|
Rep. John E. Bradley
Filed: 5/23/2012
| | 09700SB0678ham002 | | LRB097 04938 CEL 69975 a |
|
|
1 | | AMENDMENT TO SENATE BILL 678
|
2 | | AMENDMENT NO. ______. Amend Senate Bill 678 as follows: |
3 | | on page 4, immediately below line 21, by inserting the |
4 | | following: |
5 | | " "Coal gasification unit" means equipment that is designed |
6 | | to process coal and convert the energy content of coal into |
7 | | SNG. "; and |
8 | | on page 8, by replacing lines 3 through 13 with " facility using |
9 | | gasification technology or an SNG-ready generating facility |
10 | | that: (1) has a nameplate capacity of at least 500 MW; (2) |
11 | | irrevocably commits in its proposed sourcing agreement to use |
12 | | coal for at least 50% of the total feedstock over the term of a |
13 | | sourcing agreement, with all coal having high volatile |
14 | | bituminous rank and greater than 1.7 pounds of sulfur per |
15 | | million btu content, but this clause (2) shall not apply if the |
16 | | facility is an SNG-ready generating facility; (3) is designed |
|
| | 09700SB0678ham002 | - 2 - | LRB097 04938 CEL 69975 a |
|
|
1 | | to capture and sequester at least 90% of the carbon dioxide |
2 | | emissions that the portion of the facility, if any, that |
3 | | produces SNG would otherwise emit and at least 50% of the total |
4 | | carbon dioxide emissions that the facility as a whole would |
5 | | otherwise emit, but this clause (3) shall not apply if the |
6 | | facility is an SNG-ready generating facility; (4) absent an |
7 | | appeal of a permit or "; and |
8 | | on page 11, immediately below line 25, by inserting the |
9 | | following: |
10 | | " "SNG-ready capital costs" means the portion of the capital |
11 | | costs of an SNG-ready generating facility that are necessary to |
12 | | accommodate future integrated operation of such generating |
13 | | facility with one or more coal gasification units, but only to |
14 | | the extent such capital costs would not have been part of the |
15 | | capital costs of a similar electric generating facility that is |
16 | | not designed to accommodate future integrated operation with |
17 | | one or more coal gasification units. |
18 | | "SNG-ready capital rate component" means, for any year, the |
19 | | portion of the amounts paid under sourcing agreements with the |
20 | | initial clean coal facility that is attributable to SNG-ready |
21 | | capital costs being included in the return of capital and |
22 | | return on capital components of the formula rate. |
23 | | "SNG-ready generating facility" means an electric |
24 | | generating facility that is capable of using SNG as a fuel and |
25 | | is designed to accommodate future integrated operation with one |
|
| | 09700SB0678ham002 | - 3 - | LRB097 04938 CEL 69975 a |
|
|
1 | | or more coal gasification units located on or adjacent to the |
2 | | generating facility site, but with no gasification units |
3 | | constructed as part of the initial construction of such |
4 | | facility. An SNG-ready generating facility shall be designed to |
5 | | accommodate such future integrated operation if its steam |
6 | | turbine, steam piping, air cooled condenser, condensate and |
7 | | feedwater systems, and certain heat recovery steam generator |
8 | | sections (high pressure superheater, low pressure superheater |
9 | | and reheater) are designed to accommodate the steam and water |
10 | | flows expected from the coal gasification units and if the |
11 | | overall plant layout includes reservation of an adjacent plot |
12 | | space (over which such generating facility holds and shall |
13 | | maintain site control) for efficient installation of the future |
14 | | coal gasification units and related equipment, including fuel |
15 | | handling equipment. "; and |
16 | | on page 28, lines 8 and 13, by replacing " 2012 " each time it |
17 | | appears with " 2014 "; and |
18 | | on page 29, line 13, by replacing " 2012 " with " 2014 "; and |
19 | | on page 32, immediately below line 15, by inserting the |
20 | | following: |
21 | | " (7) If and for so long as the initial clean coal |
22 | | facility is an SNG-ready generating facility, the expert or |
23 | | consultant that shall develop the feedstock procurement |
|
| | 09700SB0678ham002 | - 4 - | LRB097 04938 CEL 69975 a |
|
|
1 | | plan and the feedstock procurement administrator, each as |
2 | | selected pursuant to this subsection (a-5), shall not be |
3 | | required to have experience in coal procurement. "; and |
4 | | by replacing line 17 on page 46 through line 2 on page 53 with |
5 | | the following: |
6 | | "Notwithstanding the requirements of this subsection |
7 | | (d), the total amount paid under sourcing agreements with |
8 | | clean coal facilities pursuant to the procurement plan for |
9 | | any given year shall be reduced by an amount necessary to |
10 | | limit the annual estimated average net increase due to the |
11 | | costs of these resources included in the amounts paid by |
12 | | eligible retail customers in connection with electric |
13 | | service to: |
14 | | (A) in 2010, no more than 0.5% of the amount |
15 | | paid per kilowatthour by those customers during |
16 | | the year ending May 31, 2009; |
17 | | (B) in 2011, the greater of an additional 0.5% |
18 | | of the amount paid per kilowatthour by those |
19 | | customers during the year ending May 31, 2010 or 1% |
20 | | of the amount paid per kilowatthour by those |
21 | | customers during the year ending May 31, 2009; |
22 | | (C) in 2012, the greater of an additional 0.5% |
23 | | of the amount paid per kilowatthour by those |
24 | | customers during the year ending May 31, 2011 or |
25 | | 1.5% of the amount paid per kilowatthour by those |
|
| | 09700SB0678ham002 | - 5 - | LRB097 04938 CEL 69975 a |
|
|
1 | | customers during the year ending May 31, 2009; |
2 | | (D) in 2013, the greater of an additional 0.5% |
3 | | of the amount paid per kilowatthour by those |
4 | | customers during the year ending May 31, 2012 or 2% |
5 | | of the amount paid per kilowatthour by those |
6 | | customers during the year ending May 31, 2009; and |
7 | | (E) thereafter, the total amount paid under |
8 | | sourcing agreements with clean coal facilities |
9 | | pursuant to the procurement plan for any single |
10 | | year shall be reduced by an amount necessary to |
11 | | limit the estimated average net increase due to the |
12 | | cost of these resources included in the amounts |
13 | | paid by eligible retail customers in connection |
14 | | with electric service to no more than the greater |
15 | | of (i) 2.015% of the amount paid per kilowatthour |
16 | | by those customers during the year ending May 31, |
17 | | 2009 or (ii) the incremental amount per |
18 | | kilowatthour paid for these resources in 2013. |
19 | | These requirements may be altered only as provided |
20 | | by statute. |
21 | | No later than June 30, 2015, the Commission |
22 | | shall review the limitation on the total amount |
23 | | paid under sourcing agreements, if any, with clean |
24 | | coal facilities pursuant to this subsection (d) |
25 | | and report to the General Assembly its findings as |
26 | | to whether that limitation unduly constrains the |
|
| | 09700SB0678ham002 | - 6 - | LRB097 04938 CEL 69975 a |
|
|
1 | | amount of electricity generated by cost-effective |
2 | | clean coal facilities that is covered by sourcing |
3 | | agreements. |
4 | | Notwithstanding the requirements of this subsection |
5 | | (d), the total amount purchased under sourcing agreements |
6 | | with the initial clean coal facility pursuant to the |
7 | | procurement plan for any given year shall be reduced by an |
8 | | amount necessary to limit the annual estimated average net |
9 | | increase due to the costs of these resources included in |
10 | | the amounts paid by eligible retail customers in connection |
11 | | with electric service to: |
12 | | (A) in 2010, no more than 0.5% of the amount paid |
13 | | per kilowatthour by those customers during the year |
14 | | ending May 31, 2009; |
15 | | (B) in 2011, the greater of an additional 0.5% of |
16 | | the amount paid per kilowatthour by those customers |
17 | | during the year ending May 31, 2010 or 1% of the amount |
18 | | paid per kilowatthour by those customers during the |
19 | | year ending May 31, 2009; |
20 | | (C) in 2012, the greater of an additional 0.5% of |
21 | | the amount paid per kilowatthour by those customers |
22 | | during the year ending May 31, 2011 or 1.5% of the |
23 | | amount paid per kilowatthour by those customers during |
24 | | the year ending May 31, 2009; |
25 | | (D) in 2013, the greater of an additional 0.5% of |
26 | | the amount paid per kilowatthour by those customers |
|
| | 09700SB0678ham002 | - 7 - | LRB097 04938 CEL 69975 a |
|
|
1 | | during the year ending May 31, 2012 or 2% of the amount |
2 | | paid per kilowatthour by those customers during the |
3 | | year ending May 31, 2009; and |
4 | | (E) thereafter: |
5 | | (i) A calculation shall be made for each year |
6 | | to determine whether the estimated average net per |
7 | | killowatthour increase due to the cost of electric |
8 | | power purchased under sourcing agreements and |
9 | | included in the amounts paid by small electric |
10 | | customers in connection with electric service |
11 | | exceeds the greater of (1) 2.015% of the amount |
12 | | paid per kilowatthour by eligible retail customers |
13 | | during the year ending May 31, 2009 or (2) the |
14 | | incremental amount per kilowatthour paid for these |
15 | | resources in 2013. If and for so long as the |
16 | | initial clean coal facility is an SNG-ready |
17 | | generating facility, the percentage in the |
18 | | immediately preceding sentence shall be 0.75% and |
19 | | not 2.015%. These requirements may be altered only |
20 | | as provided by statute. For purposes of such |
21 | | calculation, such average net per kilowatthour |
22 | | increase in rates of small electric customers that |
23 | | are not eligible retail customers shall be deemed |
24 | | to be equal to such average net per kilowatthour |
25 | | increase in rates of eligible retail customers. |
26 | | (ii) If, for any year, the small customer rate |
|
| | 09700SB0678ham002 | - 8 - | LRB097 04938 CEL 69975 a |
|
|
1 | | impact would exceed the limitation described in |
2 | | item (i) of this subparagraph (E), the clean coal |
3 | | fraction for each clean coal electricity buyer |
4 | | shall be adjusted for such year in a manner that |
5 | | shall result in (1) the quantity of electric power |
6 | | projected to be purchased by each clean coal |
7 | | electricity buyer being reduced by an amount |
8 | | sufficient to result in such deemed rate impact on |
9 | | all small electric customers (whether served by |
10 | | electric utilities or alternative retail electric |
11 | | suppliers) being equal to such limitation for such |
12 | | year and (2) any such reductions in amounts |
13 | | allocated to the clean coal electricity buyers in |
14 | | order to achieve the objective described in clause |
15 | | (1) of this item (ii) being allocated to, and |
16 | | purchased and paid for by, the clean coal |
17 | | electricity buyers in proportion to their retail |
18 | | sales to large electric customers. |
19 | | (iii) Each year, after taking account of the |
20 | | adjustment, if any, provided for in item (ii) of |
21 | | this subparagraph (E), a calculation shall be made |
22 | | to determine whether the large customer deemed |
23 | | rate impact for such year exceeds $0.005 per |
24 | | kilowatthour. If and for so long as the initial |
25 | | clean coal facility is an SNG-ready generating |
26 | | facility, the amount in the immediately preceding |
|
| | 09700SB0678ham002 | - 9 - | LRB097 04938 CEL 69975 a |
|
|
1 | | sentence shall be $0.00085, and not $0.005. The |
2 | | "large customer deemed rate impact" for any year is |
3 | | the projected increase in electric rates of large |
4 | | electric customers (whether served by electric |
5 | | utilities or alternative retail electric |
6 | | suppliers) due to the cost of electric power |
7 | | purchased under sourcing agreements to the extent |
8 | | it is based on each clean coal electricity buyer's |
9 | | retail sales to large electric customers, which |
10 | | shall be calculated in substantially the same |
11 | | manner as the calculation of rate impact on small |
12 | | electric customers, and shall assume that such |
13 | | cost of purchases under sourcing agreements is |
14 | | passed through proportionally by the clean coal |
15 | | electricity buyers to their large electric |
16 | | customers. The calculation of the large customer |
17 | | deemed rate impact shall (1) assume that the total |
18 | | retail sales (expressed in kilowatthours sold) to |
19 | | large electric customers by all clean coal |
20 | | electricity buyers for any year is the greater of |
21 | | the actual amount of such sales in such year and |
22 | | the amount of such sales in 2009 and (2) exclude |
23 | | from the calculation any actual costs for such year |
24 | | incurred by the initial clean coal facility to the |
25 | | extent such costs exceed the corresponding amount |
26 | | assumed in the "reference case" of the facility |
|
| | 09700SB0678ham002 | - 10 - | LRB097 04938 CEL 69975 a |
|
|
1 | | cost report for the initial clean coal facility for |
2 | | such year and are not principally within the |
3 | | reasonable control of the initial clean coal |
4 | | facility. |
5 | | Any operating costs or revenues deviating from |
6 | | the corresponding costs assumed in the "reference |
7 | | case" of the facility cost report for the initial |
8 | | clean coal facility as a result of changes in |
9 | | market prices, including, but not limited to, |
10 | | prices of coal, natural gas, electricity, |
11 | | by-products, and emissions allowances, shall be |
12 | | deemed to be outside of the reasonable control of |
13 | | the initial clean coal facility and excluded from |
14 | | the calculation. |
15 | | Any costs exceeding the corresponding costs |
16 | | assumed in the "reference case" of the facility |
17 | | cost report for the initial clean coal facility as |
18 | | a result of changes in capital costs, fixed |
19 | | operating costs, variable operating costs, |
20 | | operating efficiency, and availability, except in |
21 | | each case to the extent resulting from a change in |
22 | | market prices, as described in the immediately |
23 | | preceding paragraph, or from a change in law, as |
24 | | defined in subsection (b) of Section 1-76 of this |
25 | | Act, shall be deemed to be within the reasonable |
26 | | control of the initial clean coal facility and |
|
| | 09700SB0678ham002 | - 11 - | LRB097 04938 CEL 69975 a |
|
|
1 | | included in the calculation. |
2 | | If and for so long as the initial clean coal |
3 | | facility is an SNG-ready generating facility, |
4 | | clause (2) of the fourth sentence and all of the |
5 | | second and third paragraphs of this item (iii) |
6 | | shall not apply. |
7 | | (iv) If, for any year, the large customer |
8 | | deemed rate impact would exceed the limitation |
9 | | described in item (iii) of this subparagraph (E), |
10 | | the quantity of electric power required to be |
11 | | purchased by each clean coal electricity buyer |
12 | | that serves large electric customers under its |
13 | | sourcing agreement for such year shall be reduced |
14 | | by such amount as will result in the large customer |
15 | | deemed rate impact being equal to such limitation |
16 | | for such year, and the clean coal fractions of each |
17 | | clean coal electricity buyer that serves large |
18 | | electric customers shall be adjusted for such year |
19 | | to reflect this reduction; provided, however, that |
20 | | the reduction under this item (iv) shall not exceed |
21 | | in any year an amount that would result in revenues |
22 | | under the sourcing agreements being reduced by |
23 | | more than $50,000,000 in the aggregate for such |
24 | | year, but this provision shall not apply if and for |
25 | | so long as the initial clean coal facility is an |
26 | | SNG-ready generating facility. Any quantities of |
|
| | 09700SB0678ham002 | - 12 - | LRB097 04938 CEL 69975 a |
|
|
1 | | electric power not required to be purchased |
2 | | pursuant to the operation of the immediately |
3 | | preceding sentence may be disposed of by the |
4 | | initial clean coal facility for its own account, |
5 | | and the proceeds of any sales of such electric |
6 | | power shall not be included in the formula rate. |
7 | | (v) The details of the calculations |
8 | | contemplated by this subparagraph (E) shall be set |
9 | | forth in the sourcing agreements. |
10 | | (vi) No later than June 30, 2016, the |
11 | | Commission shall review the limitation on the |
12 | | total amount paid under sourcing agreements, if |
13 | | any, with the initial clean coal facility pursuant |
14 | | to this subsection (d) and report to the General |
15 | | Assembly its findings as to the effect of the |
16 | | limitation on the initial clean coal facility, |
17 | | electric utilities, alternative retail electric |
18 | | suppliers, and customers of the electric utilities |
19 | | and the alternative retail electric suppliers. "; |
20 | | and |
21 | | on page 54, line 4, immediately after " facility " by inserting |
22 | | " as established by engineering and design studies "; and |
23 | | on page 54, by replacing line 10 with " intermittent resources, |
24 | | the reliability and cost of "; and |
|
| | 09700SB0678ham002 | - 13 - | LRB097 04938 CEL 69975 a |
|
|
1 | | on page 54, line 12, immediately after " utilities " by inserting |
2 | | " , the amount of engineering and design work that has been done |
3 | | for the facility, including, in the case of an SNG-ready |
4 | | generating facility, the engineering and design work relating |
5 | | to features that would accommodate future integrated operation |
6 | | with one or more coal gasification units, the facility's water |
7 | | use and overall environmental attributes, and the schedule for |
8 | | commencement of construction and operation of the facility "; |
9 | | and
|
10 | | on page 54, by replacing line 15 with the following: |
11 | | " 97th General Assembly. The facility designated as the |
12 | | initial clean coal facility under this Section shall |
13 | | operate as an SNG-ready generating facility unless and |
14 | | until it becomes an electric generating facility using |
15 | | gasification technology by adding one or more coal |
16 | | gasification units. The initial clean coal facility may add |
17 | | one or more coal gasification units only after: |
18 | | (A) the General Assembly, by enactment of a law, |
19 | | authorizes the addition; provided that, within 2 years |
20 | | preceding the effective date of such enactment, the |
21 | | initial clean coal facility shall have submitted a |
22 | | facility cost report for the coal gasification unit or |
23 | | units otherwise meeting the requirements of paragraph |
24 | | (4) of subsection (d) of this Section; |
|
| | 09700SB0678ham002 | - 14 - | LRB097 04938 CEL 69975 a |
|
|
1 | | (B) a determination is made by the Commission |
2 | | either that a carbon dioxide pipeline capable of |
3 | | transporting the carbon dioxide captured from such |
4 | | gasification unit or units may be constructed, which |
5 | | shall be deemed to have been made if the Commission |
6 | | issued a certificate of authority of the construction |
7 | | of such a carbon dioxide pipeline, or that the initial |
8 | | clean coal facility has obtained a Class VI injection |
9 | | permit from the United States Environmental Protection |
10 | | Agency or the Illinois Environmental Protection Agency |
11 | | and has completed the other material elements |
12 | | necessary for it to sequester carbon dioxide captured |
13 | | from such gasification unit or units; |
14 | | (C) a determination of capital costs associated |
15 | | with the addition is made by the Capital Development |
16 | | Board and the Commission according to the process in |
17 | | subsection (b) of Section 1-76 of this Act; and |
18 | | (D) a determination of sequestration capital costs |
19 | | and sequestration operation and maintenance costs |
20 | | associated with the addition is made by the Capital |
21 | | Development Board according to the process in |
22 | | subsection (e) of Section 1-76 of this Act. |
23 | | The initial clean coal facility may accomplish the |
24 | | addition of the coal gasification unit or units either (i) |
25 | | by having the coal gasification unit or units owned by the |
26 | | same entity that owns the SNG-ready generating facility and |
|
| | 09700SB0678ham002 | - 15 - | LRB097 04938 CEL 69975 a |
|
|
1 | | the costs associated with the coal gasification unit or |
2 | | units included in the formula rate under sourcing |
3 | | agreements between the clean coal electricity buyers and |
4 | | the initial clean coal facility or (ii) by having the coal |
5 | | gasification unit or units be owned by a different entity |
6 | | that would sell the SNG produced by such gasification unit |
7 | | or units to the SNG-ready generating facility under a |
8 | | separate formula rate with the SNG-ready generating |
9 | | facility incorporating the costs of the SNG into the |
10 | | formula rate under its sourcing agreement with the clean |
11 | | coal electricity buyers. a proposed clean coal facility |
12 | | in "; and
|
13 | | on page 68, line 12, by deleting " and "; and |
14 | | on page 69, by replacing line 18 with " approved by the Agency; |
15 | | and "; and |
16 | | on page 69, immediately below line 18, by inserting: |
17 | | " (xvii) if the initial clean coal facility is an |
18 | | SNG-ready generating facility, set out a mechanism for |
19 | | adjusting the quantity of electric power purchased by |
20 | | each clean coal electricity buyer so that the small |
21 | | customer rate impact would not exceed 0.375% of the |
22 | | amount paid per kilowatthour by eligible retail |
23 | | customers during the year ending May 31, 2009 and the |
|
| | 09700SB0678ham002 | - 16 - | LRB097 04938 CEL 69975 a |
|
|
1 | | large customer deemed rate impact would not exceed |
2 | | $0.000425 per kilowatthour, in each case due to the |
3 | | SNG-ready capital rate component; such mechanism shall |
4 | | include a carryforward to subsequent years for any |
5 | | reduced revenues suffered by the initial clean coal |
6 | | facility as a result of such adjustments, but subject |
7 | | to the application of these limitations in subsequent |
8 | | years; such mechanism shall be effective for so long as |
9 | | the initial clean coal facility is an SNG-ready |
10 | | generating facility and shall be compatible with the |
11 | | provisions of subparagraph (E) of paragraph (2) of this |
12 | | subsection. " and |
13 | | on page 81, immediately below line 4, by inserting the |
14 | | following: |
15 | | " (l) If the initial clean coal facility is an SNG-ready |
16 | | generating facility, then the initial clean coal facility |
17 | | shall continue with its efforts to obtain permits for |
18 | | carbon capture and sequestration facilities that could be |
19 | | used in connection with the portion of the facility that |
20 | | produces SNG if such portion of the facility were to be |
21 | | constructed. "; and |
22 | | on page 83, line 26, after " facility. ", by inserting " If the |
23 | | initial clean coal facility is an SNG-ready generating |
24 | | facility, the capital costs of the SNG-ready generating |
|
| | 09700SB0678ham002 | - 17 - | LRB097 04938 CEL 69975 a |
|
|
1 | | facility shall include reasonable development costs relating |
2 | | to the initial clean coal facility without regard to whether |
3 | | such costs relate to the power block or the proposed portion of |
4 | | the facility that produces SNG and without regard to whether |
5 | | the proposed portion of the facility that produces SNG is to be |
6 | | constructed. If the initial clean coal facility is an SNG-ready |
7 | | generating facility, the Capital Development Board shall |
8 | | include in its calculation of capital costs an identification |
9 | | of which capital costs constitute SNG-ready capital costs and |
10 | | shall not include in the range of capital costs any SNG-ready |
11 | | capital costs that exceed 10% of the total of all capital |
12 | | costs. "; and |
13 | | on page 86, line 18, after " facility. ", by inserting " If the |
14 | | initial clean coal facility is an SNG-ready generating |
15 | | facility, any capital costs of the SNG-ready generating |
16 | | facility that exceed the pre-approved capital costs and any |
17 | | SNG-ready capital costs that exceed 10% of the pre-approved |
18 | | capital costs shall not be included in the formula rate and |
19 | | shall be borne by the initial clean coal facility and its |
20 | | contractors, provided that, to the extent any of such |
21 | | incremental costs are the result of change in law or |
22 | | non-insurable force majeure, all of such costs shall be |
23 | | included in the formula rate and recoverable by the initial |
24 | | clean coal facility. "; and |
|
| | 09700SB0678ham002 | - 18 - | LRB097 04938 CEL 69975 a |
|
|
1 | | on page 86, by replacing line 24 with " authority occurring |
2 | | after the Commission determines the amount of pre-approved |
3 | | capital costs. "; and |
4 | | on page 89, line 9, immediately after " facility ", by inserting |
5 | | " and, if the initial clean coal facility is an SNG-ready |
6 | | generating facility, for the initial construction of any coal |
7 | | gasification unit or units that may be added following |
8 | | authorization thereof pursuant to subparagraph (A) of |
9 | | paragraph (3) of subsection (d) of Section 1-75 of this Act, "; |
10 | | and |
11 | | on page 90, line 22, immediately after " electricity " by |
12 | | inserting " , provided that, if and for so long as the initial |
13 | | clean coal facility is an SNG-ready generating facility, the |
14 | | minimum feedstock procurement requirements in this sentence |
15 | | shall be inapplicable and the reference in this sentence to the |
16 | | term of a sourcing agreement shall be deemed to refer only to |
17 | | the portion, if any, of such term occurring after such |
18 | | SNG-ready generating facility adds one or more coal |
19 | | gasification units following authorization thereof pursuant to |
20 | | subparagraph (A) of paragraph (3) of subsection (d) of Section |
21 | | 1-75 of this Act "; and |
22 | | on page 91, line 20, after " rate. ", by inserting " If and for so |
23 | | long as the initial clean coal facility is an SNG-ready |
|
| | 09700SB0678ham002 | - 19 - | LRB097 04938 CEL 69975 a |
|
|
1 | | generating facility, the provisions of this subsection (e) |
2 | | shall be inapplicable. "; and |
3 | | on page 96, by replacing line 26 with " authority occurring |
4 | | after the Capital Development Board makes its final |
5 | | determination of sequestration capital costs and sequestration |
6 | | operation and maintenance costs. "; and |
7 | | on page 98, by replacing line 9 with " shall be no lower than |
8 | | the weighted "; and |
9 | | on page 98, line 12, by replacing " January 1, 2011 " with " the |
10 | | effective date of this amendatory Act of the 97th General |
11 | | Assembly "; and |
12 | | on page 103, immediately below line 20, by inserting the |
13 | | following: |
14 | | " (e) If and for so long as the initial clean coal facility |
15 | | is an SNG-ready generating facility, all requirements of this |
16 | | Section relating to carbon capture and sequestration shall be |
17 | | deemed to be satisfied if the carbon dioxide emissions from the |
18 | | SNG-ready generating facility are less than 1,000 pounds per |
19 | | megawatt-hour of electricity generated by the SNG-ready |
20 | | generating facility on an average annual basis; the initial |
21 | | clean coal facility shall submit to the Commission on an annual |
22 | | basis information demonstrating compliance with such emissions |
|
| | 09700SB0678ham002 | - 20 - | LRB097 04938 CEL 69975 a |
|
|
1 | | limit. "; and |
2 | | on page 103, by replacing lines 22 through 25 with the |
3 | | following: |
4 | | " Sec. 1-77.5. Sequestration permitting. |
5 | | (a) No initial clean coal facility "; and |
6 | | on page 104, by replacing lines 11 through 13 with the |
7 | | following: |
8 | | " (b) No later than 6 months prior to the date upon which |
9 | | the owner of the initial clean coal facility intends to |
10 | | commence construction of any coal gasification unit or units, |
11 | | the owner of such facility shall file with the Commission a |
12 | | carbon "; and |
13 | | by deleting line 17 on page 105 through line 11 on page 107; |
14 | | and |
15 | | on page 112, lines 1 and 14, by replacing " 2012 " each time it |
16 | | appears with " 2014 "; and |
17 | | on page 121, immediately below line 1, by inserting the |
18 | | following: |
19 | | " (n) If and for so long as the initial clean coal facility |
20 | | is an SNG-ready generating facility, the provisions of this |
21 | | Section relating to the procurement of coal or other feedstock |
|
| | 09700SB0678ham002 | - 21 - | LRB097 04938 CEL 69975 a |
|
|
1 | | that would be used by coal gasification units or relating to |
2 | | any minimum feedstock procurement or minimum feedstock usage |
3 | | shall not be applicable. "; and |
4 | | on page 187, by replacing lines 8 through 15 with the |
5 | | following: |
6 | | "(iii) the required sourcing of electricity |
7 | | generated by clean coal facilities, other than the |
8 | | initial clean coal facility, shall be limited to the |
9 | | amount of electricity that can be procured or sourced |
10 | | at a price at or below the benchmarks approved by the |
11 | | Commission each year in accordance with item (1) of |
12 | | subsection (c) and items (1) and (5) of subsection (d) |
13 | | of Section 1-75 of the Illinois Power Agency Act;"; and |
14 | | on page 209, immediately below line 14, by inserting the |
15 | | following:
|
16 | | "Section 999. Effective date. This Act takes effect upon |
17 | | becoming law.".
|