1 | AN ACT concerning business.
| ||||||
2 | Be it enacted by the People of the State of Illinois,
| ||||||
3 | represented in the General Assembly:
| ||||||
4 | Section 5. The Contractor Prompt Payment Act is amended by | ||||||
5 | changing Section 10 as follows: | ||||||
6 | (815 ILCS 603/10)
| ||||||
7 | Sec. 10. Construction contracts. | ||||||
8 | (a) All construction contracts shall be deemed to provide | ||||||
9 | the following: | ||||||
10 | (1) If a contractor has performed in accordance with | ||||||
11 | the provisions of a construction contract and the payment | ||||||
12 | application has been approved by the owner or the owner's | ||||||
13 | agent, the owner shall pay the amount due to the contractor | ||||||
14 | pursuant to the payment application not more than 15 | ||||||
15 | calendar days after the approval. The payment application | ||||||
16 | shall be deemed approved 25 days after the owner receives | ||||||
17 | it unless the owner provides, before the end of the 25-day | ||||||
18 | period, a written statement of the amount withheld and the | ||||||
19 | reason for withholding payment. If the owner finds that a | ||||||
20 | portion of the work not in accordance with the contract, | ||||||
21 | payment may be withheld for the reasonable value of that | ||||||
22 | portion only. Payment shall be made for any portion of the | ||||||
23 | contract for which the work has been performed in |
| |||||||
| |||||||
1 | accordance with the provisions of the contract. | ||||||
2 | Instructions or notification from an owner to his or her | ||||||
3 | lender or architect to process or pay a payment application | ||||||
4 | does not constitute approval of the payment application | ||||||
5 | under this Act. | ||||||
6 | (2) If a subcontractor has performed in accordance with | ||||||
7 | the provisions of his or her contract with the contractor | ||||||
8 | or subcontractor and the work has been accepted by the | ||||||
9 | owner, the owner's agent, or the contractor, the contractor | ||||||
10 | shall pay to his or her subcontractor and the subcontractor | ||||||
11 | shall pay to his or her subcontractor, within 15 calendar | ||||||
12 | days of the contractor's receipt from the owner or the | ||||||
13 | subcontractor's receipt from the contractor of each | ||||||
14 | periodic payment, final payment, or receipt of retainage | ||||||
15 | monies, the full amount received for the work of the | ||||||
16 | subcontractor based on the work completed or the services | ||||||
17 | rendered under the construction contract.
| ||||||
18 | (b) Under a construction contract, it is unlawful to | ||||||
19 | withhold more than 5% retainage on payments earned by | ||||||
20 | contractors and subcontractors. | ||||||
21 | (Source: P.A. 95-567, eff. 8-31-07.)
| ||||||
22 | Section 99. Effective date. This Act takes effect upon | ||||||
23 | becoming law.
|