|
| | 98TH GENERAL ASSEMBLY
State of Illinois
2013 and 2014 SB1647 Introduced 2/13/2013, by Sen. Kwame Raoul SYNOPSIS AS INTRODUCED: |
| New Act | | 20 ILCS 2705/2705-233 new | | 20 ILCS 3501/825-108 new | | 30 ILCS 500/1-10 | | 30 ILCS 535/85 new | | 30 ILCS 570/2.8 new | | 30 ILCS 575/2.8 new | | 735 ILCS 30/15-5-47 new | | 820 ILCS 130/2 | from Ch. 48, par. 39s-2 |
|
Creates the Design-Build and Construction Manager/General Contractor Transportation Infrastructure Act. Provides that the Department of Transportation is authorized to use the design-build project delivery method or the construction manager/general contractor delivery method for up to 5 transportation facilities for each delivery method. Contains provisions concerning the procurement process and terms of the contract. Provides that the Department of Transportation has eminent domain and quick take powers under the Act. Amends various other Acts to make conforming changes. Effective immediately.
|
| |
| | | FISCAL NOTE ACT MAY APPLY | |
| | A BILL FOR |
|
|
| | SB1647 | | LRB098 08041 HLH 38132 b |
|
|
1 | | AN ACT concerning State government.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | ARTICLE 1. DESIGN-BUILD AND CONSTRUCTION MANAGER/GENERAL |
5 | | CONTRACTOR TRANSPORTATION INFRASTRUCTURE ACT |
6 | | Section 1-1. Short title. This Act may be cited as the |
7 | | Design-Build and Construction Manager/General Contractor |
8 | | Transportation Infrastructure Act. |
9 | | Section 1-5. Legislative policy; procedures. |
10 | | (a) It is the public policy of the State of Illinois to |
11 | | promote the development of infrastructure projects that serve |
12 | | the needs of the public. |
13 | | (b) The design-build and construction manager/general |
14 | | contractor project delivery methods have the potential to |
15 | | safely deliver infrastructure projects on guaranteed or |
16 | | accelerated schedules, for guaranteed prices, potentially |
17 | | lower costs, and with the ability to shift risks to the private |
18 | | sector that are generally retained by the public in the |
19 | | conventional design-bid-build project delivery method. |
20 | | (c) It is the intent of the General Assembly that the |
21 | | Illinois Department of Transportation be allowed to carry out a |
22 | | demonstration program related to the design-build and |
|
| | SB1647 | - 2 - | LRB098 08041 HLH 38132 b |
|
|
1 | | construction manager/general contractor project delivery |
2 | | methods. |
3 | | (d) The powers granted in this Act are in addition to any |
4 | | other powers authorized under applicable law. |
5 | | Section 1-10. Definitions. As used in this Act: |
6 | | "Construction manager/general contractor" means a proposer |
7 | | that has entered into a construction manager/general |
8 | | contractor contract under this Act. |
9 | | "Construction manager/general contractor contract" means |
10 | | the two-phase contract between the Department and a |
11 | | construction manager/general contractor, which includes a |
12 | | first phase addressing preconstruction services and a second |
13 | | phase addressing the construction of the transportation |
14 | | facility. |
15 | | "Construction manager/general contractor delivery method" |
16 | | means a method of procurement and contracting that makes a |
17 | | construction manager/general contractor who enters in to a |
18 | | contract with the Department responsible for certain |
19 | | preconstruction services and then, if the parties reach |
20 | | agreement on key terms, responsible for construction of the |
21 | | transportation facility. |
22 | | "Department" means the Illinois Department of |
23 | | Transportation. |
24 | | "Design-bid-build project delivery method" means the |
25 | | traditional method of procuring and contracting for design and |
|
| | SB1647 | - 3 - | LRB098 08041 HLH 38132 b |
|
|
1 | | construction services used in this State, which incorporates |
2 | | the Architectural, Engineering, and Land Surveying |
3 | | Qualifications Based Selection Act and the principles of |
4 | | competitive bidding set forth in the Illinois Procurement Code. |
5 | | "Design-build project delivery method" means a method of |
6 | | procurement and contracting that provides responsibility |
7 | | within a single contract between the Department and a |
8 | | design-builder for the furnishing of architectural, |
9 | | engineering, construction, and related services for a |
10 | | transportation facility, and may also include responsibility |
11 | | for financing of that facility, procured on the basis of a |
12 | | combination of price and non-price factors. |
13 | | "Design-build contract" means a contract between the |
14 | | Department and a design-builder under which the design-builder |
15 | | agrees to furnish architectural, engineering, construction, |
16 | | and related services for a transportation facility. |
17 | | "Design-builder" means a proposer that has entered into a |
18 | | design-build contract under this Act. |
19 | | "Evaluation criteria" means the standards and requirements |
20 | | established by the Department, in its sole discretion, against |
21 | | which the qualifications and proposals of a proposer will be |
22 | | assessed during the procurement of a design-build contract or |
23 | | construction manager/general contractor contract, as |
24 | | applicable. |
25 | | "Metropolitan Planning Organization" means a metropolitan |
26 | | planning organization designated under 23 U.S.C. Section 134 |
|
| | SB1647 | - 4 - | LRB098 08041 HLH 38132 b |
|
|
1 | | whose metropolitan planning area boundaries are partially or |
2 | | completely within the State. |
3 | | "Preconstruction services" means all |
4 | | non-construction-related services that a construction |
5 | | manager/general contractor is allowed to perform during the |
6 | | first phase of a construction manager/general contractor |
7 | | contract, which includes giving advice to the Department |
8 | | regarding scheduling, work sequencing, cost engineering, |
9 | | constructability, cost estimating, and risk identification. |
10 | | "Proposal" means a proposal submitted by a proposer in |
11 | | response to a request for proposals. |
12 | | "Proposer" means any individual, sole proprietorship, |
13 | | firm, partnership, joint venture, corporation, professional |
14 | | corporation, or other entity that proposes to be the |
15 | | design-builder or construction manager/general contractor for |
16 | | any transportation facility under this Act. A proposer and its |
17 | | members shall conduct themselves in accordance with the laws of |
18 | | this State and the related provisions of the Illinois |
19 | | Administrative Code, as referenced by the licensed design |
20 | | professionals Acts of this State. |
21 | | "Qualifications" means a statement of qualifications |
22 | | submitted by a proposer in response to a request for |
23 | | qualifications. |
24 | | "Request for proposals" means the document issued by the |
25 | | Department to solicit proposals for a design-build contract or |
26 | | construction manager/general contractor contract in accordance |
|
| | SB1647 | - 5 - | LRB098 08041 HLH 38132 b |
|
|
1 | | with the design-build project delivery method or the |
2 | | construction manager/general contractor delivery method, as |
3 | | applicable. |
4 | | "Request for qualifications" means the document issued by |
5 | | the Department in the first phase of a two-phase procurement to |
6 | | solicit qualifications from proposers in accordance with the |
7 | | design-build project delivery method or the construction |
8 | | manager/general contractor delivery method, as applicable. |
9 | | "Scope and performance requirements" means the preferred |
10 | | constructed elements, activities, and standards of performance |
11 | | required by the Department to be complied with in the |
12 | | development of the transportation facility, which may include |
13 | | but not be limited to, the intended usage, capacity, size, |
14 | | scope, quality and performance standards, life-cycle costs, |
15 | | preliminary engineering, design and other requirements as |
16 | | developed and determined by the Department. |
17 | | "Transportation facility" means any new or existing |
18 | | facility or group of facilities that are the subject of a |
19 | | design-build contract or construction manager/general |
20 | | contractor contract, and which may include highways, roads, |
21 | | bridges, tunnels, overpasses, ferries, airports or other |
22 | | aviation facilities, public transportation facilities, vehicle |
23 | | parking facilities, seaport facilities, rail facilities, |
24 | | intermodal facilities, transit facilities or similar |
25 | | facilities used for the transportation of persons or goods. |
|
| | SB1647 | - 6 - | LRB098 08041 HLH 38132 b |
|
|
1 | | Section 1-15. Authorized Project Delivery Methods. |
2 | | (a) Notwithstanding any other law, and as authority |
3 | | supplemental to its existing powers, the Department, in |
4 | | accordance with this Act, is authorized to use the design-build |
5 | | project delivery method or the construction manager/general |
6 | | contractor delivery method for up to 5 transportation |
7 | | facilities for each delivery method; provided that, prior to |
8 | | commencing a procurement under this Act for either a |
9 | | design-build contract or a construction manager/general |
10 | | contractor contract, the Department has first undertaken an |
11 | | analysis and made a written determination that it is in the |
12 | | best interests of this State to utilize the selected delivery |
13 | | method for that transportation facility. The best interests of |
14 | | the State analysis shall be made available to the public. |
15 | | (b) The Department shall report to the General Assembly |
16 | | every 2 years on the progress of procurements and |
17 | | transportation facilities procured under this Act. The |
18 | | Department's obligation to submit a progress report for a |
19 | | particular transportation facility shall, as applicable, end |
20 | | two years after (i) the Department's termination of the |
21 | | procurement, (ii) early termination of the design-build |
22 | | contract or construction manager/general contractor contract, |
23 | | or (iii) completion of the transportation facility. |
24 | | (c) Any transportation facility developed pursuant to this |
25 | | Act must be consistent with the regional plan then in existence |
26 | | of any metropolitan planning organization in whose boundaries |
|
| | SB1647 | - 7 - | LRB098 08041 HLH 38132 b |
|
|
1 | | the transportation facility is located. |
2 | | Section 1-20. Preconditions to commencement of |
3 | | procurement. If the Department determines to use either the |
4 | | design-build project delivery method or construction |
5 | | manager/general contractor delivery method for a particular |
6 | | transportation facility, the Department may not commence a |
7 | | procurement for the transportation facility unless one of the |
8 | | following requirements is satisfied: (1) the transportation |
9 | | facility is included in the State's Multi-Year Highway |
10 | | Improvement Program, (2) the Department has issued a notice of |
11 | | intent to receive qualifications at least 14 days prior to the |
12 | | issuance of the request for qualifications, or (3) for a single |
13 | | phase procurement authorized pursuant to subsection (a) of |
14 | | Section 25, the Department has issued a notice of intent to |
15 | | receive proposals at least 14 days prior to the issuance of the |
16 | | request for proposals. If the Department issues one of the |
17 | | notices of intent described above, the Department shall publish |
18 | | the notice of intent in either the official procurement |
19 | | bulletin of the State or the professional services bulletin of |
20 | | the Department. The Department shall include a brief |
21 | | description of the proposed procurement in any notice of |
22 | | intent. |
23 | | Section 1-25. Procurement process. |
24 | | (a) The Department may solicit a proposer with which to |
|
| | SB1647 | - 8 - | LRB098 08041 HLH 38132 b |
|
|
1 | | enter into a design-build contract or construction |
2 | | manager/general contractor contract, as applicable, by using, |
3 | | without limitation, requests for qualifications, short-listing |
4 | | of qualified proposers, requests for proposals, negotiations, |
5 | | and best and final offers. The Department shall use a two-phase |
6 | | procurement to select the successful proposer; provided that |
7 | | the Department may use a single phase procurement if the |
8 | | transportation facility is estimated to cost less than |
9 | | $10,000,000 or the Secretary of Transportation makes a written |
10 | | determination that the Department may use a single phase |
11 | | procurement for a particular transportation facility. In a |
12 | | two-phase procurement, the Department shall use the first phase |
13 | | to evaluate and short-list proposers based on qualifications, |
14 | | and then use the second phase to evaluate and select a proposer |
15 | | based on proposals submitted by the short-listed proposers. In |
16 | | a single phase procurement, the Department shall solicit |
17 | | proposers with a request for proposals, and shall evaluate and |
18 | | select a proposer based on proposals. |
19 | | (b) The request for qualifications may contain any |
20 | | information deemed appropriate by the Department, in its |
21 | | discretion, including, without limitation, the following |
22 | | information: |
23 | | (1) the anticipated scope of work for the |
24 | | transportation facility; |
25 | | (2) a requirement that the proposer identify certain |
26 | | key personnel and certain key firms, and the experience of |
|
| | SB1647 | - 9 - | LRB098 08041 HLH 38132 b |
|
|
1 | | such personnel and firms; |
2 | | (3) the evaluation criteria for the qualifications and |
3 | | the relative importance of those criteria; the evaluation |
4 | | criteria for qualifications shall, at a minimum, address |
5 | | the proposer's ability and past performance in meeting or |
6 | | exhausting good faith efforts to meet the utilization goals |
7 | | for business enterprises established in the Business |
8 | | Enterprise for Minorities, Females, and Persons with |
9 | | Disabilities Act and in complying with Section 2-105 of the |
10 | | Illinois Human Rights Act; the evaluation criteria for |
11 | | qualifications may also address, without limitation, the |
12 | | proposer's technical qualifications, such as specialized |
13 | | experience, technical competence, capability to perform, |
14 | | and past performance, including the proposer's safety |
15 | | record; |
16 | | (4) the Department's normal prequalification, |
17 | | licensing and registration requirements to the extent |
18 | | deemed applicable by the Department, provided that nothing |
19 | | contained herein precludes the Department's use of |
20 | | additional prequalification criteria or pass/fail |
21 | | evaluation factors addressing minimum levels of technical |
22 | | experience or financial capabilities; |
23 | | (5) the maximum number of proposers the Department will |
24 | | short-list to submit proposals; and |
25 | | (6) any other relevant information. |
26 | | (c) Upon completion of the qualifications evaluation, the |
|
| | SB1647 | - 10 - | LRB098 08041 HLH 38132 b |
|
|
1 | | Department shall, based on the evaluation criteria set forth in |
2 | | the request for qualifications, create a short-list of |
3 | | proposers. The Department shall short-list no fewer than 2 |
4 | | proposers unless (i) fewer than 2 proposers submit |
5 | | qualifications, (ii) fewer than 2 proposers meet the applicable |
6 | | prequalification and pass/fail requirements, or (iii) the |
7 | | Secretary of Transportation makes a finding that the Department |
8 | | may short-list fewer than 2 proposers. |
9 | | (d) The request for proposals may contain any information |
10 | | deemed appropriate by the Department, in its discretion, |
11 | | including, without limitation, the following information: |
12 | | (1) the scheduled date for completion of the |
13 | | transportation facility; |
14 | | (2) the form and amount of required bid security; |
15 | | (3) the material terms of the design-build contract or |
16 | | construction manager/general contractor contract, as |
17 | | applicable, including, but not limited to, scope and |
18 | | performance requirements, payment and performance security |
19 | | requirements, insurance requirements and the entity's plan |
20 | | to comply with disadvantaged business enterprises |
21 | | requirements and with Section 2-105 of the Illinois Human |
22 | | Rights Act; |
23 | | (4) the proposed budget for the project; |
24 | | (5) the requirements for the technical component of the |
25 | | proposal, including a description of the level of design, |
26 | | scope and type of renderings, drawings, and specifications |
|
| | SB1647 | - 11 - | LRB098 08041 HLH 38132 b |
|
|
1 | | to be provided in the proposals; |
2 | | (6) the requirements for the price component of the |
3 | | proposal, which for construction manager/general |
4 | | contractor contracts may include a requirement for the |
5 | | proposer to submit a lump sum price for the direct costs to |
6 | | perform the required preconstruction services and a |
7 | | percentage mark-up on those direct costs; |
8 | | (7) the evaluation criteria for the proposals and the |
9 | | relative importance of those criteria, including any |
10 | | formulas to be employed by the Department; as the |
11 | | Department deems appropriate, the technical proposal |
12 | | evaluation criteria may, without limitation, include |
13 | | compliance with the Department's stated objectives for the |
14 | | project, the proposal's compliance with the request for |
15 | | proposal requirements, the level of quality of proposed |
16 | | products or materials, and the quality of the proposed |
17 | | design; |
18 | | (8) in the case of a single phase procurement, |
19 | | requirements regarding the proposer's qualifications; or |
20 | | (9) any other relevant information. |
21 | | (e) The Department shall have the right to reject any and |
22 | | all qualifications or proposals, including, but not limited to |
23 | | the right to reject any proposal as non-responsive if the |
24 | | proposal does not meet all material requirements of the request |
25 | | for proposals. The Department shall not consider a proposal |
26 | | that does not include: (i) the proposer's plan to comply with |
|
| | SB1647 | - 12 - | LRB098 08041 HLH 38132 b |
|
|
1 | | requirements regarding utilization of minority and women |
2 | | business enterprises and economically disadvantaged firms |
3 | | established by the Department; or (ii) bid security in the form |
4 | | and amount designated in the request for proposals. |
5 | | (f) The Department may offer to pay a stipend in an amount |
6 | | and on the terms and conditions determined by the Department to |
7 | | (i) all short-listed proposers if the Department cancels the |
8 | | procurement before the due date for proposals or (ii) each |
9 | | unsuccessful proposer that submits a responsive proposal. The |
10 | | Department may pay a stipend only to those proposers who agree |
11 | | that their proposal and other proposal-related submissions |
12 | | will become the property of the Department. |
13 | | (g) The Department shall directly employ or retain a |
14 | | professional engineer licensed in the State to assist in the |
15 | | evaluation of the proposals' technical submissions under a |
16 | | design-build project delivery method and determine if the |
17 | | submissions are in accordance with generally accepted industry |
18 | | standards |
19 | | (h) The date proposals are due must be at least 21 calendar |
20 | | days after the date of the issuance of the request for |
21 | | proposals. In the event the cost of the project is estimated to |
22 | | exceed $10,000,000, the proposal due date must be at least 28 |
23 | | calendar days after the date of the issuance of the request for |
24 | | proposals. |
25 | | Section 1-30. Procedures for selection. Upon completion of |
|
| | SB1647 | - 13 - | LRB098 08041 HLH 38132 b |
|
|
1 | | the evaluation of proposals, if the Department decides to award |
2 | | a design-build contract or construction manager/general |
3 | | contractor contract, as applicable, the Department shall award |
4 | | the contract to the proposer whose proposal is determined to |
5 | | offer the best value to the public based on the evaluation |
6 | | criteria set forth in the request for proposals. |
7 | | Notwithstanding the above, if, for any reason, the proposer |
8 | | submitting the best value proposal is unable or unwilling to |
9 | | execute the contract, including the failure of the proposer and |
10 | | the Department to successfully complete negotiations of the |
11 | | contract, the Department may award the contract to the proposer |
12 | | whose proposal offers the public the next best value. |
13 | | Section 1-35. Project records, confidentiality, and public |
14 | | disclosure. |
15 | | (a) The Department shall maintain all written decisions, |
16 | | evaluations, scoring documents, selection evaluations, |
17 | | proposals and procurement documents in a contract file |
18 | | maintained by the Department. |
19 | | (b) A proposer may identify those portions of a proposal or |
20 | | other submission that the proposer considers to be trade |
21 | | secrets or confidential commercial, financial, or proprietary |
22 | | information. In order for the Department to consider |
23 | | confidential and proprietary information and trade secrets to |
24 | | be exempt from disclosure, the proposer shall do all of the |
25 | | following: |
|
| | SB1647 | - 14 - | LRB098 08041 HLH 38132 b |
|
|
1 | | (1) request exclusion from disclosure upon submission |
2 | | of the information or other materials for which protection |
3 | | is sought; |
4 | | (2) identify the data or other materials for which |
5 | | protection is sought; |
6 | | (3) state the reasons why protection is necessary; and |
7 | | (4) fully comply with the federal Freedom of |
8 | | Information Act and any other applicable provisions of |
9 | | State law with respect to information the proposer contends |
10 | | should be exempt from disclosure. |
11 | | (c) Notwithstanding any other provision of law, in order to |
12 | | properly balance the need to maximize competition under this |
13 | | Act with the need to create a transparent procurement process, |
14 | | qualifications, proposals, other information and documents |
15 | | submitted by proposers and the Department's evaluation records |
16 | | shall not be subject to release or disclosure by the Department |
17 | | until execution of the design-build contract or construction |
18 | | manager/general contractor contract, as applicable. If the |
19 | | Department rejects all qualifications submitted in response to |
20 | | a request for qualifications, or rejects all proposals |
21 | | submitted in response to a request for proposals, the exemption |
22 | | from release or disclosure under this section shall remain in |
23 | | place until the Department re-procures the transportation |
24 | | facility and has entered into a design-build contract or |
25 | | construction manager/general contractor contract, as |
26 | | applicable. However, this exemption shall lapse if the |
|
| | SB1647 | - 15 - | LRB098 08041 HLH 38132 b |
|
|
1 | | Department does not commence the re-procurement of the |
2 | | transportation facility within one year of its rejection of the |
3 | | responses to the request for qualifications or request for |
4 | | proposals. |
5 | | Section 1-40. Design-build contract. A design-build |
6 | | contract may include any provisions the Department determines |
7 | | are necessary or appropriate, including but not limited to |
8 | | provisions regarding the following: |
9 | | (1) compensation or payments to the design-builder; |
10 | | (2) grounds for termination of the design-build |
11 | | contract, including the Department's right to terminate |
12 | | for convenience; |
13 | | (3) liability for damages and nonperformance; |
14 | | (4) events of default and the rights and remedies |
15 | | available to the design-builder and the Department in the |
16 | | event of a default or delay; |
17 | | (5) terms for the design-builder's compliance with |
18 | | disadvantaged business enterprises requirements and with |
19 | | Section 2-105 of the Illinois Human Rights Act; |
20 | | (6) the identification of any technical specifications |
21 | | that the design-builder must comply with when developing |
22 | | plans or performing construction work; |
23 | | (7) the procedures for review and approval of the |
24 | | design-builder's plans; |
25 | | (8) required performance and payment security; |
|
| | SB1647 | - 16 - | LRB098 08041 HLH 38132 b |
|
|
1 | | (9) the terms and conditions of indemnification and |
2 | | minimum insurance requirements; or |
3 | | (10) any other terms and conditions. |
4 | | Section 1-45. Construction Manager/General Contractor |
5 | | Contract. |
6 | | (a) The construction manager/general contractor contract |
7 | | shall divide the construction manager/general contractor's |
8 | | services into two phases. The first phase shall address |
9 | | preconstruction services and the procedures the parties will |
10 | | follow to finalize the contract terms for the second phase. The |
11 | | second phase shall address the construction manager/general |
12 | | contractor's construction of the transportation facility for a |
13 | | lump sum or a guaranteed maximum price. |
14 | | (b) A construction manager/general contractor contract |
15 | | shall include provisions regarding the following: |
16 | | (1) the construction manager/general contractor's |
17 | | provision of preconstruction services during the first |
18 | | phase of the contract, including the construction |
19 | | manager/general contractor's compensation for those |
20 | | services; |
21 | | (2) a requirement that, during the first phase of the |
22 | | contract, the construction manager/general contractor use |
23 | | a competitive bidding process to procure subcontracts for |
24 | | at least 70% of the construction work, provided that (i) |
25 | | compliance with this requirement will be based on an |
|
| | SB1647 | - 17 - | LRB098 08041 HLH 38132 b |
|
|
1 | | estimated cost for the construction work approved by the |
2 | | Department prior to the start of the competitive bidding |
3 | | process and (ii) the construction manager/general |
4 | | contractor may not use subcontracts with wholly or |
5 | | partially owned subsidiaries, parent companies or |
6 | | affiliates to satisfy this obligation; |
7 | | (3) the process the Department and construction |
8 | | manager/general contractor will use to determine a lump sum |
9 | | or guaranteed maximum price for the construction work, |
10 | | which shall include a requirement that the Department |
11 | | conduct an independent cost estimate for the construction |
12 | | work; and |
13 | | (4) grounds for termination of the construction |
14 | | manager/general contractor contract, including the |
15 | | Department's right to terminate the contract and not |
16 | | proceed with the construction phase of the project if the |
17 | | Department and construction manager/general contractor are |
18 | | unable to negotiate a guaranteed maximum price for the |
19 | | construction work. |
20 | | (c) In addition to the provisions set forth in subsection |
21 | | (b), a construction manager/general contractor contract may |
22 | | include any other provisions the Department determines are |
23 | | necessary or appropriate, including, but not limited to, |
24 | | provisions regarding the following: |
25 | | (1) liability for damages and nonperformance; |
26 | | (2) events of default and the rights and remedies |
|
| | SB1647 | - 18 - | LRB098 08041 HLH 38132 b |
|
|
1 | | available to the construction manager/general contractor |
2 | | and the Department in the event of a default or delay; |
3 | | (3) terms for the construction manager/general |
4 | | contractor's compliance with disadvantaged business |
5 | | enterprises requirements and with Section 2-105 of the |
6 | | Illinois Human Rights Act for any construction work |
7 | | performed under the construction manager/general |
8 | | contractor contract; |
9 | | (4) the identification of any technical specifications |
10 | | that the construction manager/general contractor must |
11 | | comply with when aiding the Department with developing |
12 | | plans or performing construction work; |
13 | | (5) required performance and payment security for the |
14 | | construction phase of the contract; |
15 | | (6) the terms and conditions of indemnification and |
16 | | minimum insurance requirements; and |
17 | | (7) any other terms and conditions. |
18 | | (d) If the construction manager/general contractor |
19 | | contract is terminated for any reason, the Department may, in |
20 | | its sole discretion, re-advertise the construction |
21 | | manager/general contractor contract under this Act or use any |
22 | | other authorized procurement method to complete the |
23 | | transportation facility or any portion of the transportation |
24 | | facility. Once the contract is terminated, the Department may |
25 | | use any work product developed by the construction |
26 | | manager/general contractor to complete the transportation |
|
| | SB1647 | - 19 - | LRB098 08041 HLH 38132 b |
|
|
1 | | facility. The construction manager/general contractor whose |
2 | | contract was terminated may not bid on or join a team that is |
3 | | bidding on the subsequent contract or contracts for the |
4 | | transportation facility. |
5 | | Section 1-50. Labor. |
6 | | (a) The design-builder and construction manager/general |
7 | | contractor, and all subcontractors to them, shall comply with |
8 | | the requirements of the Prevailing Wage Act, the Equal Pay Act |
9 | | of 2003, the Public Works Employment Discrimination Act, the |
10 | | Employment of Illinois Workers on Public Works Act, Section |
11 | | 2-105 of the Illinois Human Rights Act, and federal equal |
12 | | employment laws and practices, unless the application of those |
13 | | requirements would jeopardize the receipt or use of federal |
14 | | funds for a transportation facility. |
15 | | (b) The design-builder and construction manager/general |
16 | | contractor, and all subcontractors to them, shall comply with |
17 | | the requirements of federal disadvantaged business laws and |
18 | | practices or the Business Enterprise for Minorities, Females, |
19 | | and Persons with Disabilities Act. Disadvantaged business |
20 | | enterprise program compliance, enforcement, and monitoring |
21 | | shall be as established by federal law. |
22 | | (c) The Department shall consider requiring the use of a |
23 | | project labor agreement in connection with the development of a |
24 | | transportation facility under this Act. |
|
| | SB1647 | - 20 - | LRB098 08041 HLH 38132 b |
|
|
1 | | Section 1-55. Funding and financing. |
2 | | (a) The Department may utilize any lawful source of funding |
3 | | and financing to compensate a design-builder and construction |
4 | | manager/general contractor for work and services performed |
5 | | under a design-build contract or construction manager/general |
6 | | contractor contract, as applicable, and the Department may |
7 | | combine federal, State, local, and private funds to finance a |
8 | | transportation facility. |
9 | | (b) The Department may impose financing obligations and |
10 | | other financial responsibilities on a design-builder or |
11 | | construction manager/general contractor in order to finance a |
12 | | portion of the costs of a transportation facility. |
13 | | (c) Subject to appropriation by the General Assembly of the |
14 | | required amounts, the Department may obligate and make |
15 | | expenditures of funds as and when needed to satisfy its payment |
16 | | obligations under a design-build contract or construction |
17 | | manager/general contractor contract. |
18 | | Section 1-60. Acquisition of property and related |
19 | | agreements. The Department may exercise any and all powers of |
20 | | condemnation or eminent domain, including quick-take powers, |
21 | | to acquire lands or estates or interests in land for a |
22 | | transportation facility under this Act or to the extent the |
23 | | Department finds that the action serves the public purpose of |
24 | | this Act and deems the action appropriate in the exercise of |
25 | | its powers under this Act. In addition, the Department and a |
|
| | SB1647 | - 21 - | LRB098 08041 HLH 38132 b |
|
|
1 | | design-builder or construction manager/general contractor may |
2 | | enter into leases, licenses, easements, and other grants of |
3 | | property interests that the Department determines necessary to |
4 | | carry out this Act. |
5 | | Section 1-65. Administrative Procedure Act. The Illinois |
6 | | Administrative Procedure Act applies to all administrative |
7 | | rules and procedures of the Department under this Act except |
8 | | that nothing herein shall be construed to render any |
9 | | prequalification or other responsibility criteria as a |
10 | | "license" or "licensing" under that Act. |
11 | | Section 1-70. Federal requirements. In the procurement of |
12 | | design-build contracts and construction manager/general |
13 | | contractor contracts, the Department shall comply with federal |
14 | | law and regulations and take all necessary steps to adapt its |
15 | | rules, policies, and procedures to remain eligible for federal |
16 | | aid. |
17 | | Section 1-75. Powers. The powers granted to the Department |
18 | | under this Act shall be liberally construed to accomplish its |
19 | | purpose, are in addition to any existing powers of the |
20 | | Department, and shall not affect or impair any other powers |
21 | | authorized under applicable law. This includes powers to |
22 | | procure and enter into design-build contracts and construction |
23 | | manager/general contractor contracts under this Act. |
|
| | SB1647 | - 22 - | LRB098 08041 HLH 38132 b |
|
|
1 | | Section 1-80. Rules. The Department may adopt rules to |
2 | | carry out the provisions of this Act. |
3 | | Section 1-85. Repealer. This Act is repealed on the date |
4 | | that is 5 years after the effective date of this Act; provided |
5 | | that any design-build contracts and construction |
6 | | manager/general contractor contracts entered into before such |
7 | | date or any procurement of a transportation facility under this |
8 | | Act commenced before such date, and the contracts resulting |
9 | | from those procurements, shall remain effective. |
10 | | ARTICLE 5. AMENDATORY PROVISIONS |
11 | | Section 5-5. The Department of Transportation Law of the
|
12 | | Civil Administrative Code of Illinois is amended by adding |
13 | | Section 2705-233 as follows: |
14 | | (20 ILCS 2705/2705-233 new) |
15 | | Sec. 2705-233. Design-build and construction |
16 | | manager/general contractor for transportation infrastructure. |
17 | | The Department may exercise all powers granted to it under the |
18 | | Design-Build and Construction Manager/General Contractor |
19 | | Transportation Infrastructure Act, including the power to |
20 | | enter into all contracts or agreements necessary or incidental |
21 | | to the performance of its powers under the Act, and powers |
|
| | SB1647 | - 23 - | LRB098 08041 HLH 38132 b |
|
|
1 | | related to any transportation facility implemented pursuant to |
2 | | that Act. |
3 | | Section 5-10. The Illinois Finance Authority Act is amended |
4 | | by adding Section 825-108 as follows: |
5 | | (20 ILCS 3501/825-108 new) |
6 | | Sec. 825-108. Transportation project financing. For the |
7 | | purpose of financing a transportation facility undertaken |
8 | | under the Design-Build and Construction Manager/General |
9 | | Contractor Transportation Infrastructure Act, the Authority is |
10 | | authorized to apply for an allocation of tax-exempt bond |
11 | | financing authorization provided by Section 142(m) of the |
12 | | United States Internal Revenue Code, as well as financing |
13 | | available under any other federal law or program. |
14 | | Section 5-15. The Illinois Procurement Code is amended by |
15 | | changing Section 1-10 as follows:
|
16 | | (30 ILCS 500/1-10)
|
17 | | Sec. 1-10. Application.
|
18 | | (a) This Code applies only to procurements for which |
19 | | contractors were first
solicited on or after July 1, 1998. This |
20 | | Code shall not be construed to affect
or impair any contract, |
21 | | or any provision of a contract, entered into based on a
|
22 | | solicitation prior to the implementation date of this Code as |
|
| | SB1647 | - 24 - | LRB098 08041 HLH 38132 b |
|
|
1 | | described in
Article 99, including but not limited to any |
2 | | covenant entered into with respect
to any revenue bonds or |
3 | | similar instruments.
All procurements for which contracts are |
4 | | solicited between the effective date
of Articles 50 and 99 and |
5 | | July 1, 1998 shall be substantially in accordance
with this |
6 | | Code and its intent.
|
7 | | (b) This Code shall apply regardless of the source of the |
8 | | funds with which
the contracts are paid, including federal |
9 | | assistance moneys.
This Code shall
not apply to:
|
10 | | (1) Contracts between the State and its political |
11 | | subdivisions or other
governments, or between State |
12 | | governmental bodies except as specifically
provided in |
13 | | this Code.
|
14 | | (2) Grants, except for the filing requirements of |
15 | | Section 20-80.
|
16 | | (3) Purchase of care.
|
17 | | (4) Hiring of an individual as employee and not as an |
18 | | independent
contractor, whether pursuant to an employment |
19 | | code or policy or by contract
directly with that |
20 | | individual.
|
21 | | (5) Collective bargaining contracts.
|
22 | | (6) Purchase of real estate, except that notice of this |
23 | | type of contract with a value of more than $25,000 must be |
24 | | published in the Procurement Bulletin within 7 days after |
25 | | the deed is recorded in the county of jurisdiction. The |
26 | | notice shall identify the real estate purchased, the names |
|
| | SB1647 | - 25 - | LRB098 08041 HLH 38132 b |
|
|
1 | | of all parties to the contract, the value of the contract, |
2 | | and the effective date of the contract.
|
3 | | (7) Contracts necessary to prepare for anticipated |
4 | | litigation, enforcement
actions, or investigations, |
5 | | provided
that the chief legal counsel to the Governor shall |
6 | | give his or her prior
approval when the procuring agency is |
7 | | one subject to the jurisdiction of the
Governor, and |
8 | | provided that the chief legal counsel of any other |
9 | | procuring
entity
subject to this Code shall give his or her |
10 | | prior approval when the procuring
entity is not one subject |
11 | | to the jurisdiction of the Governor.
|
12 | | (8) Contracts for
services to Northern Illinois |
13 | | University by a person, acting as
an independent |
14 | | contractor, who is qualified by education, experience, and
|
15 | | technical ability and is selected by negotiation for the |
16 | | purpose of providing
non-credit educational service |
17 | | activities or products by means of specialized
programs |
18 | | offered by the university.
|
19 | | (9) Procurement expenditures by the Illinois |
20 | | Conservation Foundation
when only private funds are used.
|
21 | | (10) Procurement expenditures by the Illinois Health |
22 | | Information Exchange Authority involving private funds |
23 | | from the Health Information Exchange Fund. "Private funds" |
24 | | means gifts, donations, and private grants. |
25 | | (11) Public-private agreements entered into according |
26 | | to the procurement requirements of Section 20 of the |
|
| | SB1647 | - 26 - | LRB098 08041 HLH 38132 b |
|
|
1 | | Public-Private Partnerships for Transportation Act and |
2 | | design-build agreements entered into according to the |
3 | | procurement requirements of Section 25 of the |
4 | | Public-Private Partnerships for Transportation Act. |
5 | | (c) This Code does not apply to the electric power |
6 | | procurement process provided for under Section 1-75 of the |
7 | | Illinois Power Agency Act and Section 16-111.5 of the Public |
8 | | Utilities Act. |
9 | | (d) Except for Section 20-160 and Article 50 of this Code, |
10 | | and as expressly required by Section 9.1 of the Illinois |
11 | | Lottery Law, the provisions of this Code do not apply to the |
12 | | procurement process provided for under Section 9.1 of the |
13 | | Illinois Lottery Law. |
14 | | (e) This Code does not apply to the process used by the |
15 | | Capital Development Board to retain a person or entity to |
16 | | assist the Capital Development Board with its duties related to |
17 | | the determination of costs of a clean coal SNG brownfield |
18 | | facility, as defined by Section 1-10 of the Illinois Power |
19 | | Agency Act, as required in subsection (h-3) of Section 9-220 of |
20 | | the Public Utilities Act, including calculating the range of |
21 | | capital costs, the range of operating and maintenance costs, or |
22 | | the sequestration costs or monitoring the construction of clean |
23 | | coal SNG brownfield facility for the full duration of |
24 | | construction. |
25 | | (f) This Code does not apply to the process used by the |
26 | | Illinois Power Agency to retain a mediator to mediate sourcing |
|
| | SB1647 | - 27 - | LRB098 08041 HLH 38132 b |
|
|
1 | | agreement disputes between gas utilities and the clean coal SNG |
2 | | brownfield facility, as defined in Section 1-10 of the Illinois |
3 | | Power Agency Act, as required under subsection (h-1) of Section |
4 | | 9-220 of the Public Utilities Act. |
5 | | (g) This Code does not apply to the processes used by the |
6 | | Illinois Power Agency to retain a mediator to mediate contract |
7 | | disputes between gas utilities and the clean coal SNG facility |
8 | | and to retain an expert to assist in the review of contracts |
9 | | under subsection (h) of Section 9-220 of the Public Utilities |
10 | | Act. This Code does not apply to the process used by the |
11 | | Illinois Commerce Commission to retain an expert to assist in |
12 | | determining the actual incurred costs of the clean coal SNG |
13 | | facility and the reasonableness of those costs as required |
14 | | under subsection (h) of Section 9-220 of the Public Utilities |
15 | | Act. |
16 | | (h) This Code does not apply to the process to procure or |
17 | | contracts entered into in accordance with Sections 11-5.2 and |
18 | | 11-5.3 of the Illinois Public Aid Code. |
19 | | (i) (h) Each chief procurement officer may access records |
20 | | necessary to review whether a contract, purchase, or other |
21 | | expenditure is or is not subject to the provisions of this |
22 | | Code, unless such records would be subject to attorney-client |
23 | | privilege. |
24 | | (j) Except for Section 20-160 and Article 50 of this Code, |
25 | | the provisions of this Code do not apply to design-build |
26 | | contracts or construction manager/general contractor contracts |
|
| | SB1647 | - 28 - | LRB098 08041 HLH 38132 b |
|
|
1 | | entered into according to the procurement requirements of the |
2 | | Design-Build and Construction Manager/General Contractor |
3 | | Transportation Infrastructure Act. |
4 | | (Source: P.A. 96-840, eff. 12-23-09; 96-1331, eff. 7-27-10; |
5 | | 97-96, eff. 7-13-11; 97-239, eff. 8-2-11; 97-502, eff. 8-23-11; |
6 | | 97-689, eff. 6-14-12; 97-813, eff. 7-13-12; 97-895, eff. |
7 | | 8-3-12; revised 8-23-12.)
|
8 | | Section 5-20. The Architectural, Engineering, and Land |
9 | | Surveying
Qualifications Based Selection Act is amended by |
10 | | adding Section 85 as follows: |
11 | | (30 ILCS 535/85 new) |
12 | | Sec. 85. Design-Build and Construction Manager/General |
13 | | Contractor Contracts. This Act shall not apply to the |
14 | | procurement of or contracting for transportation facilities |
15 | | pursuant to design-build contracts or construction |
16 | | manager/general contractor contracts under the Design-Build |
17 | | and Construction Manager/General Contractor Transportation |
18 | | Infrastructure Act. |
19 | | Section 5-25. The Employment of Illinois Workers on Public |
20 | | Works Act is amended by adding Section 2.8 as follows: |
21 | | (30 ILCS 570/2.8 new) |
22 | | Sec. 2.8. Design-build and construction manager/general |
|
| | SB1647 | - 29 - | LRB098 08041 HLH 38132 b |
|
|
1 | | contractor contracts. This Act applies to any construction work |
2 | | undertaken pursuant to design-build contracts and construction |
3 | | manager/general contractor contracts entered into under the |
4 | | Design-Build and Construction Manager/General Contractor |
5 | | Transportation Infrastructure Act. |
6 | | Section 5-26. The Business Enterprise for Minorities, |
7 | | Females, and Persons with
Disabilities Act is amended by adding |
8 | | Section 2.8 as follows: |
9 | | (30 ILCS 575/2.8 new) |
10 | | Sec. 2.8. Design-build and construction manager/general |
11 | | contractor contracts. This Act applies to any design-build |
12 | | contracts and construction manager/general contractor |
13 | | contracts entered into under the Design-Build and Construction |
14 | | Manager/General Contractor Transportation Infrastructure Act. |
15 | | Section 5-27. The Eminent Domain Act is amended by adding |
16 | | Section 15-5-47 as follows: |
17 | | (735 ILCS 30/15-5-47 new) |
18 | | Sec. 15-5-47. Eminent domain powers in new Acts. The |
19 | | following provisions of law may include express grants of the |
20 | | power to acquire property by condemnation or eminent domain: |
21 | | The Design-Build and Construction Manager/General Contractor |
|
| | SB1647 | - 30 - | LRB098 08041 HLH 38132 b |
|
|
1 | | Transportation Infrastructure Act; Department of |
2 | | Transportation; for the purposes of constructing a |
3 | | transportation facility under the Act and to serve the |
4 | | public purpose of the Act. |
5 | | Section 5-30. The Prevailing Wage Act is amended by |
6 | | changing Section 2 as follows:
|
7 | | (820 ILCS 130/2) (from Ch. 48, par. 39s-2)
|
8 | | Sec. 2. This Act applies to the wages of laborers, |
9 | | mechanics and
other workers employed in any public works, as |
10 | | hereinafter defined, by
any public body and to anyone under |
11 | | contracts for public works. This includes any maintenance, |
12 | | repair, assembly, or disassembly work performed on equipment |
13 | | whether owned, leased, or rented.
|
14 | | As used in this Act, unless the context indicates |
15 | | otherwise:
|
16 | | "Public works" means all fixed works constructed or |
17 | | demolished by
any public body,
or paid for wholly or in part |
18 | | out of public funds. "Public works" as
defined herein includes |
19 | | all projects financed in whole
or in part with bonds, grants, |
20 | | loans, or other funds made available by or through the State or |
21 | | any of its political subdivisions, including but not limited |
22 | | to: bonds issued under the Industrial Project Revenue Bond
Act |
23 | | (Article 11, Division 74 of the Illinois Municipal Code), the |
24 | | Industrial
Building Revenue Bond Act, the Illinois Finance |
|
| | SB1647 | - 31 - | LRB098 08041 HLH 38132 b |
|
|
1 | | Authority Act,
the Illinois Sports Facilities Authority Act, or |
2 | | the Build Illinois Bond Act; loans or other funds made
|
3 | | available pursuant to the Build Illinois Act; or funds from the |
4 | | Fund for
Illinois' Future under Section 6z-47 of the State |
5 | | Finance Act, funds for school
construction under Section 5 of |
6 | | the General Obligation Bond Act, funds
authorized under Section |
7 | | 3 of the School Construction Bond Act, funds for
school |
8 | | infrastructure under Section 6z-45 of the State Finance Act, |
9 | | and funds
for transportation purposes under Section 4 of the |
10 | | General Obligation Bond
Act. "Public works" also includes (i) |
11 | | all projects financed in whole or in part
with funds from the |
12 | | Department of Commerce and Economic Opportunity under the |
13 | | Illinois Renewable Fuels Development Program
Act for which |
14 | | there is no project labor agreement; (ii) all work performed |
15 | | pursuant to a public private agreement under the Public Private |
16 | | Agreements for the Illiana Expressway Act; and (iii) all |
17 | | projects undertaken under a public-private agreement under the |
18 | | Public-Private Partnerships for Transportation Act ; and (iv) |
19 | | all transportation facilities undertaken under a design-build |
20 | | contract or construction manager/general contractor contract |
21 | | pursuant to the Design-Build and Construction Manager/General |
22 | | Contractor Transportation Infrastructure Act . "Public works" |
23 | | also includes all projects at leased facility property used for |
24 | | airport purposes under Section 35 of the Local Government |
25 | | Facility Lease Act. "Public works" also includes the |
26 | | construction of a new wind power facility by a business |
|
| | SB1647 | - 32 - | LRB098 08041 HLH 38132 b |
|
|
1 | | designated as a High Impact Business under Section 5.5(a)(3)(E) |
2 | | of the Illinois Enterprise Zone Act.
"Public works" does not |
3 | | include work done directly by any public utility company, |
4 | | whether or not done under public supervision or direction, or |
5 | | paid for wholly or in part out of public funds. "Public works" |
6 | | does not include projects undertaken by the owner at an |
7 | | owner-occupied single-family residence or at an owner-occupied |
8 | | unit of a multi-family residence.
|
9 | | "Construction" means all work on public works involving |
10 | | laborers,
workers or mechanics. This includes any maintenance, |
11 | | repair, assembly, or disassembly work performed on equipment |
12 | | whether owned, leased, or rented.
|
13 | | "Locality" means the county where the physical work upon |
14 | | public works
is performed, except (1) that if there is not |
15 | | available in the county a
sufficient number of competent |
16 | | skilled laborers, workers and mechanics
to construct the public |
17 | | works efficiently and properly, "locality"
includes any other |
18 | | county nearest the one in which the work or
construction is to |
19 | | be performed and from which such persons may be
obtained in |
20 | | sufficient numbers to perform the work and (2) that, with
|
21 | | respect to contracts for highway work with the Department of
|
22 | | Transportation of this State, "locality" may at the discretion |
23 | | of the
Secretary of the Department of Transportation be |
24 | | construed to include
two or more adjacent counties from which |
25 | | workers may be accessible for
work on such construction.
|
26 | | "Public body" means the State or any officer, board or |
|
| | SB1647 | - 33 - | LRB098 08041 HLH 38132 b |
|
|
1 | | commission of
the State or any political subdivision or |
2 | | department thereof, or any
institution supported in whole or in |
3 | | part by public funds,
and includes every county, city, town,
|
4 | | village, township, school district, irrigation, utility, |
5 | | reclamation
improvement or other district and every other |
6 | | political subdivision,
district or municipality of the state |
7 | | whether such political
subdivision, municipality or district |
8 | | operates under a special charter
or not.
|
9 | | The terms "general prevailing rate of hourly wages", |
10 | | "general
prevailing rate of wages" or "prevailing rate of |
11 | | wages" when used in
this Act mean the hourly cash wages plus |
12 | | fringe benefits for training and
apprenticeship programs |
13 | | approved by the U.S. Department of Labor, Bureau of
|
14 | | Apprenticeship and Training, health and welfare, insurance, |
15 | | vacations and
pensions paid generally, in the
locality in which |
16 | | the work is being performed, to employees engaged in
work of a |
17 | | similar character on public works.
|
18 | | (Source: P.A. 96-28, eff. 7-1-09; 96-58, eff. 1-1-10; 96-186, |
19 | | eff. 1-1-10; 96-913, eff. 6-9-10; 96-1000, eff. 7-2-10; 97-502, |
20 | | eff. 8-23-11.)
|
21 | | ARTICLE 99. EFFECTIVE DATE AND SEVERABILITY |
22 | | Section 99-97. Severability. The provisions of this Act are |
23 | | severable under Section 1.31 of the Statute on Statutes.
|
24 | | Section 99-99. Effective date. This Act takes effect upon |