331

For constructing a Lincoln Presidential

  Library.......................................... 642,127

OLD STATE CAPITOL - SPRINGFIELD

For repairing elevators............................ 387,464

SHAWNEETOWN BANK HISTORIC SITE - GALLATIN COUNTY

For rehabilitating exterior........................ 202,511

UNION STATION - SPRINGFIELD

For purchasing and rehabilitating................ 2,354,453

STATEWIDE

For statewide ISTEA 21 Match....................... 637,000

For replacing roofing systems at the

  following locations at the approximate

  costs set forth below:........................... 115,622

   Washburne House, Galena............... 5,378

   David Davis Mansion, Bloomington..... 22,051

   Bishop Hill House, Henry County...... 88,193

For matching ISTEA federal grant funds............. 143,310

    Total                                       $26,234,135

 

    Section 105.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 99, Section 105, of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Historic Preservation Agency for the projects hereinafter enumerated:

MT. PULASKI COURTHOUSE HISTORIC SITE - LOGAN COUNTY

(From Article 99, Section 105 of Public Act 93-0842)

For rehabilitating interior & exterior............. 206,768

BISHOP HILL HISTORIC SITE – HENRY COUNTY

For restoring interior and exterior................ 100,000

PULLMAN HISTORIC SITE

For all costs associated with the

  stabilization and restoration of the

  Pullman Historic Site.......................... 4,480,736

    Total                                        $4,787,504

 

    Section 110.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 110 of Public Act 93-0842, as amended, are reappropriated from the Capital Development Fund to the Capital Development Board for the Department of Human Services for the projects hereinafter enumerated:

ALTON MENTAL HEALTH CENTER - MADISON COUNTY

(From Article 99, Section 110 of Public Act 93-0842)

For renovating the Forensic Complex and

  constructing two building additions, in

  addition to funds previously appropriated...... 3,900,000

For renovating the central dietary,

  Phase II, in addition to funds previously

  appropriated................................... 1,060,593

For constructing two building additions

  at the Forensic Complex........................ 7,180,592

For rehabilitation of the central dietary.......... 226,935

CHESTER MENTAL HEALTH CENTER

For completing the replacement of

  smoke and heat detectors, in addition

  to funds previously appropriated................. 440,000

For upgrading HVAC systems......................... 590,176

For renovating support and residential areas,

  in addition to funds previously

  appropriated..................................... 119,777

For replacing smoke/heat detectors................. 177,589

For replacing sewer lines.......................... 189,335

For renovating support and residential

  area.............................................. 78,150

CHICAGO-READ MENTAL HEALTH CENTER - CHICAGO

For rehabbing absorbers, controls

  and valves....................................... 398,432

For renovating residential units, in

  addition to funds previously

  appropriated..................................... 236,520

For renovation of the West Campus shower

  and toilet rooms................................. 134,469

CHOATE MENTAL HEALTH AND DEVELOPMENTAL CENTER - ANNA

For renovating Sycamore Hall..................... 2,652,585

ELGIN MENTAL HEALTH CENTER - KANE COUNTY

For replacing power plant and engineering

  building....................................... 7,942,071

For renovating the central dietary

  and kitchen.................................... 3,716,955

For construction of roads, parking lots

  and street lights.............................. 1,107,902

FOX DEVELOPMENTAL CENTER - DWIGHT

For upgrading fire alarm systems................... 950,000

For replacing and repairing interior doors,

  flooring and walls, in addition to funds

  previously appropriated........................ 1,105,000

For planning and beginning replacement

  of interior doors and flooring

  and repairing walls in the Main and

  Administration Buildings......................... 869,443

HOWE DEVELOPMENTAL CENTER - TINLEY PARK

For completing replacement of HVAC

  systems, in addition to funds

  previously appropriated........................ 1,400,000

For upgrading plumbing in kitchen.................. 735,000

For planning the replacement of

  absorption-type A/C.............................. 450,000

For replacing HVAC and duct work.................... 39,704

For completing upgrade of tunnels,

  Phase II, in addition to funds previously

  appropriated..................................... 366,920

For renovating residences, in addition to

  funds previously appropriated.................. 1,156,927

For renovation of residential buildings............. 76,450

ILLINOIS SCHOOL FOR THE DEAF - JACKSONVILLE

For renovating the High School Building

  Phase II....................................... 1,580,000

For renovating the health center................... 213,013

For replacing roof and upgrading the

  mechanical system at Burns Gym................. 1,968,986

For replacing the visual alert system.............. 466,084

For renovating High School Building.............. 1,050,120

For replacing HVAC, upgrading electrical

  and replacing doors, in addition to

  funds previously appropriated.................... 455,337

ILLINOIS SCHOOL FOR THE VISUALLY IMPAIRED - JACKSONVILLE

For renovating auditorium, classroom

  and administration buildings................... 2,360,924

For renovating classrooms in Building 17......... 1,281,525

For renovating the Girls' Dormitory, in

  addition to funds previously appropriated........ 210,537

For renovations to the powerhouse,

  boilers and associated coal and ash

  equipment For installation of individual

  package boilers, in addition

  to funds previously appropriated................. 400,000

JACKSONVILLE DEVELOPMENTAL CENTER - MORGAN COUNTY

For planning and beginning the renovation

  of the power house............................... 698,226

KILEY DEVELOPMENTAL CENTER - WAUKEGAN

For converting the facility to natural

  gas, in addition to funds previously

  appropriated..................................... 495,240

For renovating homes, Phase II, in

  addition to funds previously

  appropriated..................................... 105,008

LINCOLN DEVELOPMENTAL CENTER - LOGAN

For various capital improvements,

  including planning and construction

  of four ten-bed transitional or

  residential homes.............................. 7,000,000

LUDEMAN DEVELOPMENTAL CENTER - PARK FOREST

For upgrading the electrical panel............... 1,202,840

For repairing and replacing furnaces and

  duct work, in addition to funds previously

  appropriated..................................... 500,000

For renovating residential and neighborhood

  homes, in addition to funds previously

  appropriated................................... 1,195,960

For replacing plumbing, HVAC and

  boiler systems................................... 742,685

For renovation of residential buildings,

  in addition to funds previously

  appropriated..................................... 648,823

For renovation of residences........................ 35,293

MABLEY DEVELOPMENTAL CENTER - DIXON

For replacing mechanicals and upgrading

  the fire alarm systems........................... 371,005

For planning and beginning renovation

  of residential buildings....................... 1,453,648

MADDEN MENTAL HEALTH CENTER - HINES

For planning and beginning facility

  improvements to provide for

  patient safety and suicide

  prevention........................................ 80,075

For renovating pavilions and

  administration building for safety/

  security, in addition to

  funds previously appropriated.................. 1,200,000

For renovating dietary............................. 858,550

For renovation of pavilions, in addition

  to funds previously appropriated................. 350,503

MURRAY DEVELOPMENTAL CENTER - CENTRALIA

For completing the renovation of

  the boiler house, in addition to

  funds previously appropriated.................. 3,400,000

For renovating the boiler house,

  in addition to funds previously

  appropriated..................................... 591,566

For replacing the emergency

  management system, in

  addition to funds previously

  appropriated..................................... 585,000

For planning and beginning boiler house

  renovation........................................ 38,060

For replacing energy management system.............. 43,151

SHAPIRO DEVELOPMENTAL CENTER - KANKAKEE

For replacing the sewer system in

  south campus................................... 2,112,880

For planning and beginning renovation

  of dietary....................................... 384,925

For work necessary to remedy fire

  damper deficiencies............................ 1,027,616

For replacing water mains and valves,

  in addition to funds previously

  appropriated..................................... 765,085

For replacing steam & condensate

  lines, in addition to funds previously

  appropriated..................................... 146,278

For upgrading HVAC systems in four

  residential buildings............................ 151,801

For planning and beginning the upgrade

  of steam and condensate lines..................... 98,347

SINGER MENTAL HEALTH CENTER - ROCKFORD

For upgrading fire alarm systems................... 648,684

For renovating dietary and stores.................. 833,103

For renovating patient units, Phase II,

  in addition to funds previously

  appropriated  ................................. 3,100,000

For renovating mechanicals and

  residential areas................................ 731,508

TINLEY PARK MENTAL HEALTH CENTER – COOK COUNTY

For completing the upgrade of fire

  and life/safety issues in Oak Hall,

  in addition to funds previously

  appropriated..................................... 600,000

TINLEY PARK MENTAL HEALTH CENTER/HOWE DEVELOPMENTAL CENTER

For renovation for accessibility in four

  buildings......................................... 74,856

TREATMENT AND DETENTION FACILITY - JOLIET

For improving the administration

  building for life safety......................... 160,000

STATEWIDE

For planning and beginning life

  safety/security systems........................ 1,500,000

For replacing roofing systems at

  the following locations, at the

  approximate costs set forth below.............. 2,526,737

   Chicago-Read Mental

    Health Center - Cook

    County........................... 2,026,737

   Fox Developmental

    Center - Dwight.................... 200,000

   Kiley Developmental Center -

    Waukegan........................... 300,000

For replacing and repairing roofing systems

 at the following locations, at the

 approximate cost set forth below................ 2,014,437

Alton Mental Health Center -

  Madison............................... 89,139

Shapiro Developmental Center -

  Kankakee............................. 115,000

Ludeman Developmental Center -

  Park Forest........................... 14,087

Madden Mental Health Center -

  Hines................................ 815,326

Murray Developmental Center -

  Centralia............................ 708,650

Kiley Developmental Center -

  Waukegan............................. 272,235

For replacing and repairing roofing

  systems at the following locations, at

  the approximate cost set forth below............. 934,403

   Chicago-Read Mental Health

    Center............................. 421,632

   Howe Developmental Center -

    Tinley Park........................ 283,758

   Shapiro Developmental Center -

    Kankakee............................ 42,393

   Illinois School for the

    Deaf - Jacksonville................. 69,661

   Kiley Developmental

    Center - Waukegan.................. 116,959

For repairing or replacing roofs

  at the following locations, at

  the approximate cost set forth below........... 1,440,761

   Illinois School for the

    Visually Impaired -

    Jacksonville........................ 38,369

   Jacksonville Developmental

    Center - Morgan County.............. 60,000

   Lincoln Developmental Center -

    Logan County......................... 7,001

   Murray Developmental Center -

    Centralia........................... 79,136

   Shapiro Developmental Center -

    Kankakee......................... 1,256,255

For planning and beginning construction

  of a facility for sexually violent

  persons.......................................... 250,381

For replacing and repairing roofing systems

  at the following locations at the approximate

  cost set forth below............................. 270,007

    Choate Developmental Center -

     Anna................................ 7,628

    Chicago-Read Mental Health Center.... 5,475

    Tinley Park Mental Health Center.... 12,974

    Illinois School for the Visually

     Impaired - Jacksonville............ 19,414

    Shapiro Developmental Center -

     Kankakee........................... 25,955

    Kiley Developmental Center -

     Waukegan........................... 19,284

    Ludeman Developmental Center -

     Park Forest....................... 179,277

For replacement of roofing systems at the

  following locations at the approximate costs

  set forth below:................................. 150,811

    Lincoln Development Center.......... 37,702

    Murray Developmental Center......... 37,703

    Elgin Developmental Center.......... 37,703

    Shapiro Developmental Center........ 37,703

    Total                                       $88,806,304

 

    Section 115.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 115 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Department of Human Services for the projects hereinafter enumerated:

ILLINOIS SCHOOL FOR THE VISUALLY IMPAIRED - JACKSONVILLE

(From Article 99, Section 115 of Public Act 93-0842)

For renovations to the powerhouse,

  boilers and associated coal and ash

  equipment For installation of individual

  package boilers.................................. 224,019

    Total                                          $224,019

 

    Section 120.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 120 of Public Act 93-0842, are reappropriated from the Tobacco Settlement Recovery Fund to the Capital Development Board for the Department of Human Services for the projects hereinafter enumerated:

STATEWIDE PROGRAM

(From Article 99, Section 120 of Public Act 93-0842)

For tuckpointing at the following locations

 at the approximate cost set forth below........... 171,772

  Howe Developmental Center -

   Tinley Park......................... 115,000

  Madden Mental Health

   Center - Hines....................... 43,661

  Tinley Park Mental

   Health Center........................ 13,111

For tuckpointing exterior and repairing

  masonry at various facilities.................... 394,844

    Total                                          $566,616

 

    Section 125.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 125 of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Department of Human Services for the project hereinafter enumerated:

ILLINOIS SCHOOL FOR THE DEAF – JACKSONVILLE

(From Article 99, Section 125 of Public Act 93-0842)

For replacing dorm doors......................... 1,962,500

JACKSONVILLE DEVELOPMENTAL CENTER – MORGAN

For upgrading the mechanicals in the

  power plant, in addition to funds

  previously appropriated....................... 1,000,000

SINGER MENTAL HEALTH CENTER

For repair and/or replacement of roofs.............. 71,994

TINLEY PARK MENTAL HEALTH CENTER

For upgrading fire/life safety systems

  and lighting, in addition to funds

  previously appropriated.......................... 281,942

FOX DEVELOPMENTAL CENTER - DWIGHT

For renovating the water treatment plant........... 884,788

    Total                                        $4,201,224

 

    Section 130.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriation and reappropriations heretofore made in Article 99, Section 130 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Illinois Medical District Commission for the projects hereinafter enumerated:

ILLINOIS MEDICAL DISTRICT COMMISSION - CHICAGO

(From Article 99, Section 130 of Public Act 93-0842)

For upgrading utility and infrastructure,

  in addition to funds previously

  appropriated..................................... 650,000

For upgrading core utilities....................... 211,806

For upgrading research center...................... 373,362

For constructing a Lab and Research

  Biotech Grad Facility............................. 94,638

    Total                                        $1,329,806

 

    Section 140.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 140 of Public Act 93-0842, as amended, are reappropriated from the Capital Development Fund to the Capital Development Board for the Department of Military Affairs for the projects hereinafter enumerated:

BLOOMINGTON ARMORY - McLEAN COUNTY

(From Article 99, Section 140 of Public Act 93-0842)

For rehabilitating the mechanical/electrical

  systems and renovating the interior............ 2,971,900

CAIRO ARMORY

For replacing roof and renovating the

  interior and exterior............................ 623,311

CAMP LINCOLN - SPRINGFIELD

For converting commissary to a military

  museum, in addition to funds

  previously appropriated.......................... 110,832

For construction of a military academy

  facility......................................... 541,339

ELGIN ARMORY - KANE COUNTY

For upgrading the interior and exterior............ 843,352

GENERAL JONES ARMORY

For rehabilitating the armory building,

  in addition to funds previously

  appropriated..................................... 140,401

LITCHFIELD ARMORY

For remodeling and installing a

  kitchen.......................................... 362,450

MACOMB ARMORY - McDONOUGH

For completing the mechanical/electrical

  systems upgrade, renovating the interior,

  and installing a kitchen, in addition to

  funds previously appropriated.................. 2,565,000

For replacing the mechanical and electrical

  systems and installing a kitchen................. 837,345

MATTOON ARMORY

For replacing the roof and renovating

  the interior and exterior........................ 467,035

NORTH RIVERSIDE ARMORY

For rehabilitating the interior and

  exterior......................................... 302,380

NORTHWEST ARMORY - CHICAGO

For upgrading the electrical system.............. 2,815,000

For replacing the mechanical systems............... 549,233

For renovation of interior and exterior,

  in addition to funds previously

  appropriated for such purposes................... 303,337

ROCK FALLS ARMORY

For replacing the mechanical and

  electrical systems and upgrading

  the interior..................................... 715,866

SALEM ARMORY

For remodeling and installing a

  kitchen.......................................... 279,780

SYCAMORE ARMORY

For replacing the electrical system,

  renovating the interior and installing

  air conditioning................................. 934,832

STATEWIDE

For replacing roofing systems, windows

  and doors, and rehabilitating the

  exterior walls at the following

  locations, at the approximate cost

  set forth below................................... 76,244

   Bloomington Armory................... 15,248

   Kewanee Armory....................... 15,249

   Macomb Armory........................ 15,249

   Rock Falls Armory.................... 15,249

   Sycamore Armory...................... 15,249

    Total                                       $15,439,637

 

    Section 145.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 99, Section 145, of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Department of Military Affairs for the projects hereinafter enumerated:

 

NORTHWEST ARMORY - CHICAGO

(From Article 99, Section 145 of Public Act 93-0842)

For renovating the mechanical systems,

  in addition to funds previously

  appropriated..................................... 351,715

LAWRENCEVILLE ARMORY

For rehabilitating the exterior and

  replacing roofing systems....................... 177,017

    Total                                          $528,732

 

    Section 150.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 150 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Department of Revenue for the projects hereinafter enumerated:

WILLARD ICE BUILDING - SPRINGFIELD

(From Article 99, Section 150 of Public Act 93-0842)

For completing the upgrade of

  building management controls,

  in addition to funds

  previously appropriated.......................... 400,000

For replacing the dock exhaust system.............. 555,000

For replacing and repairing concrete

  stairway and completing of parking

  deck, in addition to funds

  previously appropriated.......................... 285,000

For upgrading building management

  controls....................................... 3,496,768

For upgrading the plumbing system.................. 931,655

For upgrading parking lot/parking deck

  structural repair................................ 830,119

For renovating the interior and

  upgrading HVAC................................. 3,300,768

    Total                                        $9,799,310

 

    Section 155.  The following named amounts, or so much thereof as may be necessary and as remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 99, Section 155 of Public Act 93-0842, are reappropriated from the Tobacco Settlement Recovery Fund to the Capital Development Board for the Department of Revenue for the project hereinafter enumerated:

WILLARD ICE BUILDING - SPRINGFIELD

(From Article 99, Section 155 of Public Act 93-0842)

For completing security system upgrade, in

  addition to funds previously appropriated....... $110,394

    Total                                          $110,394

 

    Section 160.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 160 of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Department of Revenue for the project hereinafter enumerated:

WILLARD ICE BUILDING – SPRINGFIELD

(From Article 99, Section 160 of Public Act 93-0842)

For completing the upgrade of the

  Plumbing System.................................. 600,000

For planning the curtain wall renovation........... 38,950

    Total                                          $638,950

 

    Section 165.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 165 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Department of State Police for the projects hereinafter enumerated:

CHICAGO FORENSIC LABORATORY 

(From Article 99, Section 165 of Public Act 93-0842)

For construction of a laboratory and

  parking facilities................................ 84,737

DISTRICT 13 HEADQUARTERS - DuQUOIN

For constructing a district 13

  headquarters..................................... 132,840

DISTRICT 6 HEADQUARTERS - PONTIAC

For planning, construction, reconstruction,

  demolition of existing buildings, and

  all costs related to replacing

  the facilities................................... 196,259

SPRINGFIELD ARMORY

For planning and design of the rehabilitation

  and site improvements of the Springfield

  Armory, in addition to funds previously

  appropriated................................... 1,216,439

STATEWIDE

For replacing communications towers

  equipment and tower buildings.................. 1,850,902

For upgrading generators and UPS systems............ 39,996

For replacing roofing system at the

  following locations at the approximate

  cost set forth below............................. 297,191

   District 13 Headquarters,

     DuQuoin............................ 46,752

   Joliet Laboratory.................... 40,000

   District 6 Headquarters,

     Pontiac............................ 38,900

   District 9 Headquarters,

     Springfield....................... 109,510

   State Police Training Center,

     Pawnee............................. 10,000

   District 18 Headquarters,

     Litchfield......................... 45,000

   District 19 Headquarters,

     Carmi............................... 7,029

For replacing radio communication towers,

  equipment buildings and installing emergency

  power generators at the following locations at the approximate costs set forth below.................................. 1,109,792

  Harlem & Irving – Cook County......... 93,966

  Savanna – Carroll County.............. 95,000

  Fairfield – Wayne County............. 225,000

  Niota – Hancock County............... 695,826

  Pecatonica, Elwood, Kingston, Mason

  City........................................... 1,109,792

    Total                                        $4,928,156

 

    Section 170.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 170 of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Department of State Police for the project hereinafter enumerated:

SPRINGFIELD STATE POLICE, PAWNEE FACILITY

(From Article 99, Section 170 of Public Act 93-0842)

  For safety improvements at

   the firing range................................ 178,106

STATEWIDE

For upgrading firing range facilities.............. 375,233

    Total                                          $553,339

 

    Section 175.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 175 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Department of Veterans' Affairs for the projects hereinafter enumerated:

ANNA VETERANS HOME

(From Article 99, Section 175 of Public Act 93-0842)

For constructing a garage.......................... 315,292

LASALLE VETERANS' HOME

For replacing the roofing system................... 310,000

For replacing the domestic water system............ 110,000

MANTENO VETERANS' HOME - KANKAKEE COUNTY

For replacing air conditioner chillers........... 1,170,000

For replacing condensing units..................... 176,939

For upgrading or constructing

  roads and parking lots............................ 55,922

For planning and constructing

  additional storage and support areas.............. 95,233

For upgrading courtyard program spaces............. 346,362

For upgrading storm sewer........................... 99,428

QUINCY VETERANS' HOME - ADAMS COUNTY

For constructing a bus and ambulance

  garage........................................... 849,073

For improvements to various buildings

  and replacement of Fletcher Building

  to meet licensure standards.................... 2,528,743

    Total                                        $6,056,992

 

    Section 180.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 99, Section 180 of Public Act 93-0842, are reappropriated from the Tobacco Settlement Recovery Fund to the Capital Development Board for the Department of Veterans' Affairs for the projects hereinafter enumerated:

MANTENO VETERANS' HOME - KANKAKEE COUNTY

(From Article 99, Section 180 of Public Act 93-0842)

For installing humidifiers and

  dehumidifiers.................................... 407,950

For resurfacing roads and parking lots.............. 40,355

For demolishing buildings........................ 1,224,881

    Total                                        $1,673,186

 

    Section 185.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 185 of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Department of Veterans' Affairs for the project hereinafter enumerated:

MANTENO VETERANS HOME

(From Article 99, Section 185 of Public Act 93-0842)

For completing the upgrade of emergency

  generators....................................... 600,000

For installing humidifiers and

  dehumidifiers, in addition to funds

  previously appropriated....................... 1,000,000

LASALLE VETERANS HOME - LASALLE COUNTY

For planning expansion of facility  ..............  379,045

MANTENO VETERANS HOME - KANKAKEE COUNTY

For constructing an equipment storage

  building......................................... 667,966

    Total                                        $2,647,011

 

    Section 190.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 190 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the projects hereinafter enumerated:

EXECUTIVE MANSION - SPRINGFIELD

(From Article 99, Section 190 of Public Act 93-0842)

For building improvements.......................... 376,011

ATTORNEY GENERAL BUILDING - SPRINGFIELD

For planning an annex or addition and

  beginning construction of

  parking facilities................................ 35,932

For upgrading environmental equipment

  and HVAC, in addition to funds previously

  appropriated - Archives Building................. 255,609

STATE CAPITOL BUILDING

For upgrading the life/safety and

  security systems, in addition to

  funds previously appropriated.................... 161,784

STATEWIDE

For the purposes of capital planning

  and condition assessment and analysis

  of State capital facilities, to be

  expended only upon the direction of

  the Director of the Bureau of

  the Budget..................................... 3,389,055

For abating hazardous materials.................. 1,627,855

For retrofitting or upgrading mechanized

  refrigeration equipment (CFCs)................... 650,000

For surveys and modifications to buildings

  to meet requirements of the federal

  Americans with Disabilities Act (ADA)............ 593,405

For surveys and modifications to buildings

  to meet requirements of the federal

  Americans with Disabilities Act (ADA)............ 973,346

For abating hazardous materials.................... 135,878

For retrofitting or upgrading mechanized

  refrigeration equipment (CFCs)................. 4,000,000

For surveys and modifications to buildings

  to meet requirements of the federal

  Americans with Disabilities Act................ 2,717,127

For abating hazardous materials.................... 468,800

For retrofitting or upgrading mechanized

  refrigeration equipment (CFCs)................. 2,901,557

For upgrading and remediating

  aboveground and underground storage tanks...... 2,000,000

For surveys and modifications to buildings

  to meet requirements of the federal

  Americans With Disabilities Act.................. 101,945

For retrofitting or upgrading mechanized

  refrigeration equipment (CFCs)................... 782,922

For abating hazardous materials.................... 375,029

For surveys and modifications to

  buildings to meet requirements of the

  federal Americans with Disabilities Act.......... 153,701

For abatement of hazardous materials............... 320,187

For upgrading/retrofitting mechanized

  refrigeration equipment (CFCs).................... 53,118

For abatement of hazardous materials............... 146,234

For survey for and abatement of

  asbestos-containing materials..................... 59,592

For upgrade/retrofit of mechanized

  refrigeration equipment (CFCs).................... 36,346

For surveys and modifications to buildings

  to meet requirements of the federal

  Americans with Disabilities Act................ 1,256,572

For demolition of buildings......................... 82,050

For retrofitting/upgrading mechanical

  refrigeration equipment........................... 30,551

For the planning, upgrade

  and replacement of potentially

  hazardous underground storage tanks............... 64,692

For surveys and abatement of asbestos-

  containing materials.............................. 41,423

    Total                                       $22,961,385

 

    Section 195.  The amount of $530,819, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 195 of Public Act 93-0842, is reappropriated from the Asbestos Abatement Fund to the Capital Development Board for surveying and abating asbestos-containing materials statewide.

 

    Section 200.  The amount of $994,978, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 200 of Public Act 93-0842, is reappropriated from the Asbestos Abatement Fund to the Capital Development Board for asbestos surveys and emergency abatement in relation to asbestos abatement in state governmental buildings or higher education residential and auxiliary enterprise buildings.

 

    Section 205.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 99, Section 205 of Public Act 93-0842, are reappropriated from the Tobacco Settlement Recovery Fund to the Capital Development Board for the projects hereinafter enumerated:

STATEWIDE

(From Article 99, Section 205 of Public Act 93-0842)

Survey for and abate hazardous

  materials........................................ 710,011

For repairing minor problems and

  emergencies...................................... 985,117

For tuckpointing and repairing exterior

  of buildings..................................... 182,900

For demolition of buildings........................ 393,437

For archeological studies of

  construction sites............................... 100,000

For repairing minor problems and

  emergencies.................................... 1,180,186

    Total                                        $3,551,651

 

    Section 210.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 210 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Illinois Community College Board for the projects hereinafter enumerated:

CARL SANDBURG COLLEGE

(From Article 99, Section 210 of Public Act 93-0842)

For constructing a computer/

  student center.................................... 33,928

CITY COLLEGES OF CHICAGO

For various bondable capital improvements........ 8,116,582

CITY COLLEGES OF CHICAGO/KENNEDY KING

For remodeling for Workforce Preparation

  Centers........................................ 3,642,334

For remodeling for a culinary arts

  educational facility.......................... 10,875,000

CITY COLLEGES OF CHICAGO - MALCOLM X COLLEGE

For remodeling the Allied Health

  program facilities............................. 4,304,223

COLLEGE OF DUPAGE

For upgrading the Instructional Center

  heating, ventilating and air

  conditioning systems............................. 273,534

COLLEGE OF LAKE COUNTY

For planning and beginning construction

  of a technology building -

  Phase 1.......................................... 296,283

ILLINOIS VALLEY COMMUNITY COLLEGE

For planning, construction and renovations

  necessary to abate asbestos containing

  materials at campus facilities................. 1,062,277

JOHN A. LOGAN COMMUNITY COLLEGE - CARTERVILLE

For planning, construction, utilities,

  site improvements, equipment and other

  costs necessary for a new Workforce

  Development and Community Education

  Facility.  The provisions of Article V

  of the Public Community College Act

  are not applicable to this   appropriation........ 31,185

KANKAKEE COMMUNITY COLLEGE

For constructing a laboratory/classroom

  facility......................................... 628,881

LAKELAND COLLEGE

Student Services Building addition............... 6,602,331

LEWIS and CLARK COLLEGE - GODFREY

For constructing classroom

  and office building and additions,

  and remodeling of Haskell Hall.................... 27,425

LINCOLN LAND COMMUNITY COLLEGE - SPRINGFIELD

For constructing an addition and remodeling

  Sangamon and Menard Halls......................... 31,388

MCHENRY COUNTY COLLEGE

For constructing classrooms and a

  student services building and remodeling

  space, in addition to funds previously

  appropriated..................................... 572,723

MORAINE VALLEY COMMUNITY COLLEGE - PALOS HILLS

For constructing a classroom/administration

  building, providing site improvements and

  purchasing equipment, in addition to

  funds previously appropriated..................... 42,688

PRAIRIE STATE COLLEGE - CHICAGO HEIGHTS

For constructing an addition to the Adult

  Training/Outreach Center, in addition to

  funds previously appropriated.................. 2,236,307

RICHLAND COMMUNITY COLLEGE - DECATUR

For remodeling and constructing additions.......... 147,526

SOUTHWESTERN ILLINOIS COLLEGE

(Formerly BELLEVILLE AREA COLLEGE)

For renovating campus buildings and site

  improvements at the Belleville and Red

  Bud campuses...................................... 39,334

SOUTH SUBURBAN COLLEGE

For improving flood retention...................... 437,000

SPOON RIVER COLLEGE

For remodeling Engle Hall and

  constructing a maintenance building.............. 145,625

TRITON COMMUNITY COLLEGE - RIVER GROVE

For rehabilitating the Liberal Arts

  Building....................................... 1,553,487

For rehabilitating the potable water

  distribution system............................... 70,146

STATEWIDE

For the Illinois Community College Board

  miscellaneous capital improvements including

  construction, capital facilities, cost of

  planning, supplies, equipment, materials,

  services and all other expenses required to

  complete the work at the various community

  Colleges.  This appropriated amount shall be

  in addition to any other appropriated amounts

  which can be expended for this purpose......... 1,679,988

STATEWIDE

For miscellaneous capital improvements

  including construction, capital facilities,

  cost of planning, supplies, equipment,

  materials, services and all other expenses

  required to complete the work at the

  various community colleges.  This appropriated

  amount shall be in addition to any other

  appropriated amounts which can be

  expended for these purposes.................... 5,139,784

For miscellaneous capital improvements

  including construction, capital facilities,

  cost of planning, supplies, equipment,

  materials, services and all other expenses

  required to complete the work at the

  various community colleges.  This appropriated

  amount shall be in addition to any other

  appropriated amounts which can be

  expended for these purposes.................... 4,007,063

STATEWIDE - CONSTRUCTION DEFECTS

For planning, construction and renovation

  to correct defectively designed or

  constructed community college facilities,

  provided that monies recovered based upon

  claims arising out of such defective design

  or construction shall be paid to the state

  as required by Section 105.12 of the Public

  Community College Act as reimbursement for

  monies expended pursuant to this

  appropriation.................................... 395,324

    Total                                       $52,392,366

 

    Section 220.  The amount of $431,062, or so much thereof as may be necessary, and remains unexpended on June 30, 2005, from a reappropriation heretofore made for such purposes in Article 99, Section 220 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Illinois Community College Board for grants to community colleges repair, renovation, and miscellaneous capital improvements including construction, reconstruction, remodeling, improvement, repair and installation of capital facilities, costs of planning, supplies, equipment, materials, services, and all other expenses required to complete the work.  This appropriation shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 225.  The sum of $1,471,018, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 99, Section 225 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Capital Development Board for the Illinois Community College Board for miscellaneous capital improvements including construction, capital facilities, cost of planning, supplies, equipment, materials, services and all other expenses required to complete the work at the various community colleges.  This appropriation shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 230.  The sum of $1,801,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purposes in Article 99, Section 230 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Capital Development Board for the Illinois Community College Board for miscellaneous capital improvements including construction, reconstruction, remodeling, improvement, repair and installation of capital facilities, cost of planning, supplies, equipment, materials, services and all other expenses required to complete the work at the various community colleges.  This appropriation shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 235.  The sum of $2,594,875, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purposes in Article 99, Section 235 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Capital Development Board for the Illinois Community College Board for miscellaneous capital improvements including construction, reconstruction, remodeling, improvement, repair and installation of capital facilities, cost of planning, supplies, equipment, materials, services and all other expenses required to complete the work at the various community colleges.  This appropriation shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 240.  The sum of $696,475, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purposes in Article 99, Section 240 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Capital Development Board for the Illinois Community College Board for grants to community colleges for miscellaneous capital improvements including construction, reconstruction, remodeling, improvements, repair and installation of capital facilities, cost of planning, supplies, equipment, materials, services, and all other expenses required to complete the work. This appropriation shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 245.  The sum of $3,009,481, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 99, Section 245 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Capital Development Board for miscellaneous capital improvements at various educational facilities statewide, in addition to funds previously appropriated.

 

    Section 250.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 250 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Board of Higher Education for the projects hereinafter enumerated:

ILLINOIS MATHEMATICS AND SCIENCE ACADEMY - AURORA

To plan and begin construction of a

  space for the delivery of teacher

  training and development and student

  enrichment programs.............................. 108,843

 

    Section 255.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 99, Section 255 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Illinois Board of Higher Education for the projects hereinafter enumerated:

STATEWIDE

(From Article 99, Section 255 of Public Act 93-0842)

For miscellaneous capital improvements

  including construction, capital facilities,

  cost of planning, supplies, equipment,

  materials, services and all other expenses

  required to complete the work at the various

  universities.  This appropriated amount

  shall be in addition to any other appropriated

  amounts which can be expended for these

  purposes...................................... 19,716,312

   Chicago State University............ 322,100

   Eastern Illinois University......... 515,500

   Governors State University.......... 189,700

   Illinois State University......... 1,021,300

   Northeastern Illinois University.... 383,700

   Northern Illinois University...... 1,159,000

   Western Illinois University......... 792,200

   Southern Illinois University -

    Carbondale....................... 1,520,564

   Southern Illinois University -

    Edwardsville....................... 763,100

   University of Illinois -

    Chicago.......................... 2,777,300

   University of Illinois -

    Springfield........................ 229,100

   University of Illinois -

    Urbana/Champaign................. 4,131,963

   Illinois Community

    College Board.................... 5,910,785

For miscellaneous capital improvements

  including construction, capital

  facilities, cost of planning, supplies,

  equipment, materials, services and

  all other expenses required to complete

  the work at the various universities

  This appropriated amount shall be in

  addition to any other appropriated amounts

  which can be expended for these purposes...... 18,829,241

   Chicago State University............ 322,100

   Eastern Illinois University......... 515,500

   Governors State University.......... 132,852

   Illinois State University......... 1,021,300

   Northeastern Illinois

    University......................... 383,700

   Northern Illinois University...... 1,159,000

   Western Illinois University......... 792,200

   Southern Illinois University -

    Carbondale......................... 522,333

   Southern Illinois University -

    Edwardsville....................... 763,100

   University of Illinois -

    Chicago.......................... 2,777,300

   University of Illinois -

    Springfield........................ 217,856

   University of Illinois -

    Urbana/Champaign................. 4,150,300

   Illinois Community

    College Board.................... 6,071,700

For miscellaneous capital improvements

  including construction, capital

  facilities, cost of planning, supplies,

  equipment, materials, services and

  all other expenses required to complete

  the work at the various universities

  This appropriated amount shall be in

  addition to any other appropriated amounts

  which can be expended for these purposes....... 6,481,377

   Chicago State University............ 211,574

   Eastern Illinois University......... 515,500

   Illinois State University........... 506,274

   Northern Illinois University...... 1,159,000

   Western Illinois University......... 596,046

   Southern Illinois University -

    Carbondale......................... 180,242

   University of Illinois -

    Chicago.......................... 2,199,079

   University of Illinois -

    Springfield........................ 209,126

   University of Illinois -

    Urbana/Champaign................... 904,536

For miscellaneous capital improvements,

  including construction, capital

  facilities, cost of planning,

  supplies, equipment, materials, services

  and all other expenses required to

  complete the work at the various universities.

  This appropriated amount shall be in

  addition to any other appropriated

  amounts which can be expended

  for these purposes............................. 4,194,758

   Eastern Illinois University......... 477,768

   Illinois State University........... 413,841

   Northeastern Illinois

    University.......................... 46,499

   Northern Illinois University...... 1,217,700

   Western Illinois University......... 198,034

   Southern Illinois University -

    Carbondale......................... 103,987

   University of Illinois -

    Chicago............................ 506,116

   University of Illinois -

    Urbana/Champaign................. 1,230,813

For miscellaneous capital improvements

  including construction, reconstruction

  remodeling, improvements, repair

  and installation of capital

  facilities, cost of planning, supplies,

  equipment, materials, services and all

  other expenses required to complete

  the work at the various universities set

  forth below.  This appropriated amount

  shall be in addition to any other

  appropriated amounts which can

  be expended for these purposes................. 2,341,715

  Chicago State University............. 191,127

  Eastern Illinois University........... 42,140

  Illinois State University............. 85,627

  Northeastern Illinois University..... 151,480

  Northern Illinois University......... 861,486

  Western Illinois University........... 53,892

  Southern Illinois University -

   Carbondale............................ 9,130

  University of Illinois -

   Chicago Campus....................... 41,721

  University of Illinois -

   Champaign/Urbana Campus............. 905,112

For miscellaneous capital improvements

  including construction, capital

  facilities, cost of planning, supplies,

  equipment, materials, services and

 all other expenses required to

  complete the work at the various

  universities set forth below.  This

  appropriation shall be in addition

  to any other appropriated amounts

  which can be expended for these purposes....... 1,419,262

For Eastern Illinois University........ 261,412

For Northeastern Illinois University .. 143,597

For Northern Illinois University....... 248,136

For Western Illinois University......... 39,423

For University of Illinois –

  Chicago.............................. 91,348

For University of Illinois -

  Urbana-Champaign..................... 635,346

For miscellaneous capital improvements,

  including construction, reconstruction,

  remodeling, improvement, repair and

  installation of capital facilities, cost of

  planning, supplies, equipment, materials,

  services and all other expenses

  required to complete the work at the various

  universities set forth below.  This

  appropriation shall be in addition to

  any other appropriated amounts which

  can be expended for these purposes............... 707,360

  For Northern Illinois University..... 153,202

  For Southern Illinois University -

   Carbondale........................... 22,188

  For Southern Illinois University -

   Edwardsville......................... 35,137

  For University of Illinois -

   Chicago............................. 362,299

  For University of Illinois -

   Urbana-Champaign.................... 134,534

For miscellaneous capital improvements

  including construction, reconstruction,

  remodeling, improvement, repair and

  installation of capital facilities,

  cost of planning, supplies, equipment,

  materials, services and all other expenses

  required to complete the work at the

  various universities set forth below.

  This appropriation shall be in addition

  to any other appropriated amounts which

  can be expended for these purposes............... 813,375

  For Chicago State University.......... 37,159

  For Eastern Illinois University...... 150,380

  For Governors State University........ 71,798

  For Illinois State University......... 85,165

  For Northeastern Illinois University . 36,177

  For Northern Illinois University..... 207,446

  For University of Illinois........... 225,250

SOUTHERN ILLINOIS UNIVERSITY

For Southern Illinois University

  for miscellaneous capital improvements

  including construction, reconstruction,

  remodeling, improvements, repair and

  installation of capital facilities, cost

  of planning, supplies, equipment, materials

  services and all other expenses

  required to complete the work.  This

  appropriation shall be in addition to any

  other appropriated amounts which can

  be expended for these purposes................... 121,599

UNIVERSITY OF ILLINOIS

For the Board of Trustees of the University of

  Illinois for miscellaneous capital

  improvements including construction,

  reconstruction, remodeling, improvement,

  repair and installation of capital

  facilities, cost of planning, supplies,

  equipment, materials, services and

  all other expenses required for completing

  the work at the colleges and

  universities.  This appropriation shall

  be in addition to any other

  appropriated amounts which can be

  expended for these purposes....................... 89,723

For the Board of Higher Education for

  miscellaneous capital improvements,

  including construction, reconstruction,

  remodeling, improvements, repair and

  installation of capital facilities, cost

  of planning, supplies, equipment,

  materials, services, and all other

  expenses required to complete the

  work at the colleges and universities

  hereinafter enumerated.  This appropriation

  shall be in addition to any other

  appropriated amounts which can be

  expended for these purposes:

Northern Illinois University........................ 24,118

 

    Section 260.  The sum of $145,472, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purposes in Article 99, Section 260 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Capital Development Board for the Board of Higher Education for miscellaneous capital improvements, including construction, reconstruction, remodeling, improvement, repair and installation of capital facilities, cost of planning, supplies, equipment, materials, services and all other expenses required for completing the work at the colleges and universities.  This appropriation shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 265.  The following named amounts, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 265 of Public Act 93-0842, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Illinois Board of Higher Education for the projects hereinafter enumerated:

(From Article 99, Section 265 of Public Act 93-0842)

For miscellaneous capital improvements

  including construction, capital

  facilities, cost of planning, supplies,

  equipment, materials, services and

  all other expenses required to complete

  the work at the various universities.

  This appropriated amount shall be in

  addition to any other appropriated amounts

  which can be expended for these purposes.

Chicago State University........................... 150,676

Eastern Illinois University........................ 257,800

Governors State University.......................... 94,900

Illinois State University.......................... 510,700

Northeastern Illinois

  University....................................... 191,800

Northern Illinois University....................... 579,500

Western Illinois University........................ 396,100

Southern Illinois University - Carbondale.......... 704,001

Southern Illinois University - Edwardsville ....... 381,500

University of Illinois - Chicago................. 1,388,600

University of Illinois - Springfield............... 114,600

University of Illinois - Urbana/Champaign........ 2,075,100

Illinois Community College Board................. 2,899,808

    Total                                        $9,745,085

For miscellaneous capital improvements

  including construction, capital

  facilities, cost of planning, supplies,

  equipment, materials, services and

  all other expenses required to complete

  the work at the various universities.

  This appropriated amount shall be in

  addition to any other appropriated amounts

  which can be expended for these purposes.

Chicago State University.......................... 161,000

Eastern Illinois University........................ 256,301

Governors State University.......................... 94,900

Illinois State University.......................... 510,700

Northeastern Illinois University................... 191,800

Northern Illinois University....................... 579,500

Western Illinois University........................ 396,100

Southern Illinois University - Carbondale.......... 266,056

Southern Illinois University - Edwardsville........ 366,202

University of Illinois - Chicago................. 1,388,600

University of Illinois - Springfield............... 114,600

University of Illinois - Urbana/Champaign........ 2,075,100

Illinois Community College Board................. 2,943,540

    Total                                        $9,344,399

For miscellaneous capital improvements

  including construction, capital

  facilities, cost of planning, supplies,

  equipment, materials, services and

  all other expenses required to complete

  the work at the various universities.

  This appropriated amount shall be in

  addition to any other appropriated amounts

  which can be expended for these purposes.

Chicago State University.......................... 160,400

Eastern Illinois University........................ 185,800

Governors State University.......................... 45,618

Illinois State University........................... 57,613

Northeastern Illinois University.................... 17,303

Northern Illinois University....................... 579,500

Western Illinois University......................... 75,413

Southern Illinois University - Carbondale........... 88,789

University of Illinois - Chicago................. 1,156,733

University of Illinois - Springfield................ 78,866

University of Illinois - Urbana/Champaign........ 1,579,289

    Total                                        $4,025,324

For miscellaneous capital improvements

  including construction, capital

  facilities, cost of planning, supplies,

  equipment, materials, services and

  all other expenses required to complete

  the work at the various universities.

  This appropriated amount shall be in

  addition to any other appropriated amounts

  which can be expended for these purposes.

Eastern Illinois University......................... 96,014

Governors State University.......................... 26,826

Illinois State University.......................... 237,820

Northeastern Illinois University.................... 87,701

Northern Illinois University....................... 624,700

Western Illinois University......................... 11,275

University of Illinois - Chicago................... 176,727

University of Illinois - Springfield................ 30,052

University of Illinois - Urbana/Champaign.......... 268,540

    Total                                        $1,559,655

For miscellaneous capital improvements

  including construction, capital

  facilities, cost of planning, supplies,

  equipment, materials, services and

  all other expenses required to complete

  the work at the various universities.

  This appropriated amount shall be in

  addition to any other appropriated amounts

  which can be expended for these purposes.

Chicago State University............................ 92,223

Eastern Illinois University........................ 134,474

Illinois State University........................... 11,254

Northeastern Illinois University.................... 74,725

Northern Illinois University....................... 340,000

Western Illinois University......................... 38,564

University of Illinois- Champaign/Urbana............ 65,946

    Total                                          $757,186

 

    Section 270.  The sum of $2,285,308, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 270 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Illinois Community College Board for miscellaneous capital improvements including construction, capital facilities, cost of planning, supplies, equipment, materials, services and all other expenses required to complete the work at the various community colleges. This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 275.  The sum of $1,444,090, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 275 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Illinois Community College Board for miscellaneous capital improvements including construction, capital facilities, cost of planning, supplies, equipment, materials, services and all other expenses required to complete the work at the various community colleges. This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 280.  The following named amounts, or so much thereof as may be necessary and remain unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 99, Section 280 of Public Act 93-0842, are reappropriated from the Capital Development Fund to the Capital Development Board for the Illinois Board of Higher Education for the projects hereinafter enumerated:

CHICAGO STATE UNIVERSITY

(From Article 99, Section 280 of Public Act 93-0842)

For replacing primary electrical

  feeder cable..................................... 978,753

For roof replacement projects.................... 4,286,667

For the construction of a conference

  center......................................... 5,000,000

For the construction of a day care

  facility....................................... 4,927,811

For the construction of a student

  financial outreach building.................... 5,000,000

For constructing a new library facility,

  site improvements, utilities, and

  purchasing equipment, in addition

  to funds previously appropriated.............. 10,375,477

For technology improvements and

  deferred maintenance........................... 1,790,400

For remodeling Building K, in addition

  to funds previously appropriated............... 8,769,881

For planning and beginning to remodel

  Building K and improving site.................. 1,005,474

For planning, site improvements, utilities,

  construction, equipment and other costs

  necessary for a new library facility........... 3,272,481

For a grant to Chicago State University for

  all costs associated with construction of

  a Convocation Center........................... 8,146,687

For upgrading campus infrastructure,

  in addition to the funds

  previously appropriated.......................... 589,681

For renovating buildings and upgrading

  mechanical systems............................... 456,091

EASTERN ILLINOIS UNIVERSITY

For upgrading the electrical

  distribution system............................ 4,145,823

For renovating and expanding the

  Fine Arts Center, in addition to

  funds previously appropriated................. 39,702,200

For planning and beginning to renovate

  and expand the Fine Arts Center -

  Phase 1, in addition to funds

  previously appropriated........................ 1,471,247

For planning and beginning to renovate

  and expand the Fine Arts Center................ 1,824,490

For upgrading campus buildings for health,

  safety and environmental improvements............ 386,432

GOVERNORS STATE UNIVERSITY

For constructing addition and

  remodeling the teaching & learning

  complex, in addition to funds

  previously appropriated....................... 14,665,099

For costs associated with establishing

  a campus-wide fire alarm system at

  Governor's State University...................... 680,870

For constructing a child development center

  and an addition to the main building

  and remodeling Wings E and F...................... 88,290

ILLINOIS STATE UNIVERSITY

For renovating Stevenson and Turner

  Halls for life/safety......................... 22,092,850

For the upgrade and remodeling

  of Schroeder Hall.............................. 8,663,848

For planning and beginning to rehabilitate

  Schroeder Hall................................... 185,319

For planning, site improvements, utilities,

  construction, equipment and other costs

  necessary for a new facility for the

  College of Business.............................. 735,054

For remodeling Julian and Moulton Halls............ 510,501

NORTHEASTERN ILLINOIS UNIVERSITY

For renovating Building "C" and

  remodeling and expanding Building "E"

  and Building "F"............................... 6,586,254

For planning and beginning to remodel

  Buildings A, B and E........................... 3,666,246

For remodeling in the Science Building

  to upgrade heating, ventilating and air

  conditioning systems........................... 2,021,400

For replacing fire alarm systems, lighting

  and ceilings..................................... 672,525

NORTHERN ILLINOIS UNIVERSITY

For renovating the Founders Library

  basement, in addition to funds previously

  appropriated..................................... 669,635

For planning a classroom building and

  developing site in Hoffman Estates............. 1,314,500

For completing the construction of the

  Engineering Building, in addition to

  amounts previously appropriated for

  such purpose................................... 3,638,856

For renovating Altgeld Hall and

  purchasing equipment........................... 1,327,625

For upgrading storm waterway controls in

  addition to funds previously appropriated........ 424,233

SOUTHERN ILLINOIS UNIVERSITY

For planning, construction and equipment

  for a cancer center........................... 13,162,762

SOUTHERN ILLINOIS UNIVERSITY - CARBONDALE

For renovating and constructing an

  addition to the Morris Library, in

  addition to funds previously

  appropriated.................................. 25,690,000

For planning a renovation and

  addition to the Morris Library................... 714,077

For renovating Altgeld Hall and Old

  Baptist Foundation, in addition to funds

  previously appropriated........................... 60,861

SOUTHERN ILLINOIS UNIVERSITY - EDWARDSVILLE

For planning, construction and equipment

  for an advanced technical worker

  training facility................................ 482,034

For replacement of the high temperature water

  distribution system.............................. 168,709

SIU SCHOOL OF MEDICINE - SPRINGFIELD

For constructing and for equipment for

  an addition to the combined laboratory,

  in addition to funds previously

  appropriated..................................... 865,835

UNIVERSITY OF ILLINOIS AT CHICAGO

Plan, construct, and equip the Chemical

  Sciences Building............................. 57,600,000

For planning, construction and equipment

  for a chemical sciences building............... 4,934,349

To plan and begin construction of

  a medical imaging research/clinical

  facility....................................... 2,197,561

For remodeling the Clinical

  Sciences Building................................ 884,715

For the renovation of the court area and

  Lecture Center, in addition to funds

  previously appropriated.......................... 237,122

UNIVERSITY OF ILLINOIS AT CHAMPAIGN-URBANA

For planning, analysis and design

  of Lincoln Hall.  Design cannot proceed

  beyond Program Analysis/Preliminary

  Design unless approved in writing by

  the Governor................................... 2,000,000

Expansion of Microelectronics Lab............... 17,151,200

For planning, construction and equipment

  for a biotechnology genomic facility.......... 55,887,983

For planning, construction and equipment

  for a supercomputing application facility...... 8,832,152

To plan and begin construction of a

  biotechnology/genomic facility................. 1,600,780

To plan and begin construction of a

  supercomputing application

  facility......................................... 432,842

To plan and begin construction of a

  technology transfer incubator

  facility.......................................... 58,263

For remodeling the Mechanical Engineering

  Laboratory Building............................... 36,644

For initiating a campus flood

  control project................................... 60,806

UNIVERSITY CENTER OF LAKE COUNTY

For constructing a university center and

  purchasing equipment, in addition to

  funds previously appropriated.................. 3,494,909

For land, planning, remodeling, construction

  and all costs necessary to construct a

  facility....................................... 8,574,716

WESTERN ILLINOIS UNIVERSITY - MACOMB

Plan and construct performing arts center........ 4,000,000

For improvements to Memorial

  Hall.......................................... 11,889,325

 

    Section 285.  The following named amount, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 99, Section 285 of Public Act 93-0842 is reappropriated from the Capital Development Fund to the Capital Development Board for Southern Illinois University School of Medicine, Springfield, for the project hereinafter enumerated:

SOUTHERN ILLINOIS UNIVERSITY SCHOOL

OF MEDICINE – SPRINGFIELD

(From Article 99, Section 285 of Public Act 93-0842)

  For construction and equipment

   for an addition to the combined

   laboratory for Illinois State Police

   Crime Lab..................................... 1,738,475

 

    Section 290.  The following named amounts, or so much thereof as may be necessary, and remain unexpended on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 290 of Public Act 93-0842, as amended, are reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Board of Higher Education for the projects hereinafter enumerated:

NORTHERN ILLINOIS UNIVERSITY - DEKALB

(From Article 99, Section 290 of Public Act 93-0842)

To construct and equip the Engineering

  Building.......................................... 30,308

To purchase equipment and complete

  construction for Faraday Hall Addition............ 93,085

 

    Section 295.  The following named amount, or so much thereof as may be necessary, and remains unexpended on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 99, Section 295 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the University of Illinois for the projects hereinafter enumerated:

UNIVERSITY OF ILLINOIS URBANA-CHAMPAIGN

(From Article 99, Section 295 of Public Act 93-0842)

To construct and equip the Chemical and Life

  Sciences Building................................. 41,746

 

    Section 300.  The following named amount, or so much thereof as may be necessary, and remains unexpended on June 30, 2005, from reappropriations heretofore made for such purposes in Article 99, Section 300 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Board of Higher Education for the projects hereinafter enumerated:

NORTHERN ILLINOIS UNIVERSITY - DE KALB

(From Article 99, Section 300 of Public Act 93-0842)

For construction of the Engineering Building

  including extension of utilities, in

  addition to funds previously appropriated

  for such purpose.................................. 39,614

 

    Section 305.  The amount of $73,780, or so much thereof as may be necessary, and remains unexpended on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 99, Section 305 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the University of Illinois for miscellaneous capital improvements including construction, reconstruction, remodeling, improvement, repair and installation of capital facilities, costs of planning, supplies, equipment, materials, services, and all other expenses required to complete the work.  This appropriation shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 310.  The sum of $22,390, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purposes in Article 99, Section 310 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Capital Development Board for the Board of Trustees of the University of Illinois (formerly for the Department of Human Services) for renovation of the School of Public Health and Psychiatric Institute (formerly the ISPI building).

 

    Section 315.  The sum of $1,500,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 315 Public Act 93-0842, is reappropriated from the Tobacco Settlement Recovery Fund to the Capital Development Board for a grant to the University of Illinois College of Medicine at Peoria for planning a Clinical and Basic Research Oncology Center.

 

    Section 320.  The following named amount, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 320 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Capital Development Board for the project hereinafter enumerated:

EAST ST. LOUIS COLLEGE CENTER

(From Article 99, Section 320 of Public Act 93-0842)

For construction of facilities, remodeling,

  site improvements, utilities and other

  costs necessary for adapting the former

  campus of Metropolitan Community College

  for a Community College Center and Southern

  Illinois University, in addition to funds

  previously appropriated........................ 3,986,581

 

    Section 325.  The following named amount or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 99, Section 325 of Public Act 93-0842, is reappropriated from the School Construction Fund to the Capital Development Board for the State Board of Education for the projects hereinafter enumerated:

STATEWIDE

(From Article 99, Section 325 of Public Act 93-0842)

Grants for facility construction............... 185,039,757

 

    Section 330.  The sum of $119,133,286, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 330 of Public Act 93-0842, is reappropriated from the School Construction Fund to the Capital Development Board for school construction grants pursuant to the School Construction Law, in addition to amounts previously appropriated for such purposes.

 

    Section 335.  The sum of $26,121,120, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 335 Public Act 93-0842, is reappropriated from the School Construction Fund to the Capital Development Board for school construction grants pursuant to the School Construction Law, in addition to amounts previously appropriated for such purposes.

 

    Section 340.  The sum of $38,356,618, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 340 of Public Act 93-0842, is reappropriated from the School Construction Fund to the Capital Development Board for school construction grants pursuant to the School Construction Law, in addition to amounts previously appropriated for such purposes.

 

    Section 345.  The sum of $6,602,038, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 345 of Public Act 93-0842, is reappropriated from the School Construction Fund to the Capital Development Board for school construction grants pursuant to the School Construction Law, in addition to amounts previously appropriated for such purposes.

 

    Section 350.  The sum of $456,208, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purposes in Article 99, Section 350 of Public Act 93-0842, is reappropriated from the School Construction Fund to the Capital Development Board for school construction grants pursuant to the School Construction Law.

 

    Section 360.  The amount of $11,618,001 or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 360 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Capital Development Board for grants to units of local government and other eligible entities for all costs associated with land acquisition, construction and rehabilitation projects.

 

    Section 365.  The sum of $50,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 365 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Illinois Community College Board for miscellaneous capital improvements including construction, capital facilities, cost of planning, supplies, equipment, materials and all other expenses required to complete the work at the various community colleges.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 370.  The sum of $42,293,889, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 370 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Illinois Community College Board for miscellaneous capital improvements including construction, capital facilities, cost of planning, supplies, equipment, materials and all other expenses required to complete the work at the various community colleges.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 380.  The sum of $17,606,687, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 380 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for the Illinois Community College Board for miscellaneous capital improvements including construction, capital facilities, cost of planning, supplies, equipment, materials and all other expenses required to complete the work at the various community colleges.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 385.  The sum of $5,500,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 385 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for a grant to Northwestern University for planning and construction of a Bio-Medical Research Facility.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 390.  The sum of $3,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 390 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for a grant to Northwestern University for planning, construction, and equipment for a Nanofabrication and Molecular Center.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

    Section 410.  The amount of $1,100,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 99, Section 410 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for a grant to Northwestern University for planning, construction and equipment for a nanofabrication and molecular center.

 

    Section 415.  The sum of $58,584, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 99, Section 415 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Capital Development Board for miscellaneous capital improvements to state facilities including construction, reconstruction, remodeling, improvement, repair and installation of capital facilities, cost of planning, supplies, equipment, materials, services and all other expenses required to complete the work at the facilities.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

Total, Article 11                            $2,235,126,843

 

ARTICLE 12

ILLINOIS COMMERCE COMMISSION

 

    Section 5.  The sum of $430,753, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 100, Section 5 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Illinois Commerce Commission for train whistle abatement in counties with over 3,000,000 in population, where a public highway crosses a railroad at grade.

 

Total, Article 12                                  $430,753

 

ARTICLE 13

ENVIRONMENTAL PROTECTION AGENCY

 

    Section 5.  The sum of $19,000,000, or so much thereof as may be necessary, is appropriated from the Anti-Pollution Fund to the Environmental Protection Agency for deposit into the Water Revolving Fund.

 

    Section 7.  The sum of $19,000,000, or so much thereof as may be necessary, is appropriated from the Build Illinois Bond Fund to the Environmental Protection Agency for grants and contracts for site remediations, including the Lake Calumet area, in accordance with Section 22.2 and Title XVII of the Environmental Protection Act.

 

    Section 10.  The sum of $8,942,400, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 101, Section 10 of Public Act 93-842, as amended, is reappropriated from the Anti-Pollution Fund to the Environmental Protection Agency for deposit into the Water Revolving Fund.

 

    Section 15.  The sum of $6,657,600, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made for such purpose in Article 101, Section 15 of Public Act 93-0842, as amended, is reappropriated from the Anti-Pollution Fund to the Environmental Protection Agency for deposit into the Water Revolving Fund.

 

    Section 20.  The sum of $5,848,400, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 101, Section 20 of Public Act 93-0842, as amended, is reappropriated from the Anti-Pollution Fund to the Environmental Protection Agency for grants to units of local government for wastewater facilities, pursuant to provisions of the "Anti-Pollution Bond Act."

 

    Section 25.  The amount of $69,056,000, or so much thereof as may be necessary and remains unexpended on June 30, 2005, from reappropriations heretofore made for such purposes in Article 101, Section 25 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund to the Environmental Protection Agency for wastewater compliance grants to units of local government or sewer systems and wastewater treatment facilities pursuant to procedures and rules established under the Anti-Pollution Bond Act.  These grants are limited to projects for which the local government provides at least 30% of the project cost.  There is an approved project compliance plan, and there is an enforceable compliance schedule prior to the grant award.  The grant award will be based on eligible project cost contained in the approved compliance plan.

 

    Section 30.  The sum of $2,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 101, Section 30 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Environmental Protection Agency for deposit into the Brownfields Redevelopment Fund for use pursuant to Sections 58.13 and 58.15 of the Environmental Protection Act.

 

    Section 35.  The sum of $2,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 101, Section 35 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Environmental Protection Agency for deposit into the Brownfields Redevelopment Fund for use pursuant to Sections 58.13 and 58.15 of the Environmental Protection Act.

 

    Section 40.  The sum of $10,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 101, Section 40 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Environmental Protection Agency for deposit into the Hazardous Waste Fund for use pursuant to Section 22.2 of the Environmental Protection Act.

 

    Section 45.  The sum of $1,082,400, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 101, Section 45 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Environmental Protection Agency for grants and contracts for public drinking water infrastructure, including design and construction, where private drinking water wells have been contaminated by a hazardous substance.

 

    Section 50.  The sum of $180,000,000, or so much thereof as may be necessary, is appropriated from the Water Revolving Fund to the Environmental Protection Agency for financial assistance to units of local government for sewer systems and wastewater treatment facilities pursuant to rules defining the Water Pollution Control Revolving Loan program and for transfer of funds to establish reserve accounts, construction accounts or any other necessary funds or accounts in order to implement a leveraged loan program.

 

    Section 55.  The sum of $133,000,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made in Article 24, Section 200 of Public Act 93-842, as amended, is reappropriated from the Water Revolving Fund to the Environmental Protection Agency for financial assistance to units of local government for sewer systems and wastewater treatment facilities pursuant to rules defining the Water Pollution Control Revolving Loan program and for transfer of funds to establish reserve accounts, construction accounts or any other necessary funds or accounts in order to implement a leveraged loan program.

 

    Section 60.  The sum of $249,859,400, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 24, Section 200 of Public Act 93-842, as amended, is reappropriated from the Water Revolving Fund to the Environmental Protection Agency for financial assistance to units of local government for sewer systems and wastewater treatment facilities pursuant to rules defining the Water Pollution Control Revolving Loan program and for transfer of funds to establish reserve accounts, construction accounts or any other necessary funds or accounts in order to implement a leveraged loan program.

 

    Section 65.  The sum of $63,000,000, or so much thereof as may be necessary, is appropriated from the Water Revolving Fund to the Environmental Protection Agency for financial assistance to units of local government and privately owned community water supplies for drinking water infrastructure projects pursuant to the Safe Drinking Water Act, as amended, and for transfer of funds to establish reserve accounts, construction accounts or any other necessary funds or accounts in order to implement a leveraged program.

 

    Section 70.  The sum of $43,000,000, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made in Article 24, Section 205 of Public Act 93-842, as amended, is reappropriated from the Water Revolving Fund to the Environmental Protection Agency for financial assistance to units of local government and privately owned community water supplies for drinking water infrastructure projects pursuant to the Safe Drinking Water Act, as amended, and for transfer of funds to establish reserve accounts, construction accounts or any other necessary funds or accounts in order to implement a leveraged loan program.

 

    Section 75.  The sum of $133,016,400, or so much thereof as may be necessary and as remains unexpended at the close of business on June 30, 2005, from reappropriations heretofore made in Article 24, Section 205 of Public Act 93-842, as amended, is reappropriated from the Water Revolving Fund to the Environmental Protection Agency for financial assistance to units of local government and privately owned community water supplies for drinking water infrastructure projects pursuant to the Safe Drinking Water Act, as amended, and for transfer of funds to establish reserve accounts, construction accounts or any other necessary funds or accounts in order to implement a leveraged loan program.

 

Total, Article 13                              $945,462,600

 

ARTICLE 14

HISTORIC PRESERVATION AGENCY

 

    Section 5.  The sum of $1,000,000, or so much thereof as may be necessary, and as remains unexpended at the close of business on June 30, 2005, from appropriations heretofore made in Article 102, Section 5 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Historic Preservation Agency for a grant to the Lake County Forest Preserve District for planning, construction and renovation of the Adlai Stevenson Home State Historic Site.

 

    Section 10.  The sum of $437,800, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 102, Section 10 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Historic Preservation Agency for costs associated with the acquisition or improvements of Sugar Loaf and/or Fox Mounds or other properties within the Cahokia Mounds National Historic Landmark Boundary.

 

    Section 15.  The sum of $460,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 102, Section 15 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Historic Preservation Agency for support facilities, acquisition or improvements for Sugar Loaf and/or Fox Mounds or other properties within the Cahokia Mounds National Historic Landmark Boundary.

 

Total, Article 14                                $1,897,800

 

ARTICLE 15

ILLINOIS FINANCE AUTHORITY

 

    Section 5.  The sum of $500,000, or so much thereof as may be necessary, is appropriated from the Fire Truck Revolving Loan Fund to the Illinois Finance Authority for the purpose of making loans to fire departments, fire protection districts, and township fire departments as successor in interest to the Illinois Rural Bond Bank, pursuant to Section 845-75 of Public Act 93-0205.

 

Total, Article 15                                  $500,000

 

ARTICLE 16

ILLINOIS FINANCE AUTHORITY

 

    Section 10.  The sum of $5,500,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 103, Section 5 of Public Act 93-0842, is reappropriated from the Build Illinois Bond Fund to the Illinois Finance Authority for deposit into the Fire Truck Revolving Loan Fund for the purpose of making loans to fire departments, fire protection districts, and township fire departments as successor in interest to the Illinois Rural Bond Bank, pursuant to Section 845-75 of Public Act 93-0205.

 

    Section 15.  The sum of $9,025,632, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 103, Section 10 of Public Act 93-0842, is reappropriated from the Fire Truck Revolving Loan Fund to the Illinois Finance Authority for loans to fire departments, fire protection districts, and township fire departments as successor in interest to the Illinois Rural Bond Bank, pursuant to Section 845-75 of Public Act 93-0205.

 

Total, Article 16                               $14,525,632

 

ARTICLE 17

MEDICAL DISTRICT COMMISSION

 

    Section 5.  The sum of $3,000,000, or so much thereof as may be necessary, is appropriated from the Capital Development Fund to the Illinois Medical District Commission for acquisition of property, demolition and site improvements, and related costs within the Medical Center District, City of Chicago for Phase IV of District Development Initiative.

 

Total, Article 17                                $3,000,000

 

ARTICLE 18

MEDICAL DISTRICT COMMISSION

 

    Section 5.  The sum of $10,768, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 104, Section 5 of Public Act 93-842, is reappropriated from the Capital Development Fund to the Illinois Medical District Commission for acquisition of property, demolition and site improvements, and related costs within the Medical Center District, City of Chicago for Phase III and IV of District Development Initiative.

 

    Section 10.  The sum of $149,012, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made in Article 104, Section 10 of Public Act 93-842, is reappropriated from the Capital Development Fund to the Illinois Medical District Commission for acquisition of property, demolition and site improvements, and related costs within the Medical Center District, City of Chicago for Phase IV of District Development Initiative.

 

    Section 20.  No contract shall be entered into or obligation incurred for any expenditures from appropriations in Sections 10 and 15 of this Article until the purposes and amounts have been approved in writing by the Governor.

 

Total, Article 18                                  $159,780

 

ARTICLE 19

ILLINOIS EMERGENCY MANAGEMENT AGENCY

 

Section 10.  The sum of $436,600, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Public Act 93-0842, Article 76, Section 100, as amended, is reappropriated from the Build Illinois Bond Fund to the Illinois Emergency Management Agency for the capital costs associated with the Gubernatorial Proclamation of disaster dated April 21, 2004 relating to Kankakee, LaSalle, Putnam, and Will Counties.

 

Total, Article 19                                  $436,600

 

ARTICLE 20

EASTERN ILLINOIS UNIVERSITY

 

    Section 5.  The sum of $9,422, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 106, Section 10 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Board of Trustees of Eastern Illinois University for digitalization infrastructure for WEIU-TV, in addition to amounts previously appropriated for such purpose for this fiscal year.  No contract shall be entered into or obligation incurred for any expenditure from the appropriation made in this Section until after the purposes and amounts have been approved in writing by the Governor.

 

    Section 10.  The sum of $5,430,384, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made for such purpose in Article 106, Section 15 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Board of Trustees of Eastern Illinois University to purchase equipment for the renovation and expansion of the Fine Arts Center.  No contract shall be entered into or obligation incurred for any expenditure from the appropriation made in this Section until after the purpose and amounts have been approved in writing by the Governor.

 

    Section 15.  The sum of $404,157, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 106, Section 20 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Board of Trustees of Eastern Illinois University to purchase equipment for the renovation and expansion of Booth Library.  No contract shall be entered into or obligation incurred for any expenditure from the appropriation made in this Section until after the purposes and amounts have been approved in writing by the Governor.

 

Total, Article 20                                $5,843,963

 

ARTICLE 21

NORTHEASTERN ILLINOIS UNIVERSITY

 

    Section 5.  The sum of $2,071,805, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 107, Section 5 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Board of Trustees of Northeastern Illinois University to purchase equipment and remodel buildings A, B and E.  This appropriation is in addition to any funds previously appropriated.

 

Total, Article 21                                $2,071,805

 

ARTICLE 22

NORTHERN ILLINOIS UNIVERSITY

 

    Section 5.  The sum of $523,827, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for that purpose in Article 108, Section 5 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Board of Trustees of Northern Illinois University for technology infrastructure improvements at Northern Illinois University. No contract shall be entered into or obligation incurred for any expenditures from the reappropriation made in this Section until after the purposes and amounts have been approved in writing by the Governor.

 

    Section 10.  The sum of $43,366, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for that purpose in Article 108, Section 10 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Board of Trustees of Northern Illinois University for purchasing Engineering Building equipment.

 

Total, Article 22                                  $567,193

 

ARTICLE 23

SOUTHERN ILLINOIS UNIVERSITY

 

    Section 5.  The amount of $28,497, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 109, Section 10 of Public Act 93-0842, is reappropriated to Southern Illinois University from the Capital Development Fund for digitalization infrastructure for WUSI-TV (Olney).

 

    Section 10.  The sum of $800,000, or so much thereof as may be necessary, and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 109, Section 20 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Board of Trustees of Southern Illinois University at Carbondale to purchase equipment for Altgeld Hall and the Old Baptist Foundation Building.  This appropriation is in addition to any funds previously appropriated.

 

Total, Article 23                                  $828,497

 

ARTICLE 24

UNIVERSITY OF ILLINOIS

 

    Section 5.  The sum of $10,599,574, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 110, Section 10 of Public Act 93-0842, as amended, is reappropriated from the Capital Development Fund to the Board of Trustees of the University of Illinois for all costs associated with the space needs of the Department of Natural Resources, Illinois Natural History Survey Division and State Water Survey Division on the campus of the University of Illinois in Champaign, including construction, capital facilities, planning, relocation, renovation and rehabilitation, mechanical systems, materials, services and all other costs required to complete the work.

 

    Section 10.  The sum of $3,775,922, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 110, Section 15 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Board of Trustees of the University of Illinois to plan and construct an Education and Research facility for the College of Medicine in Chicago, including planning, land acquisition, demolition, construction, remodeling, landscaping, site improvements, equipment, extension or modification of campus utility systems, relocation of programs, and such expenses as may be necessary to complete the facility.  This appropriation is in addition to any other funds appropriated for this purpose for this fiscal year.

 

    Section 15.  The sum of $688,089, or so much thereof as may be necessary and remains unexpended on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 110, Section 25 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the University of Illinois for digitalization infrastructure for WILL-TV (Urbana-Champaign).

 

    Section 20.  The sum of $814,444, or so much thereof as may be necessary and remains unexpended on June 30, 2005, from an appropriation heretofore made for such purpose in Article 110, Section 30 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the University of Illinois for digitalization infrastructure for WILL-TV (Urbana-Champaign).

 

    Section 25.  The sum of $431,068, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made in Article 110, Section 35 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the Board of Trustees of the University of Illinois to plan and construct a Classroom and Office Building at the Springfield Campus and related utility systems, including planning, land acquisition, demolition, construction, remodeling, landscaping, site improvements, equipment, extension or modification of campus utility systems, and such expenses as may be necessary to complete the facility.  This appropriation is in addition to any other funds appropriated for this purpose for this fiscal year.

 

    Section 30.  The sum of $2,949,074, or so much thereof as may be necessary and remains unexpended on June 30, 2005, from an appropriation heretofore made for such purpose in Article 110, Section 45 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the University of Illinois at Springfield for constructing a classroom and office building, in addition to funds previously appropriated.

 

Total, Article 24                               $19,258,171

 

ARTICLE 25

ILLINOIS COMMUNITY COLLEGE BOARD

 

    Section 5.  The sum of $2,019,599, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from a reappropriation heretofore made for such purpose in Article 111, Section 15 of Public Act 93-0842, as amended, is reappropriated from the Build Illinois Bond Fund for the Illinois Community College Board for remodeling of facilities for compliance with the Americans with Disabilities Act.  This appropriated amount shall be in addition to any other appropriated amounts which can be expended for these purposes.

 

Total, Article 25                                $2,019,599

 

ARTICLE 26

STATE BOARD OF EDUCATION

 

    Section 5.  The following named amount, or so much thereof as may be necessary, is appropriated from the School Construction Fund to the State Board of Education for School Construction Maintenance Grants:

  For School Construction Grants............... $50,000,000

 

Total, Article 26                               $50,000,000

 

ARTICLE 27

STATE BOARD OF ELECTIONS

    Section 5.  The sum of $5,000,000, or so much thereof as may be necessary and remains unexpended at the close of business on June 30, 2005, from an appropriation heretofore made for such purpose in Article 22, Section 15 of Public Act 93-0842, is reappropriated from the Capital Development Fund to the State Board of Elections for grants to local governments for the purchase of handicapped accessible polling machines.

 

Total, Article 27                                $5,000,000

 

ARTICLE 99

 

Section 999-99. Effective date. This Act takes effect on July 1, 2005.