|
| | HB0390 Enrolled | - 2 - | LRB097 03906 KTG 43945 b |
|
|
1 | | Preserve. |
2 | | (2) mining operations are feasible on the adjacent |
3 | | property; |
4 | | (3) such operations shall consist of overburden |
5 | | removal and, at the option of the Department, replacement |
6 | | of topsoil in reclamation; |
7 | | (4) such operations shall have a significant impact on |
8 | | the local economy as they are projected to create |
9 | | employment opportunities for approximately 45 persons and |
10 | | to serve as the source of payroll and direct expenditures |
11 | | of approximately $12 to $15 million per year; |
12 | | (5) no surface mining for the extraction of coal shall |
13 | | be conducted on the property described in subsection (b) of |
14 | | this Section; |
15 | | (6) the property described in subsection (b) of this |
16 | | Section and the property adjacent thereto on which mining |
17 | | operations are planned shall be reclaimed by the private |
18 | | entity on the expiration of the lease and shall be fit for |
19 | | conservation and recreation purposes; and |
20 | | (7) the adjacent property consists of 240 acres and |
21 | | shall ultimately be conveyed to the State, Department of |
22 | | Natural Resources. |
23 | | (b) The property is described as follows: |
24 | | The East 300 feet of even width of the Northwest |
25 | | Quarter, of Section 8, |
26 | | And |
|
| | HB0390 Enrolled | - 3 - | LRB097 03906 KTG 43945 b |
|
|
1 | | The East 300 feet of even width of the South 1,620 feet |
2 | | of the Southwest Quarter, Section 5, |
3 | | And |
4 | | South 300 feet of even width of the North Half of the |
5 | | Southeast Quarter, Section 5, |
6 | | And |
7 | | The West 300 feet of even width of the South 1,620 feet |
8 | | of the Southwest Quarter, Section 4, |
9 | | And |
10 | | The West 300 feet of even width of the North 2,940 feet |
11 | | of the West Half, Section 9, |
12 | | And |
13 | | North Half of the Southeast Quarter, Section 8. |
14 | | All in Township 6 South, Range 3 West, of the Third |
15 | | Principal Meridian, Perry County, Illinois. |
16 | | (c) The Department of Natural Resources shall lease the |
17 | | property described in subsection (b) of this Section for fair |
18 | | market value, and the term of the lease shall be for a period |
19 | | of no longer than 10 years with no option for renewal. |
20 | | (d) Prior to the execution of the lease, the private entity |
21 | | must receive Department approval of a plan for the reclamation |
22 | | of both the property described in subsection (b) of this |
23 | | Section and the property adjacent thereto on which mining |
24 | | operations are planned. The plan shall include a cost estimate |
25 | | and timeline for reclamation activities. The private entity |
26 | | shall provide financial assurance in an amount and in a form |
|
| | HB0390 Enrolled | - 4 - | LRB097 03906 KTG 43945 b |
|
|
1 | | sufficient to fund all reclamation activities in the |
2 | | Department-approved reclamation plan. At the option of the |
3 | | Department, both properties shall be reclaimed to farmland |
4 | | standards, with reclamation activities occurring |
5 | | contemporaneously with farmland activities. On the expiration |
6 | | of the lease and upon the request of the Department of Natural |
7 | | Resources, the private entity must execute the reclamation |
8 | | plan. |
9 | | (e) Any and all leases for the property described in |
10 | | subsection (b) of this Section in effect on the effective date |
11 | | of this amendatory Act of the 97th General Assembly are |
12 | | terminated by operation of law. |
13 | | (f) The provisions of this Section only apply to property |
14 | | described in subsection (b) of this Section and property |
15 | | adjacent thereto, and do not apply to any other property within |
16 | | Pyramid State Park, any other property within any other |
17 | | designated State park under the jurisdiction of the Department |
18 | | of Natural Resources, or any other State property. |
19 | | (g) The authorization for the Department lease property |
20 | | under this Section shall not apply if the Department determines |
21 | | that mining activities pose a risk to the recreational uses, |
22 | | wildlife, hydrology, water quality, habitat, or potential for |
23 | | habitat restoration of lands owned by the Department.
|
24 | | Section 99. Effective date. This Act takes effect upon |
25 | | becoming law.
|