Sen. James F. Clayborne, Jr.

Filed: 2/22/2012

 

 


 

 


 
09700SB3173sam001LRB097 19727 CEL 65893 a

1
AMENDMENT TO SENATE BILL 3173

2    AMENDMENT NO. ______. Amend Senate Bill 3173 by replacing
3everything after the enacting clause with the following:
 
4    "Section 5. The Illinois Power Agency Act is amended by
5changing Sections 1-10 and 1-20 and by adding Section 1-76 as
6follows:
 
7    (20 ILCS 3855/1-10)
8    Sec. 1-10. Definitions.
9    "Agency" means the Illinois Power Agency.
10    "Agency loan agreement" means any agreement pursuant to
11which the Illinois Finance Authority agrees to loan the
12proceeds of revenue bonds issued with respect to a project to
13the Agency upon terms providing for loan repayment installments
14at least sufficient to pay when due all principal of, interest
15and premium, if any, on those revenue bonds, and providing for
16maintenance, insurance, and other matters in respect of the

 

 

09700SB3173sam001- 2 -LRB097 19727 CEL 65893 a

1project.
2    "Authority" means the Illinois Finance Authority.
3    "Clean coal facility" means an electric generating
4facility that uses primarily coal as a feedstock and that
5captures and sequesters carbon dioxide emissions at the
6following levels: at least 50% of the total carbon dioxide
7emissions that the facility would otherwise emit if, at the
8time construction commences, the facility is scheduled to
9commence operation before 2016, at least 70% of the total
10carbon dioxide emissions that the facility would otherwise emit
11if, at the time construction commences, the facility is
12scheduled to commence operation during 2016 or 2017, and at
13least 90% of the total carbon dioxide emissions that the
14facility would otherwise emit if, at the time construction
15commences, the facility is scheduled to commence operation
16after 2017. The power block of the clean coal facility shall
17not exceed allowable emission rates for sulfur dioxide,
18nitrogen oxides, carbon monoxide, particulates and mercury for
19a natural gas-fired combined-cycle facility the same size as
20and in the same location as the clean coal facility at the time
21the clean coal facility obtains an approved air permit. All
22coal used by a clean coal facility shall have high volatile
23bituminous rank and greater than 1.7 pounds of sulfur per
24million btu content, unless the clean coal facility does not
25use gasification technology and was operating as a conventional
26coal-fired electric generating facility on June 1, 2009 (the

 

 

09700SB3173sam001- 3 -LRB097 19727 CEL 65893 a

1effective date of Public Act 95-1027).
2    "Clean coal SNG brownfield facility" means a facility that
3(1) has commenced construction by July 1, 2015 on an urban
4brownfield site in a municipality with at least 1,000,000
5residents; (2) uses a gasification process to produce
6substitute natural gas; (3) uses coal as at least 50% of the
7total feedstock over the term of any sourcing agreement with a
8utility and the remainder of the feedstock may be either
9petroleum coke or coal, with all such coal having a high
10bituminous rank and greater than 1.7 pounds of sulfur per
11million Btu content unless the facility reasonably determines
12that it is necessary to use additional petroleum coke to
13deliver additional consumer savings, in which case the facility
14shall use coal for at least 35% of the total feedstock over the
15term of any sourcing agreement; and (4) captures and sequesters
16at least 85% of the total carbon dioxide emissions that the
17facility would otherwise emit.
18    "Clean coal SNG facility" means a facility that uses a
19gasification process to produce substitute natural gas, that
20sequesters at least 90% of the total carbon dioxide emissions
21that the facility would otherwise emit, that uses at least 90%
22coal as a feedstock, with all such coal having a high
23bituminous rank and greater than 1.7 pounds of sulfur per
24million btu content, and that has a valid and effective permit
25to construct emission sources and air pollution control
26equipment and approval with respect to the federal regulations

 

 

09700SB3173sam001- 4 -LRB097 19727 CEL 65893 a

1for Prevention of Significant Deterioration of Air Quality
2(PSD) for the plant pursuant to the federal Clean Air Act;
3provided, however, a clean coal SNG brownfield facility shall
4not be a clean coal SNG facility.
5    "Commission" means the Illinois Commerce Commission.
6    "Costs incurred in connection with the development and
7construction of a facility" means:
8        (1) the cost of acquisition of all real property,
9    fixtures, and improvements in connection therewith and
10    equipment, personal property, and other property, rights,
11    and easements acquired that are deemed necessary for the
12    operation and maintenance of the facility;
13        (2) financing costs with respect to bonds, notes, and
14    other evidences of indebtedness of the Agency;
15        (3) all origination, commitment, utilization,
16    facility, placement, underwriting, syndication, credit
17    enhancement, and rating agency fees;
18        (4) engineering, design, procurement, consulting,
19    legal, accounting, title insurance, survey, appraisal,
20    escrow, trustee, collateral agency, interest rate hedging,
21    interest rate swap, capitalized interest, contingency, as
22    required by lenders, and other financing costs, and other
23    expenses for professional services; and
24        (5) the costs of plans, specifications, site study and
25    investigation, installation, surveys, other Agency costs
26    and estimates of costs, and other expenses necessary or

 

 

09700SB3173sam001- 5 -LRB097 19727 CEL 65893 a

1    incidental to determining the feasibility of any project,
2    together with such other expenses as may be necessary or
3    incidental to the financing, insuring, acquisition, and
4    construction of a specific project and starting up,
5    commissioning, and placing that project in operation.
6    "Department" means the Department of Commerce and Economic
7Opportunity.
8    "Director" means the Director of the Illinois Power Agency.
9    "Demand-response" means measures that decrease peak
10electricity demand or shift demand from peak to off-peak
11periods.
12    "Distributed renewable energy generation device" means a
13device that is:
14        (1) powered by wind, solar thermal energy,
15    photovoltaic cells and panels, biodiesel, crops and
16    untreated and unadulterated organic waste biomass, tree
17    waste, and hydropower that does not involve new
18    construction or significant expansion of hydropower dams;
19        (2) interconnected at the distribution system level of
20    either an electric utility as defined in this Section, an
21    alternative retail electric supplier as defined in Section
22    16-102 of the Public Utilities Act, a municipal utility as
23    defined in Section 3-105 of the Public Utilities Act, or a
24    rural electric cooperative as defined in Section 3-119 of
25    the Public Utilities Act;
26        (3) located on the customer side of the customer's

 

 

09700SB3173sam001- 6 -LRB097 19727 CEL 65893 a

1    electric meter and is primarily used to offset that
2    customer's electricity load; and
3        (4) limited in nameplate capacity to no more than 2,000
4    kilowatts.
5    "Energy efficiency" means measures that reduce the amount
6of electricity or natural gas required to achieve a given end
7use.
8    "Electric utility" has the same definition as found in
9Section 16-102 of the Public Utilities Act.
10    "Facility" means an electric generating unit or a
11co-generating unit that produces electricity along with
12related equipment necessary to connect the facility to an
13electric transmission or distribution system.
14    "Governmental aggregator" means one or more units of local
15government that individually or collectively procure
16electricity to serve residential retail electrical loads
17located within its or their jurisdiction.
18    "Local government" means a unit of local government as
19defined in Article VII of Section 1 of Article VII of the
20Illinois Constitution.
21    "Municipal brownfield site" means a site (1) that is owned
22by a municipality and conveyed or leased to a person proposing
23to operate a qualified solar remediation facility on such site
24and (2) that is the subject of a Superfund alternative approach
25agreement between the United States Environmental Protection
26Agency and potentially responsible parties in accordance with

 

 

09700SB3173sam001- 7 -LRB097 19727 CEL 65893 a

1the federal Comprehensive Environmental Response,
2Compensation, and Liability Act of 1980, as amended, requiring
3remedial clean up of such site.
4    "Municipality" means a city, village, or incorporated
5town.
6    "Person" means any natural person, firm, partnership,
7corporation, either domestic or foreign, company, association,
8limited liability company, joint stock company, or association
9and includes any trustee, receiver, assignee, or personal
10representative thereof.
11    "Project" means the planning, bidding, and construction of
12a facility.
13    "Public utility" has the same definition as found in
14Section 3-105 of the Public Utilities Act.
15    "Qualified solar power purchase agreement" means an
16agreement between the operator of a qualified solar remediation
17facility and an electric utility that has terms and conditions
18meeting the requirements of subsection (c) of Section 1-76 of
19this Act.
20    "Qualified solar remediation facility" means an electric
21generating facility:
22        (1) that uses primarily photovoltaic cells and panels
23    to produce energy;
24        (2) that is located at a municipal brownfield site;
25        (3) that has a nameplate capacity of no more than 20
26    megawatts; and

 

 

09700SB3173sam001- 8 -LRB097 19727 CEL 65893 a

1        (4) where construction of the electric generating
2    facility structure has not commenced on or before the date
3    the application to approve a qualified solar power purchase
4    agreement for such facility is submitted to the Agency in
5    accordance with Section 1-76 of this Act.
6    "Real property" means any interest in land together with
7all structures, fixtures, and improvements thereon, including
8lands under water and riparian rights, any easements,
9covenants, licenses, leases, rights-of-way, uses, and other
10interests, together with any liens, judgments, mortgages, or
11other claims or security interests related to real property.
12    "Renewable energy credit" means a tradable credit that
13represents the environmental attributes of a certain amount of
14energy produced from a renewable energy resource.
15    "Renewable energy resources" includes energy and its
16associated renewable energy credit or renewable energy credits
17from wind, solar thermal energy, photovoltaic cells and panels,
18biodiesel, anaerobic digestion, crops and untreated and
19unadulterated organic waste biomass, tree waste, hydropower
20that does not involve new construction or significant expansion
21of hydropower dams, and other alternative sources of
22environmentally preferable energy. For purposes of this Act,
23landfill gas produced in the State is considered a renewable
24energy resource. "Renewable energy resources" does not include
25the incineration or burning of tires, garbage, general
26household, institutional, and commercial waste, industrial

 

 

09700SB3173sam001- 9 -LRB097 19727 CEL 65893 a

1lunchroom or office waste, landscape waste other than tree
2waste, railroad crossties, utility poles, or construction or
3demolition debris, other than untreated and unadulterated
4waste wood.
5    "Revenue bond" means any bond, note, or other evidence of
6indebtedness issued by the Authority, the principal and
7interest of which is payable solely from revenues or income
8derived from any project or activity of the Agency.
9    "Sequester" means permanent storage of carbon dioxide by
10injecting it into a saline aquifer, a depleted gas reservoir,
11or an oil reservoir, directly or through an enhanced oil
12recovery process that may involve intermediate storage,
13regardless of whether these activities are conducted by a clean
14coal facility, a clean coal SNG facility, a clean coal SNG
15brownfield facility, or a party with which a clean coal
16facility, or clean coal SNG facility, or clean coal SNG
17brownfield facility has contracted for such purposes.
18    "Sourcing agreement" means (i) in the case of an electric
19utility, an agreement between the owner of a clean coal
20facility and such electric utility, which agreement shall have
21terms and conditions meeting the requirements of paragraph (3)
22of subsection (d) of Section 1-75, (ii) in the case of an
23alternative retail electric supplier, an agreement between the
24owner of a clean coal facility and such alternative retail
25electric supplier, which agreement shall have terms and
26conditions meeting the requirements of Section 16-115(d)(5) of

 

 

09700SB3173sam001- 10 -LRB097 19727 CEL 65893 a

1the Public Utilities Act, and (iii) in case of a gas utility,
2an agreement between the owner of a clean coal SNG brownfield
3facility and the gas utility, which agreement shall have the
4terms and conditions meeting the requirements of subsection
5(h-1) of Section 9-220 of the Public Utilities Act.
6    "Substitute natural gas" or "SNG" means a gas manufactured
7by gasification of hydrocarbon feedstock, which is
8substantially interchangeable in use and distribution with
9conventional natural gas.
10    "Total resource cost test" or "TRC test" means a standard
11that is met if, for an investment in energy efficiency or
12demand-response measures, the benefit-cost ratio is greater
13than one. The benefit-cost ratio is the ratio of the net
14present value of the total benefits of the program to the net
15present value of the total costs as calculated over the
16lifetime of the measures. A total resource cost test compares
17the sum of avoided electric utility costs, representing the
18benefits that accrue to the system and the participant in the
19delivery of those efficiency measures, as well as other
20quantifiable societal benefits, including avoided natural gas
21utility costs, to the sum of all incremental costs of end-use
22measures that are implemented due to the program (including
23both utility and participant contributions), plus costs to
24administer, deliver, and evaluate each demand-side program, to
25quantify the net savings obtained by substituting the
26demand-side program for supply resources. In calculating

 

 

09700SB3173sam001- 11 -LRB097 19727 CEL 65893 a

1avoided costs of power and energy that an electric utility
2would otherwise have had to acquire, reasonable estimates shall
3be included of financial costs likely to be imposed by future
4regulations and legislation on emissions of greenhouse gases.
5(Source: P.A. 96-33, eff. 7-10-09; 96-159, eff. 8-10-09;
696-784, eff. 8-28-09; 96-1000, eff. 7-2-10; 97-96, eff.
77-13-11; 97-239, eff. 8-2-11; 97-491, eff. 8-22-11; 97-616,
8eff. 10-26-11; revised 11-10-11.)
 
9    (20 ILCS 3855/1-20)
10    Sec. 1-20. General powers of the Agency.
11    (a) The Agency is authorized to do each of the following:
12        (1) Develop electricity procurement plans to ensure
13    adequate, reliable, affordable, efficient, and
14    environmentally sustainable electric service at the lowest
15    total cost over time, taking into account any benefits of
16    price stability, for electric utilities that on December
17    31, 2005 provided electric service to at least 100,000
18    customers in Illinois and for small multi-jurisdictional
19    electric utilities that (A) on December 31, 2005 served
20    less than 100,000 customers in Illinois and (B) request a
21    procurement plan for their Illinois jurisdictional load.
22    The procurement plans shall be updated on an annual basis
23    and shall include electricity generated from renewable
24    resources sufficient to achieve the standards specified in
25    this Act.

 

 

09700SB3173sam001- 12 -LRB097 19727 CEL 65893 a

1        (2) Conduct competitive procurement processes to
2    procure the supply resources identified in the procurement
3    plan, pursuant to Section 16-111.5 of the Public Utilities
4    Act.
5        (3) Develop electric generation and co-generation
6    facilities that use indigenous coal or renewable
7    resources, or both, financed with bonds issued by the
8    Illinois Finance Authority.
9        (4) Supply electricity from the Agency's facilities at
10    cost to one or more of the following: municipal electric
11    systems, governmental aggregators, or rural electric
12    cooperatives in Illinois.
13    (b) Except as otherwise limited by this Act, the Agency has
14all of the powers necessary or convenient to carry out the
15purposes and provisions of this Act, including without
16limitation, each of the following:
17        (1) To have a corporate seal, and to alter that seal at
18    pleasure, and to use it by causing it or a facsimile to be
19    affixed or impressed or reproduced in any other manner.
20        (2) To use the services of the Illinois Finance
21    Authority necessary to carry out the Agency's purposes.
22        (3) To negotiate and enter into loan agreements and
23    other agreements with the Illinois Finance Authority.
24        (4) To obtain and employ personnel and hire consultants
25    that are necessary to fulfill the Agency's purposes, and to
26    make expenditures for that purpose within the

 

 

09700SB3173sam001- 13 -LRB097 19727 CEL 65893 a

1    appropriations for that purpose.
2        (5) To purchase, receive, take by grant, gift, devise,
3    bequest, or otherwise, lease, or otherwise acquire, own,
4    hold, improve, employ, use, and otherwise deal in and with,
5    real or personal property whether tangible or intangible,
6    or any interest therein, within the State.
7        (6) To acquire real or personal property, whether
8    tangible or intangible, including without limitation
9    property rights, interests in property, franchises,
10    obligations, contracts, and debt and equity securities,
11    and to do so by the exercise of the power of eminent domain
12    in accordance with Section 1-21; except that any real
13    property acquired by the exercise of the power of eminent
14    domain must be located within the State.
15        (7) To sell, convey, lease, exchange, transfer,
16    abandon, or otherwise dispose of, or mortgage, pledge, or
17    create a security interest in, any of its assets,
18    properties, or any interest therein, wherever situated.
19        (8) To purchase, take, receive, subscribe for, or
20    otherwise acquire, hold, make a tender offer for, vote,
21    employ, sell, lend, lease, exchange, transfer, or
22    otherwise dispose of, mortgage, pledge, or grant a security
23    interest in, use, and otherwise deal in and with, bonds and
24    other obligations, shares, or other securities (or
25    interests therein) issued by others, whether engaged in a
26    similar or different business or activity.

 

 

09700SB3173sam001- 14 -LRB097 19727 CEL 65893 a

1        (9) To make and execute agreements, contracts, and
2    other instruments necessary or convenient in the exercise
3    of the powers and functions of the Agency under this Act,
4    including contracts with any person, including personal
5    service contracts, or with any local government, State
6    agency, or other entity; and all State agencies and all
7    local governments are authorized to enter into and do all
8    things necessary to perform any such agreement, contract,
9    or other instrument with the Agency. No such agreement,
10    contract, or other instrument shall exceed 40 years.
11        (10) To lend money, invest and reinvest its funds in
12    accordance with the Public Funds Investment Act, and take
13    and hold real and personal property as security for the
14    payment of funds loaned or invested.
15        (11) To borrow money at such rate or rates of interest
16    as the Agency may determine, issue its notes, bonds, or
17    other obligations to evidence that indebtedness, and
18    secure any of its obligations by mortgage or pledge of its
19    real or personal property, machinery, equipment,
20    structures, fixtures, inventories, revenues, grants, and
21    other funds as provided or any interest therein, wherever
22    situated.
23        (12) To enter into agreements with the Illinois Finance
24    Authority to issue bonds whether or not the income
25    therefrom is exempt from federal taxation.
26        (13) To procure insurance against any loss in

 

 

09700SB3173sam001- 15 -LRB097 19727 CEL 65893 a

1    connection with its properties or operations in such amount
2    or amounts and from such insurers, including the federal
3    government, as it may deem necessary or desirable, and to
4    pay any premiums therefor.
5        (14) To negotiate and enter into agreements with
6    trustees or receivers appointed by United States
7    bankruptcy courts or federal district courts or in other
8    proceedings involving adjustment of debts and authorize
9    proceedings involving adjustment of debts and authorize
10    legal counsel for the Agency to appear in any such
11    proceedings.
12        (15) To file a petition under Chapter 9 of Title 11 of
13    the United States Bankruptcy Code or take other similar
14    action for the adjustment of its debts.
15        (16) To enter into management agreements for the
16    operation of any of the property or facilities owned by the
17    Agency.
18        (17) To enter into an agreement to transfer and to
19    transfer any land, facilities, fixtures, or equipment of
20    the Agency to one or more municipal electric systems,
21    governmental aggregators, or rural electric agencies or
22    cooperatives, for such consideration and upon such terms as
23    the Agency may determine to be in the best interest of the
24    citizens of Illinois.
25        (18) To enter upon any lands and within any building
26    whenever in its judgment it may be necessary for the

 

 

09700SB3173sam001- 16 -LRB097 19727 CEL 65893 a

1    purpose of making surveys and examinations to accomplish
2    any purpose authorized by this Act.
3        (19) To maintain an office or offices at such place or
4    places in the State as it may determine.
5        (20) To request information, and to make any inquiry,
6    investigation, survey, or study that the Agency may deem
7    necessary to enable it effectively to carry out the
8    provisions of this Act.
9        (21) To accept and expend appropriations.
10        (22) To engage in any activity or operation that is
11    incidental to and in furtherance of efficient operation to
12    accomplish the Agency's purposes, including hiring
13    employees that the Director deems essential for the
14    operations of the Agency.
15        (23) To adopt, revise, amend, and repeal rules with
16    respect to its operations, properties, and facilities as
17    may be necessary or convenient to carry out the purposes of
18    this Act, subject to the provisions of the Illinois
19    Administrative Procedure Act and Sections 1-22 and 1-35 of
20    this Act.
21        (24) To establish and collect charges and fees as
22    described in this Act.
23        (25) To conduct competitive gasification feedstock
24    procurement processes to procure the feedstocks for the
25    clean coal SNG brownfield facility in accordance with the
26    requirements of Section 1-78 of this Act.

 

 

09700SB3173sam001- 17 -LRB097 19727 CEL 65893 a

1        (26) To review, revise, and approve sourcing
2    agreements and mediate and resolve disputes between gas
3    utilities and the clean coal SNG brownfield facility
4    pursuant to subsection (h-1) of Section 9-220 of the Public
5    Utilities Act.
6        (27) To review and approve qualified solar power
7    purchase agreements pursuant to Section 1-76 of this Act.
8(Source: P.A. 96-784, eff. 8-28-09; 96-1000, eff. 7-2-10;
997-96, eff. 7-13-11; 97-325, eff. 8-12-11; 97-618, eff.
1010-26-11; revised 11-10-11.)
 
11    (20 ILCS 3855/1-76 new)
12    Sec. 1-76. Qualified solar power purchase agreements.
13    (a) The General Assembly finds that encouraging the
14development and use of solar energy is in the public interest
15and consistent with the renewable energy goals of the State.
16The General Assembly further finds that repurposing and
17redeveloping brownfield sites owned by municipalities,
18including in particular those sites that are in need of
19remedial clean up due to prior contamination, to host solar
20energy producing facilities is in the economic and
21environmental interests of the State, those municipalities,
22and the public.
23    (b) The Agency shall accept applications from proposed
24operators of proposed qualified solar remediation facilities
25to approve qualified solar power purchase agreements for a

 

 

09700SB3173sam001- 18 -LRB097 19727 CEL 65893 a

1period of one year after the effective date of this amendatory
2Act of the 97th General Assembly. Each application shall
3include a proposed qualified solar power purchase agreement
4between the applicant and an electric utility.
5    (c) Each qualified solar power purchase agreement shall:
6        (1) include provisions governing the prices paid for
7    electricity generated by the qualified solar remediation
8    facility and for renewable energy credits purchased in
9    connection with the electricity, which prices in aggregate
10    (for both electricity and renewable energy credits) shall
11    not:
12            (A) exceed 23 cents per kilowatt hour in the first
13        year of the sale thereof pursuant to such qualified
14        solar power purchase agreement; and
15            (B) increase during the term of the qualified solar
16        power purchase agreement by more than 1.5% per year;
17        (2) specify a term of no more than 25 years, commencing
18    on the commercial operation date of the facility;
19        (3) require the facility to be constructed on the
20    specified municipal brownfield site and to achieve the
21    commercial operation date within 5 years after the approval
22    of the qualified solar power purchase agreement by the
23    Agency; and
24        (4) have been executed by the applicant and the
25    electric utility, but provide that the effectiveness of
26    such agreement is contingent upon approval by the Agency

 

 

09700SB3173sam001- 19 -LRB097 19727 CEL 65893 a

1    pursuant to this Section.
2    (d) The Agency shall promptly review an application
3submitted pursuant to this Section. The Agency shall approve a
4qualified solar power purchase agreement within 90 days after
5the Agency has received an application to approve the
6agreement, unless the Agency finds that the agreement does not
7conform to the requirements of subsection (c) of this Section.
8    (e) The Agency may assess a fee to the applicant to recover
9the costs incurred in reviewing the application pursuant to
10this Section.
11    (f) Costs incurred by an electric utility pursuant to a
12qualified solar power purchase agreement approved by the Agency
13pursuant to this Section, including costs for renewable energy
14credits purchased in connection with electricity generated by
15that qualified solar remediation facility, shall be deemed
16prudently incurred and reasonable in amount, and the electric
17utility shall be entitled to full cost recovery pursuant to the
18tariffs filed with the Commission.
19    (g) Any renewable energy credits purchased by an electric
20utility pursuant to a qualified solar power purchase agreement
21approved by the Agency pursuant to this Section shall count
22towards the required percentages for solar photovoltaic energy
23for the purposes of subsection (c) of Section 1-75 of this Act.
 
24    Section 99. Effective date. This Act takes effect upon
25becoming law.".