| | HB2959 | - 2 - | LRB098 10954 JWD 41567 b |
|
|
1 | | planning process. The Director of the Governor's Office |
2 | | Management and Budget may assign to any State agency such |
3 | | duties and responsibilities as may, in the Director's judgment, |
4 | | be necessary to the successful administration of the capital |
5 | | improvement planning process.
|
6 | | Section 10. Definitions. As used in this Act: |
7 | | "Department" means the Department of Central Management |
8 | | Services. |
9 | | "Director" means the Director of the Governor's Office |
10 | | Management and Budget. |
11 | | "Office" means the Governor's Office Management and |
12 | | Budget. |
13 | | "State agency" has the meaning provided in Section 1.05 of |
14 | | the State Property Control Act. |
15 | | "State university" means Chicago State University, Eastern |
16 | | Illinois University, Governors State University, Illinois |
17 | | State University, Northeastern Illinois University, Northern |
18 | | Illinois University, Southern Illinois University, the |
19 | | University of Illinois, or Western Illinois University. |
20 | | Section 15. Capital facilities inventory. The Department |
21 | | shall develop and maintain an automated inventory of all |
22 | | facilities owned by the State of Illinois. The inventory shall |
23 | | include the location, occupying agency, ownership, size, |
24 | | description, condition assessment, maintenance record, parking |
|
| | HB2959 | - 3 - | LRB098 10954 JWD 41567 b |
|
|
1 | | and employee facilities, and other information to determine |
2 | | maintenance needs and prepare life cycle cost evaluations of |
3 | | each facility listed in the inventory. The Department shall |
4 | | update and publish the inventory at least once every 3 years. |
5 | | The Department shall also record in the inventory acquisitions |
6 | | of new facilities and significant changes in existing |
7 | | facilities as they occur. |
8 | | Section 20. Capital improvement needs criteria. The Office |
9 | | shall develop a weighted list of factors that may be used to |
10 | | evaluate the need for capital improvement projects. The list |
11 | | must include, but is not limited to, the following:
|
12 | | (1) Preservation, adequacy, and use of existing |
13 | | facilities.
|
14 | | (2) Health and safety considerations.
|
15 | | (3) Operational efficiencies.
|
16 | | (4) Projected demand for governmental services. |
17 | | Section 25. Agency capital improvement needs estimates. |
18 | | (a) On or before September 1 of each year, each State |
19 | | agency shall submit to the Office and to the Commission on |
20 | | Government Forecasting and Accountability a 5-year capital |
21 | | improvement needs estimate. This estimate shall describe the |
22 | | agency's anticipated capital needs for each year of the 5-year |
23 | | planning period. Capital improvement needs estimates shall be |
24 | | shown in 2 parts, as provided in subsections (b) and (c) of |
|
| | HB2959 | - 4 - | LRB098 10954 JWD 41567 b |
|
|
1 | | this Section.
|
2 | | (b) The first part of the capital improvement needs |
3 | | estimates shall include only requirements for repairs and |
4 | | renovations necessary to maintain the existing use of existing |
5 | | facilities. Each proposed repair and renovation expenditure |
6 | | shall be justified by a cost benefit analysis and such other |
7 | | criteria as the Capital Development Board may by rule require.
|
8 | | (c) The second part of the capital improvement needs |
9 | | estimates shall include only proposals for real property |
10 | | acquisition and projects involving construction of new |
11 | | facilities or rehabilitation of existing facilities to |
12 | | accommodate uses for which the existing facilities were not |
13 | | originally designed. Each project included in this part shall |
14 | | be justified by a cost benefit analysis and such other criteria |
15 | | as the Director may require. |
16 | | For capital projects of a State university, the Office |
17 | | shall utilize the needs evaluation information approved by the |
18 | | board of trustees of that State university. |
19 | | Section 30. Five-year capital improvements plan. |
20 | | (a) The State capital improvement plan shall address the |
21 | | long term capital improvement needs of all State agencies and |
22 | | shall incorporate all capital projects, however financed, |
23 | | proposed to meet those needs, except that transportation |
24 | | infrastructure projects shall be excluded. On or before |
25 | | December 31 of each year, the Director shall prepare and |
|
| | HB2959 | - 5 - | LRB098 10954 JWD 41567 b |
|
|
1 | | transmit to the General Assembly a 5-year capital improvement |
2 | | plan. When preparing the plan, the Director shall consider the |
3 | | capital improvement needs estimates submitted by State |
4 | | agencies. The plan shall be prepared in 2 parts, as provided in |
5 | | subsections (b) and (c) of this Section.
|
6 | | (b) The first part of the capital improvement plan shall |
7 | | set forth repair and renovations requirements that, in the |
8 | | judgment of the Director, should be met within each year of the |
9 | | 5-year planning period to protect and preserve existing capital |
10 | | improvement facilities. The plan shall identify individual |
11 | | projects in priority order by State agency and shall specify |
12 | | the means of financing for each project.
|
13 | | (c) The second part of the capital improvement plan shall |
14 | | set forth an integrated schedule for real property acquisition, |
15 | | new construction, or rehabilitation of existing facilities |
16 | | that, in the judgment of the Director, should be initiated |
17 | | within each year of the 5-year planning period. The plan shall |
18 | | contain for each project: |
19 | | (1) estimates of real property acquisition, and |
20 | | construction or rehabilitation costs; |
21 | | (2) a means of financing the project; and |
22 | | (3) an estimated schedule for the completion of the |
23 | | project. |
24 | | Where the means of financing would involve direct or |
25 | | indirect debt service obligations, a schedule of those |
26 | | obligations shall be presented.
|
|
| | HB2959 | - 6 - | LRB098 10954 JWD 41567 b |
|
|
1 | | Section 35. Recommendations for capital improvements. |
2 | | (a) The Director shall recommend expenditures for repairs |
3 | | and renovations of existing facilities, and real property |
4 | | acquisition, new construction, or rehabilitation of existing |
5 | | facilities in the State Budget proposed by the Governor.
|
6 | | (b) The State Budget proposed by the Governor shall contain |
7 | | for repairs and renovations of existing facilities: |
8 | | (1) the amount recommended for each State agency; |
9 | | (2) a summary of the recommendations by project type; |
10 | | and |
11 | | (3) the means of financing.
|
12 | | (c) The Budget Support Document shall contain for each |
13 | | repair and renovation project recommended in accordance with |
14 | | subsection (b) of this Section: |
15 | | (1) a project description and justification; |
16 | | (2) a detailed cost estimate; |
17 | | (3) an estimated schedule for the completion of the |
18 | | project; and |
19 | | (4) an explanation of the means of financing.
|
20 | | (d) The State Budget proposed by the Governor shall contain |
21 | | for each capital project involving real property acquisition, |
22 | | new construction, building area (expressed in square footage) |
23 | | expansions, or the rehabilitation of existing facilities to |
24 | | accommodate new or expanded uses: |
25 | | (1) a project description and statement of need; |
|
| | HB2959 | - 7 - | LRB098 10954 JWD 41567 b |
|
|
1 | | (2) an estimate of acquisition and construction or |
2 | | rehabilitation costs; and |
3 | | (3) a means of financing the project.
|
4 | | (e) The Budget Support Document shall contain for each |
5 | | capital project recommended in accordance with subsection (d) |
6 | | of this Section: |
7 | | (1) a detailed project description and justification; |
8 | | (2) a detailed estimate of acquisition, planning, |
9 | | design, site development, construction, contingency and |
10 | | other related costs; |
11 | | (3) an estimated schedule of cash flow requirements |
12 | | over the life of the project; |
13 | | (4) an estimated schedule for the completion of the |
14 | | project; |
15 | | (5) an estimate of maintenance and operating costs, |
16 | | including personnel, for the project, covering the first 5 |
17 | | years of operation; |
18 | | (6) an estimate of revenues, if any, likely to be |
19 | | derived from the project, covering the first 5 years of |
20 | | operation; and |
21 | | (7) an explanation of the means of financing. |
22 | | Section 40. When a State agency may begin a capital |
23 | | improvement project. No State agency may expend funds for the |
24 | | construction or renovation of any capital improvement project |
25 | | except as needed to comply with this Act or as otherwise |
|
| | HB2959 | - 8 - | LRB098 10954 JWD 41567 b |
|
|
1 | | authorized by the General Assembly. Funds that become available |
2 | | by gifts, federal or private grants, receipts becoming a part |
3 | | of special funds by Act of the General Assembly, or any other |
4 | | funds available to a State agency or institution may be |
5 | | utilized for advanced planning through the working drawing |
6 | | phase of capital improvement projects, upon approval of the |
7 | | Director. |
8 | | Section 45. When a State agency may increase the cost of a |
9 | | capital improvement project. Upon the request of the |
10 | | administration of a State agency, the Director may, when in the |
11 | | Director's opinion it is in the best interest of the State to |
12 | | do so, increase the cost of a capital improvement project. |
13 | | Provided, however, that if the Director increases the cost of a |
14 | | project, the Director shall immediately report that action by |
15 | | written message to the General Assembly. The increase may be |
16 | | funded from gifts, federal or private grants, special fund |
17 | | receipts, or direct capital improvement appropriations to that |
18 | | State agency. |
19 | | Section 50. When a State agency may change the scope of a |
20 | | capital improvement project. A State agency may increase the |
21 | | scope of a capital improvement project only if the General |
22 | | Assembly authorizes the increase. A State agency may decrease |
23 | | the scope of a capital improvement project if the Director |
24 | | authorizes the decrease. To obtain the Director's |
|
| | HB2959 | - 9 - | LRB098 10954 JWD 41567 b |
|
|
1 | | authorization for a decrease in the scope of a capital |
2 | | improvement project, a State agency shall submit its request to |
3 | | the Director in writing and shall state the reason for the |
4 | | request. |
5 | | Section 55. Project Reserve Fund. |
6 | | (a) There is created the Project Reserve Fund as a special |
7 | | fund in the State treasury. When a construction contract is |
8 | | entered for a capital improvement project for which the General |
9 | | Assembly has enacted an appropriation, the appropriation is |
10 | | encumbered for the project's costs of real property |
11 | | acquisition, planning, design, site development, construction, |
12 | | contingencies, and other related costs. If the amount |
13 | | appropriated for the project exceeds the amount encumbered, the |
14 | | excess shall be credited to the Project Reserve Fund, unless |
15 | | otherwise required by law. The Director may authorize funds in |
16 | | the Fund to be used for any of the following:
|
17 | | (1) An emergency repair and renovation project at a |
18 | | State facility.
|
19 | | (2) The award of a project contract when bids for the |
20 | | contract exceed the amount appropriated for it if the |
21 | | project was designed within the scope intended by the |
22 | | appropriation and if the Director finds that all means to |
23 | | award the contract within the appropriation were |
24 | | reasonably attempted.
|
25 | | (3) A reversion to the principal fund from which |
|
| | HB2959 | - 10 - | LRB098 10954 JWD 41567 b |
|
|
1 | | revenue was appropriated for a project when the amount |
2 | | encumbered for the project is less than the amount |
3 | | appropriated.
|
4 | | (b) Whenever the Director authorizes the use of moneys from |
5 | | the Project Reserve Fund, the Director shall immediately report |
6 | | that action by written message to the General Assembly. |
7 | | Section 60. Reversion of appropriation and lapse of project |
8 | | authorization. |
9 | | (a) A State agency shall begin the planning of or the |
10 | | construction of an authorized capital improvement project |
11 | | during the fiscal year in which the funds are appropriated. If |
12 | | it does not, the Director may credit the appropriation to the |
13 | | Project Reserve Fund, unless otherwise required by law. If the |
14 | | Director does not credit the appropriation to the Project |
15 | | Reserve Fund, the appropriation shall revert to the principal |
16 | | fund from which it was appropriated. The Director may, for good |
17 | | cause, allow a State agency to take up to an additional 12 |
18 | | months to take the actions required by this subsection.
|
19 | | (b) Authorizations for capital improvement projects shall |
20 | | lapse if any of the following occur: |
21 | | (1) the appropriation for a capital improvement |
22 | | project reverts; |
23 | | (2) the construction of a project does not begin during |
24 | | the first 2 fiscal years in which funds are appropriated; |
25 | | or |
|
| | HB2959 | - 11 - | LRB098 10954 JWD 41567 b |
|
|
1 | | (3) the Director redirects funds appropriated for a |
2 | | capital improvement project, where authorized to do so by |
3 | | the General Assembly. |
4 | | The Director may, for good cause, allow a State agency to |
5 | | take up to an additional 12 months to begin construction of a |
6 | | project; however, if the Director approves an extension of time |
7 | | under this subsection and construction of the project has not |
8 | | begun by the end of the extension, the authorization for the |
9 | | project shall lapse.
|
10 | | Section 65. State university capital improvement projects |
11 | | from sources that are not General Fund sources; approval of new |
12 | | project or change in scope of existing project. Notwithstanding |
13 | | any other provision of this Act, the board of trustees of a |
14 | | State university may approve: |
15 | | (1) expenditures to plan a capital improvement project |
16 | | of that State university the planning for which is to be |
17 | | funded entirely with non-General Fund money; |
18 | | (2) expenditures for a capital improvement project of |
19 | | that State university that is to be funded and operated |
20 | | entirely with non-General Fund money; or |
21 | | (3) a change in the scope of any previously approved |
22 | | capital improvement project of that State university, |
23 | | provided that both the project and change in scope are |
24 | | funded entirely with non-General Fund money. |
25 | | The board of trustees of that State university shall report |