| | HB0576 Enrolled | | LRB098 03406 AMC 33421 b |
|
|
1 | | AN ACT concerning regulation.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | Section 5. The Public Utilities Act is amended by changing |
5 | | Section 9-201 as follows:
|
6 | | (220 ILCS 5/9-201) (from Ch. 111 2/3, par. 9-201)
|
7 | | Sec. 9-201.
(a) Unless the Commission otherwise orders, and |
8 | | except as
otherwise provided in this Section, no change shall |
9 | | be made by any
public utility in any rate or other charge or |
10 | | classification, or in any
rule, regulation, practice or |
11 | | contract relating to or affecting any rate
or other charge, |
12 | | classification or service, or in any privilege or
facility, |
13 | | except after 45 days' notice to the Commission and to the
|
14 | | public as herein provided. Such notice shall be given by filing |
15 | | with
the Commission and keeping open for public inspection new |
16 | | schedules or
supplements stating plainly the change or changes |
17 | | to be made in the
schedule or schedules then in force, and the |
18 | | time when the change or
changes will go into effect, and by |
19 | | publication in a newspaper of
general circulation or such other |
20 | | notice to persons affected by such
change as may be prescribed |
21 | | by rule of the Commission. The Commission,
for good cause |
22 | | shown, may allow changes without requiring the 45 days'
notice |
23 | | herein provided for, by an order specifying the changes so to |
|
| | HB0576 Enrolled | - 2 - | LRB098 03406 AMC 33421 b |
|
|
1 | | be
made and the time when they shall take effect and the manner |
2 | | in which
they shall be filed and published.
|
3 | | When any change is proposed in any rate or other charge, or
|
4 | | classification, or in any rule, regulation, practice, or |
5 | | contract
relating to or affecting any rate or other charge, |
6 | | classification or
service, or in any privilege or facility, |
7 | | such proposed change shall be
plainly indicated on the new |
8 | | schedule filed with the Commission, by some
character to be |
9 | | designated by the Commission, immediately preceding or
|
10 | | following the item.
|
11 | | When any public utility providing water or sewer service |
12 | | proposes any
change in any rate or other charge, or |
13 | | classification, or in any rule,
regulation, practice, or |
14 | | contract relating to or affecting any rate or
other charge, |
15 | | classification or service, or in any privilege or facility,
|
16 | | such utility shall, in addition to the other notice |
17 | | requirements of this
Act, provide notice of such change to all |
18 | | customers potentially affected by
including a notice and |
19 | | description of such change, and of Commission
procedures for |
20 | | intervention, in the first bill sent to each such customer
|
21 | | after the filing of the proposed change.
|
22 | | For water or sewer utilities with greater than 15,000 total |
23 | | customers, the following notice requirements are applicable, |
24 | | in addition to the other notice requirements of this Act: |
25 | | (1) As a separate bill insert, an initial notice in the |
26 | | first bill sent to all customers potentially affected by |
|
| | HB0576 Enrolled | - 3 - | LRB098 03406 AMC 33421 b |
|
|
1 | | the proposed change after the filing of the proposed change |
2 | | shall include: |
3 | | (A) the approximate date when the change or changes |
4 | | shall go into effect assuming the Commission utilizes |
5 | | the 11-month process as described in this Section; |
6 | | (B) a statement indicating that the estimated bill |
7 | | impact may vary based on multiple factors, including, |
8 | | but not limited to, meter size, usage volume, and the |
9 | | fire protection district; |
10 | | (C) the water or sewer utility's customer service |
11 | | number or other number as may be appropriate where an |
12 | | authorized agent of the water or sewer utility can |
13 | | explain how the proposed increase might impact an |
14 | | individual customer's bill; |
15 | | (D) if the proposed change involves a change from a |
16 | | flat to a volumetric rate, an explanation of volumetric |
17 | | rate; |
18 | | (E) a reference to the water or sewer utility's |
19 | | website where customers can find tips on water |
20 | | conservation; and |
21 | | (F) for customers receiving both water and sewer |
22 | | service from a utility and if the customer has an |
23 | | option to install a separate meter for irrigation to |
24 | | mitigate sewer charges, an explanation of the water and |
25 | | sewer utility's and the customer's responsibilities |
26 | | for installation of a separate meter if such a change |
|
| | HB0576 Enrolled | - 4 - | LRB098 03406 AMC 33421 b |
|
|
1 | | is approved. |
2 | | (2) A second notice to all customers shall be included |
3 | | on the first bill after the Commission suspends the tariffs |
4 | | initiating the rate case. |
5 | | (3) Final notice of such change shall be sent to all |
6 | | customers potentially affected by the proposed change by |
7 | | including information required under this paragraph (3) |
8 | | with the first bill after the effective date of the rates |
9 | | approved by the Final Order of the Commission in a rate |
10 | | case. The notice shall include the following: |
11 | | (A) the date when the change or changes went into |
12 | | effect; |
13 | | (B) the water or sewer utility's customer service |
14 | | number or other number as may be appropriate where an |
15 | | authorized agent of the water or sewer utility can |
16 | | explain how the proposed increase might impact an |
17 | | individual customer's bill; |
18 | | (C) an explanation that usage shall now be charged |
19 | | at a volumetric rate rather than a flat rate, if |
20 | | applicable; |
21 | | (D) a reference to the water or sewer utility's |
22 | | website where the customer can find tips on water |
23 | | conservation; and |
24 | | (E) for customers receiving both water and sewer |
25 | | service from a utility and if the customer has an |
26 | | option to install a separate meter for irrigation to |
|
| | HB0576 Enrolled | - 5 - | LRB098 03406 AMC 33421 b |
|
|
1 | | mitigate sewer charges, an explanation of the water and |
2 | | sewer utility's and the customer's responsibilities |
3 | | for installation of a separate meter if such a change |
4 | | is approved. |
5 | | (b) Whenever there shall be filed with the Commission any |
6 | | schedule
stating an individual or joint rate or other charge, |
7 | | classification,
contract, practice, rule or regulation, the |
8 | | Commission shall have power,
and it is hereby given authority, |
9 | | either upon complaint or upon its own
initiative without |
10 | | complaint, at once, and if it so orders, without
answer or |
11 | | other formal pleadings by the interested public utility or
|
12 | | utilities, but upon reasonable notice, to enter upon a hearing
|
13 | | concerning the propriety of such rate or other charge, |
14 | | classification,
contract, practice, rule or regulation, and |
15 | | pending the hearing and
decision thereon, such rate or other |
16 | | charge, classification, contract,
practice, rule or regulation |
17 | | shall not go into effect. The period of
suspension of such rate |
18 | | or other charge, classification, contract,
practice, rule or |
19 | | regulation shall not extend more than 105 days beyond
the time |
20 | | when such rate or other charge, classification, contract,
|
21 | | practice, rule or regulation would otherwise go into effect |
22 | | unless the
Commission, in its discretion, extends the period of |
23 | | suspension for a
further period not exceeding 6 months.
|
24 | | All rates or other charges, classifications, contracts, |
25 | | practices, rules or
regulations not so suspended shall, on the |
26 | | expiration of 45 days from
the time of filing the same with the |
|
| | HB0576 Enrolled | - 6 - | LRB098 03406 AMC 33421 b |
|
|
1 | | Commission, or of such lesser time
as the Commission may grant, |
2 | | go into effect and be the established and
effective rates or |
3 | | other charges, classifications, contracts, practices,
rules |
4 | | and regulations, subject to the power of the Commission, after |
5 | | a
hearing had on its own motion or upon complaint, as herein |
6 | | provided, to
alter or modify the same.
|
7 | | Within 30 days after such changes have been
authorized by |
8 | | the Commission, copies of the new or revised schedules
shall be |
9 | | posted or filed in accordance with the terms of Section 9-103 |
10 | | of
this Act, in such a manner that all changes shall be plainly |
11 | | indicated. The Commission shall incorporate into the period of |
12 | | suspension a review period of 4 business days during which the |
13 | | Commission may review and determine whether the new or revised |
14 | | schedules comply with the Commission's decision approving a |
15 | | change to the public utility's rates. Such review period shall |
16 | | not extend the suspension period by more than 2 days. Absent |
17 | | notification to the contrary within the 4 business day period, |
18 | | the new or revised schedules shall be deemed approved.
|
19 | | (c) If the Commission enters upon a hearing concerning the |
20 | | propriety of
any proposed rate or other charge, classification, |
21 | | contract, practice, rule
or regulation, the Commission shall |
22 | | establish the rates or other charges,
classifications, |
23 | | contracts, practices, rules or regulations proposed, in
whole |
24 | | or in part, or others in lieu thereof, which it shall find to |
25 | | be just
and reasonable. In such hearing, the burden of proof to |
26 | | establish the justness
and reasonableness of the proposed rates |
|
| | HB0576 Enrolled | - 7 - | LRB098 03406 AMC 33421 b |
|
|
1 | | or other charges, classifications,
contracts, practices, rules |
2 | | or regulations, in whole and in part, shall be
upon the |
3 | | utility. The utility, the staff of the Commission, the Attorney |
4 | | General, or any party to a proceeding initiated under this |
5 | | Section who has been granted intervenor status and submitted a |
6 | | post-hearing brief must be given the opportunity to present |
7 | | oral argument, if requested no later than the date for filing |
8 | | exceptions, on the propriety of any proposed rate or other |
9 | | charge, classification, contract, practice, rule, or |
10 | | regulation. No rate or other charge, classification, contract,
|
11 | | practice, rule or regulation shall be found just and reasonable |
12 | | unless it
is consistent with Sections of this Article. |
13 | | (d) Except where compliance with Section 8-401 of this Act |
14 | | is of urgent and immediate concern, no representative of a |
15 | | public utility may discuss with a commissioner, commissioner's |
16 | | assistant, or hearing examiner in a non-public setting a |
17 | | planned filing for a general rate increase. If a public utility |
18 | | makes a filing under this Section, then no substantive |
19 | | communication by any such person with a commissioner, |
20 | | commissioner's assistant or hearing examiner concerning the |
21 | | filing is permitted until a notice of hearing has been issued. |
22 | | After the notice of hearing has been issued, the only |
23 | | communications by any such person with a commissioner, |
24 | | commissioner's assistant, or hearing examiner concerning the |
25 | | filing permitted are communications permitted under Section |
26 | | 10-103 of this Act. If any such communication does occur, then |
|
| | HB0576 Enrolled | - 8 - | LRB098 03406 AMC 33421 b |
|
|
1 | | within 5 days of the docket being initiated all details |
2 | | relating to the communication shall be placed on the public |
3 | | record of the proceeding. The record shall include any |
4 | | materials, whether written, recorded, filmed, or graphic in |
5 | | nature, produced or reproduced on any media, used in connection |
6 | | with the communication. The record shall reflect the names of |
7 | | all persons who transmitted, received, or were otherwise |
8 | | involved in the communication, the duration of the |
9 | | communication, and whether the communication occurred in |
10 | | person or by other means. In the case of an oral communication, |
11 | | the record shall also reflect the location or locations of all |
12 | | persons involved in the communication and, if the communication |
13 | | occurred by telephone, the telephone numbers for the callers |
14 | | and recipients of the communication. A commissioner, |
15 | | commissioner's assistant, or hearing examiner who is involved |
16 | | in any such communication shall be recused from the affected |
17 | | proceeding. The Commission, or any commissioner or hearing |
18 | | examiner presiding over the proceeding shall, in the event of a |
19 | | violation of this Section, take action necessary to ensure that |
20 | | such violation does not prejudice any party or adversely affect |
21 | | the fairness of the proceedings including dismissing the |
22 | | affected proceeding. Nothing in this subsection (d) is intended |
23 | | to preclude otherwise allowable updates on issues that may be |
24 | | indirectly related to a general rate case filing because cost |
25 | | recovery for the underlying activity may be requested. Such |
26 | | updates may include, without limitation, issues related to |
|
| | HB0576 Enrolled | - 9 - | LRB098 03406 AMC 33421 b |
|
|
1 | | outages and restoration, credit ratings, security issuances, |
2 | | reliability, Federal Energy Regulatory Commission matters, |
3 | | Federal Communications Commission matters, regional |
4 | | reliability organizations, consumer education, or labor |
5 | | matters, provided that such updates may not include cost |
6 | | recovery in a planned rate case.
|
7 | | (Source: P.A. 96-33, eff. 7-10-09.)
|