6 | | (770 ILCS 60/6) (from Ch. 82, par. 6)
|
7 | | Sec. 6.
In no event shall it be necessary to fix or |
8 | | stipulate in any
contract a time for the completion or a time |
9 | | for payment in order to obtain
a lien under this act, provided, |
10 | | that the work is done or material
furnished within three years |
11 | | from the commencement of said work or the
commencement of |
12 | | furnishing said material , but if the work is not done within 3 |
13 | | years from the commencement of the work or the material is not |
14 | | furnished within 3 years from the commencement of the |
15 | | furnishing of the material, then a lien may be obtained under |
16 | | this Act within one year after the work is done or after the |
17 | | material is completely furnished, whichever is later .
|