1 | AN ACT concerning finance.
| |||||||||||||||||||
2 | Be it enacted by the People of the State of Illinois,
| |||||||||||||||||||
3 | represented in the General Assembly:
| |||||||||||||||||||
4 | Section 5. The Public Construction Bond Act is amended by | |||||||||||||||||||
5 | changing Section 1 as follows:
| |||||||||||||||||||
6 | (30 ILCS 550/1) (from Ch. 29, par. 15)
| |||||||||||||||||||
7 | Sec. 1. Except as otherwise provided by this Act, all | |||||||||||||||||||
8 | officials, boards,
commissions, or agents of this State in | |||||||||||||||||||
9 | making contracts for public work of
any kind costing over | |||||||||||||||||||
10 | $50,000 to be performed for the State, and all officials, | |||||||||||||||||||
11 | boards, commissions, or agents of any political subdivision of | |||||||||||||||||||
12 | this State in making contracts for public work of any kind | |||||||||||||||||||
13 | costing over $5,000 to be performed for the political | |||||||||||||||||||
14 | subdivision,
including work intended to be conveyed by a | |||||||||||||||||||
15 | developer to the State or political subdivision pursuant to a | |||||||||||||||||||
16 | development agreement, shall require every contractor for the | |||||||||||||||||||
17 | work to furnish, supply and deliver
a bond to the State, or to | |||||||||||||||||||
18 | the political subdivision thereof entering into
the contract, | |||||||||||||||||||
19 | as the case may be, with good and sufficient sureties. The
| |||||||||||||||||||
20 | amount of the bond shall be fixed by the officials, boards, | |||||||||||||||||||
21 | commissions,
commissioners or agents, and the bond, among other | |||||||||||||||||||
22 | conditions,
shall be
conditioned for the completion of the | |||||||||||||||||||
23 | contract, for the payment of material
used in the work and for |
| |||||||
| |||||||
1 | all labor performed in the work, whether by
subcontractor or | ||||||
2 | otherwise.
| ||||||
3 | If the contract is for emergency repairs as provided in the | ||||||
4 | Illinois
Procurement
Code, proof of payment for all labor, | ||||||
5 | materials, apparatus, fixtures, and
machinery may be
furnished | ||||||
6 | in lieu of the bond required by this Section.
| ||||||
7 | Each such bond is deemed to contain the following | ||||||
8 | provisions whether
such provisions are inserted in such bond or | ||||||
9 | not:
| ||||||
10 | "The principal and sureties on this bond agree that all the
| ||||||
11 | undertakings, covenants, terms, conditions and agreements of | ||||||
12 | the contract
or contracts entered into between the principal | ||||||
13 | and the State or any
political subdivision thereof will be | ||||||
14 | performed and fulfilled and to pay
all persons, firms and | ||||||
15 | corporations having contracts with the principal or
with | ||||||
16 | subcontractors, all just claims due them under the provisions | ||||||
17 | of such
contracts for labor performed or materials furnished in | ||||||
18 | the performance of
the contract on account of which this bond | ||||||
19 | is given, when such claims are
not satisfied out of the | ||||||
20 | contract price of the contract on account of which
this bond is | ||||||
21 | given, after final settlement between the officer, board,
| ||||||
22 | commission or agent of the State or of any political | ||||||
23 | subdivision thereof
and the principal has been made.". | ||||||
24 | Each bond securing contracts between the Capital | ||||||
25 | Development Board or any board of a public institution of | ||||||
26 | higher education and a contractor shall contain the following |
| |||||||
| |||||||
1 | provisions, whether the provisions are inserted in the bond or | ||||||
2 | not: | ||||||
3 | "Upon the default of the principal with respect to | ||||||
4 | undertakings, covenants, terms, conditions, and agreements, | ||||||
5 | the termination of the contractor's right to proceed with the | ||||||
6 | work, and written notice of that default and termination by the | ||||||
7 | State or any political subdivision to the surety ("Notice"), | ||||||
8 | the surety shall promptly remedy the default by taking one of | ||||||
9 | the following actions: | ||||||
10 | (1) The surety shall complete the work pursuant to a | ||||||
11 | written takeover agreement, using a completing contractor | ||||||
12 | jointly selected by the surety and the State or any | ||||||
13 | political subdivision; or | ||||||
14 | (2) The surety shall pay a sum of money to the obligee, | ||||||
15 | up to the penal sum of the bond, that represents the | ||||||
16 | reasonable cost to complete the work that exceeds the | ||||||
17 | unpaid balance of the contract sum. | ||||||
18 | The surety shall respond to the Notice within 15 working | ||||||
19 | days of receipt indicating the course of action that it intends | ||||||
20 | to take or advising that it requires more time to investigate | ||||||
21 | the default and select a course of action. If the surety | ||||||
22 | requires more than 15 working days to investigate the default | ||||||
23 | and select a course of action or if the surety elects to | ||||||
24 | complete the work with a completing contractor that is not | ||||||
25 | prepared to commence performance within 15 working days after | ||||||
26 | receipt of Notice, and if the State or any political |
| |||||||
| |||||||
1 | subdivision determines it is in the best interest of the State | ||||||
2 | to maintain the progress of the work, the State or any | ||||||
3 | political subdivision may continue to work until the completing | ||||||
4 | contractor is prepared to commence performance. Unless | ||||||
5 | otherwise agreed to by the procuring agency, in no case may the | ||||||
6 | surety take longer than 30 working days to advise the State or | ||||||
7 | political subdivision on the course of action it intends to | ||||||
8 | take. The surety shall be liable for reasonable costs incurred | ||||||
9 | by the State or any political subdivision to maintain the | ||||||
10 | progress to the extent the costs exceed the unpaid balance of | ||||||
11 | the contract sum, subject to the penal sum of the bond.".
| ||||||
12 | The surety bond required by this Section may be acquired | ||||||
13 | from the
company, agent or broker of the contractor's choice. | ||||||
14 | The bond and sureties
shall
be subject to the right of | ||||||
15 | reasonable approval or disapproval, including
suspension, by | ||||||
16 | the State or political subdivision thereof concerned. In the
| ||||||
17 | case of State construction contracts, a contractor shall not be | ||||||
18 | required to
post a cash bond or letter of credit in addition to | ||||||
19 | or as a substitute for the
surety bond required by this | ||||||
20 | Section.
| ||||||
21 | When other than motor fuel tax funds, federal-aid funds, or | ||||||
22 | other
funds received from the State are used, a political | ||||||
23 | subdivision may allow
the contractor to provide a | ||||||
24 | non-diminishing irrevocable bank letter of
credit, in lieu of | ||||||
25 | the bond required by this Section, on contracts under
$100,000 | ||||||
26 | to comply with the requirements of this Section. Any such bank
|
| |||||||
| |||||||
1 | letter of credit shall contain all provisions required for | ||||||
2 | bonds by this
Section.
| ||||||
3 | (Source: P.A. 95-1011, eff. 12-15-08; 96-1000, eff. 7-2-10.)
| ||||||
4 | Section 99. Effective date. This Act takes effect upon | ||||||
5 | becoming law.
|