|
| | HB5539 Engrossed | | LRB103 38494 CES 68630 b |
|
|
1 | | AN ACT concerning utilities. |
2 | | Be it enacted by the People of the State of Illinois, |
3 | | represented in the General Assembly: |
4 | | Section 5. The Public Utilities Act is amended by changing |
5 | | Sections 8-103, 8-103B, and 8-104 as follows: |
6 | | (220 ILCS 5/8-103) |
7 | | Sec. 8-103. Energy efficiency and demand-response |
8 | | measures. |
9 | | (a) It is the policy of the State that electric utilities |
10 | | are required to use cost-effective energy efficiency and |
11 | | demand-response measures to reduce delivery load. Requiring |
12 | | investment in cost-effective energy efficiency and |
13 | | demand-response measures will reduce direct and indirect costs |
14 | | to consumers by decreasing environmental impacts and by |
15 | | avoiding or delaying the need for new generation, |
16 | | transmission, and distribution infrastructure. It serves the |
17 | | public interest to allow electric utilities to recover costs |
18 | | for reasonably and prudently incurred expenses for energy |
19 | | efficiency and demand-response measures. As used in this |
20 | | Section, "cost-effective" means that the measures satisfy the |
21 | | total resource cost test. The low-income measures described in |
22 | | subsection (f)(4) of this Section shall not be required to |
23 | | meet the total resource cost test. For purposes of this |
|
| | HB5539 Engrossed | - 2 - | LRB103 38494 CES 68630 b |
|
|
1 | | Section, the terms "energy-efficiency", "demand-response", |
2 | | "electric utility", and "total resource cost test" shall have |
3 | | the meanings set forth in the Illinois Power Agency Act. For |
4 | | purposes of this Section, the amount per kilowatthour means |
5 | | the total amount paid for electric service expressed on a per |
6 | | kilowatthour basis. For purposes of this Section, the total |
7 | | amount paid for electric service includes without limitation |
8 | | estimated amounts paid for supply, transmission, distribution, |
9 | | surcharges, and add-on-taxes. |
10 | | (a-5) This Section applies to electric utilities serving |
11 | | 500,000 or less but more than 200,000 retail customers in this |
12 | | State. Through December 31, 2017, this Section also applies to |
13 | | electric utilities serving more than 500,000 retail customers |
14 | | in the State. |
15 | | (b) Electric utilities shall implement cost-effective |
16 | | energy efficiency measures to meet the following incremental |
17 | | annual energy savings goals: |
18 | | (1) 0.2% of energy delivered in the year commencing |
19 | | June 1, 2008; |
20 | | (2) 0.4% of energy delivered in the year commencing |
21 | | June 1, 2009; |
22 | | (3) 0.6% of energy delivered in the year commencing |
23 | | June 1, 2010; |
24 | | (4) 0.8% of energy delivered in the year commencing |
25 | | June 1, 2011; |
26 | | (5) 1% of energy delivered in the year commencing June |
|
| | HB5539 Engrossed | - 3 - | LRB103 38494 CES 68630 b |
|
|
1 | | 1, 2012; |
2 | | (6) 1.4% of energy delivered in the year commencing |
3 | | June 1, 2013; |
4 | | (7) 1.8% of energy delivered in the year commencing |
5 | | June 1, 2014; and |
6 | | (8) 2% of energy delivered in the year commencing June |
7 | | 1, 2015 and each year thereafter. |
8 | | Electric utilities may comply with this subsection (b) by |
9 | | meeting the annual incremental savings goal in the applicable |
10 | | year or by showing that the total cumulative annual savings |
11 | | within a 3-year planning period associated with measures |
12 | | implemented after May 31, 2014 was equal to the sum of each |
13 | | annual incremental savings requirement from May 31, 2014 |
14 | | through the end of the applicable year. |
15 | | (c) Electric utilities shall implement cost-effective |
16 | | demand-response measures to reduce peak demand by 0.1% over |
17 | | the prior year for eligible retail customers, as defined in |
18 | | Section 16-111.5 of this Act, and for customers that elect |
19 | | hourly service from the utility pursuant to Section 16-107 of |
20 | | this Act, provided those customers have not been declared |
21 | | competitive. This requirement commences June 1, 2008 and |
22 | | continues for 10 years. |
23 | | (d) Notwithstanding the requirements of subsections (b) |
24 | | and (c) of this Section, an electric utility shall reduce the |
25 | | amount of energy efficiency and demand-response measures |
26 | | implemented over a 3-year planning period by an amount |
|
| | HB5539 Engrossed | - 4 - | LRB103 38494 CES 68630 b |
|
|
1 | | necessary to limit the estimated average annual increase in |
2 | | the amounts paid by retail customers in connection with |
3 | | electric service due to the cost of those measures to: |
4 | | (1) in 2008, no more than 0.5% of the amount paid per |
5 | | kilowatthour by those customers during the year ending May |
6 | | 31, 2007; |
7 | | (2) in 2009, the greater of an additional 0.5% of the |
8 | | amount paid per kilowatthour by those customers during the |
9 | | year ending May 31, 2008 or 1% of the amount paid per |
10 | | kilowatthour by those customers during the year ending May |
11 | | 31, 2007; |
12 | | (3) in 2010, the greater of an additional 0.5% of the |
13 | | amount paid per kilowatthour by those customers during the |
14 | | year ending May 31, 2009 or 1.5% of the amount paid per |
15 | | kilowatthour by those customers during the year ending May |
16 | | 31, 2007; |
17 | | (4) in 2011, the greater of an additional 0.5% of the |
18 | | amount paid per kilowatthour by those customers during the |
19 | | year ending May 31, 2010 or 2% of the amount paid per |
20 | | kilowatthour by those customers during the year ending May |
21 | | 31, 2007; and |
22 | | (5) thereafter, the amount of energy efficiency and |
23 | | demand-response measures implemented for any single year |
24 | | shall be reduced by an amount necessary to limit the |
25 | | estimated average net increase due to the cost of these |
26 | | measures included in the amounts paid by eligible retail |
|
| | HB5539 Engrossed | - 5 - | LRB103 38494 CES 68630 b |
|
|
1 | | customers in connection with electric service to no more |
2 | | than the greater of 2.015% of the amount paid per |
3 | | kilowatthour by those customers during the year ending May |
4 | | 31, 2007 or the incremental amount per kilowatthour paid |
5 | | for these measures in 2011. |
6 | | No later than June 30, 2011, the Commission shall review |
7 | | the limitation on the amount of energy efficiency and |
8 | | demand-response measures implemented pursuant to this Section |
9 | | and report to the General Assembly its findings as to whether |
10 | | that limitation unduly constrains the procurement of energy |
11 | | efficiency and demand-response measures. |
12 | | (e) Electric utilities shall be responsible for overseeing |
13 | | the design, development, and filing of energy efficiency and |
14 | | demand-response plans with the Commission. Electric utilities |
15 | | shall implement 100% of the demand-response measures in the |
16 | | plans. Electric utilities shall implement 75% of the energy |
17 | | efficiency measures approved by the Commission, and may, as |
18 | | part of that implementation, outsource various aspects of |
19 | | program development and implementation. The remaining 25% of |
20 | | those energy efficiency measures approved by the Commission |
21 | | shall be implemented by the Department of Commerce and |
22 | | Economic Opportunity, and must be designed in conjunction with |
23 | | the utility and the filing process. The Department may |
24 | | outsource development and implementation of energy efficiency |
25 | | measures. A minimum of 10% of the entire portfolio of |
26 | | cost-effective energy efficiency measures shall be procured |
|
| | HB5539 Engrossed | - 6 - | LRB103 38494 CES 68630 b |
|
|
1 | | from units of local government, municipal corporations, school |
2 | | districts, public institutions of higher education, and |
3 | | community college districts. The Department shall coordinate |
4 | | the implementation of these measures. |
5 | | The apportionment of the dollars to cover the costs to |
6 | | implement the Department's share of the portfolio of energy |
7 | | efficiency measures shall be made to the Department once the |
8 | | Department has executed rebate agreements, grants, or |
9 | | contracts for energy efficiency measures and provided |
10 | | supporting documentation for those rebate agreements, grants, |
11 | | and contracts to the utility. The Department is authorized to |
12 | | adopt any rules necessary and prescribe procedures in order to |
13 | | ensure compliance by applicants in carrying out the purposes |
14 | | of rebate agreements for energy efficiency measures |
15 | | implemented by the Department made under this Section. |
16 | | The details of the measures implemented by the Department |
17 | | shall be submitted by the Department to the Commission in |
18 | | connection with the utility's filing regarding the energy |
19 | | efficiency and demand-response measures that the utility |
20 | | implements. |
21 | | A utility providing approved energy efficiency and |
22 | | demand-response measures in the State shall be permitted to |
23 | | recover costs of those measures through an automatic |
24 | | adjustment clause tariff filed with and approved by the |
25 | | Commission. The tariff shall be established outside the |
26 | | context of a general rate case. Each year the Commission shall |
|
| | HB5539 Engrossed | - 7 - | LRB103 38494 CES 68630 b |
|
|
1 | | initiate a review to reconcile any amounts collected with the |
2 | | actual costs and to determine the required adjustment to the |
3 | | annual tariff factor to match annual expenditures. |
4 | | Each utility shall include, in its recovery of costs, the |
5 | | costs estimated for both the utility's and the Department's |
6 | | implementation of energy efficiency and demand-response |
7 | | measures. Costs collected by the utility for measures |
8 | | implemented by the Department shall be submitted to the |
9 | | Department pursuant to Section 605-323 of the Civil |
10 | | Administrative Code of Illinois, shall be deposited into the |
11 | | Energy Efficiency Portfolio Standards Fund, and shall be used |
12 | | by the Department solely for the purpose of implementing these |
13 | | measures. A utility shall not be required to advance any |
14 | | moneys to the Department but only to forward such funds as it |
15 | | has collected. The Department shall report to the Commission |
16 | | on an annual basis regarding the costs actually incurred by |
17 | | the Department in the implementation of the measures. Any |
18 | | changes to the costs of energy efficiency measures as a result |
19 | | of plan modifications shall be appropriately reflected in |
20 | | amounts recovered by the utility and turned over to the |
21 | | Department. |
22 | | The portfolio of measures, administered by both the |
23 | | utilities and the Department, shall, in combination, be |
24 | | designed to achieve the annual savings targets described in |
25 | | subsections (b) and (c) of this Section, as modified by |
26 | | subsection (d) of this Section. |
|
| | HB5539 Engrossed | - 8 - | LRB103 38494 CES 68630 b |
|
|
1 | | The utility and the Department shall agree upon a |
2 | | reasonable portfolio of measures and determine the measurable |
3 | | corresponding percentage of the savings goals associated with |
4 | | measures implemented by the utility or Department. |
5 | | No utility shall be assessed a penalty under subsection |
6 | | (f) of this Section for failure to make a timely filing if that |
7 | | failure is the result of a lack of agreement with the |
8 | | Department with respect to the allocation of responsibilities |
9 | | or related costs or target assignments. In that case, the |
10 | | Department and the utility shall file their respective plans |
11 | | with the Commission and the Commission shall determine an |
12 | | appropriate division of measures and programs that meets the |
13 | | requirements of this Section. |
14 | | If the Department is unable to meet incremental annual |
15 | | performance goals for the portion of the portfolio implemented |
16 | | by the Department, then the utility and the Department shall |
17 | | jointly submit a modified filing to the Commission explaining |
18 | | the performance shortfall and recommending an appropriate |
19 | | course going forward, including any program modifications that |
20 | | may be appropriate in light of the evaluations conducted under |
21 | | item (7) of subsection (f) of this Section. In this case, the |
22 | | utility obligation to collect the Department's costs and turn |
23 | | over those funds to the Department under this subsection (e) |
24 | | shall continue only if the Commission approves the |
25 | | modifications to the plan proposed by the Department. |
26 | | (f) No later than November 15, 2007, each electric utility |
|
| | HB5539 Engrossed | - 9 - | LRB103 38494 CES 68630 b |
|
|
1 | | shall file an energy efficiency and demand-response plan with |
2 | | the Commission to meet the energy efficiency and |
3 | | demand-response standards for 2008 through 2010. No later than |
4 | | October 1, 2010, each electric utility shall file an energy |
5 | | efficiency and demand-response plan with the Commission to |
6 | | meet the energy efficiency and demand-response standards for |
7 | | 2011 through 2013. Every 3 years thereafter, each electric |
8 | | utility shall file, no later than September 1, an energy |
9 | | efficiency and demand-response plan with the Commission. If a |
10 | | utility does not file such a plan by September 1 of an |
11 | | applicable year, it shall face a penalty of $100,000 per day |
12 | | until the plan is filed. Each utility's plan shall set forth |
13 | | the utility's proposals to meet the utility's portion of the |
14 | | energy efficiency standards identified in subsection (b) and |
15 | | the demand-response standards identified in subsection (c) of |
16 | | this Section as modified by subsections (d) and (e), taking |
17 | | into account the unique circumstances of the utility's service |
18 | | territory. The Commission shall seek public comment on the |
19 | | utility's plan and shall issue an order approving or |
20 | | disapproving each plan within 5 months after its submission. |
21 | | If the Commission disapproves a plan, the Commission shall, |
22 | | within 30 days, describe in detail the reasons for the |
23 | | disapproval and describe a path by which the utility may file a |
24 | | revised draft of the plan to address the Commission's concerns |
25 | | satisfactorily. If the utility does not refile with the |
26 | | Commission within 60 days, the utility shall be subject to |
|
| | HB5539 Engrossed | - 10 - | LRB103 38494 CES 68630 b |
|
|
1 | | penalties at a rate of $100,000 per day until the plan is |
2 | | filed. This process shall continue, and penalties shall |
3 | | accrue, until the utility has successfully filed a portfolio |
4 | | of energy efficiency and demand-response measures. Penalties |
5 | | shall be deposited into the Energy Efficiency Trust Fund. In |
6 | | submitting proposed energy efficiency and demand-response |
7 | | plans and funding levels to meet the savings goals adopted by |
8 | | this Act the utility shall: |
9 | | (1) Demonstrate that its proposed energy efficiency |
10 | | and demand-response measures will achieve the requirements |
11 | | that are identified in subsections (b) and (c) of this |
12 | | Section, as modified by subsections (d) and (e). |
13 | | (2) Present specific proposals to implement new |
14 | | building and appliance standards that have been placed |
15 | | into effect. |
16 | | (3) Present estimates of the total amount paid for |
17 | | electric service expressed on a per kilowatthour basis |
18 | | associated with the proposed portfolio of measures |
19 | | designed to meet the requirements that are identified in |
20 | | subsections (b) and (c) of this Section, as modified by |
21 | | subsections (d) and (e). |
22 | | (4) Coordinate with the Department to present a |
23 | | portfolio of energy efficiency measures proportionate to |
24 | | the share of total annual utility revenues in Illinois |
25 | | from households at or below 150% of the poverty level. The |
26 | | energy efficiency programs shall be targeted to households |
|
| | HB5539 Engrossed | - 11 - | LRB103 38494 CES 68630 b |
|
|
1 | | with incomes at or below 80% of area median income. |
2 | | (5) Demonstrate that its overall portfolio of energy |
3 | | efficiency and demand-response measures, not including |
4 | | programs covered by item (4) of this subsection (f), are |
5 | | cost-effective using the total resource cost test and |
6 | | represent a diverse cross-section of opportunities for |
7 | | customers of all rate classes to participate in the |
8 | | programs. |
9 | | (6) Include a proposed cost-recovery tariff mechanism |
10 | | to fund the proposed energy efficiency and demand-response |
11 | | measures and to ensure the recovery of the prudently and |
12 | | reasonably incurred costs of Commission-approved programs. |
13 | | (7) Provide for an annual independent evaluation of |
14 | | the performance of the cost-effectiveness of the utility's |
15 | | portfolio of measures and the Department's portfolio of |
16 | | measures, as well as a full review of the 3-year results of |
17 | | the broader net program impacts and, to the extent |
18 | | practical, for adjustment of the measures on a |
19 | | going-forward basis as a result of the evaluations. The |
20 | | resources dedicated to evaluation shall not exceed 3% of |
21 | | portfolio resources in any given year. |
22 | | (g) No more than 3% of energy efficiency and |
23 | | demand-response program revenue may be allocated for |
24 | | demonstration of breakthrough equipment and devices. |
25 | | (h) This Section does not apply to an electric utility |
26 | | that on December 31, 2005 provided electric service to fewer |
|
| | HB5539 Engrossed | - 12 - | LRB103 38494 CES 68630 b |
|
|
1 | | than 100,000 customers in Illinois. |
2 | | (i) If, after 2 years, an electric utility fails to meet |
3 | | the efficiency standard specified in subsection (b) of this |
4 | | Section, as modified by subsections (d) and (e), it shall make |
5 | | a contribution to the Low-Income Home Energy Assistance |
6 | | Program. The combined total liability for failure to meet the |
7 | | goal shall be $1,000,000, which shall be assessed as follows: |
8 | | a large electric utility shall pay $665,000, and a medium |
9 | | electric utility shall pay $335,000. If, after 3 years, an |
10 | | electric utility fails to meet the efficiency standard |
11 | | specified in subsection (b) of this Section, as modified by |
12 | | subsections (d) and (e), it shall make a contribution to the |
13 | | Low-Income Home Energy Assistance Program. The combined total |
14 | | liability for failure to meet the goal shall be $1,000,000, |
15 | | which shall be assessed as follows: a large electric utility |
16 | | shall pay $665,000, and a medium electric utility shall pay |
17 | | $335,000. In addition, the responsibility for implementing the |
18 | | energy efficiency measures of the utility making the payment |
19 | | shall be transferred to the Illinois Power Agency if, after 3 |
20 | | years, or in any subsequent 3-year period, the utility fails |
21 | | to meet the efficiency standard specified in subsection (b) of |
22 | | this Section, as modified by subsections (d) and (e). The |
23 | | Agency shall implement a competitive procurement program to |
24 | | procure resources necessary to meet the standards specified in |
25 | | this Section as modified by subsections (d) and (e), with |
26 | | costs for those resources to be recovered in the same manner as |
|
| | HB5539 Engrossed | - 13 - | LRB103 38494 CES 68630 b |
|
|
1 | | products purchased through the procurement plan as provided in |
2 | | Section 16-111.5. The Director shall implement this |
3 | | requirement in connection with the procurement plan as |
4 | | provided in Section 16-111.5. |
5 | | For purposes of this Section, (i) a "large electric |
6 | | utility" is an electric utility that, on December 31, 2005, |
7 | | served more than 2,000,000 electric customers in Illinois; |
8 | | (ii) a "medium electric utility" is an electric utility that, |
9 | | on December 31, 2005, served 2,000,000 or fewer but more than |
10 | | 100,000 electric customers in Illinois; and (iii) Illinois |
11 | | electric utilities that are affiliated by virtue of a common |
12 | | parent company are considered a single electric utility. |
13 | | (j) If, after 3 years, or any subsequent 3-year period, |
14 | | the Department fails to implement the Department's share of |
15 | | energy efficiency measures required by the standards in |
16 | | subsection (b), then the Illinois Power Agency may assume |
17 | | responsibility for and control of the Department's share of |
18 | | the required energy efficiency measures. The Agency shall |
19 | | implement a competitive procurement program to procure |
20 | | resources necessary to meet the standards specified in this |
21 | | Section, with the costs of these resources to be recovered in |
22 | | the same manner as provided for the Department in this |
23 | | Section. |
24 | | (k) No electric utility shall be deemed to have failed to |
25 | | meet the energy efficiency standards to the extent any such |
26 | | failure is due to a failure of the Department or the Agency. |
|
| | HB5539 Engrossed | - 14 - | LRB103 38494 CES 68630 b |
|
|
1 | | (l)(1) The energy efficiency and demand-response plans of |
2 | | electric utilities serving more than 500,000 retail customers |
3 | | in the State that were approved by the Commission on or before |
4 | | the effective date of this amendatory Act of the 99th General |
5 | | Assembly for the period June 1, 2014 through May 31, 2017 shall |
6 | | continue to be in force and effect through December 31, 2017 so |
7 | | that the energy efficiency programs set forth in those plans |
8 | | continue to be offered during the period June 1, 2017 through |
9 | | December 31, 2017. Each such utility is authorized to |
10 | | increase, on a pro rata basis, the energy savings goals and |
11 | | budgets approved in its plan to reflect the additional 7 |
12 | | months of the plan's operation, provided that such increase |
13 | | shall also incorporate reductions to goals and budgets to |
14 | | reflect the proportion of the utility's load attributable to |
15 | | customers who are exempt from this Section under subsection |
16 | | (m) of this Section. |
17 | | (2) If an electric utility serving more than 500,000 |
18 | | retail customers in the State filed with the Commission, under |
19 | | subsection (f) of this Section, its proposed energy efficiency |
20 | | and demand-response plan for the period June 1, 2017 through |
21 | | May 31, 2020, and the Commission has not yet entered its final |
22 | | order approving such plan on or before the effective date of |
23 | | this amendatory Act of the 99th General Assembly, then the |
24 | | utility shall file a notice of withdrawal with the Commission, |
25 | | following such effective date, to withdraw the proposed energy |
26 | | efficiency and demand-response plan. Upon receipt of such |
|
| | HB5539 Engrossed | - 15 - | LRB103 38494 CES 68630 b |
|
|
1 | | notice, the Commission shall dismiss with prejudice any docket |
2 | | that had been initiated to investigate such plan, and the plan |
3 | | and the record related thereto shall not be the subject of any |
4 | | further hearing, investigation, or proceeding of any kind. |
5 | | (3) For those electric utilities that serve more than |
6 | | 500,000 retail customers in the State, this amendatory Act of |
7 | | the 99th General Assembly preempts and supersedes any orders |
8 | | entered by the Commission that approved such utilities' energy |
9 | | efficiency and demand response plans for the period commencing |
10 | | June 1, 2017 and ending May 31, 2020. Any such orders shall be |
11 | | void, and the provisions of paragraph (1) of this subsection |
12 | | (l) shall apply. |
13 | | (m) Notwithstanding anything to the contrary, after May |
14 | | 31, 2017, this Section does not apply to any retail customers |
15 | | of an electric utility that serves more than 3,000,000 retail |
16 | | customers in the State and whose total highest 30 minute |
17 | | demand was more than 10,000 kilowatts, or any retail customers |
18 | | of an electric utility that serves less than 3,000,000 retail |
19 | | customers but more than 500,000 retail customers in the State |
20 | | and whose total highest 15 minute demand was more than 10,000 |
21 | | kilowatts. For purposes of this subsection (m), "retail |
22 | | customer" has the meaning set forth in Section 16-102 of this |
23 | | Act. The criteria for determining whether this subsection (m) |
24 | | is applicable to a retail customer shall be based on the 12 |
25 | | consecutive billing periods prior to the start of the first |
26 | | year of each such multi-year plan. |
|
| | HB5539 Engrossed | - 16 - | LRB103 38494 CES 68630 b |
|
|
1 | | (Source: P.A. 98-90, eff. 7-15-13; 99-906, eff. 6-1-17 .) |
2 | | (220 ILCS 5/8-103B) |
3 | | Sec. 8-103B. Energy efficiency and demand-response |
4 | | measures. |
5 | | (a) It is the policy of the State that electric utilities |
6 | | are required to use cost-effective energy efficiency and |
7 | | demand-response measures to reduce delivery load. Requiring |
8 | | investment in cost-effective energy efficiency and |
9 | | demand-response measures will reduce direct and indirect costs |
10 | | to consumers by decreasing environmental impacts and by |
11 | | avoiding or delaying the need for new generation, |
12 | | transmission, and distribution infrastructure. It serves the |
13 | | public interest to allow electric utilities to recover costs |
14 | | for reasonably and prudently incurred expenditures for energy |
15 | | efficiency and demand-response measures. As used in this |
16 | | Section, "cost-effective" means that the measures satisfy the |
17 | | total resource cost test. The low-income measures described in |
18 | | subsection (c) of this Section shall not be required to meet |
19 | | the total resource cost test. For purposes of this Section, |
20 | | the terms "energy-efficiency", "demand-response", "electric |
21 | | utility", and "total resource cost test" have the meanings set |
22 | | forth in the Illinois Power Agency Act. "Black, indigenous, |
23 | | and people of color" and "BIPOC" means people who are members |
24 | | of the groups described in subparagraphs (a) through (e) of |
25 | | paragraph (A) of subsection (1) of Section 2 of the Business |
|
| | HB5539 Engrossed | - 17 - | LRB103 38494 CES 68630 b |
|
|
1 | | Enterprise for Minorities, Women, and Persons with |
2 | | Disabilities Act. |
3 | | (a-5) This Section applies to electric utilities serving |
4 | | more than 500,000 retail customers in the State for those |
5 | | multi-year plans commencing after December 31, 2017. |
6 | | (b) For purposes of this Section, electric utilities |
7 | | subject to this Section that serve more than 3,000,000 retail |
8 | | customers in the State shall be deemed to have achieved a |
9 | | cumulative persisting annual savings of 6.6% from energy |
10 | | efficiency measures and programs implemented during the period |
11 | | beginning January 1, 2012 and ending December 31, 2017, which |
12 | | percent is based on the deemed average weather normalized |
13 | | sales of electric power and energy during calendar years 2014, |
14 | | 2015, and 2016 of 88,000,000 MWhs. For the purposes of this |
15 | | subsection (b) and subsection (b-5), the 88,000,000 MWhs of |
16 | | deemed electric power and energy sales shall be reduced by the |
17 | | number of MWhs equal to the sum of the annual consumption of |
18 | | customers that have opted out of subsections (a) through (j) |
19 | | of this Section under paragraph (1) of subsection (l) of this |
20 | | Section, as averaged across the calendar years 2014, 2015, and |
21 | | 2016. After 2017, the deemed value of cumulative persisting |
22 | | annual savings from energy efficiency measures and programs |
23 | | implemented during the period beginning January 1, 2012 and |
24 | | ending December 31, 2017, shall be reduced each year, as |
25 | | follows, and the applicable value shall be applied to and |
26 | | count toward the utility's achievement of the cumulative |
|
| | HB5539 Engrossed | - 18 - | LRB103 38494 CES 68630 b |
|
|
1 | | persisting annual savings goals set forth in subsection (b-5): |
2 | | (1) 5.8% deemed cumulative persisting annual savings |
3 | | for the year ending December 31, 2018; |
4 | | (2) 5.2% deemed cumulative persisting annual savings |
5 | | for the year ending December 31, 2019; |
6 | | (3) 4.5% deemed cumulative persisting annual savings |
7 | | for the year ending December 31, 2020; |
8 | | (4) 4.0% deemed cumulative persisting annual savings |
9 | | for the year ending December 31, 2021; |
10 | | (5) 3.5% deemed cumulative persisting annual savings |
11 | | for the year ending December 31, 2022; |
12 | | (6) 3.1% deemed cumulative persisting annual savings |
13 | | for the year ending December 31, 2023; |
14 | | (7) 2.8% deemed cumulative persisting annual savings |
15 | | for the year ending December 31, 2024; |
16 | | (8) 2.5% deemed cumulative persisting annual savings |
17 | | for the year ending December 31, 2025; |
18 | | (9) 2.3% deemed cumulative persisting annual savings |
19 | | for the year ending December 31, 2026; |
20 | | (10) 2.1% deemed cumulative persisting annual savings |
21 | | for the year ending December 31, 2027; |
22 | | (11) 1.8% deemed cumulative persisting annual savings |
23 | | for the year ending December 31, 2028; |
24 | | (12) 1.7% deemed cumulative persisting annual savings |
25 | | for the year ending December 31, 2029; |
26 | | (13) 1.5% deemed cumulative persisting annual savings |
|
| | HB5539 Engrossed | - 19 - | LRB103 38494 CES 68630 b |
|
|
1 | | for the year ending December 31, 2030; |
2 | | (14) 1.3% deemed cumulative persisting annual savings |
3 | | for the year ending December 31, 2031; |
4 | | (15) 1.1% deemed cumulative persisting annual savings |
5 | | for the year ending December 31, 2032; |
6 | | (16) 0.9% deemed cumulative persisting annual savings |
7 | | for the year ending December 31, 2033; |
8 | | (17) 0.7% deemed cumulative persisting annual savings |
9 | | for the year ending December 31, 2034; |
10 | | (18) 0.5% deemed cumulative persisting annual savings |
11 | | for the year ending December 31, 2035; |
12 | | (19) 0.4% deemed cumulative persisting annual savings |
13 | | for the year ending December 31, 2036; |
14 | | (20) 0.3% deemed cumulative persisting annual savings |
15 | | for the year ending December 31, 2037; |
16 | | (21) 0.2% deemed cumulative persisting annual savings |
17 | | for the year ending December 31, 2038; |
18 | | (22) 0.1% deemed cumulative persisting annual savings |
19 | | for the year ending December 31, 2039; and |
20 | | (23) 0.0% deemed cumulative persisting annual savings |
21 | | for the year ending December 31, 2040 and all subsequent |
22 | | years. |
23 | | For purposes of this Section, "cumulative persisting |
24 | | annual savings" means the total electric energy savings in a |
25 | | given year from measures installed in that year or in previous |
26 | | years, but no earlier than January 1, 2012, that are still |
|
| | HB5539 Engrossed | - 20 - | LRB103 38494 CES 68630 b |
|
|
1 | | operational and providing savings in that year because the |
2 | | measures have not yet reached the end of their useful lives. |
3 | | (b-5) Beginning in 2018, electric utilities subject to |
4 | | this Section that serve more than 3,000,000 retail customers |
5 | | in the State shall achieve the following cumulative persisting |
6 | | annual savings goals, as modified by subsection (f) of this |
7 | | Section and as compared to the deemed baseline of 88,000,000 |
8 | | MWhs of electric power and energy sales set forth in |
9 | | subsection (b), as reduced by the number of MWhs equal to the |
10 | | sum of the annual consumption of customers that have opted out |
11 | | of subsections (a) through (j) of this Section under paragraph |
12 | | (1) of subsection (l) of this Section as averaged across the |
13 | | calendar years 2014, 2015, and 2016, through the |
14 | | implementation of energy efficiency measures during the |
15 | | applicable year and in prior years, but no earlier than |
16 | | January 1, 2012: |
17 | | (1) 7.8% cumulative persisting annual savings for the |
18 | | year ending December 31, 2018; |
19 | | (2) 9.1% cumulative persisting annual savings for the |
20 | | year ending December 31, 2019; |
21 | | (3) 10.4% cumulative persisting annual savings for the |
22 | | year ending December 31, 2020; |
23 | | (4) 11.8% cumulative persisting annual savings for the |
24 | | year ending December 31, 2021; |
25 | | (5) 13.1% cumulative persisting annual savings for the |
26 | | year ending December 31, 2022; |
|
| | HB5539 Engrossed | - 21 - | LRB103 38494 CES 68630 b |
|
|
1 | | (6) 14.4% cumulative persisting annual savings for the |
2 | | year ending December 31, 2023; |
3 | | (7) 15.7% cumulative persisting annual savings for the |
4 | | year ending December 31, 2024; |
5 | | (8) 17% cumulative persisting annual savings for the |
6 | | year ending December 31, 2025; |
7 | | (9) 17.9% cumulative persisting annual savings for the |
8 | | year ending December 31, 2026; |
9 | | (10) 18.8% cumulative persisting annual savings for |
10 | | the year ending December 31, 2027; |
11 | | (11) 19.7% cumulative persisting annual savings for |
12 | | the year ending December 31, 2028; |
13 | | (12) 20.6% cumulative persisting annual savings for |
14 | | the year ending December 31, 2029; and |
15 | | (13) 21.5% cumulative persisting annual savings for |
16 | | the year ending December 31, 2030. |
17 | | No later than December 31, 2021, the Illinois Commerce |
18 | | Commission shall establish additional cumulative persisting |
19 | | annual savings goals for the years 2031 through 2035. No later |
20 | | than December 31, 2024, the Illinois Commerce Commission shall |
21 | | establish additional cumulative persisting annual savings |
22 | | goals for the years 2036 through 2040. The Commission shall |
23 | | also establish additional cumulative persisting annual savings |
24 | | goals every 5 years thereafter to ensure that utilities always |
25 | | have goals that extend at least 11 years into the future. The |
26 | | cumulative persisting annual savings goals beyond the year |
|
| | HB5539 Engrossed | - 22 - | LRB103 38494 CES 68630 b |
|
|
1 | | 2030 shall increase by 0.9 percentage points per year, absent |
2 | | a Commission decision to initiate a proceeding to consider |
3 | | establishing goals that increase by more or less than that |
4 | | amount. Such a proceeding must be conducted in accordance with |
5 | | the procedures described in subsection (f) of this Section. If |
6 | | such a proceeding is initiated, the cumulative persisting |
7 | | annual savings goals established by the Commission through |
8 | | that proceeding shall reflect the Commission's best estimate |
9 | | of the maximum amount of additional savings that are forecast |
10 | | to be cost-effectively achievable unless such best estimates |
11 | | would result in goals that represent less than 0.5 percentage |
12 | | point annual increases in total cumulative persisting annual |
13 | | savings. The Commission may only establish goals that |
14 | | represent less than 0.5 percentage point annual increases in |
15 | | cumulative persisting annual savings if it can demonstrate, |
16 | | based on clear and convincing evidence and through independent |
17 | | analysis, that 0.5 percentage point increases are not |
18 | | cost-effectively achievable. The Commission shall inform its |
19 | | decision based on an energy efficiency potential study that |
20 | | conforms to the requirements of this Section. |
21 | | (b-10) For purposes of this Section, electric utilities |
22 | | subject to this Section that serve less than 3,000,000 retail |
23 | | customers but more than 500,000 retail customers in the State |
24 | | shall be deemed to have achieved a cumulative persisting |
25 | | annual savings of 6.6% from energy efficiency measures and |
26 | | programs implemented during the period beginning January 1, |
|
| | HB5539 Engrossed | - 23 - | LRB103 38494 CES 68630 b |
|
|
1 | | 2012 and ending December 31, 2017, which is based on the deemed |
2 | | average weather normalized sales of electric power and energy |
3 | | during calendar years 2014, 2015, and 2016 of 36,900,000 MWhs. |
4 | | For the purposes of this subsection (b-10) and subsection |
5 | | (b-15), the 36,900,000 MWhs of deemed electric power and |
6 | | energy sales shall be reduced by the number of MWhs equal to |
7 | | the sum of the annual consumption of customers that have opted |
8 | | out of subsections (a) through (j) of this Section under |
9 | | paragraph (1) of subsection (l) of this Section, as averaged |
10 | | across the calendar years 2014, 2015, and 2016. After 2017, |
11 | | the deemed value of cumulative persisting annual savings from |
12 | | energy efficiency measures and programs implemented during the |
13 | | period beginning January 1, 2012 and ending December 31, 2017, |
14 | | shall be reduced each year, as follows, and the applicable |
15 | | value shall be applied to and count toward the utility's |
16 | | achievement of the cumulative persisting annual savings goals |
17 | | set forth in subsection (b-15): |
18 | | (1) 5.8% deemed cumulative persisting annual savings |
19 | | for the year ending December 31, 2018; |
20 | | (2) 5.2% deemed cumulative persisting annual savings |
21 | | for the year ending December 31, 2019; |
22 | | (3) 4.5% deemed cumulative persisting annual savings |
23 | | for the year ending December 31, 2020; |
24 | | (4) 4.0% deemed cumulative persisting annual savings |
25 | | for the year ending December 31, 2021; |
26 | | (5) 3.5% deemed cumulative persisting annual savings |
|
| | HB5539 Engrossed | - 24 - | LRB103 38494 CES 68630 b |
|
|
1 | | for the year ending December 31, 2022; |
2 | | (6) 3.1% deemed cumulative persisting annual savings |
3 | | for the year ending December 31, 2023; |
4 | | (7) 2.8% deemed cumulative persisting annual savings |
5 | | for the year ending December 31, 2024; |
6 | | (8) 2.5% deemed cumulative persisting annual savings |
7 | | for the year ending December 31, 2025; |
8 | | (9) 2.3% deemed cumulative persisting annual savings |
9 | | for the year ending December 31, 2026; |
10 | | (10) 2.1% deemed cumulative persisting annual savings |
11 | | for the year ending December 31, 2027; |
12 | | (11) 1.8% deemed cumulative persisting annual savings |
13 | | for the year ending December 31, 2028; |
14 | | (12) 1.7% deemed cumulative persisting annual savings |
15 | | for the year ending December 31, 2029; |
16 | | (13) 1.5% deemed cumulative persisting annual savings |
17 | | for the year ending December 31, 2030; |
18 | | (14) 1.3% deemed cumulative persisting annual savings |
19 | | for the year ending December 31, 2031; |
20 | | (15) 1.1% deemed cumulative persisting annual savings |
21 | | for the year ending December 31, 2032; |
22 | | (16) 0.9% deemed cumulative persisting annual savings |
23 | | for the year ending December 31, 2033; |
24 | | (17) 0.7% deemed cumulative persisting annual savings |
25 | | for the year ending December 31, 2034; |
26 | | (18) 0.5% deemed cumulative persisting annual savings |
|
| | HB5539 Engrossed | - 25 - | LRB103 38494 CES 68630 b |
|
|
1 | | for the year ending December 31, 2035; |
2 | | (19) 0.4% deemed cumulative persisting annual savings |
3 | | for the year ending December 31, 2036; |
4 | | (20) 0.3% deemed cumulative persisting annual savings |
5 | | for the year ending December 31, 2037; |
6 | | (21) 0.2% deemed cumulative persisting annual savings |
7 | | for the year ending December 31, 2038; |
8 | | (22) 0.1% deemed cumulative persisting annual savings |
9 | | for the year ending December 31, 2039; and |
10 | | (23) 0.0% deemed cumulative persisting annual savings |
11 | | for the year ending December 31, 2040 and all subsequent |
12 | | years. |
13 | | (b-15) Beginning in 2018, electric utilities subject to |
14 | | this Section that serve less than 3,000,000 retail customers |
15 | | but more than 500,000 retail customers in the State shall |
16 | | achieve the following cumulative persisting annual savings |
17 | | goals, as modified by subsection (b-20) and subsection (f) of |
18 | | this Section and as compared to the deemed baseline as reduced |
19 | | by the number of MWhs equal to the sum of the annual |
20 | | consumption of customers that have opted out of subsections |
21 | | (a) through (j) of this Section under paragraph (1) of |
22 | | subsection (l) of this Section as averaged across the calendar |
23 | | years 2014, 2015, and 2016, through the implementation of |
24 | | energy efficiency measures during the applicable year and in |
25 | | prior years, but no earlier than January 1, 2012: |
26 | | (1) 7.4% cumulative persisting annual savings for the |
|
| | HB5539 Engrossed | - 26 - | LRB103 38494 CES 68630 b |
|
|
1 | | year ending December 31, 2018; |
2 | | (2) 8.2% cumulative persisting annual savings for the |
3 | | year ending December 31, 2019; |
4 | | (3) 9.0% cumulative persisting annual savings for the |
5 | | year ending December 31, 2020; |
6 | | (4) 9.8% cumulative persisting annual savings for the |
7 | | year ending December 31, 2021; |
8 | | (5) 10.6% cumulative persisting annual savings for the |
9 | | year ending December 31, 2022; |
10 | | (6) 11.4% cumulative persisting annual savings for the |
11 | | year ending December 31, 2023; |
12 | | (7) 12.2% cumulative persisting annual savings for the |
13 | | year ending December 31, 2024; |
14 | | (8) 13% cumulative persisting annual savings for the |
15 | | year ending December 31, 2025; |
16 | | (9) 13.6% cumulative persisting annual savings for the |
17 | | year ending December 31, 2026; |
18 | | (10) 14.2% cumulative persisting annual savings for |
19 | | the year ending December 31, 2027; |
20 | | (11) 14.8% cumulative persisting annual savings for |
21 | | the year ending December 31, 2028; |
22 | | (12) 15.4% cumulative persisting annual savings for |
23 | | the year ending December 31, 2029; and |
24 | | (13) 16% cumulative persisting annual savings for the |
25 | | year ending December 31, 2030. |
26 | | No later than December 31, 2021, the Illinois Commerce |
|
| | HB5539 Engrossed | - 27 - | LRB103 38494 CES 68630 b |
|
|
1 | | Commission shall establish additional cumulative persisting |
2 | | annual savings goals for the years 2031 through 2035. No later |
3 | | than December 31, 2024, the Illinois Commerce Commission shall |
4 | | establish additional cumulative persisting annual savings |
5 | | goals for the years 2036 through 2040. The Commission shall |
6 | | also establish additional cumulative persisting annual savings |
7 | | goals every 5 years thereafter to ensure that utilities always |
8 | | have goals that extend at least 11 years into the future. The |
9 | | cumulative persisting annual savings goals beyond the year |
10 | | 2030 shall increase by 0.6 percentage points per year, absent |
11 | | a Commission decision to initiate a proceeding to consider |
12 | | establishing goals that increase by more or less than that |
13 | | amount. Such a proceeding must be conducted in accordance with |
14 | | the procedures described in subsection (f) of this Section. If |
15 | | such a proceeding is initiated, the cumulative persisting |
16 | | annual savings goals established by the Commission through |
17 | | that proceeding shall reflect the Commission's best estimate |
18 | | of the maximum amount of additional savings that are forecast |
19 | | to be cost-effectively achievable unless such best estimates |
20 | | would result in goals that represent less than 0.4 percentage |
21 | | point annual increases in total cumulative persisting annual |
22 | | savings. The Commission may only establish goals that |
23 | | represent less than 0.4 percentage point annual increases in |
24 | | cumulative persisting annual savings if it can demonstrate, |
25 | | based on clear and convincing evidence and through independent |
26 | | analysis, that 0.4 percentage point increases are not |
|
| | HB5539 Engrossed | - 28 - | LRB103 38494 CES 68630 b |
|
|
1 | | cost-effectively achievable. The Commission shall inform its |
2 | | decision based on an energy efficiency potential study that |
3 | | conforms to the requirements of this Section. |
4 | | (b-20) Each electric utility subject to this Section may |
5 | | include cost-effective voltage optimization measures in its |
6 | | plans submitted under subsections (f) and (g) of this Section, |
7 | | and the costs incurred by a utility to implement the measures |
8 | | under a Commission-approved plan shall be recovered under the |
9 | | provisions of Article IX or Section 16-108.5 of this Act. For |
10 | | purposes of this Section, the measure life of voltage |
11 | | optimization measures shall be 15 years. The measure life |
12 | | period is independent of the depreciation rate of the voltage |
13 | | optimization assets deployed. Utilities may claim savings from |
14 | | voltage optimization on circuits for more than 15 years if |
15 | | they can demonstrate that they have made additional |
16 | | investments necessary to enable voltage optimization savings |
17 | | to continue beyond 15 years. Such demonstrations must be |
18 | | subject to the review of independent evaluation. |
19 | | Within 270 days after June 1, 2017 (the effective date of |
20 | | Public Act 99-906), an electric utility that serves less than |
21 | | 3,000,000 retail customers but more than 500,000 retail |
22 | | customers in the State shall file a plan with the Commission |
23 | | that identifies the cost-effective voltage optimization |
24 | | investment the electric utility plans to undertake through |
25 | | December 31, 2024. The Commission, after notice and hearing, |
26 | | shall approve or approve with modification the plan within 120 |
|
| | HB5539 Engrossed | - 29 - | LRB103 38494 CES 68630 b |
|
|
1 | | days after the plan's filing and, in the order approving or |
2 | | approving with modification the plan, the Commission shall |
3 | | adjust the applicable cumulative persisting annual savings |
4 | | goals set forth in subsection (b-15) to reflect any amount of |
5 | | cost-effective energy savings approved by the Commission that |
6 | | is greater than or less than the following cumulative |
7 | | persisting annual savings values attributable to voltage |
8 | | optimization for the applicable year: |
9 | | (1) 0.0% of cumulative persisting annual savings for |
10 | | the year ending December 31, 2018; |
11 | | (2) 0.17% of cumulative persisting annual savings for |
12 | | the year ending December 31, 2019; |
13 | | (3) 0.17% of cumulative persisting annual savings for |
14 | | the year ending December 31, 2020; |
15 | | (4) 0.33% of cumulative persisting annual savings for |
16 | | the year ending December 31, 2021; |
17 | | (5) 0.5% of cumulative persisting annual savings for |
18 | | the year ending December 31, 2022; |
19 | | (6) 0.67% of cumulative persisting annual savings for |
20 | | the year ending December 31, 2023; |
21 | | (7) 0.83% of cumulative persisting annual savings for |
22 | | the year ending December 31, 2024; and |
23 | | (8) 1.0% of cumulative persisting annual savings for |
24 | | the year ending December 31, 2025 and all subsequent |
25 | | years. |
26 | | (b-25) In the event an electric utility jointly offers an |
|
| | HB5539 Engrossed | - 30 - | LRB103 38494 CES 68630 b |
|
|
1 | | energy efficiency measure or program with a gas utility under |
2 | | plans approved under this Section and Section 8-104 of this |
3 | | Act, the electric utility may continue offering the program, |
4 | | including the gas energy efficiency measures, in the event the |
5 | | gas utility discontinues funding the program. In that event, |
6 | | the energy savings value associated with such other fuels |
7 | | shall be converted to electric energy savings on an equivalent |
8 | | Btu basis for the premises. However, the electric utility |
9 | | shall prioritize programs for low-income residential customers |
10 | | to the extent practicable. An electric utility may recover the |
11 | | costs of offering the gas energy efficiency measures under |
12 | | this subsection (b-25). |
13 | | For those energy efficiency measures or programs that save |
14 | | both electricity and other fuels but are not jointly offered |
15 | | with a gas utility under plans approved under this Section and |
16 | | Section 8-104 or not offered with an affiliated gas utility |
17 | | under paragraph (6) of subsection (f) of Section 8-104 of this |
18 | | Act, the electric utility may count savings of fuels other |
19 | | than electricity toward the achievement of its annual savings |
20 | | goal, and the energy savings value associated with such other |
21 | | fuels shall be converted to electric energy savings on an |
22 | | equivalent Btu basis at the premises. |
23 | | In no event shall more than 10% of each year's applicable |
24 | | annual total savings requirement as defined in paragraph (7.5) |
25 | | of subsection (g) of this Section be met through savings of |
26 | | fuels other than electricity. |
|
| | HB5539 Engrossed | - 31 - | LRB103 38494 CES 68630 b |
|
|
1 | | (b-27) Beginning in 2022, an electric utility may offer |
2 | | and promote measures that electrify space heating, water |
3 | | heating, cooling, drying, cooking, industrial processes, and |
4 | | other building and industrial end uses that would otherwise be |
5 | | served by combustion of fossil fuel at the premises, provided |
6 | | that the electrification measures reduce total energy |
7 | | consumption at the premises. The electric utility may count |
8 | | the reduction in energy consumption at the premises toward |
9 | | achievement of its annual savings goals. The reduction in |
10 | | energy consumption at the premises shall be calculated as the |
11 | | difference between: (A) the reduction in Btu consumption of |
12 | | fossil fuels as a result of electrification, converted to |
13 | | kilowatt-hour equivalents by dividing by 3,412 Btus per |
14 | | kilowatt hour; and (B) the increase in kilowatt hours of |
15 | | electricity consumption resulting from the displacement of |
16 | | fossil fuel consumption as a result of electrification. An |
17 | | electric utility may recover the costs of offering and |
18 | | promoting electrification measures under this subsection |
19 | | (b-27). |
20 | | In no event shall electrification savings counted toward |
21 | | each year's applicable annual total savings requirement, as |
22 | | defined in paragraph (7.5) of subsection (g) of this Section, |
23 | | be greater than: |
24 | | (1) 5% per year for each year from 2022 through 2025; |
25 | | (2) 10% per year for each year from 2026 through 2029; |
26 | | and |
|
| | HB5539 Engrossed | - 32 - | LRB103 38494 CES 68630 b |
|
|
1 | | (3) 15% per year for 2030 and all subsequent years. |
2 | | In addition, a minimum of 25% of all electrification savings |
3 | | counted toward a utility's applicable annual total savings |
4 | | requirement must be from electrification of end uses in |
5 | | low-income housing. The limitations on electrification savings |
6 | | that may be counted toward a utility's annual savings goals |
7 | | are separate from and in addition to the subsection (b-25) |
8 | | limitations governing the counting of the other fuel savings |
9 | | resulting from efficiency measures and programs. |
10 | | As part of the annual informational filing to the |
11 | | Commission that is required under paragraph (9) of subsection |
12 | | (g) of this Section, each utility shall identify the specific |
13 | | electrification measures offered under this subsection (b-27); |
14 | | the quantity of each electrification measure that was |
15 | | installed by its customers; the average total cost, average |
16 | | utility cost, average reduction in fossil fuel consumption, |
17 | | and average increase in electricity consumption associated |
18 | | with each electrification measure; the portion of |
19 | | installations of each electrification measure that were in |
20 | | low-income single-family housing, low-income multifamily |
21 | | housing, non-low-income single-family housing, non-low-income |
22 | | multifamily housing, commercial buildings, and industrial |
23 | | facilities; and the quantity of savings associated with each |
24 | | measure category in each customer category that are being |
25 | | counted toward the utility's applicable annual total savings |
26 | | requirement. Prior to installing an electrification measure, |
|
| | HB5539 Engrossed | - 33 - | LRB103 38494 CES 68630 b |
|
|
1 | | the utility shall provide a customer with an estimate of the |
2 | | impact of the new measure on the customer's average monthly |
3 | | electric bill and total annual energy expenses. |
4 | | (c) Electric utilities shall be responsible for overseeing |
5 | | the design, development, and filing of energy efficiency plans |
6 | | with the Commission and may, as part of that implementation, |
7 | | outsource various aspects of program development and |
8 | | implementation. A minimum of 10%, for electric utilities that |
9 | | serve more than 3,000,000 retail customers in the State, and a |
10 | | minimum of 7%, for electric utilities that serve less than |
11 | | 3,000,000 retail customers but more than 500,000 retail |
12 | | customers in the State, of the utility's entire portfolio |
13 | | funding level for a given year shall be used to procure |
14 | | cost-effective energy efficiency measures from units of local |
15 | | government, municipal corporations, school districts, public |
16 | | housing, public institutions of higher education, and |
17 | | community college districts, provided that a minimum |
18 | | percentage of available funds shall be used to procure energy |
19 | | efficiency from public housing, which percentage shall be |
20 | | equal to public housing's share of public building energy |
21 | | consumption. |
22 | | The utilities shall also implement energy efficiency |
23 | | measures targeted at low-income households, which, for |
24 | | purposes of this Section, shall be defined as households at or |
25 | | below 80% of area median income, and expenditures to implement |
26 | | the measures shall be no less than $40,000,000 per year for |
|
| | HB5539 Engrossed | - 34 - | LRB103 38494 CES 68630 b |
|
|
1 | | electric utilities that serve more than 3,000,000 retail |
2 | | customers in the State and no less than $13,000,000 per year |
3 | | for electric utilities that serve less than 3,000,000 retail |
4 | | customers but more than 500,000 retail customers in the State. |
5 | | The ratio of spending on efficiency programs targeted at |
6 | | low-income multifamily buildings to spending on efficiency |
7 | | programs targeted at low-income single-family buildings shall |
8 | | be designed to achieve levels of savings from each building |
9 | | type that are approximately proportional to the magnitude of |
10 | | cost-effective lifetime savings potential in each building |
11 | | type. Investment in low-income whole-building weatherization |
12 | | programs shall constitute a minimum of 80% of a utility's |
13 | | total budget specifically dedicated to serving low-income |
14 | | customers. |
15 | | The utilities shall work to bundle low-income energy |
16 | | efficiency offerings with other programs that serve low-income |
17 | | households to maximize the benefits going to these households. |
18 | | The utilities shall market and implement low-income energy |
19 | | efficiency programs in coordination with low-income assistance |
20 | | programs, the Illinois Solar for All Program, and |
21 | | weatherization whenever practicable. The program implementer |
22 | | shall walk the customer through the enrollment process for any |
23 | | programs for which the customer is eligible. The utilities |
24 | | shall also pilot targeting customers with high arrearages, |
25 | | high energy intensity (ratio of energy usage divided by home |
26 | | or unit square footage), or energy assistance programs with |
|
| | HB5539 Engrossed | - 35 - | LRB103 38494 CES 68630 b |
|
|
1 | | energy efficiency offerings, and then track reduction in |
2 | | arrearages as a result of the targeting. This targeting and |
3 | | bundling of low-income energy programs shall be offered to |
4 | | both low-income single-family and multifamily customers |
5 | | (owners and residents). |
6 | | The utilities shall invest in health and safety measures |
7 | | appropriate and necessary for comprehensively weatherizing a |
8 | | home or multifamily building, and shall implement a health and |
9 | | safety fund of at least 15% of the total income-qualified |
10 | | weatherization budget that shall be used for the purpose of |
11 | | making grants for technical assistance, construction, |
12 | | reconstruction, improvement, or repair of buildings to |
13 | | facilitate their participation in the energy efficiency |
14 | | programs targeted at low-income single-family and multifamily |
15 | | households. These funds may also be used for the purpose of |
16 | | making grants for technical assistance, construction, |
17 | | reconstruction, improvement, or repair of the following |
18 | | buildings to facilitate their participation in the energy |
19 | | efficiency programs created by this Section: (1) buildings |
20 | | that are owned or operated by registered 501(c)(3) public |
21 | | charities; and (2) day care centers, day care homes, or group |
22 | | day care homes, as defined under 89 Ill. Adm. Code Part 406, |
23 | | 407, or 408, respectively. |
24 | | Each electric utility shall assess opportunities to |
25 | | implement cost-effective energy efficiency measures and |
26 | | programs through a public housing authority or authorities |
|
| | HB5539 Engrossed | - 36 - | LRB103 38494 CES 68630 b |
|
|
1 | | located in its service territory. If such opportunities are |
2 | | identified, the utility shall propose such measures and |
3 | | programs to address the opportunities. Expenditures to address |
4 | | such opportunities shall be credited toward the minimum |
5 | | procurement and expenditure requirements set forth in this |
6 | | subsection (c). |
7 | | Implementation of energy efficiency measures and programs |
8 | | targeted at low-income households should be contracted, when |
9 | | it is practicable, to independent third parties that have |
10 | | demonstrated capabilities to serve such households, with a |
11 | | preference for not-for-profit entities and government agencies |
12 | | that have existing relationships with or experience serving |
13 | | low-income communities in the State. |
14 | | Each electric utility shall develop and implement |
15 | | reporting procedures that address and assist in determining |
16 | | the amount of energy savings that can be applied to the |
17 | | low-income procurement and expenditure requirements set forth |
18 | | in this subsection (c). Each electric utility shall also track |
19 | | the types and quantities or volumes of insulation and air |
20 | | sealing materials, and their associated energy saving |
21 | | benefits, installed in energy efficiency programs targeted at |
22 | | low-income single-family and multifamily households. |
23 | | The electric utilities shall participate in a low-income |
24 | | energy efficiency accountability committee ("the committee"), |
25 | | which will directly inform the design, implementation, and |
26 | | evaluation of the low-income and public-housing energy |
|
| | HB5539 Engrossed | - 37 - | LRB103 38494 CES 68630 b |
|
|
1 | | efficiency programs. The committee shall be comprised of the |
2 | | electric utilities subject to the requirements of this |
3 | | Section, the gas utilities subject to the requirements of |
4 | | Section 8-104 of this Act, the utilities' low-income energy |
5 | | efficiency implementation contractors, nonprofit |
6 | | organizations, community action agencies, advocacy groups, |
7 | | State and local governmental agencies, public-housing |
8 | | organizations, and representatives of community-based |
9 | | organizations, especially those living in or working with |
10 | | environmental justice communities and BIPOC communities. The |
11 | | committee shall be composed of 2 geographically differentiated |
12 | | subcommittees: one for stakeholders in northern Illinois and |
13 | | one for stakeholders in central and southern Illinois. The |
14 | | subcommittees shall meet together at least twice per year. |
15 | | There shall be one statewide leadership committee led by |
16 | | and composed of community-based organizations that are |
17 | | representative of BIPOC and environmental justice communities |
18 | | and that includes equitable representation from BIPOC |
19 | | communities. The leadership committee shall be composed of an |
20 | | equal number of representatives from the 2 subcommittees. The |
21 | | subcommittees shall address specific programs and issues, with |
22 | | the leadership committee convening targeted workgroups as |
23 | | needed. The leadership committee may elect to work with an |
24 | | independent facilitator to solicit and organize feedback, |
25 | | recommendations and meeting participation from a wide variety |
26 | | of community-based stakeholders. If a facilitator is used, |
|
| | HB5539 Engrossed | - 38 - | LRB103 38494 CES 68630 b |
|
|
1 | | they shall be fair and responsive to the needs of all |
2 | | stakeholders involved in the committee. |
3 | | All committee meetings must be accessible, with rotating |
4 | | locations if meetings are held in-person, virtual |
5 | | participation options, and materials and agendas circulated in |
6 | | advance. |
7 | | There shall also be opportunities for direct input by |
8 | | committee members outside of committee meetings, such as via |
9 | | individual meetings, surveys, emails and calls, to ensure |
10 | | robust participation by stakeholders with limited capacity and |
11 | | ability to attend committee meetings. Committee meetings shall |
12 | | emphasize opportunities to bundle and coordinate delivery of |
13 | | low-income energy efficiency with other programs that serve |
14 | | low-income communities, such as the Illinois Solar for All |
15 | | Program and bill payment assistance programs. Meetings shall |
16 | | include educational opportunities for stakeholders to learn |
17 | | more about these additional offerings, and the committee shall |
18 | | assist in figuring out the best methods for coordinated |
19 | | delivery and implementation of offerings when serving |
20 | | low-income communities. The committee shall directly and |
21 | | equitably influence and inform utility low-income and |
22 | | public-housing energy efficiency programs and priorities. |
23 | | Participating utilities shall implement recommendations from |
24 | | the committee whenever possible. |
25 | | Participating utilities shall track and report how input |
26 | | from the committee has led to new approaches and changes in |
|
| | HB5539 Engrossed | - 39 - | LRB103 38494 CES 68630 b |
|
|
1 | | their energy efficiency portfolios. This reporting shall occur |
2 | | at committee meetings and in quarterly energy efficiency |
3 | | reports to the Stakeholder Advisory Group and Illinois |
4 | | Commerce Commission, and other relevant reporting mechanisms. |
5 | | Participating utilities shall also report on relevant equity |
6 | | data and metrics requested by the committee, such as energy |
7 | | burden data, geographic, racial, and other relevant |
8 | | demographic data on where programs are being delivered and |
9 | | what populations programs are serving. |
10 | | The Illinois Commerce Commission shall oversee and have |
11 | | relevant staff participate in the committee. The committee |
12 | | shall have a budget of 0.25% of each utility's entire |
13 | | efficiency portfolio funding for a given year. The budget |
14 | | shall be overseen by the Commission. The budget shall be used |
15 | | to provide grants for community-based organizations serving on |
16 | | the leadership committee, stipends for community-based |
17 | | organizations participating in the committee, grants for |
18 | | community-based organizations to do energy efficiency outreach |
19 | | and education, and relevant meeting needs as determined by the |
20 | | leadership committee. The education and outreach shall |
21 | | include, but is not limited to, basic energy efficiency |
22 | | education, information about low-income energy efficiency |
23 | | programs, and information on the committee's purpose, |
24 | | structure, and activities. |
25 | | (d) Notwithstanding any other provision of law to the |
26 | | contrary, a utility providing approved energy efficiency |
|
| | HB5539 Engrossed | - 40 - | LRB103 38494 CES 68630 b |
|
|
1 | | measures and, if applicable, demand-response measures in the |
2 | | State shall be permitted to recover all reasonable and |
3 | | prudently incurred costs of those measures from all retail |
4 | | customers, except as provided in subsection (l) of this |
5 | | Section, as follows, provided that nothing in this subsection |
6 | | (d) permits the double recovery of such costs from customers: |
7 | | (1) The utility may recover its costs through an |
8 | | automatic adjustment clause tariff filed with and approved |
9 | | by the Commission. The tariff shall be established outside |
10 | | the context of a general rate case. Each year the |
11 | | Commission shall initiate a review to reconcile any |
12 | | amounts collected with the actual costs and to determine |
13 | | the required adjustment to the annual tariff factor to |
14 | | match annual expenditures. To enable the financing of the |
15 | | incremental capital expenditures, including regulatory |
16 | | assets, for electric utilities that serve less than |
17 | | 3,000,000 retail customers but more than 500,000 retail |
18 | | customers in the State, the utility's actual year-end |
19 | | capital structure that includes a common equity ratio, |
20 | | excluding goodwill, of up to and including 50% of the |
21 | | total capital structure shall be deemed reasonable and |
22 | | used to set rates. |
23 | | (2) A utility may recover its costs through an energy |
24 | | efficiency formula rate approved by the Commission under a |
25 | | filing under subsections (f) and (g) of this Section, |
26 | | which shall specify the cost components that form the |
|
| | HB5539 Engrossed | - 41 - | LRB103 38494 CES 68630 b |
|
|
1 | | basis of the rate charged to customers with sufficient |
2 | | specificity to operate in a standardized manner and be |
3 | | updated annually with transparent information that |
4 | | reflects the utility's actual costs to be recovered during |
5 | | the applicable rate year, which is the period beginning |
6 | | with the first billing day of January and extending |
7 | | through the last billing day of the following December. |
8 | | The energy efficiency formula rate shall be implemented |
9 | | through a tariff filed with the Commission under |
10 | | subsections (f) and (g) of this Section that is consistent |
11 | | with the provisions of this paragraph (2) and that shall |
12 | | be applicable to all delivery services customers. The |
13 | | Commission shall conduct an investigation of the tariff in |
14 | | a manner consistent with the provisions of this paragraph |
15 | | (2), subsections (f) and (g) of this Section, and the |
16 | | provisions of Article IX of this Act to the extent they do |
17 | | not conflict with this paragraph (2). The energy |
18 | | efficiency formula rate approved by the Commission shall |
19 | | remain in effect at the discretion of the utility and |
20 | | shall do the following: |
21 | | (A) Provide for the recovery of the utility's |
22 | | actual costs incurred under this Section that are |
23 | | prudently incurred and reasonable in amount consistent |
24 | | with Commission practice and law. The sole fact that a |
25 | | cost differs from that incurred in a prior calendar |
26 | | year or that an investment is different from that made |
|
| | HB5539 Engrossed | - 42 - | LRB103 38494 CES 68630 b |
|
|
1 | | in a prior calendar year shall not imply the |
2 | | imprudence or unreasonableness of that cost or |
3 | | investment. |
4 | | (B) Reflect the utility's actual year-end capital |
5 | | structure for the applicable calendar year, excluding |
6 | | goodwill, subject to a determination of prudence and |
7 | | reasonableness consistent with Commission practice and |
8 | | law. To enable the financing of the incremental |
9 | | capital expenditures, including regulatory assets, for |
10 | | electric utilities that serve less than 3,000,000 |
11 | | retail customers but more than 500,000 retail |
12 | | customers in the State, a participating electric |
13 | | utility's actual year-end capital structure that |
14 | | includes a common equity ratio, excluding goodwill, of |
15 | | up to and including 50% of the total capital structure |
16 | | shall be deemed reasonable and used to set rates. |
17 | | (C) Include a cost of equity, which shall be |
18 | | calculated as the sum of the following: |
19 | | (i) the average for the applicable calendar |
20 | | year of the monthly average yields of 30-year U.S. |
21 | | Treasury bonds published by the Board of Governors |
22 | | of the Federal Reserve System in its weekly H.15 |
23 | | Statistical Release or successor publication; and |
24 | | (ii) 580 basis points. |
25 | | At such time as the Board of Governors of the |
26 | | Federal Reserve System ceases to include the monthly |
|
| | HB5539 Engrossed | - 43 - | LRB103 38494 CES 68630 b |
|
|
1 | | average yields of 30-year U.S. Treasury bonds in its |
2 | | weekly H.15 Statistical Release or successor |
3 | | publication, the monthly average yields of the U.S. |
4 | | Treasury bonds then having the longest duration |
5 | | published by the Board of Governors in its weekly H.15 |
6 | | Statistical Release or successor publication shall |
7 | | instead be used for purposes of this paragraph (2). |
8 | | (D) Permit and set forth protocols, subject to a |
9 | | determination of prudence and reasonableness |
10 | | consistent with Commission practice and law, for the |
11 | | following: |
12 | | (i) recovery of incentive compensation expense |
13 | | that is based on the achievement of operational |
14 | | metrics, including metrics related to budget |
15 | | controls, outage duration and frequency, safety, |
16 | | customer service, efficiency and productivity, and |
17 | | environmental compliance; however, this protocol |
18 | | shall not apply if such expense related to costs |
19 | | incurred under this Section is recovered under |
20 | | Article IX or Section 16-108.5 of this Act; |
21 | | incentive compensation expense that is based on |
22 | | net income or an affiliate's earnings per share |
23 | | shall not be recoverable under the energy |
24 | | efficiency formula rate; |
25 | | (ii) recovery of pension and other |
26 | | post-employment benefits expense, provided that |
|
| | HB5539 Engrossed | - 44 - | LRB103 38494 CES 68630 b |
|
|
1 | | such costs are supported by an actuarial study; |
2 | | however, this protocol shall not apply if such |
3 | | expense related to costs incurred under this |
4 | | Section is recovered under Article IX or Section |
5 | | 16-108.5 of this Act; |
6 | | (iii) recovery of existing regulatory assets |
7 | | over the periods previously authorized by the |
8 | | Commission; |
9 | | (iv) as described in subsection (e), |
10 | | amortization of costs incurred under this Section; |
11 | | and |
12 | | (v) projected, weather normalized billing |
13 | | determinants for the applicable rate year. |
14 | | (E) Provide for an annual reconciliation, as |
15 | | described in paragraph (3) of this subsection (d), |
16 | | less any deferred taxes related to the reconciliation, |
17 | | with interest at an annual rate of return equal to the |
18 | | utility's weighted average cost of capital, including |
19 | | a revenue conversion factor calculated to recover or |
20 | | refund all additional income taxes that may be payable |
21 | | or receivable as a result of that return, of the energy |
22 | | efficiency revenue requirement reflected in rates for |
23 | | each calendar year, beginning with the calendar year |
24 | | in which the utility files its energy efficiency |
25 | | formula rate tariff under this paragraph (2), with |
26 | | what the revenue requirement would have been had the |
|
| | HB5539 Engrossed | - 45 - | LRB103 38494 CES 68630 b |
|
|
1 | | actual cost information for the applicable calendar |
2 | | year been available at the filing date. |
3 | | The utility shall file, together with its tariff, the |
4 | | projected costs to be incurred by the utility during the |
5 | | rate year under the utility's multi-year plan approved |
6 | | under subsections (f) and (g) of this Section, including, |
7 | | but not limited to, the projected capital investment costs |
8 | | and projected regulatory asset balances with |
9 | | correspondingly updated depreciation and amortization |
10 | | reserves and expense, that shall populate the energy |
11 | | efficiency formula rate and set the initial rates under |
12 | | the formula. |
13 | | The Commission shall review the proposed tariff in |
14 | | conjunction with its review of a proposed multi-year plan, |
15 | | as specified in paragraph (5) of subsection (g) of this |
16 | | Section. The review shall be based on the same evidentiary |
17 | | standards, including, but not limited to, those concerning |
18 | | the prudence and reasonableness of the costs incurred by |
19 | | the utility, the Commission applies in a hearing to review |
20 | | a filing for a general increase in rates under Article IX |
21 | | of this Act. The initial rates shall take effect beginning |
22 | | with the January monthly billing period following the |
23 | | Commission's approval. |
24 | | The tariff's rate design and cost allocation across |
25 | | customer classes shall be consistent with the utility's |
26 | | automatic adjustment clause tariff in effect on June 1, |
|
| | HB5539 Engrossed | - 46 - | LRB103 38494 CES 68630 b |
|
|
1 | | 2017 (the effective date of Public Act 99-906); however, |
2 | | the Commission may revise the tariff's rate design and |
3 | | cost allocation in subsequent proceedings under paragraph |
4 | | (3) of this subsection (d). |
5 | | If the energy efficiency formula rate is terminated, |
6 | | the then current rates shall remain in effect until such |
7 | | time as the energy efficiency costs are incorporated into |
8 | | new rates that are set under this subsection (d) or |
9 | | Article IX of this Act, subject to retroactive rate |
10 | | adjustment, with interest, to reconcile rates charged with |
11 | | actual costs. |
12 | | (3) The provisions of this paragraph (3) shall only |
13 | | apply to an electric utility that has elected to file an |
14 | | energy efficiency formula rate under paragraph (2) of this |
15 | | subsection (d). Subsequent to the Commission's issuance of |
16 | | an order approving the utility's energy efficiency formula |
17 | | rate structure and protocols, and initial rates under |
18 | | paragraph (2) of this subsection (d), the utility shall |
19 | | file, on or before June 1 of each year, with the Chief |
20 | | Clerk of the Commission its updated cost inputs to the |
21 | | energy efficiency formula rate for the applicable rate |
22 | | year and the corresponding new charges, as well as the |
23 | | information described in paragraph (9) of subsection (g) |
24 | | of this Section. Each such filing shall conform to the |
25 | | following requirements and include the following |
26 | | information: |
|
| | HB5539 Engrossed | - 47 - | LRB103 38494 CES 68630 b |
|
|
1 | | (A) The inputs to the energy efficiency formula |
2 | | rate for the applicable rate year shall be based on the |
3 | | projected costs to be incurred by the utility during |
4 | | the rate year under the utility's multi-year plan |
5 | | approved under subsections (f) and (g) of this |
6 | | Section, including, but not limited to, projected |
7 | | capital investment costs and projected regulatory |
8 | | asset balances with correspondingly updated |
9 | | depreciation and amortization reserves and expense. |
10 | | The filing shall also include a reconciliation of the |
11 | | energy efficiency revenue requirement that was in |
12 | | effect for the prior rate year (as set by the cost |
13 | | inputs for the prior rate year) with the actual |
14 | | revenue requirement for the prior rate year |
15 | | (determined using a year-end rate base) that uses |
16 | | amounts reflected in the applicable FERC Form 1 that |
17 | | reports the actual costs for the prior rate year. Any |
18 | | over-collection or under-collection indicated by such |
19 | | reconciliation shall be reflected as a credit against, |
20 | | or recovered as an additional charge to, respectively, |
21 | | with interest calculated at a rate equal to the |
22 | | utility's weighted average cost of capital approved by |
23 | | the Commission for the prior rate year, the charges |
24 | | for the applicable rate year. Such over-collection or |
25 | | under-collection shall be adjusted to remove any |
26 | | deferred taxes related to the reconciliation, for |
|
| | HB5539 Engrossed | - 48 - | LRB103 38494 CES 68630 b |
|
|
1 | | purposes of calculating interest at an annual rate of |
2 | | return equal to the utility's weighted average cost of |
3 | | capital approved by the Commission for the prior rate |
4 | | year, including a revenue conversion factor calculated |
5 | | to recover or refund all additional income taxes that |
6 | | may be payable or receivable as a result of that |
7 | | return. Each reconciliation shall be certified by the |
8 | | participating utility in the same manner that FERC |
9 | | Form 1 is certified. The filing shall also include the |
10 | | charge or credit, if any, resulting from the |
11 | | calculation required by subparagraph (E) of paragraph |
12 | | (2) of this subsection (d). |
13 | | Notwithstanding any other provision of law to the |
14 | | contrary, the intent of the reconciliation is to |
15 | | ultimately reconcile both the revenue requirement |
16 | | reflected in rates for each calendar year, beginning |
17 | | with the calendar year in which the utility files its |
18 | | energy efficiency formula rate tariff under paragraph |
19 | | (2) of this subsection (d), with what the revenue |
20 | | requirement determined using a year-end rate base for |
21 | | the applicable calendar year would have been had the |
22 | | actual cost information for the applicable calendar |
23 | | year been available at the filing date. |
24 | | For purposes of this Section, "FERC Form 1" means |
25 | | the Annual Report of Major Electric Utilities, |
26 | | Licensees and Others that electric utilities are |
|
| | HB5539 Engrossed | - 49 - | LRB103 38494 CES 68630 b |
|
|
1 | | required to file with the Federal Energy Regulatory |
2 | | Commission under the Federal Power Act, Sections 3, |
3 | | 4(a), 304 and 209, modified as necessary to be |
4 | | consistent with 83 Ill. Adm. Code Part 415 as of May 1, |
5 | | 2011. Nothing in this Section is intended to allow |
6 | | costs that are not otherwise recoverable to be |
7 | | recoverable by virtue of inclusion in FERC Form 1. |
8 | | (B) The new charges shall take effect beginning on |
9 | | the first billing day of the following January billing |
10 | | period and remain in effect through the last billing |
11 | | day of the next December billing period regardless of |
12 | | whether the Commission enters upon a hearing under |
13 | | this paragraph (3). |
14 | | (C) The filing shall include relevant and |
15 | | necessary data and documentation for the applicable |
16 | | rate year. Normalization adjustments shall not be |
17 | | required. |
18 | | Within 45 days after the utility files its annual |
19 | | update of cost inputs to the energy efficiency formula |
20 | | rate, the Commission shall with reasonable notice, |
21 | | initiate a proceeding concerning whether the projected |
22 | | costs to be incurred by the utility and recovered during |
23 | | the applicable rate year, and that are reflected in the |
24 | | inputs to the energy efficiency formula rate, are |
25 | | consistent with the utility's approved multi-year plan |
26 | | under subsections (f) and (g) of this Section and whether |
|
| | HB5539 Engrossed | - 50 - | LRB103 38494 CES 68630 b |
|
|
1 | | the costs incurred by the utility during the prior rate |
2 | | year were prudent and reasonable. The Commission shall |
3 | | also have the authority to investigate the information and |
4 | | data described in paragraph (9) of subsection (g) of this |
5 | | Section, including the proposed adjustment to the |
6 | | utility's return on equity component of its weighted |
7 | | average cost of capital. During the course of the |
8 | | proceeding, each objection shall be stated with |
9 | | particularity and evidence provided in support thereof, |
10 | | after which the utility shall have the opportunity to |
11 | | rebut the evidence. Discovery shall be allowed consistent |
12 | | with the Commission's Rules of Practice, which Rules of |
13 | | Practice shall be enforced by the Commission or the |
14 | | assigned administrative law judge. The Commission shall |
15 | | apply the same evidentiary standards, including, but not |
16 | | limited to, those concerning the prudence and |
17 | | reasonableness of the costs incurred by the utility, |
18 | | during the proceeding as it would apply in a proceeding to |
19 | | review a filing for a general increase in rates under |
20 | | Article IX of this Act. The Commission shall not, however, |
21 | | have the authority in a proceeding under this paragraph |
22 | | (3) to consider or order any changes to the structure or |
23 | | protocols of the energy efficiency formula rate approved |
24 | | under paragraph (2) of this subsection (d). In a |
25 | | proceeding under this paragraph (3), the Commission shall |
26 | | enter its order no later than the earlier of 195 days after |
|
| | HB5539 Engrossed | - 51 - | LRB103 38494 CES 68630 b |
|
|
1 | | the utility's filing of its annual update of cost inputs |
2 | | to the energy efficiency formula rate or December 15. The |
3 | | utility's proposed return on equity calculation, as |
4 | | described in paragraphs (7) through (9) of subsection (g) |
5 | | of this Section, shall be deemed the final, approved |
6 | | calculation on December 15 of the year in which it is filed |
7 | | unless the Commission enters an order on or before |
8 | | December 15, after notice and hearing, that modifies such |
9 | | calculation consistent with this Section. The Commission's |
10 | | determinations of the prudence and reasonableness of the |
11 | | costs incurred, and determination of such return on equity |
12 | | calculation, for the applicable calendar year shall be |
13 | | final upon entry of the Commission's order and shall not |
14 | | be subject to reopening, reexamination, or collateral |
15 | | attack in any other Commission proceeding, case, docket, |
16 | | order, rule, or regulation; however, nothing in this |
17 | | paragraph (3) shall prohibit a party from petitioning the |
18 | | Commission to rehear or appeal to the courts the order |
19 | | under the provisions of this Act. |
20 | | (e) Beginning on June 1, 2017 (the effective date of |
21 | | Public Act 99-906), a utility subject to the requirements of |
22 | | this Section may elect to defer, as a regulatory asset, up to |
23 | | the full amount of its expenditures incurred under this |
24 | | Section for each annual period, including, but not limited to, |
25 | | any expenditures incurred above the funding level set by |
26 | | subsection (f) of this Section for a given year. The total |
|
| | HB5539 Engrossed | - 52 - | LRB103 38494 CES 68630 b |
|
|
1 | | expenditures deferred as a regulatory asset in a given year |
2 | | shall be amortized and recovered over a period that is equal to |
3 | | the weighted average of the energy efficiency measure lives |
4 | | implemented for that year that are reflected in the regulatory |
5 | | asset. The unamortized balance shall be recognized as of |
6 | | December 31 for a given year. The utility shall also earn a |
7 | | return on the total of the unamortized balances of all of the |
8 | | energy efficiency regulatory assets, less any deferred taxes |
9 | | related to those unamortized balances, at an annual rate equal |
10 | | to the utility's weighted average cost of capital that |
11 | | includes, based on a year-end capital structure, the utility's |
12 | | actual cost of debt for the applicable calendar year and a cost |
13 | | of equity, which shall be calculated as the sum of the (i) the |
14 | | average for the applicable calendar year of the monthly |
15 | | average yields of 30-year U.S. Treasury bonds published by the |
16 | | Board of Governors of the Federal Reserve System in its weekly |
17 | | H.15 Statistical Release or successor publication; and (ii) |
18 | | 580 basis points, including a revenue conversion factor |
19 | | calculated to recover or refund all additional income taxes |
20 | | that may be payable or receivable as a result of that return. |
21 | | Capital investment costs shall be depreciated and recovered |
22 | | over their useful lives consistent with generally accepted |
23 | | accounting principles. The weighted average cost of capital |
24 | | shall be applied to the capital investment cost balance, less |
25 | | any accumulated depreciation and accumulated deferred income |
26 | | taxes, as of December 31 for a given year. |
|
| | HB5539 Engrossed | - 53 - | LRB103 38494 CES 68630 b |
|
|
1 | | When an electric utility creates a regulatory asset under |
2 | | the provisions of this Section, the costs are recovered over a |
3 | | period during which customers also receive a benefit which is |
4 | | in the public interest. Accordingly, it is the intent of the |
5 | | General Assembly that an electric utility that elects to |
6 | | create a regulatory asset under the provisions of this Section |
7 | | shall recover all of the associated costs as set forth in this |
8 | | Section. After the Commission has approved the prudence and |
9 | | reasonableness of the costs that comprise the regulatory |
10 | | asset, the electric utility shall be permitted to recover all |
11 | | such costs, and the value and recoverability through rates of |
12 | | the associated regulatory asset shall not be limited, altered, |
13 | | impaired, or reduced. |
14 | | (f) Beginning in 2017, each electric utility shall file an |
15 | | energy efficiency plan with the Commission to meet the energy |
16 | | efficiency standards for the next applicable multi-year period |
17 | | beginning January 1 of the year following the filing, |
18 | | according to the schedule set forth in paragraphs (1) through |
19 | | (3) of this subsection (f). If a utility does not file such a |
20 | | plan on or before the applicable filing deadline for the plan, |
21 | | it shall face a penalty of $100,000 per day until the plan is |
22 | | filed. |
23 | | (1) No later than 30 days after June 1, 2017 (the |
24 | | effective date of Public Act 99-906), each electric |
25 | | utility shall file a 4-year energy efficiency plan |
26 | | commencing on January 1, 2018 that is designed to achieve |
|
| | HB5539 Engrossed | - 54 - | LRB103 38494 CES 68630 b |
|
|
1 | | the cumulative persisting annual savings goals specified |
2 | | in paragraphs (1) through (4) of subsection (b-5) of this |
3 | | Section or in paragraphs (1) through (4) of subsection |
4 | | (b-15) of this Section, as applicable, through |
5 | | implementation of energy efficiency measures; however, the |
6 | | goals may be reduced if the utility's expenditures are |
7 | | limited pursuant to subsection (m) of this Section or, for |
8 | | a utility that serves less than 3,000,000 retail |
9 | | customers, if each of the following conditions are met: |
10 | | (A) the plan's analysis and forecasts of the utility's |
11 | | ability to acquire energy savings demonstrate that |
12 | | achievement of such goals is not cost effective; and (B) |
13 | | the amount of energy savings achieved by the utility as |
14 | | determined by the independent evaluator for the most |
15 | | recent year for which savings have been evaluated |
16 | | preceding the plan filing was less than the average annual |
17 | | amount of savings required to achieve the goals for the |
18 | | applicable 4-year plan period. Except as provided in |
19 | | subsection (m) of this Section, annual increases in |
20 | | cumulative persisting annual savings goals during the |
21 | | applicable 4-year plan period shall not be reduced to |
22 | | amounts that are less than the maximum amount of |
23 | | cumulative persisting annual savings that is forecast to |
24 | | be cost-effectively achievable during the 4-year plan |
25 | | period. The Commission shall review any proposed goal |
26 | | reduction as part of its review and approval of the |
|
| | HB5539 Engrossed | - 55 - | LRB103 38494 CES 68630 b |
|
|
1 | | utility's proposed plan. |
2 | | (2) No later than March 1, 2021, each electric utility |
3 | | shall file a 4-year energy efficiency plan commencing on |
4 | | January 1, 2022 that is designed to achieve the cumulative |
5 | | persisting annual savings goals specified in paragraphs |
6 | | (5) through (8) of subsection (b-5) of this Section or in |
7 | | paragraphs (5) through (8) of subsection (b-15) of this |
8 | | Section, as applicable, through implementation of energy |
9 | | efficiency measures; however, the goals may be reduced if |
10 | | either (1) clear and convincing evidence demonstrates, |
11 | | through independent analysis, that the expenditure limits |
12 | | in subsection (m) of this Section preclude full |
13 | | achievement of the goals or (2) each of the following |
14 | | conditions are met: (A) the plan's analysis and forecasts |
15 | | of the utility's ability to acquire energy savings |
16 | | demonstrate by clear and convincing evidence and through |
17 | | independent analysis that achievement of such goals is not |
18 | | cost effective; and (B) the amount of energy savings |
19 | | achieved by the utility as determined by the independent |
20 | | evaluator for the most recent year for which savings have |
21 | | been evaluated preceding the plan filing was less than the |
22 | | average annual amount of savings required to achieve the |
23 | | goals for the applicable 4-year plan period. If there is |
24 | | not clear and convincing evidence that achieving the |
25 | | savings goals specified in paragraph (b-5) or (b-15) of |
26 | | this Section is possible both cost-effectively and within |
|
| | HB5539 Engrossed | - 56 - | LRB103 38494 CES 68630 b |
|
|
1 | | the expenditure limits in subsection (m), such savings |
2 | | goals shall not be reduced. Except as provided in |
3 | | subsection (m) of this Section, annual increases in |
4 | | cumulative persisting annual savings goals during the |
5 | | applicable 4-year plan period shall not be reduced to |
6 | | amounts that are less than the maximum amount of |
7 | | cumulative persisting annual savings that is forecast to |
8 | | be cost-effectively achievable during the 4-year plan |
9 | | period. The Commission shall review any proposed goal |
10 | | reduction as part of its review and approval of the |
11 | | utility's proposed plan. |
12 | | (3) No later than March 1, 2025, each electric utility |
13 | | shall file a 4-year energy efficiency plan commencing on |
14 | | January 1, 2026 that is designed to achieve the cumulative |
15 | | persisting annual savings goals specified in paragraphs |
16 | | (9) through (12) of subsection (b-5) of this Section or in |
17 | | paragraphs (9) through (12) of subsection (b-15) of this |
18 | | Section, as applicable, through implementation of energy |
19 | | efficiency measures; however, the goals may be reduced if |
20 | | either (1) clear and convincing evidence demonstrates, |
21 | | through independent analysis, that the expenditure limits |
22 | | in subsection (m) of this Section preclude full |
23 | | achievement of the goals or (2) each of the following |
24 | | conditions are met: (A) the plan's analysis and forecasts |
25 | | of the utility's ability to acquire energy savings |
26 | | demonstrate by clear and convincing evidence and through |
|
| | HB5539 Engrossed | - 57 - | LRB103 38494 CES 68630 b |
|
|
1 | | independent analysis that achievement of such goals is not |
2 | | cost effective; and (B) the amount of energy savings |
3 | | achieved by the utility as determined by the independent |
4 | | evaluator for the most recent year for which savings have |
5 | | been evaluated preceding the plan filing was less than the |
6 | | average annual amount of savings required to achieve the |
7 | | goals for the applicable 4-year plan period. If there is |
8 | | not clear and convincing evidence that achieving the |
9 | | savings goals specified in paragraphs (b-5) or (b-15) of |
10 | | this Section is possible both cost-effectively and within |
11 | | the expenditure limits in subsection (m), such savings |
12 | | goals shall not be reduced. Except as provided in |
13 | | subsection (m) of this Section, annual increases in |
14 | | cumulative persisting annual savings goals during the |
15 | | applicable 4-year plan period shall not be reduced to |
16 | | amounts that are less than the maximum amount of |
17 | | cumulative persisting annual savings that is forecast to |
18 | | be cost-effectively achievable during the 4-year plan |
19 | | period. The Commission shall review any proposed goal |
20 | | reduction as part of its review and approval of the |
21 | | utility's proposed plan. |
22 | | (4) No later than March 1, 2029, and every 4 years |
23 | | thereafter, each electric utility shall file a 4-year |
24 | | energy efficiency plan commencing on January 1, 2030, and |
25 | | every 4 years thereafter, respectively, that is designed |
26 | | to achieve the cumulative persisting annual savings goals |
|
| | HB5539 Engrossed | - 58 - | LRB103 38494 CES 68630 b |
|
|
1 | | established by the Illinois Commerce Commission pursuant |
2 | | to direction of subsections (b-5) and (b-15) of this |
3 | | Section, as applicable, through implementation of energy |
4 | | efficiency measures; however, the goals may be reduced if |
5 | | either (1) clear and convincing evidence and independent |
6 | | analysis demonstrates that the expenditure limits in |
7 | | subsection (m) of this Section preclude full achievement |
8 | | of the goals or (2) each of the following conditions are |
9 | | met: (A) the plan's analysis and forecasts of the |
10 | | utility's ability to acquire energy savings demonstrate by |
11 | | clear and convincing evidence and through independent |
12 | | analysis that achievement of such goals is not |
13 | | cost-effective; and (B) the amount of energy savings |
14 | | achieved by the utility as determined by the independent |
15 | | evaluator for the most recent year for which savings have |
16 | | been evaluated preceding the plan filing was less than the |
17 | | average annual amount of savings required to achieve the |
18 | | goals for the applicable 4-year plan period. If there is |
19 | | not clear and convincing evidence that achieving the |
20 | | savings goals specified in paragraphs (b-5) or (b-15) of |
21 | | this Section is possible both cost-effectively and within |
22 | | the expenditure limits in subsection (m), such savings |
23 | | goals shall not be reduced. Except as provided in |
24 | | subsection (m) of this Section, annual increases in |
25 | | cumulative persisting annual savings goals during the |
26 | | applicable 4-year plan period shall not be reduced to |
|
| | HB5539 Engrossed | - 59 - | LRB103 38494 CES 68630 b |
|
|
1 | | amounts that are less than the maximum amount of |
2 | | cumulative persisting annual savings that is forecast to |
3 | | be cost-effectively achievable during the 4-year plan |
4 | | period. The Commission shall review any proposed goal |
5 | | reduction as part of its review and approval of the |
6 | | utility's proposed plan. |
7 | | Each utility's plan shall set forth the utility's |
8 | | proposals to meet the energy efficiency standards identified |
9 | | in subsection (b-5) or (b-15), as applicable and as such |
10 | | standards may have been modified under this subsection (f), |
11 | | taking into account the unique circumstances of the utility's |
12 | | service territory. For those plans commencing on January 1, |
13 | | 2018, the Commission shall seek public comment on the |
14 | | utility's plan and shall issue an order approving or |
15 | | disapproving each plan no later than 105 days after June 1, |
16 | | 2017 (the effective date of Public Act 99-906). For those |
17 | | plans commencing after December 31, 2021, the Commission shall |
18 | | seek public comment on the utility's plan and shall issue an |
19 | | order approving or disapproving each plan within 6 months |
20 | | after its submission. If the Commission disapproves a plan, |
21 | | the Commission shall, within 30 days, describe in detail the |
22 | | reasons for the disapproval and describe a path by which the |
23 | | utility may file a revised draft of the plan to address the |
24 | | Commission's concerns satisfactorily. If the utility does not |
25 | | refile with the Commission within 60 days, the utility shall |
26 | | be subject to penalties at a rate of $100,000 per day until the |
|
| | HB5539 Engrossed | - 60 - | LRB103 38494 CES 68630 b |
|
|
1 | | plan is filed. This process shall continue, and penalties |
2 | | shall accrue, until the utility has successfully filed a |
3 | | portfolio of energy efficiency and demand-response measures. |
4 | | Penalties shall be deposited into the Energy Efficiency Trust |
5 | | Fund. |
6 | | (g) In submitting proposed plans and funding levels under |
7 | | subsection (f) of this Section to meet the savings goals |
8 | | identified in subsection (b-5) or (b-15) of this Section, as |
9 | | applicable, the utility shall: |
10 | | (1) Demonstrate that its proposed energy efficiency |
11 | | measures will achieve the applicable requirements that are |
12 | | identified in subsection (b-5) or (b-15) of this Section, |
13 | | as modified by subsection (f) of this Section. |
14 | | (2) (Blank). |
15 | | (2.5) Demonstrate consideration of program options for |
16 | | (A) advancing new building codes, appliance standards, and |
17 | | municipal regulations governing existing and new building |
18 | | efficiency improvements and (B) supporting efforts to |
19 | | improve compliance with new building codes, appliance |
20 | | standards and municipal regulations, as potentially |
21 | | cost-effective means of acquiring energy savings to count |
22 | | toward savings goals. |
23 | | (3) Demonstrate that its overall portfolio of |
24 | | measures, not including low-income programs described in |
25 | | subsection (c) of this Section, is cost-effective using |
26 | | the total resource cost test or complies with paragraphs |
|
| | HB5539 Engrossed | - 61 - | LRB103 38494 CES 68630 b |
|
|
1 | | (1) through (3) of subsection (f) of this Section and |
2 | | represents a diverse cross-section of opportunities for |
3 | | customers of all rate classes, other than those customers |
4 | | described in subsection (l) of this Section, to |
5 | | participate in the programs. Individual measures need not |
6 | | be cost effective. |
7 | | (3.5) Demonstrate that the utility's plan integrates |
8 | | the delivery of energy efficiency programs with natural |
9 | | gas efficiency programs, programs promoting distributed |
10 | | solar, programs promoting demand response and other |
11 | | efforts to address bill payment issues, including, but not |
12 | | limited to, LIHEAP and the Percentage of Income Payment |
13 | | Plan, to the extent such integration is practical and has |
14 | | the potential to enhance customer engagement, minimize |
15 | | market confusion, or reduce administrative costs. |
16 | | (4) Present a third-party energy efficiency |
17 | | implementation program subject to the following |
18 | | requirements: |
19 | | (A) beginning with the year commencing January 1, |
20 | | 2019, electric utilities that serve more than |
21 | | 3,000,000 retail customers in the State shall fund |
22 | | third-party energy efficiency programs in an amount |
23 | | that is no less than $25,000,000 per year, and |
24 | | electric utilities that serve less than 3,000,000 |
25 | | retail customers but more than 500,000 retail |
26 | | customers in the State shall fund third-party energy |
|
| | HB5539 Engrossed | - 62 - | LRB103 38494 CES 68630 b |
|
|
1 | | efficiency programs in an amount that is no less than |
2 | | $8,350,000 per year; |
3 | | (B) during 2018, the utility shall conduct a |
4 | | solicitation process for purposes of requesting |
5 | | proposals from third-party vendors for those |
6 | | third-party energy efficiency programs to be offered |
7 | | during one or more of the years commencing January 1, |
8 | | 2019, January 1, 2020, and January 1, 2021; for those |
9 | | multi-year plans commencing on January 1, 2022 and |
10 | | January 1, 2026, the utility shall conduct a |
11 | | solicitation process during 2021 and 2025, |
12 | | respectively, for purposes of requesting proposals |
13 | | from third-party vendors for those third-party energy |
14 | | efficiency programs to be offered during one or more |
15 | | years of the respective multi-year plan period; for |
16 | | each solicitation process, the utility shall identify |
17 | | the sector, technology, or geographical area for which |
18 | | it is seeking requests for proposals; the solicitation |
19 | | process must be either for programs that fill gaps in |
20 | | the utility's program portfolio and for programs that |
21 | | target low-income customers, business sectors, |
22 | | building types, geographies, or other specific parts |
23 | | of its customer base with initiatives that would be |
24 | | more effective at reaching these customer segments |
25 | | than the utilities' programs filed in its energy |
26 | | efficiency plans; |
|
| | HB5539 Engrossed | - 63 - | LRB103 38494 CES 68630 b |
|
|
1 | | (C) the utility shall propose the bidder |
2 | | qualifications, performance measurement process, and |
3 | | contract structure, which must include a performance |
4 | | payment mechanism and general terms and conditions; |
5 | | the proposed qualifications, process, and structure |
6 | | shall be subject to Commission approval; and |
7 | | (D) the utility shall retain an independent third |
8 | | party to score the proposals received through the |
9 | | solicitation process described in this paragraph (4), |
10 | | rank them according to their cost per lifetime |
11 | | kilowatt-hours saved, and assemble the portfolio of |
12 | | third-party programs. |
13 | | The electric utility shall recover all costs |
14 | | associated with Commission-approved, third-party |
15 | | administered programs regardless of the success of those |
16 | | programs. |
17 | | (4.5) Implement cost-effective demand-response |
18 | | measures to reduce peak demand by 0.1% over the prior year |
19 | | for eligible retail customers, as defined in Section |
20 | | 16-111.5 of this Act, and for customers that elect hourly |
21 | | service from the utility pursuant to Section 16-107 of |
22 | | this Act, provided those customers have not been declared |
23 | | competitive. This requirement continues until December 31, |
24 | | 2026. |
25 | | (5) Include a proposed or revised cost-recovery tariff |
26 | | mechanism, as provided for under subsection (d) of this |
|
| | HB5539 Engrossed | - 64 - | LRB103 38494 CES 68630 b |
|
|
1 | | Section, to fund the proposed energy efficiency and |
2 | | demand-response measures and to ensure the recovery of the |
3 | | prudently and reasonably incurred costs of |
4 | | Commission-approved programs. |
5 | | (6) Provide for an annual independent evaluation of |
6 | | the performance of the cost-effectiveness of the utility's |
7 | | portfolio of measures, as well as a full review of the |
8 | | multi-year plan results of the broader net program impacts |
9 | | and, to the extent practical, for adjustment of the |
10 | | measures on a going-forward basis as a result of the |
11 | | evaluations. The resources dedicated to evaluation shall |
12 | | not exceed 3% of portfolio resources in any given year. |
13 | | (7) For electric utilities that serve more than |
14 | | 3,000,000 retail customers in the State: |
15 | | (A) Through December 31, 2025, provide for an |
16 | | adjustment to the return on equity component of the |
17 | | utility's weighted average cost of capital calculated |
18 | | under subsection (d) of this Section: |
19 | | (i) If the independent evaluator determines |
20 | | that the utility achieved a cumulative persisting |
21 | | annual savings that is less than the applicable |
22 | | annual incremental goal, then the return on equity |
23 | | component shall be reduced by a maximum of 200 |
24 | | basis points in the event that the utility |
25 | | achieved no more than 75% of such goal. If the |
26 | | utility achieved more than 75% of the applicable |
|
| | HB5539 Engrossed | - 65 - | LRB103 38494 CES 68630 b |
|
|
1 | | annual incremental goal but less than 100% of such |
2 | | goal, then the return on equity component shall be |
3 | | reduced by 8 basis points for each percent by |
4 | | which the utility failed to achieve the goal. |
5 | | (ii) If the independent evaluator determines |
6 | | that the utility achieved a cumulative persisting |
7 | | annual savings that is more than the applicable |
8 | | annual incremental goal, then the return on equity |
9 | | component shall be increased by a maximum of 200 |
10 | | basis points in the event that the utility |
11 | | achieved at least 125% of such goal. If the |
12 | | utility achieved more than 100% of the applicable |
13 | | annual incremental goal but less than 125% of such |
14 | | goal, then the return on equity component shall be |
15 | | increased by 8 basis points for each percent by |
16 | | which the utility achieved above the goal. If the |
17 | | applicable annual incremental goal was reduced |
18 | | under paragraph (1) or (2) of subsection (f) of |
19 | | this Section, then the following adjustments shall |
20 | | be made to the calculations described in this item |
21 | | (ii): |
22 | | (aa) the calculation for determining |
23 | | achievement that is at least 125% of the |
24 | | applicable annual incremental goal shall use |
25 | | the unreduced applicable annual incremental |
26 | | goal to set the value; and |
|
| | HB5539 Engrossed | - 66 - | LRB103 38494 CES 68630 b |
|
|
1 | | (bb) the calculation for determining |
2 | | achievement that is less than 125% but more |
3 | | than 100% of the applicable annual incremental |
4 | | goal shall use the reduced applicable annual |
5 | | incremental goal to set the value for 100% |
6 | | achievement of the goal and shall use the |
7 | | unreduced goal to set the value for 125% |
8 | | achievement. The 8 basis point value shall |
9 | | also be modified, as necessary, so that the |
10 | | 200 basis points are evenly apportioned among |
11 | | each percentage point value between 100% and |
12 | | 125% achievement. |
13 | | (B) For the period January 1, 2026 through |
14 | | December 31, 2029 and in all subsequent 4-year |
15 | | periods, provide for an adjustment to the return on |
16 | | equity component of the utility's weighted average |
17 | | cost of capital calculated under subsection (d) of |
18 | | this Section: |
19 | | (i) If the independent evaluator determines |
20 | | that the utility achieved a cumulative persisting |
21 | | annual savings that is less than the applicable |
22 | | annual incremental goal, then the return on equity |
23 | | component shall be reduced by a maximum of 200 |
24 | | basis points in the event that the utility |
25 | | achieved no more than 66% of such goal. If the |
26 | | utility achieved more than 66% of the applicable |
|
| | HB5539 Engrossed | - 67 - | LRB103 38494 CES 68630 b |
|
|
1 | | annual incremental goal but less than 100% of such |
2 | | goal, then the return on equity component shall be |
3 | | reduced by 6 basis points for each percent by |
4 | | which the utility failed to achieve the goal. |
5 | | (ii) If the independent evaluator determines |
6 | | that the utility achieved a cumulative persisting |
7 | | annual savings that is more than the applicable |
8 | | annual incremental goal, then the return on equity |
9 | | component shall be increased by a maximum of 200 |
10 | | basis points in the event that the utility |
11 | | achieved at least 134% of such goal. If the |
12 | | utility achieved more than 100% of the applicable |
13 | | annual incremental goal but less than 134% of such |
14 | | goal, then the return on equity component shall be |
15 | | increased by 6 basis points for each percent by |
16 | | which the utility achieved above the goal. If the |
17 | | applicable annual incremental goal was reduced |
18 | | under paragraph (3) of subsection (f) of this |
19 | | Section, then the following adjustments shall be |
20 | | made to the calculations described in this item |
21 | | (ii): |
22 | | (aa) the calculation for determining |
23 | | achievement that is at least 134% of the |
24 | | applicable annual incremental goal shall use |
25 | | the unreduced applicable annual incremental |
26 | | goal to set the value; and |
|
| | HB5539 Engrossed | - 68 - | LRB103 38494 CES 68630 b |
|
|
1 | | (bb) the calculation for determining |
2 | | achievement that is less than 134% but more |
3 | | than 100% of the applicable annual incremental |
4 | | goal shall use the reduced applicable annual |
5 | | incremental goal to set the value for 100% |
6 | | achievement of the goal and shall use the |
7 | | unreduced goal to set the value for 134% |
8 | | achievement. The 6 basis point value shall |
9 | | also be modified, as necessary, so that the |
10 | | 200 basis points are evenly apportioned among |
11 | | each percentage point value between 100% and |
12 | | 134% achievement. |
13 | | (C) Notwithstanding the provisions of |
14 | | subparagraphs (A) and (B) of this paragraph (7), if |
15 | | the applicable annual incremental goal for an electric |
16 | | utility is ever less than 0.6% of deemed average |
17 | | weather normalized sales of electric power and energy |
18 | | during calendar years 2014, 2015, and 2016, an |
19 | | adjustment to the return on equity component of the |
20 | | utility's weighted average cost of capital calculated |
21 | | under subsection (d) of this Section shall be made as |
22 | | follows: |
23 | | (i) If the independent evaluator determines |
24 | | that the utility achieved a cumulative persisting |
25 | | annual savings that is less than would have been |
26 | | achieved had the applicable annual incremental |
|
| | HB5539 Engrossed | - 69 - | LRB103 38494 CES 68630 b |
|
|
1 | | goal been achieved, then the return on equity |
2 | | component shall be reduced by a maximum of 200 |
3 | | basis points if the utility achieved no more than |
4 | | 75% of its applicable annual total savings |
5 | | requirement as defined in paragraph (7.5) of this |
6 | | subsection. If the utility achieved more than 75% |
7 | | of the applicable annual total savings requirement |
8 | | but less than 100% of such goal, then the return on |
9 | | equity component shall be reduced by 8 basis |
10 | | points for each percent by which the utility |
11 | | failed to achieve the goal. |
12 | | (ii) If the independent evaluator determines |
13 | | that the utility achieved a cumulative persisting |
14 | | annual savings that is more than would have been |
15 | | achieved had the applicable annual incremental |
16 | | goal been achieved, then the return on equity |
17 | | component shall be increased by a maximum of 200 |
18 | | basis points if the utility achieved at least 125% |
19 | | of its applicable annual total savings |
20 | | requirement. If the utility achieved more than |
21 | | 100% of the applicable annual total savings |
22 | | requirement but less than 125% of such goal, then |
23 | | the return on equity component shall be increased |
24 | | by 8 basis points for each percent by which the |
25 | | utility achieved above the applicable annual total |
26 | | savings requirement. If the applicable annual |
|
| | HB5539 Engrossed | - 70 - | LRB103 38494 CES 68630 b |
|
|
1 | | incremental goal was reduced under paragraph (1) |
2 | | or (2) of subsection (f) of this Section, then the |
3 | | following adjustments shall be made to the |
4 | | calculations described in this item (ii): |
5 | | (aa) the calculation for determining |
6 | | achievement that is at least 125% of the |
7 | | applicable annual total savings requirement |
8 | | shall use the unreduced applicable annual |
9 | | incremental goal to set the value; and |
10 | | (bb) the calculation for determining |
11 | | achievement that is less than 125% but more |
12 | | than 100% of the applicable annual total |
13 | | savings requirement shall use the reduced |
14 | | applicable annual incremental goal to set the |
15 | | value for 100% achievement of the goal and |
16 | | shall use the unreduced goal to set the value |
17 | | for 125% achievement. The 8 basis point value |
18 | | shall also be modified, as necessary, so that |
19 | | the 200 basis points are evenly apportioned |
20 | | among each percentage point value between 100% |
21 | | and 125% achievement. |
22 | | (7.5) For purposes of this Section, the term |
23 | | "applicable annual incremental goal" means the difference |
24 | | between the cumulative persisting annual savings goal for |
25 | | the calendar year that is the subject of the independent |
26 | | evaluator's determination and the cumulative persisting |
|
| | HB5539 Engrossed | - 71 - | LRB103 38494 CES 68630 b |
|
|
1 | | annual savings goal for the immediately preceding calendar |
2 | | year, as such goals are defined in subsections (b-5) and |
3 | | (b-15) of this Section and as these goals may have been |
4 | | modified as provided for under subsection (b-20) and |
5 | | paragraphs (1) through (3) of subsection (f) of this |
6 | | Section. Under subsections (b), (b-5), (b-10), and (b-15) |
7 | | of this Section, a utility must first replace energy |
8 | | savings from measures that have expired before any |
9 | | progress towards achievement of its applicable annual |
10 | | incremental goal may be counted. Savings may expire |
11 | | because measures installed in previous years have reached |
12 | | the end of their lives, because measures installed in |
13 | | previous years are producing lower savings in the current |
14 | | year than in the previous year, or for other reasons |
15 | | identified by independent evaluators. Notwithstanding |
16 | | anything else set forth in this Section, the difference |
17 | | between the actual annual incremental savings achieved in |
18 | | any given year, including the replacement of energy |
19 | | savings that have expired, and the applicable annual |
20 | | incremental goal shall not affect adjustments to the |
21 | | return on equity for subsequent calendar years under this |
22 | | subsection (g). |
23 | | In this Section, "applicable annual total savings |
24 | | requirement" means the total amount of new annual savings |
25 | | that the utility must achieve in any given year to achieve |
26 | | the applicable annual incremental goal. This is equal to |
|
| | HB5539 Engrossed | - 72 - | LRB103 38494 CES 68630 b |
|
|
1 | | the applicable annual incremental goal plus the total new |
2 | | annual savings that are required to replace savings that |
3 | | expired in or at the end of the previous year. |
4 | | (8) For electric utilities that serve less than |
5 | | 3,000,000 retail customers but more than 500,000 retail |
6 | | customers in the State: |
7 | | (A) Through December 31, 2025, the applicable |
8 | | annual incremental goal shall be compared to the |
9 | | annual incremental savings as determined by the |
10 | | independent evaluator. |
11 | | (i) The return on equity component shall be |
12 | | reduced by 8 basis points for each percent by |
13 | | which the utility did not achieve 84.4% of the |
14 | | applicable annual incremental goal. |
15 | | (ii) The return on equity component shall be |
16 | | increased by 8 basis points for each percent by |
17 | | which the utility exceeded 100% of the applicable |
18 | | annual incremental goal. |
19 | | (iii) The return on equity component shall not |
20 | | be increased or decreased if the annual |
21 | | incremental savings as determined by the |
22 | | independent evaluator is greater than 84.4% of the |
23 | | applicable annual incremental goal and less than |
24 | | 100% of the applicable annual incremental goal. |
25 | | (iv) The return on equity component shall not |
26 | | be increased or decreased by an amount greater |
|
| | HB5539 Engrossed | - 73 - | LRB103 38494 CES 68630 b |
|
|
1 | | than 200 basis points pursuant to this |
2 | | subparagraph (A). |
3 | | (B) For the period of January 1, 2026 through |
4 | | December 31, 2029 and in all subsequent 4-year |
5 | | periods, the applicable annual incremental goal shall |
6 | | be compared to the annual incremental savings as |
7 | | determined by the independent evaluator. |
8 | | (i) The return on equity component shall be |
9 | | reduced by 6 basis points for each percent by |
10 | | which the utility did not achieve 100% of the |
11 | | applicable annual incremental goal. |
12 | | (ii) The return on equity component shall be |
13 | | increased by 6 basis points for each percent by |
14 | | which the utility exceeded 100% of the applicable |
15 | | annual incremental goal. |
16 | | (iii) The return on equity component shall not |
17 | | be increased or decreased by an amount greater |
18 | | than 200 basis points pursuant to this |
19 | | subparagraph (B). |
20 | | (C) Notwithstanding provisions in subparagraphs |
21 | | (A) and (B) of paragraph (7) of this subsection, if the |
22 | | applicable annual incremental goal for an electric |
23 | | utility is ever less than 0.6% of deemed average |
24 | | weather normalized sales of electric power and energy |
25 | | during calendar years 2014, 2015 and 2016, an |
26 | | adjustment to the return on equity component of the |
|
| | HB5539 Engrossed | - 74 - | LRB103 38494 CES 68630 b |
|
|
1 | | utility's weighted average cost of capital calculated |
2 | | under subsection (d) of this Section shall be made as |
3 | | follows: |
4 | | (i) The return on equity component shall be |
5 | | reduced by 8 basis points for each percent by |
6 | | which the utility did not achieve 100% of the |
7 | | applicable annual total savings requirement. |
8 | | (ii) The return on equity component shall be |
9 | | increased by 8 basis points for each percent by |
10 | | which the utility exceeded 100% of the applicable |
11 | | annual total savings requirement. |
12 | | (iii) The return on equity component shall not |
13 | | be increased or decreased by an amount greater |
14 | | than 200 basis points pursuant to this |
15 | | subparagraph (C). |
16 | | (D) If the applicable annual incremental goal was |
17 | | reduced under paragraph (1), (2), (3), or (4) of |
18 | | subsection (f) of this Section, then the following |
19 | | adjustments shall be made to the calculations |
20 | | described in subparagraphs (A), (B), and (C) of this |
21 | | paragraph (8): |
22 | | (i) The calculation for determining |
23 | | achievement that is at least 125% or 134%, as |
24 | | applicable, of the applicable annual incremental |
25 | | goal or the applicable annual total savings |
26 | | requirement, as applicable, shall use the |
|
| | HB5539 Engrossed | - 75 - | LRB103 38494 CES 68630 b |
|
|
1 | | unreduced applicable annual incremental goal to |
2 | | set the value. |
3 | | (ii) For the period through December 31, 2025, |
4 | | the calculation for determining achievement that |
5 | | is less than 125% but more than 100% of the |
6 | | applicable annual incremental goal or the |
7 | | applicable annual total savings requirement, as |
8 | | applicable, shall use the reduced applicable |
9 | | annual incremental goal to set the value for 100% |
10 | | achievement of the goal and shall use the |
11 | | unreduced goal to set the value for 125% |
12 | | achievement. The 8 basis point value shall also be |
13 | | modified, as necessary, so that the 200 basis |
14 | | points are evenly apportioned among each |
15 | | percentage point value between 100% and 125% |
16 | | achievement. |
17 | | (iii) For the period of January 1, 2026 |
18 | | through December 31, 2029 and all subsequent |
19 | | 4-year periods, the calculation for determining |
20 | | achievement that is less than 125% or 134%, as |
21 | | applicable, but more than 100% of the applicable |
22 | | annual incremental goal or the applicable annual |
23 | | total savings requirement, as applicable, shall |
24 | | use the reduced applicable annual incremental goal |
25 | | to set the value for 100% achievement of the goal |
26 | | and shall use the unreduced goal to set the value |
|
| | HB5539 Engrossed | - 76 - | LRB103 38494 CES 68630 b |
|
|
1 | | for 125% achievement. The 6 basis-point value or 8 |
2 | | basis-point value, as applicable, shall also be |
3 | | modified, as necessary, so that the 200 basis |
4 | | points are evenly apportioned among each |
5 | | percentage point value between 100% and 125% or |
6 | | between 100% and 134% achievement, as applicable. |
7 | | (9) The utility shall submit the energy savings data |
8 | | to the independent evaluator no later than 30 days after |
9 | | the close of the plan year. The independent evaluator |
10 | | shall determine the cumulative persisting annual savings |
11 | | for a given plan year, as well as an estimate of job |
12 | | impacts and other macroeconomic impacts of the efficiency |
13 | | programs for that year, no later than 120 days after the |
14 | | close of the plan year. The utility shall submit an |
15 | | informational filing to the Commission no later than 160 |
16 | | days after the close of the plan year that attaches the |
17 | | independent evaluator's final report identifying the |
18 | | cumulative persisting annual savings for the year and |
19 | | calculates, under paragraph (7) or (8) of this subsection |
20 | | (g), as applicable, any resulting change to the utility's |
21 | | return on equity component of the weighted average cost of |
22 | | capital applicable to the next plan year beginning with |
23 | | the January monthly billing period and extending through |
24 | | the December monthly billing period. However, if the |
25 | | utility recovers the costs incurred under this Section |
26 | | under paragraphs (2) and (3) of subsection (d) of this |
|
| | HB5539 Engrossed | - 77 - | LRB103 38494 CES 68630 b |
|
|
1 | | Section, then the utility shall not be required to submit |
2 | | such informational filing, and shall instead submit the |
3 | | information that would otherwise be included in the |
4 | | informational filing as part of its filing under paragraph |
5 | | (3) of such subsection (d) that is due on or before June 1 |
6 | | of each year. |
7 | | For those utilities that must submit the informational |
8 | | filing, the Commission may, on its own motion or by |
9 | | petition, initiate an investigation of such filing, |
10 | | provided, however, that the utility's proposed return on |
11 | | equity calculation shall be deemed the final, approved |
12 | | calculation on December 15 of the year in which it is filed |
13 | | unless the Commission enters an order on or before |
14 | | December 15, after notice and hearing, that modifies such |
15 | | calculation consistent with this Section. |
16 | | The adjustments to the return on equity component |
17 | | described in paragraphs (7) and (8) of this subsection (g) |
18 | | shall be applied as described in such paragraphs through a |
19 | | separate tariff mechanism, which shall be filed by the |
20 | | utility under subsections (f) and (g) of this Section. |
21 | | (9.5) The utility must demonstrate how it will ensure |
22 | | that program implementation contractors and energy |
23 | | efficiency installation vendors will promote workforce |
24 | | equity and quality jobs. |
25 | | (9.6) Utilities shall collect data necessary to ensure |
26 | | compliance with paragraph (9.5) no less than quarterly and |
|
| | HB5539 Engrossed | - 78 - | LRB103 38494 CES 68630 b |
|
|
1 | | shall communicate progress toward compliance with |
2 | | paragraph (9.5) to program implementation contractors and |
3 | | energy efficiency installation vendors no less than |
4 | | quarterly. Utilities shall work with relevant vendors, |
5 | | providing education, training, and other resources needed |
6 | | to ensure compliance and, where necessary, adjusting or |
7 | | terminating work with vendors that cannot assist with |
8 | | compliance. |
9 | | (10) Utilities required to implement efficiency |
10 | | programs under subsections (b-5) and (b-10) shall report |
11 | | annually to the Illinois Commerce Commission and the |
12 | | General Assembly on how hiring, contracting, job training, |
13 | | and other practices related to its energy efficiency |
14 | | programs enhance the diversity of vendors working on such |
15 | | programs. These reports must include data on vendor and |
16 | | employee diversity, including data on the implementation |
17 | | of paragraphs (9.5) and (9.6). If the utility is not |
18 | | meeting the requirements of paragraphs (9.5) and (9.6), |
19 | | the utility shall submit a plan to adjust their activities |
20 | | so that they meet the requirements of paragraphs (9.5) and |
21 | | (9.6) within the following year. |
22 | | (h) No more than 4% of energy efficiency and |
23 | | demand-response program revenue may be allocated for research, |
24 | | development, or pilot deployment of new equipment or measures. |
25 | | Electric utilities shall work with interested stakeholders to |
26 | | formulate a plan for how these funds should be spent, |
|
| | HB5539 Engrossed | - 79 - | LRB103 38494 CES 68630 b |
|
|
1 | | incorporate statewide approaches for these allocations, and |
2 | | file a 4-year plan that demonstrates that collaboration. If a |
3 | | utility files a request for modified annual energy savings |
4 | | goals with the Commission, then a utility shall forgo spending |
5 | | portfolio dollars on research and development proposals. |
6 | | (i) When practicable, electric utilities shall incorporate |
7 | | advanced metering infrastructure data into the planning, |
8 | | implementation, and evaluation of energy efficiency measures |
9 | | and programs, subject to the data privacy and confidentiality |
10 | | protections of applicable law. |
11 | | (j) The independent evaluator shall follow the guidelines |
12 | | and use the savings set forth in Commission-approved energy |
13 | | efficiency policy manuals and technical reference manuals, as |
14 | | each may be updated from time to time. Until such time as |
15 | | measure life values for energy efficiency measures implemented |
16 | | for low-income households under subsection (c) of this Section |
17 | | are incorporated into such Commission-approved manuals, the |
18 | | low-income measures shall have the same measure life values |
19 | | that are established for same measures implemented in |
20 | | households that are not low-income households. |
21 | | (k) Notwithstanding any provision of law to the contrary, |
22 | | an electric utility subject to the requirements of this |
23 | | Section may file a tariff cancelling an automatic adjustment |
24 | | clause tariff in effect under this Section or Section 8-103, |
25 | | which shall take effect no later than one business day after |
26 | | the date such tariff is filed. Thereafter, the utility shall |
|
| | HB5539 Engrossed | - 80 - | LRB103 38494 CES 68630 b |
|
|
1 | | be authorized to defer and recover its expenditures incurred |
2 | | under this Section through a new tariff authorized under |
3 | | subsection (d) of this Section or in the utility's next rate |
4 | | case under Article IX or Section 16-108.5 of this Act, with |
5 | | interest at an annual rate equal to the utility's weighted |
6 | | average cost of capital as approved by the Commission in such |
7 | | case. If the utility elects to file a new tariff under |
8 | | subsection (d) of this Section, the utility may file the |
9 | | tariff within 10 days after June 1, 2017 (the effective date of |
10 | | Public Act 99-906), and the cost inputs to such tariff shall be |
11 | | based on the projected costs to be incurred by the utility |
12 | | during the calendar year in which the new tariff is filed and |
13 | | that were not recovered under the tariff that was cancelled as |
14 | | provided for in this subsection. Such costs shall include |
15 | | those incurred or to be incurred by the utility under its |
16 | | multi-year plan approved under subsections (f) and (g) of this |
17 | | Section, including, but not limited to, projected capital |
18 | | investment costs and projected regulatory asset balances with |
19 | | correspondingly updated depreciation and amortization reserves |
20 | | and expense. The Commission shall, after notice and hearing, |
21 | | approve, or approve with modification, such tariff and cost |
22 | | inputs no later than 75 days after the utility filed the |
23 | | tariff, provided that such approval, or approval with |
24 | | modification, shall be consistent with the provisions of this |
25 | | Section to the extent they do not conflict with this |
26 | | subsection (k). The tariff approved by the Commission shall |
|
| | HB5539 Engrossed | - 81 - | LRB103 38494 CES 68630 b |
|
|
1 | | take effect no later than 5 days after the Commission enters |
2 | | its order approving the tariff. |
3 | | No later than 60 days after the effective date of the |
4 | | tariff cancelling the utility's automatic adjustment clause |
5 | | tariff, the utility shall file a reconciliation that |
6 | | reconciles the moneys collected under its automatic adjustment |
7 | | clause tariff with the costs incurred during the period |
8 | | beginning June 1, 2016 and ending on the date that the electric |
9 | | utility's automatic adjustment clause tariff was cancelled. In |
10 | | the event the reconciliation reflects an under-collection, the |
11 | | utility shall recover the costs as specified in this |
12 | | subsection (k). If the reconciliation reflects an |
13 | | over-collection, the utility shall apply the amount of such |
14 | | over-collection as a one-time credit to retail customers' |
15 | | bills. |
16 | | (l) For the calendar years covered by a multi-year plan |
17 | | commencing after December 31, 2017, subsections (a) through |
18 | | (j) of this Section do not apply to eligible large private |
19 | | energy customers that have chosen to opt out of multi-year |
20 | | plans consistent with this subsection (1). |
21 | | (1) For purposes of this subsection (l), "eligible |
22 | | large private energy customer" means any retail customers, |
23 | | except for federal, State, municipal, and other public |
24 | | customers, of an electric utility that serves more than |
25 | | 3,000,000 retail customers, except for federal, State, |
26 | | municipal and other public customers, in the State and |
|
| | HB5539 Engrossed | - 82 - | LRB103 38494 CES 68630 b |
|
|
1 | | whose total highest 30 minute demand was more than 10,000 |
2 | | kilowatts, or any retail customers of an electric utility |
3 | | that serves less than 3,000,000 retail customers but more |
4 | | than 500,000 retail customers in the State and whose total |
5 | | highest 15 minute demand was more than 10,000 kilowatts. |
6 | | For purposes of this subsection (l), "retail customer" has |
7 | | the meaning set forth in Section 16-102 of this Act. |
8 | | However, for a business entity with multiple sites located |
9 | | in the State, where at least one of those sites qualifies |
10 | | as an eligible large private energy customer, then any of |
11 | | that business entity's sites, properly identified on a |
12 | | form for notice, shall be considered eligible large |
13 | | private energy customers for the purposes of this |
14 | | subsection (l). A determination of whether this subsection |
15 | | is applicable to a customer shall be made for each |
16 | | multi-year plan beginning after December 31, 2017. The |
17 | | criteria for determining whether this subsection (l) is |
18 | | applicable to a retail customer shall be based on the 12 |
19 | | consecutive billing periods prior to the start of the |
20 | | first year of each such multi-year plan. |
21 | | (2) Within 45 days after September 15, 2021 (the |
22 | | effective date of Public Act 102-662), the Commission |
23 | | shall prescribe the form for notice required for opting |
24 | | out of energy efficiency programs. The notice must be |
25 | | submitted to the retail electric utility 12 months before |
26 | | the next energy efficiency planning cycle. However, within |
|
| | HB5539 Engrossed | - 83 - | LRB103 38494 CES 68630 b |
|
|
1 | | 120 days after the Commission's initial issuance of the |
2 | | form for notice, eligible large private energy customers |
3 | | may submit a form for notice to an electric utility. The |
4 | | form for notice for opting out of energy efficiency |
5 | | programs shall include all of the following: |
6 | | (A) a statement indicating that the customer has |
7 | | elected to opt out; |
8 | | (B) the account numbers for the customer accounts |
9 | | to which the opt out shall apply; |
10 | | (C) the mailing address associated with the |
11 | | customer accounts identified under subparagraph (B); |
12 | | (D) an American Society of Heating, Refrigerating, |
13 | | and Air-Conditioning Engineers (ASHRAE) level 2 or |
14 | | higher audit report conducted by an independent |
15 | | third-party expert identifying cost-effective energy |
16 | | efficiency project opportunities that could be |
17 | | invested in over the next 10 years. A retail customer |
18 | | with specialized processes may utilize a self-audit |
19 | | process in lieu of the ASHRAE audit; |
20 | | (E) a description of the customer's plans to |
21 | | reallocate the funds toward internal energy efficiency |
22 | | efforts identified in the subparagraph (D) report, |
23 | | including, but not limited to: (i) strategic energy |
24 | | management or other programs, including descriptions |
25 | | of targeted buildings, equipment and operations; (ii) |
26 | | eligible energy efficiency measures; and (iii) |
|
| | HB5539 Engrossed | - 84 - | LRB103 38494 CES 68630 b |
|
|
1 | | expected energy savings, itemized by technology. If |
2 | | the subparagraph (D) audit report identifies that the |
3 | | customer currently utilizes the best available energy |
4 | | efficient technology, equipment, programs, and |
5 | | operations, the customer may provide a statement that |
6 | | more efficient technology, equipment, programs, and |
7 | | operations are not reasonably available as a means of |
8 | | satisfying this subparagraph (E); and |
9 | | (F) the effective date of the opt out, which will |
10 | | be the next January 1 following notice of the opt out. |
11 | | (3) Upon receipt of a properly and timely noticed |
12 | | request for opt out submitted by an eligible large private |
13 | | energy customer, the retail electric utility shall grant |
14 | | the request, file the request with the Commission and, |
15 | | beginning January 1 of the following year, the opted out |
16 | | customer shall no longer be assessed the costs of the plan |
17 | | and shall be prohibited from participating in that 4-year |
18 | | plan cycle to give the retail utility the certainty to |
19 | | design program plan proposals. |
20 | | (4) Upon a customer's election to opt out under |
21 | | paragraphs (1) and (2) of this subsection (l) and |
22 | | commencing on the effective date of said opt out, the |
23 | | account properly identified in the customer's notice under |
24 | | paragraph (2) shall not be subject to any cost recovery |
25 | | and shall not be eligible to participate in, or directly |
26 | | benefit from, compliance with energy efficiency cumulative |
|
| | HB5539 Engrossed | - 85 - | LRB103 38494 CES 68630 b |
|
|
1 | | persisting savings requirements under subsections (a) |
2 | | through (j). |
3 | | (5) A utility's cumulative persisting annual savings |
4 | | targets will exclude any opted out load. |
5 | | (6) The request to opt out is only valid for the |
6 | | requested plan cycle. An eligible large private energy |
7 | | customer must also request to opt out for future energy |
8 | | plan cycles, otherwise the customer will be included in |
9 | | the future energy plan cycle. |
10 | | (m) Notwithstanding the requirements of this Section, as |
11 | | part of a proceeding to approve a multi-year plan under |
12 | | subsections (f) and (g) of this Section if the multi-year plan |
13 | | has been designed to maximize savings, but does not meet the |
14 | | cost cap limitations of this Section, the Commission shall |
15 | | reduce the amount of energy efficiency measures implemented |
16 | | for any single year, and whose costs are recovered under |
17 | | subsection (d) of this Section, by an amount necessary to |
18 | | limit the estimated average net increase due to the cost of the |
19 | | measures to no more than |
20 | | (1) 3.5% for each of the 4 years beginning January 1, |
21 | | 2018, |
22 | | (2) (blank), |
23 | | (3) 4% for each of the 4 years beginning January 1, |
24 | | 2022, |
25 | | (4) 4.25% for the 4 years beginning January 1, 2026, |
26 | | and |
|
| | HB5539 Engrossed | - 86 - | LRB103 38494 CES 68630 b |
|
|
1 | | (5) 4.25% plus an increase sufficient to account for |
2 | | the rate of inflation between January 1, 2026 and January |
3 | | 1 of the first year of each subsequent 4-year plan cycle, |
4 | | of the average amount paid per kilowatthour by residential |
5 | | eligible retail customers during calendar year 2015. An |
6 | | electric utility may plan to spend up to 10% more in any year |
7 | | during an applicable multi-year plan period to |
8 | | cost-effectively achieve additional savings so long as the |
9 | | average over the applicable multi-year plan period does not |
10 | | exceed the percentages defined in items (1) through (5). To |
11 | | determine the total amount that may be spent by an electric |
12 | | utility in any single year, the applicable percentage of the |
13 | | average amount paid per kilowatthour shall be multiplied by |
14 | | the total amount of energy delivered by such electric utility |
15 | | in the calendar year 2015, adjusted to reflect the proportion |
16 | | of the utility's load attributable to customers that have |
17 | | opted out of subsections (a) through (j) of this Section under |
18 | | subsection (l) of this Section. For purposes of this |
19 | | subsection (m), the amount paid per kilowatthour includes, |
20 | | without limitation, estimated amounts paid for supply, |
21 | | transmission, distribution, surcharges, and add-on taxes. For |
22 | | purposes of this Section, "eligible retail customers" shall |
23 | | have the meaning set forth in Section 16-111.5 of this Act. |
24 | | Once the Commission has approved a plan under subsections (f) |
25 | | and (g) of this Section, no subsequent rate impact |
26 | | determinations shall be made. |
|
| | HB5539 Engrossed | - 87 - | LRB103 38494 CES 68630 b |
|
|
1 | | (n) A utility shall take advantage of the efficiencies |
2 | | available through existing Illinois Home Weatherization |
3 | | Assistance Program infrastructure and services, such as |
4 | | enrollment, marketing, quality assurance and implementation, |
5 | | which can reduce the need for similar services at a lower cost |
6 | | than utility-only programs, subject to capacity constraints at |
7 | | community action agencies, for both single-family and |
8 | | multifamily weatherization services, to the extent Illinois |
9 | | Home Weatherization Assistance Program community action |
10 | | agencies provide multifamily services. A utility's plan shall |
11 | | demonstrate that in formulating annual weatherization budgets, |
12 | | it has sought input and coordination with community action |
13 | | agencies regarding agencies' capacity to expand and maximize |
14 | | Illinois Home Weatherization Assistance Program delivery using |
15 | | the ratepayer dollars collected under this Section. |
16 | | (Source: P.A. 102-662, eff. 9-15-21; 103-154, eff. 6-30-23.) |
17 | | (220 ILCS 5/8-104) |
18 | | Sec. 8-104. Natural gas energy efficiency programs. |
19 | | (a) It is the policy of the State that natural gas |
20 | | utilities and the Department of Commerce and Economic |
21 | | Opportunity are required to use cost-effective energy |
22 | | efficiency to reduce direct and indirect costs to consumers. |
23 | | It serves the public interest to allow natural gas utilities |
24 | | to recover costs for reasonably and prudently incurred |
25 | | expenses for cost-effective energy efficiency measures. |
|
| | HB5539 Engrossed | - 88 - | LRB103 38494 CES 68630 b |
|
|
1 | | (b) For purposes of this Section, "energy efficiency" |
2 | | means measures that reduce the amount of energy required to |
3 | | achieve a given end use. "Energy efficiency" also includes |
4 | | measures that reduce the total Btus of electricity and natural |
5 | | gas needed to meet the end use or uses. "Cost-effective" means |
6 | | that the measures satisfy the total resource cost test which, |
7 | | for purposes of this Section, means a standard that is met if, |
8 | | for an investment in energy efficiency, the benefit-cost ratio |
9 | | is greater than one. The benefit-cost ratio is the ratio of the |
10 | | net present value of the total benefits of the measures to the |
11 | | net present value of the total costs as calculated over the |
12 | | lifetime of the measures. The total resource cost test |
13 | | compares the sum of avoided natural gas utility costs, |
14 | | representing the benefits that accrue to the system and the |
15 | | participant in the delivery of those efficiency measures, as |
16 | | well as other quantifiable societal benefits, including |
17 | | avoided electric utility costs, to the sum of all incremental |
18 | | costs of end use measures (including both utility and |
19 | | participant contributions), plus costs to administer, deliver, |
20 | | and evaluate each demand-side measure, to quantify the net |
21 | | savings obtained by substituting demand-side measures for |
22 | | supply resources. In calculating avoided costs, reasonable |
23 | | estimates shall be included for financial costs likely to be |
24 | | imposed by future regulation of emissions of greenhouse gases. |
25 | | The low-income programs described in item (4) of subsection |
26 | | (f) of this Section shall not be required to meet the total |
|
| | HB5539 Engrossed | - 89 - | LRB103 38494 CES 68630 b |
|
|
1 | | resource cost test. |
2 | | (c) Natural gas utilities shall implement cost-effective |
3 | | energy efficiency measures to meet at least the following |
4 | | natural gas savings requirements, which shall be based upon |
5 | | the total amount of gas delivered to retail customers, other |
6 | | than the customers described in subsection (m) of this |
7 | | Section, during calendar year 2009 multiplied by the |
8 | | applicable percentage. Natural gas utilities may comply with |
9 | | this Section by meeting the annual incremental savings goal in |
10 | | the applicable year or by showing that total cumulative annual |
11 | | savings within a multi-year planning period associated with |
12 | | measures implemented after May 31, 2011 were equal to the sum |
13 | | of each annual incremental savings requirement from the first |
14 | | day of the multi-year planning period through the last day of |
15 | | the multi-year planning period: |
16 | | (1) 0.2% by May 31, 2012; |
17 | | (2) an additional 0.4% by May 31, 2013, increasing |
18 | | total savings to .6%; |
19 | | (3) an additional 0.6% by May 31, 2014, increasing |
20 | | total savings to 1.2%; |
21 | | (4) an additional 0.8% by May 31, 2015, increasing |
22 | | total savings to 2.0%; |
23 | | (5) an additional 1% by May 31, 2016, increasing total |
24 | | savings to 3.0%; |
25 | | (6) an additional 1.2% by May 31, 2017, increasing |
26 | | total savings to 4.2%; |
|
| | HB5539 Engrossed | - 90 - | LRB103 38494 CES 68630 b |
|
|
1 | | (7) an additional 1.4% in the year commencing January |
2 | | 1, 2018; |
3 | | (8) an additional 1.5% in the year commencing January |
4 | | 1, 2019; and |
5 | | (9) an additional 1.5% in each 12-month period |
6 | | thereafter. |
7 | | (d) Notwithstanding the requirements of subsection (c) of |
8 | | this Section, a natural gas utility shall limit the amount of |
9 | | energy efficiency implemented in any multi-year reporting |
10 | | period established by subsection (f) of Section 8-104 of this |
11 | | Act, by an amount necessary to limit the estimated average |
12 | | increase in the amounts paid by retail customers in connection |
13 | | with natural gas service to no more than 2% in the applicable |
14 | | multi-year reporting period. The energy savings requirements |
15 | | in subsection (c) of this Section may be reduced by the |
16 | | Commission for the subject plan, if the utility demonstrates |
17 | | by substantial evidence that it is highly unlikely that the |
18 | | requirements could be achieved without exceeding the |
19 | | applicable spending limits in any multi-year reporting period. |
20 | | No later than September 1, 2013, the Commission shall review |
21 | | the limitation on the amount of energy efficiency measures |
22 | | implemented pursuant to this Section and report to the General |
23 | | Assembly, in the report required by subsection (k) of this |
24 | | Section, its findings as to whether that limitation unduly |
25 | | constrains the procurement of energy efficiency measures. |
26 | | (e) The provisions of this subsection (e) apply to those |
|
| | HB5539 Engrossed | - 91 - | LRB103 38494 CES 68630 b |
|
|
1 | | multi-year plans that commence prior to January 1, 2018. The |
2 | | utility shall utilize 75% of the available funding associated |
3 | | with energy efficiency programs approved by the Commission, |
4 | | and may outsource various aspects of program development and |
5 | | implementation. The remaining 25% of available funding shall |
6 | | be used by the Department of Commerce and Economic Opportunity |
7 | | to implement energy efficiency measures that achieve no less |
8 | | than 20% of the requirements of subsection (c) of this |
9 | | Section. Such measures shall be designed in conjunction with |
10 | | the utility and approved by the Commission. The Department may |
11 | | outsource development and implementation of energy efficiency |
12 | | measures. A minimum of 10% of the entire portfolio of |
13 | | cost-effective energy efficiency measures shall be procured |
14 | | from local government, municipal corporations, school |
15 | | districts, public institutions of higher education, and |
16 | | community college districts. Five percent of the entire |
17 | | portfolio of cost-effective energy efficiency measures may be |
18 | | granted to local government and municipal corporations for |
19 | | market transformation initiatives. The Department shall |
20 | | coordinate the implementation of these measures and shall |
21 | | integrate delivery of natural gas efficiency programs with |
22 | | electric efficiency programs delivered pursuant to Section |
23 | | 8-103 of this Act, unless the Department can show that |
24 | | integration is not feasible. |
25 | | The apportionment of the dollars to cover the costs to |
26 | | implement the Department's share of the portfolio of energy |
|
| | HB5539 Engrossed | - 92 - | LRB103 38494 CES 68630 b |
|
|
1 | | efficiency measures shall be made to the Department once the |
2 | | Department has executed rebate agreements, grants, or |
3 | | contracts for energy efficiency measures and provided |
4 | | supporting documentation for those rebate agreements, grants, |
5 | | and contracts to the utility. The Department is authorized to |
6 | | adopt any rules necessary and prescribe procedures in order to |
7 | | ensure compliance by applicants in carrying out the purposes |
8 | | of rebate agreements for energy efficiency measures |
9 | | implemented by the Department made under this Section. |
10 | | The details of the measures implemented by the Department |
11 | | shall be submitted by the Department to the Commission in |
12 | | connection with the utility's filing regarding the energy |
13 | | efficiency measures that the utility implements. |
14 | | The portfolio of measures, administered by both the |
15 | | utilities and the Department, shall, in combination, be |
16 | | designed to achieve the annual energy savings requirements set |
17 | | forth in subsection (c) of this Section, as modified by |
18 | | subsection (d) of this Section. |
19 | | The utility and the Department shall agree upon a |
20 | | reasonable portfolio of measures and determine the measurable |
21 | | corresponding percentage of the savings goals associated with |
22 | | measures implemented by the Department. |
23 | | No utility shall be assessed a penalty under subsection |
24 | | (f) of this Section for failure to make a timely filing if that |
25 | | failure is the result of a lack of agreement with the |
26 | | Department with respect to the allocation of responsibilities |
|
| | HB5539 Engrossed | - 93 - | LRB103 38494 CES 68630 b |
|
|
1 | | or related costs or target assignments. In that case, the |
2 | | Department and the utility shall file their respective plans |
3 | | with the Commission and the Commission shall determine an |
4 | | appropriate division of measures and programs that meets the |
5 | | requirements of this Section. |
6 | | (e-5) The provisions of this subsection (e-5) shall be |
7 | | applicable to those multi-year plans that commence after |
8 | | December 31, 2017. Natural gas utilities shall be responsible |
9 | | for overseeing the design, development, and filing of their |
10 | | efficiency plans with the Commission and may outsource |
11 | | development and implementation of energy efficiency measures. |
12 | | A minimum of 10% of the entire portfolio of cost-effective |
13 | | energy efficiency measures shall be procured from local |
14 | | government, municipal corporations, school districts, public |
15 | | institutions of higher education, and community college |
16 | | districts. Five percent of the entire portfolio of |
17 | | cost-effective energy efficiency measures may be granted to |
18 | | local government and municipal corporations for market |
19 | | transformation initiatives. |
20 | | The utilities shall also present a portfolio of energy |
21 | | efficiency measures proportionate to the share of total annual |
22 | | utility revenues in Illinois from households at or below 150% |
23 | | of the poverty level. Such programs shall be targeted to |
24 | | households with incomes at or below 80% of area median income. |
25 | | (e-10) A utility providing approved energy efficiency |
26 | | measures in this State shall be permitted to recover costs of |
|
| | HB5539 Engrossed | - 94 - | LRB103 38494 CES 68630 b |
|
|
1 | | those measures through an automatic adjustment clause tariff |
2 | | filed with and approved by the Commission. The tariff shall be |
3 | | established outside the context of a general rate case and |
4 | | shall be applicable to the utility's customers other than the |
5 | | customers described in subsection (m) of this Section. Each |
6 | | year the Commission shall initiate a review to reconcile any |
7 | | amounts collected with the actual costs and to determine the |
8 | | required adjustment to the annual tariff factor to match |
9 | | annual expenditures. |
10 | | (e-15) For those multi-year plans that commence prior to |
11 | | January 1, 2018, each utility shall include, in its recovery |
12 | | of costs, the costs estimated for both the utility's and the |
13 | | Department's implementation of energy efficiency measures. |
14 | | Costs collected by the utility for measures implemented by the |
15 | | Department shall be submitted to the Department pursuant to |
16 | | Section 605-323 of the Civil Administrative Code of Illinois, |
17 | | shall be deposited into the Energy Efficiency Portfolio |
18 | | Standards Fund, and shall be used by the Department solely for |
19 | | the purpose of implementing these measures. A utility shall |
20 | | not be required to advance any moneys to the Department but |
21 | | only to forward such funds as it has collected. The Department |
22 | | shall report to the Commission on an annual basis regarding |
23 | | the costs actually incurred by the Department in the |
24 | | implementation of the measures. Any changes to the costs of |
25 | | energy efficiency measures as a result of plan modifications |
26 | | shall be appropriately reflected in amounts recovered by the |
|
| | HB5539 Engrossed | - 95 - | LRB103 38494 CES 68630 b |
|
|
1 | | utility and turned over to the Department. |
2 | | (f) No later than October 1, 2010, each gas utility shall |
3 | | file an energy efficiency plan with the Commission to meet the |
4 | | energy efficiency standards through May 31, 2014. No later |
5 | | than October 1, 2013, each gas utility shall file an energy |
6 | | efficiency plan with the Commission to meet the energy |
7 | | efficiency standards through May 31, 2017. Beginning in 2017 |
8 | | and every 4 years thereafter, each utility shall file an |
9 | | energy efficiency plan with the Commission to meet the energy |
10 | | efficiency standards for the next applicable 4-year period |
11 | | beginning January 1 of the year following the filing. For |
12 | | those multi-year plans commencing on January 1, 2018, each |
13 | | utility shall file its proposed energy efficiency plan no |
14 | | later than 30 days after the effective date of this amendatory |
15 | | Act of the 99th General Assembly or May 1, 2017, whichever is |
16 | | later. Beginning in 2021 and every 4 years thereafter, each |
17 | | utility shall file its energy efficiency plan no later than |
18 | | March 1. If a utility does not file such a plan on or before |
19 | | the applicable filing deadline for the plan, then it shall |
20 | | face a penalty of $100,000 per day until the plan is filed. |
21 | | Each utility's plan shall set forth the utility's |
22 | | proposals to meet the utility's portion of the energy |
23 | | efficiency standards identified in subsection (c) of this |
24 | | Section, as modified by subsection (d) of this Section, taking |
25 | | into account the unique circumstances of the utility's service |
26 | | territory. For those plans commencing after December 31, 2021, |
|
| | HB5539 Engrossed | - 96 - | LRB103 38494 CES 68630 b |
|
|
1 | | the Commission shall seek public comment on the utility's plan |
2 | | and shall issue an order approving or disapproving each plan |
3 | | within 6 months after its submission. For those plans |
4 | | commencing on January 1, 2018, the Commission shall seek |
5 | | public comment on the utility's plan and shall issue an order |
6 | | approving or disapproving each plan no later than August 31, |
7 | | 2017, or 105 days after the effective date of this amendatory |
8 | | Act of the 99th General Assembly, whichever is later. If the |
9 | | Commission disapproves a plan, the Commission shall, within 30 |
10 | | days, describe in detail the reasons for the disapproval and |
11 | | describe a path by which the utility may file a revised draft |
12 | | of the plan to address the Commission's concerns |
13 | | satisfactorily. If the utility does not refile with the |
14 | | Commission within 60 days after the disapproval, the utility |
15 | | shall be subject to penalties at a rate of $100,000 per day |
16 | | until the plan is filed. This process shall continue, and |
17 | | penalties shall accrue, until the utility has successfully |
18 | | filed a portfolio of energy efficiency measures. Penalties |
19 | | shall be deposited into the Energy Efficiency Trust Fund and |
20 | | the cost of any such penalties may not be recovered from |
21 | | ratepayers. In submitting proposed energy efficiency plans and |
22 | | funding levels to meet the savings goals adopted by this Act |
23 | | the utility shall: |
24 | | (1) Demonstrate that its proposed energy efficiency |
25 | | measures will achieve the requirements that are identified |
26 | | in subsection (c) of this Section, as modified by |
|
| | HB5539 Engrossed | - 97 - | LRB103 38494 CES 68630 b |
|
|
1 | | subsection (d) of this Section. |
2 | | (2) Present specific proposals to implement new |
3 | | building and appliance standards that have been placed |
4 | | into effect. |
5 | | (3) Present estimates of the total amount paid for gas |
6 | | service expressed on a per therm basis associated with the |
7 | | proposed portfolio of measures designed to meet the |
8 | | requirements that are identified in subsection (c) of this |
9 | | Section, as modified by subsection (d) of this Section. |
10 | | (4) For those multi-year plans that commence prior to |
11 | | January 1, 2018, coordinate with the Department to present |
12 | | a portfolio of energy efficiency measures proportionate to |
13 | | the share of total annual utility revenues in Illinois |
14 | | from households at or below 150% of the poverty level. |
15 | | Such programs shall be targeted to households with incomes |
16 | | at or below 80% of area median income. |
17 | | (5) Demonstrate that its overall portfolio of energy |
18 | | efficiency measures, not including low-income programs |
19 | | described in item (4) of this subsection (f) and |
20 | | subsection (e-5) of this Section, are cost-effective using |
21 | | the total resource cost test and represent a diverse cross |
22 | | section of opportunities for customers of all rate classes |
23 | | to participate in the programs. |
24 | | (6) Demonstrate that a gas utility affiliated with an |
25 | | electric utility that is required to comply with Section |
26 | | 8-103 or 8-103B of this Act has integrated gas and |
|
| | HB5539 Engrossed | - 98 - | LRB103 38494 CES 68630 b |
|
|
1 | | electric efficiency measures into a single program that |
2 | | reduces program or participant costs and appropriately |
3 | | allocates costs to gas and electric ratepayers. For those |
4 | | multi-year plans that commence prior to January 1, 2018, |
5 | | the Department shall integrate all gas and electric |
6 | | programs it delivers in any such utilities' service |
7 | | territories, unless the Department can show that |
8 | | integration is not feasible or appropriate. |
9 | | (7) Include a proposed cost recovery tariff mechanism |
10 | | to fund the proposed energy efficiency measures and to |
11 | | ensure the recovery of the prudently and reasonably |
12 | | incurred costs of Commission-approved programs. |
13 | | (8) Provide for quarterly status reports tracking |
14 | | implementation of and expenditures for the utility's |
15 | | portfolio of measures and, if applicable, the Department's |
16 | | portfolio of measures, an annual independent review, and a |
17 | | full independent evaluation of the multi-year results of |
18 | | the performance and the cost-effectiveness of the |
19 | | utility's and, if applicable, Department's portfolios of |
20 | | measures and broader net program impacts and, to the |
21 | | extent practical, for adjustment of the measures on a |
22 | | going forward basis as a result of the evaluations. The |
23 | | resources dedicated to evaluation shall not exceed 3% of |
24 | | portfolio resources in any given multi-year period. |
25 | | (g) No more than 3% of expenditures on energy efficiency |
26 | | measures may be allocated for demonstration of breakthrough |
|
| | HB5539 Engrossed | - 99 - | LRB103 38494 CES 68630 b |
|
|
1 | | equipment and devices. |
2 | | (h) Illinois natural gas utilities that are affiliated by |
3 | | virtue of a common parent company may, at the utilities' |
4 | | request, be considered a single natural gas utility for |
5 | | purposes of complying with this Section. |
6 | | (i) If, after 3 years, a gas utility fails to meet the |
7 | | efficiency standard specified in subsection (c) of this |
8 | | Section as modified by subsection (d), then it shall make a |
9 | | contribution to the Low-Income Home Energy Assistance Program. |
10 | | The total liability for failure to meet the goal shall be |
11 | | assessed as follows: |
12 | | (1) a large gas utility shall pay $600,000; |
13 | | (2) a medium gas utility shall pay $400,000; and |
14 | | (3) a small gas utility shall pay $200,000. |
15 | | For purposes of this Section, (i) a "large gas utility" is |
16 | | a gas utility that on December 31, 2008, served more than |
17 | | 1,500,000 gas customers in Illinois; (ii) a "medium gas |
18 | | utility" is a gas utility that on December 31, 2008, served |
19 | | fewer than 1,500,000, but more than 500,000 gas customers in |
20 | | Illinois; and (iii) a "small gas utility" is a gas utility that |
21 | | on December 31, 2008, served fewer than 500,000 and more than |
22 | | 100,000 gas customers in Illinois. The costs of this |
23 | | contribution may not be recovered from ratepayers. |
24 | | If a gas utility fails to meet the efficiency standard |
25 | | specified in subsection (c) of this Section, as modified by |
26 | | subsection (d) of this Section, in any 2 consecutive |
|
| | HB5539 Engrossed | - 100 - | LRB103 38494 CES 68630 b |
|
|
1 | | multi-year planning periods, then the responsibility for |
2 | | implementing the utility's energy efficiency measures shall be |
3 | | transferred to an independent program administrator selected |
4 | | by the Commission. Reasonable and prudent costs incurred by |
5 | | the independent program administrator to meet the efficiency |
6 | | standard specified in subsection (c) of this Section, as |
7 | | modified by subsection (d) of this Section, may be recovered |
8 | | from the customers of the affected gas utilities, other than |
9 | | customers described in subsection (m) of this Section. The |
10 | | utility shall provide the independent program administrator |
11 | | with all information and assistance necessary to perform the |
12 | | program administrator's duties including but not limited to |
13 | | customer, account, and energy usage data, and shall allow the |
14 | | program administrator to include inserts in customer bills. |
15 | | The utility may recover reasonable costs associated with any |
16 | | such assistance. |
17 | | (j) No utility shall be deemed to have failed to meet the |
18 | | energy efficiency standards to the extent any such failure is |
19 | | due to a failure of the Department. |
20 | | (k) Not later than January 1, 2012, the Commission shall |
21 | | develop and solicit public comment on a plan to foster |
22 | | statewide coordination and consistency between statutorily |
23 | | mandated natural gas and electric energy efficiency programs |
24 | | to reduce program or participant costs or to improve program |
25 | | performance. Not later than September 1, 2013, the Commission |
26 | | shall issue a report to the General Assembly containing its |
|
| | HB5539 Engrossed | - 101 - | LRB103 38494 CES 68630 b |
|
|
1 | | findings and recommendations. |
2 | | (l) This Section does not apply to a gas utility that on |
3 | | January 1, 2009, provided gas service to fewer than 100,000 |
4 | | customers in Illinois. |
5 | | (m) Subsections (a) through (k) of this Section do not |
6 | | apply to customers of a natural gas utility that have a North |
7 | | American Industry Classification System code number that is |
8 | | 22111 or any such code number beginning with the digits 31, 32, |
9 | | or 33 and (i) annual usage in the aggregate of 4 million therms |
10 | | or more within the service territory of the affected gas |
11 | | utility or with aggregate usage of 8 million therms or more in |
12 | | this State and complying with the provisions of item (l) of |
13 | | this subsection (m); or (ii) using natural gas as feedstock |
14 | | and meeting the usage requirements described in item (i) of |
15 | | this subsection (m), to the extent such annual feedstock usage |
16 | | is greater than 60% of the customer's total annual usage of |
17 | | natural gas. |
18 | | (1) Customers described in this subsection (m) of this |
19 | | Section shall apply, on a form approved on or before |
20 | | October 1, 2009 by the Department, to the Department to be |
21 | | designated as a self-directing customer ("SDC") or as an |
22 | | exempt customer using natural gas as a feedstock from |
23 | | which other products are made, including, but not limited |
24 | | to, feedstock for a hydrogen plant, on or before the 1st |
25 | | day of February, 2010. Thereafter, application may be made |
26 | | not less than 6 months before the filing date of the gas |
|
| | HB5539 Engrossed | - 102 - | LRB103 38494 CES 68630 b |
|
|
1 | | utility energy efficiency plan described in subsection (f) |
2 | | of this Section; however, a new customer that commences |
3 | | taking service from a natural gas utility after February |
4 | | 1, 2010 may apply to become a SDC or exempt customer up to |
5 | | 30 days after beginning service. Customers described in |
6 | | this subsection (m) that have not already been approved by |
7 | | the Department may apply to be designated a self-directing |
8 | | customer or exempt customer, on a form approved by the |
9 | | Department, between September 1, 2013 and September 30, |
10 | | 2013. Customer applications that are approved by the |
11 | | Department under this amendatory Act of the 98th General |
12 | | Assembly shall be considered to be a self-directing |
13 | | customer or exempt customer, as applicable, for the |
14 | | current 3-year planning period effective December 1, 2013. |
15 | | Such application shall contain the following: |
16 | | (A) the customer's certification that, at the time |
17 | | of its application, it qualifies to be a SDC or exempt |
18 | | customer described in this subsection (m) of this |
19 | | Section; |
20 | | (B) in the case of a SDC, the customer's |
21 | | certification that it has established or will |
22 | | establish by the beginning of the utility's multi-year |
23 | | planning period commencing subsequent to the |
24 | | application, and will maintain for accounting |
25 | | purposes, an energy efficiency reserve account and |
26 | | that the customer will accrue funds in said account to |
|
| | HB5539 Engrossed | - 103 - | LRB103 38494 CES 68630 b |
|
|
1 | | be held for the purpose of funding, in whole or in |
2 | | part, energy efficiency measures of the customer's |
3 | | choosing, which may include, but are not limited to, |
4 | | projects involving combined heat and power systems |
5 | | that use the same energy source both for the |
6 | | generation of electrical or mechanical power and the |
7 | | production of steam or another form of useful thermal |
8 | | energy or the use of combustible gas produced from |
9 | | biomass, or both; |
10 | | (C) in the case of a SDC, the customer's |
11 | | certification that annual funding levels for the |
12 | | energy efficiency reserve account will be equal to 2% |
13 | | of the customer's cost of natural gas, composed of the |
14 | | customer's commodity cost and the delivery service |
15 | | charges paid to the gas utility, or $150,000, |
16 | | whichever is less; |
17 | | (D) in the case of a SDC, the customer's |
18 | | certification that the required reserve account |
19 | | balance will be capped at 3 years' worth of accruals |
20 | | and that the customer may, at its option, make further |
21 | | deposits to the account to the extent such deposit |
22 | | would increase the reserve account balance above the |
23 | | designated cap level; |
24 | | (E) in the case of a SDC, the customer's |
25 | | certification that by October 1 of each year, |
26 | | beginning no sooner than October 1, 2012, the customer |
|
| | HB5539 Engrossed | - 104 - | LRB103 38494 CES 68630 b |
|
|
1 | | will report to the Department information, for the |
2 | | 12-month period ending May 31 of the same year, on all |
3 | | deposits and reductions, if any, to the reserve |
4 | | account during the reporting year, and to the extent |
5 | | deposits to the reserve account in any year are in an |
6 | | amount less than $150,000, the basis for such reduced |
7 | | deposits; reserve account balances by month; a |
8 | | description of energy efficiency measures undertaken |
9 | | by the customer and paid for in whole or in part with |
10 | | funds from the reserve account; an estimate of the |
11 | | energy saved, or to be saved, by the measure; and that |
12 | | the report shall include a verification by an officer |
13 | | or plant manager of the customer or by a registered |
14 | | professional engineer or certified energy efficiency |
15 | | trade professional that the funds withdrawn from the |
16 | | reserve account were used for the energy efficiency |
17 | | measures; |
18 | | (F) in the case of an exempt customer, the |
19 | | customer's certification of the level of gas usage as |
20 | | feedstock in the customer's operation in a typical |
21 | | year and that it will provide information establishing |
22 | | this level, upon request of the Department; |
23 | | (G) in the case of either an exempt customer or a |
24 | | SDC, the customer's certification that it has provided |
25 | | the gas utility or utilities serving the customer with |
26 | | a copy of the application as filed with the |
|
| | HB5539 Engrossed | - 105 - | LRB103 38494 CES 68630 b |
|
|
1 | | Department; |
2 | | (H) in the case of either an exempt customer or a |
3 | | SDC, certification of the natural gas utility or |
4 | | utilities serving the customer in Illinois including |
5 | | the natural gas utility accounts that are the subject |
6 | | of the application; and |
7 | | (I) in the case of either an exempt customer or a |
8 | | SDC, a verification signed by a plant manager or an |
9 | | authorized corporate officer attesting to the |
10 | | truthfulness and accuracy of the information contained |
11 | | in the application. |
12 | | (2) The Department shall review the application to |
13 | | determine that it contains the information described in |
14 | | provisions (A) through (I) of item (1) of this subsection |
15 | | (m), as applicable. The review shall be completed within |
16 | | 30 days after the date the application is filed with the |
17 | | Department. Absent a determination by the Department |
18 | | within the 30-day period, the applicant shall be |
19 | | considered to be a SDC or exempt customer, as applicable, |
20 | | for all subsequent multi-year planning periods, as of the |
21 | | date of filing the application described in this |
22 | | subsection (m). If the Department determines that the |
23 | | application does not contain the applicable information |
24 | | described in provisions (A) through (I) of item (1) of |
25 | | this subsection (m), it shall notify the customer, in |
26 | | writing, of its determination that the application does |
|
| | HB5539 Engrossed | - 106 - | LRB103 38494 CES 68630 b |
|
|
1 | | not contain the required information and identify the |
2 | | information that is missing, and the customer shall |
3 | | provide the missing information within 15 working days |
4 | | after the date of receipt of the Department's |
5 | | notification. |
6 | | (3) The Department shall have the right to audit the |
7 | | information provided in the customer's application and |
8 | | annual reports to ensure continued compliance with the |
9 | | requirements of this subsection. Based on the audit, if |
10 | | the Department determines the customer is no longer in |
11 | | compliance with the requirements of items (A) through (I) |
12 | | of item (1) of this subsection (m), as applicable, the |
13 | | Department shall notify the customer in writing of the |
14 | | noncompliance. The customer shall have 30 days to |
15 | | establish its compliance, and failing to do so, may have |
16 | | its status as a SDC or exempt customer revoked by the |
17 | | Department. The Department shall treat all information |
18 | | provided by any customer seeking SDC status or exemption |
19 | | from the provisions of this Section as strictly |
20 | | confidential. |
21 | | (4) Upon request, or on its own motion, the Commission |
22 | | may open an investigation, no more than once every 3 years |
23 | | and not before October 1, 2014, to evaluate the |
24 | | effectiveness of the self-directing program described in |
25 | | this subsection (m). |
26 | | Customers described in this subsection (m) that applied to |
|
| | HB5539 Engrossed | - 107 - | LRB103 38494 CES 68630 b |
|
|
1 | | the Department on January 3, 2013, were approved by the |
2 | | Department on February 13, 2013 to be a self-directing |
3 | | customer or exempt customer, and receive natural gas from a |
4 | | utility that provides gas service to at least 500,000 retail |
5 | | customers in Illinois and electric service to at least |
6 | | 1,000,000 retail customers in Illinois shall be considered to |
7 | | be a self-directing customer or exempt customer, as |
8 | | applicable, for the current 3-year planning period effective |
9 | | December 1, 2013. |
10 | | (n) The applicability of this Section to customers |
11 | | described in subsection (m) of this Section is conditioned on |
12 | | the existence of the SDC program. In no event will any |
13 | | provision of this Section apply to such customers after |
14 | | January 1, 2020. |
15 | | (o) Utilities' 3-year energy efficiency plans approved by |
16 | | the Commission on or before the effective date of this |
17 | | amendatory Act of the 99th General Assembly for the period |
18 | | June 1, 2014 through May 31, 2017 shall continue to be in force |
19 | | and effect through December 31, 2017 so that the energy |
20 | | efficiency programs set forth in those plans continue to be |
21 | | offered during the period June 1, 2017 through December 31, |
22 | | 2017. Each utility is authorized to increase, on a pro rata |
23 | | basis, the energy savings goals and budgets approved in its |
24 | | plan to reflect the additional 7 months of the plan's |
25 | | operation. |
26 | | (Source: P.A. 98-90, eff. 7-15-13; 98-225, eff. 8-9-13; |