|
| | SB3282 Engrossed | | LRB097 17986 JDS 63209 b |
|
|
1 | | AN ACT concerning safety.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | Section 5. The Environmental Protection Act is amended by |
5 | | changing Section 39.14 as follows: |
6 | | (415 ILCS 5/39.14) |
7 | | Sec. 39.14. Expedited review of permits. |
8 | | (a) It is the intent of this Section to promote an |
9 | | expedited permit review process for any permit required under |
10 | | this Act. |
11 | | (b) Any applicant for a permit under this Act may request |
12 | | in writing from the Agency an expedited review of the |
13 | | application for a permit. Within a reasonable time, the Agency |
14 | | shall respond in writing, indicating whether the Agency will |
15 | | perform an expedited review. |
16 | | (c) In addition to any other fees required by this Act or |
17 | | Board regulations, an applicant requesting expedited review |
18 | | under this Section shall pay to the Agency an expedited permit |
19 | | fee. The amount of the expedited permit fee shall be 4 times |
20 | | the standard permit fee required for the requested permit under |
21 | | this Act or Board regulations; provided that the expedited |
22 | | permit fee shall not exceed $100,000. For recurring permit |
23 | | fees, such as annual fees, operating fees, or discharge fees, |
|
| | SB3282 Engrossed | - 2 - | LRB097 17986 JDS 63209 b |
|
|
1 | | the expedited permit fee shall be 4 times the amount of the |
2 | | recurring fee on a one-time basis for each expedited permitting |
3 | | action. If an owner or operator is not required to pay a |
4 | | standard permit fee for the requested permit, the amount of the |
5 | | expedited permit fee shall be mutually agreed upon by the |
6 | | Agency and the applicant. Prior to any Agency review, the |
7 | | applicant shall make full payment of the expedited permit fee |
8 | | to the Agency. All amounts paid to the Agency pursuant to this |
9 | | Section shall be deposited into the Environmental Protection |
10 | | Permit and Inspection Fund. The applicant shall also pay all |
11 | | standard permit fees in accordance with the applicable fee |
12 | | provisions of this Act or Board regulations. |
13 | | (d) The Agency's expedited review under this Section shall |
14 | | include the usual and customary review by the Agency as |
15 | | necessary for processing any similar application. |
16 | | (e) "Expedited review" means, for the purposes of this |
17 | | Section, the Agency taking action on a permit application |
18 | | within a period of time mutually agreed upon by the Agency and |
19 | | the applicant; provided, however, that the agreed-upon period |
20 | | of time shall be tolled during any times the Agency is waiting |
21 | | for the applicant or another party to provide information |
22 | | necessary for the Agency to complete its expedited review. |
23 | | (f) If the Agency fails to complete an expedited review |
24 | | within the period of time agreed upon by the Agency and the |
25 | | applicant, taking into account the tolling provided under |
26 | | subsection (e) of this Section, the applicant shall be entitled |
|
| | SB3282 Engrossed | - 3 - | LRB097 17986 JDS 63209 b |
|
|
1 | | to a refund of the expedited permit fee paid under this |
2 | | Section, on a prorated basis, as mutually agreed upon by the |
3 | | Agency and the applicant. |
4 | | (g) This Section shall not apply to applications related to |
5 | | emergency events necessitating immediate action by the Agency |
6 | | on permit applications. |
7 | | (h) The Agency may adopt rules for the implementation of |
8 | | this Section.
|
9 | | (i) Upon the Agency taking action on a permit application |
10 | | pursuant to this Section, the Agency shall provide the |
11 | | applicant with an invoice setting forth the total fee paid |
12 | | pursuant to this Section, as well as the number of overtime |
13 | | hours that were expended by Agency staff in the expedited |
14 | | review. |
15 | | (Source: P.A. 97-95, eff. 7-12-11.)
|
16 | | Section 99. Effective date. This Act takes effect upon |
17 | | becoming law.
|