|
| | HR1157HAM001 | | LRB097 21882 CEL 70680 a |
|
|
1 | | AMENDMENT TO HOUSE RESOLUTION 1157
|
2 | | AMENDMENT NO. ___. Amend House Resolution 1157 by replacing |
3 | | everything after the title with the following: |
4 | | "WHEREAS, The 97th Illinois General Assembly passed Senate |
5 | | Bill 1652 and House Bill 3036 with supermajority votes in both |
6 | | legislative chambers; Senate Bill 1652 became law on October |
7 | | 26, 2011 as Public Act 97-616 and House Bill 3036 became law on |
8 | | December 30, 2011 as Public Act 97-646; and
|
9 | | WHEREAS, Public Act 97-616, which is commonly referred to |
10 | | as the Energy Infrastructure Modernization Act, confers |
11 | | substantial benefits upon the State's electric utility |
12 | | customers; it established detailed infrastructure investment |
13 | | plans to modernize and upgrade the State's aging electric grid |
14 | | in order to ensure the continued provision of safe, reliable, |
15 | | and affordable service to Illinoisans; participating utilities |
16 | | that elect to undertake the infrastructure investment plan may |
|
| | HR1157HAM001 | - 2 - | LRB097 21882 CEL 70680 a |
|
|
1 | | recover their costs through a performance-based formula rate |
2 | | tariff mechanism, which was designed to increase |
3 | | predictability, stability, and transparency in the ratemaking |
4 | | process; and
|
5 | | WHEREAS, Public Act 97-646 was enacted as "trailer |
6 | | legislation" to Public Act 97-616 with the intent to amend the |
7 | | Energy Infrastructure Modernization Act to provide additional |
8 | | benefits to customers; and
|
9 | | WHEREAS, To make this investment possible, the |
10 | | performance-based formula rate tariff must, among other |
11 | | things, establish and set forth certain protocols providing |
12 | | that participating utilities recover the costs of service and |
13 | | these investments, including, but not limited to, allowing for |
14 | | the recovery of an "investment return on pension assets net of |
15 | | deferred tax benefits equal to the utility's long-term debt |
16 | | cost of capital as of the end of the applicable calendar year", |
17 | | which is set forth in subparagraph (D) of paragraph (4) of |
18 | | subsection (c) of Section 16-108.5 of the Public Utilities Act; |
19 | | and
|
20 | | WHEREAS, In so providing, the General Assembly did not, and |
21 | | did not intend to, overturn or generally depart from Illinois |
22 | | Commerce Commission practice and law regarding the |
23 | | establishment of these protocols, including the electric |
|
| | HR1157HAM001 | - 3 - | LRB097 21882 CEL 70680 a |
|
|
1 | | utility's ability to continue to recover a debt return on its |
2 | | pension assets as the Commission has previously allowed; and
|
3 | | WHEREAS, No statutory authority was given to the Illinois |
4 | | Commerce Commission to deny recovery of a debt return on what |
5 | | is commonly referred to as, what is reported in the Federal |
6 | | Energy Regulatory Commission Form 1 (FERC Form 1) as, and what |
7 | | the General Assembly regarded to be a pension asset; and |
8 | | WHEREAS, The Energy Infrastructure Modernization Act |
9 | | further provides in subsections (c) and (d) of Section 16-108.5 |
10 | | that those amounts to be credited or charged to customers |
11 | | following the annual reconciliation process under the |
12 | | performance-based formula rate shall be "with interest" so the |
13 | | utility will be made whole for unrecovered amounts that were |
14 | | prudently and reasonably incurred and customers will be made |
15 | | whole for amounts they overpaid, if any; and |
16 | | WHEREAS, Such interest is intended to be set at the |
17 | | utility's weighted average cost of capital, determined in |
18 | | accordance with the statute, which represents the reasonable |
19 | | cost and means of financing a utility's investments and |
20 | | operating costs, so that the utility and customers are made |
21 | | whole when charges or credits are necessary to reconcile to |
22 | | actual prudent and reasonable investments and costs; and |
|
| | HR1157HAM001 | - 4 - | LRB097 21882 CEL 70680 a |
|
|
1 | | WHEREAS, The Energy Infrastructure Modernization Act also |
2 | | provides that the final year-end cost data filed in FERC Form 1 |
3 | | should generally be used to determine rates; and |
4 | | WHEREAS, No statutory authority was given to the Illinois |
5 | | Commerce Commission to set rate base and capital structure |
6 | | using average numbers that do not represent final year-end |
7 | | values reflected in the FERC Form 1, and the Illinois Commerce |
8 | | Commission's use of such average is contrary to the statute; |
9 | | and |
10 | | WHEREAS, The Illinois Supreme and Appellate Courts have |
11 | | consistently held that, because the administrative agencies |
12 | | are creatures of statute, administrative agencies possess only |
13 | | those powers expressly delegated by law and may not act beyond |
14 | | its statutorily delegated authority; and |
15 | | WHEREAS, The Illinois Supreme and Appellate Courts have |
16 | | consistently held that public policy in Illinois is expressed |
17 | | by the General Assembly, and it is not the province of an |
18 | | administrative agency to inquire into the wisdom and propriety |
19 | | of the legislature's act or to substitute its own judgment for |
20 | | that of the legislature; therefore, be it
|
21 | | RESOLVED, BY THE HOUSE OF REPRESENTATIVES OF THE |
22 | | NINETY-SEVENTH GENERAL ASSEMBLY OF THE STATE OF ILLINOIS, that |
|
| | HR1157HAM001 | - 5 - | LRB097 21882 CEL 70680 a |
|
|
1 | | we express serious concerns that the Illinois Commerce |
2 | | Commission Order, entered on May 29, 2012 in Commission Docket |
3 | | No. 11-0721, fails to reflect the statutory directives and the |
4 | | intent of the Illinois General Assembly by: (1) not allowing |
5 | | Commonwealth Edison Company to earn a debt return on what is |
6 | | commonly referred to as, identified in the FERC Form 1 as, and |
7 | | what the General Assembly referred to as a pension asset in |
8 | | subparagraph (D) of paragraph (4) of subsection (c) of Section |
9 | | 16-108.5; (2) assessing interest on those amounts to be |
10 | | credited or charged to customers as set forth in subsection (d) |
11 | | of Section 16-108.5 of the Public Utilities Act at an amount |
12 | | that is not based on the utility's weighted average cost of |
13 | | capital; and (3) determining rate base and capital structure |
14 | | using an average, rather than the year-end amounts as reflected |
15 | | in FERC Form 1; and be it further
|
16 | | RESOLVED, That we urge that the Illinois Commerce |
17 | | Commission, on rehearing, strongly consider reversing its |
18 | | conclusions with respect to each of these 3 issues and reach a |
19 | | decision that reflects the statutory directives and the intent |
20 | | of the General Assembly in passing Public Acts 97-616 and |
21 | | 97-646 as reaffirmed in this resolution; and be it further
|
22 | | RESOLVED, That suitable copies of this resolution be |
23 | | delivered to the Governor of the State of Illinois and the |
24 | | Chairman and Commissioners of the Illinois Commerce |