|
Rep. Gary Hannig
Filed: 5/30/2008
|
|
09500SB1987ham001 |
|
LRB095 14199 MJR 51793 a |
|
|
1 |
| AMENDMENT TO SENATE BILL 1987
|
2 |
| AMENDMENT NO. ______. Amend Senate Bill 1987 by replacing |
3 |
| everything after the enacting clause with the following:
|
4 |
| "ARTICLE 1 |
5 |
| Section 1-1. Short title. This Article may be cited as the |
6 |
| Clean Coal Portfolio Standard Law. |
7 |
| Section 1-5. The Illinois Power Agency Act is amended by |
8 |
| changing Sections 1-5, 1-10, 1-75, and 1-80 as follows: |
9 |
| (20 ILCS 3855/1-5)
|
10 |
| Sec. 1-5. Legislative declarations and findings. The |
11 |
| General Assembly finds and declares: |
12 |
| (1) The health, welfare, and prosperity of all Illinois |
13 |
| citizens require the provision of adequate, reliable, |
14 |
| affordable, efficient, and environmentally sustainable |
|
|
|
09500SB1987ham001 |
- 2 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| electric service at the lowest total cost over time, taking |
2 |
| into account any benefits of price stability. |
3 |
| (2) The transition to retail competition is not |
4 |
| complete. Some customers, especially residential and small |
5 |
| commercial customers, have failed to benefit from lower |
6 |
| electricity costs from retail and wholesale competition. |
7 |
| (3) Escalating prices for electricity in Illinois pose |
8 |
| a serious threat to the economic well-being, health, and |
9 |
| safety of the residents of and the commerce and industry of |
10 |
| the State. |
11 |
| (4) To protect against this threat to economic |
12 |
| well-being, health, and safety it is necessary to improve |
13 |
| the process of procuring electricity to serve Illinois |
14 |
| residents, to promote investment in energy efficiency and |
15 |
| demand-response measures, and to support development of |
16 |
| clean coal technologies and renewable resources. |
17 |
| (5) Procuring a diverse electricity supply portfolio |
18 |
| will ensure the lowest total cost over time for adequate, |
19 |
| reliable, efficient, and environmentally sustainable |
20 |
| electric service. |
21 |
| (6) Including cost-effective renewable resources in |
22 |
| that portfolio will reduce long-term direct and indirect |
23 |
| costs to consumers by decreasing environmental impacts and |
24 |
| by avoiding or delaying the need for new generation, |
25 |
| transmission, and distribution infrastructure. |
26 |
| (7) Energy efficiency, demand-response measures, and |
|
|
|
09500SB1987ham001 |
- 3 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| renewable energy are resources currently underused in |
2 |
| Illinois. |
3 |
| (8) The State should encourage the use of advanced |
4 |
| clean coal technologies that capture and sequester carbon |
5 |
| dioxide emissions to advance environmental protection |
6 |
| goals and to demonstrate the viability of coal and |
7 |
| coal-derived fuels in a carbon-constrained economy. |
8 |
| The General Assembly therefore finds that it is necessary |
9 |
| to create the Illinois Power Agency and that the goals and |
10 |
| objectives of that Agency are to accomplish each of the |
11 |
| following: |
12 |
| (A) Develop electricity procurement plans to ensure |
13 |
| adequate, reliable, affordable, efficient, and |
14 |
| environmentally sustainable electric service at the lowest |
15 |
| total cost over time, taking into account any benefits of |
16 |
| price stability, for electric utilities that on December |
17 |
| 31, 2005 provided electric service to at least 100,000 |
18 |
| customers in Illinois. The procurement plan shall be |
19 |
| updated on an annual basis and shall include renewable |
20 |
| energy resources sufficient to achieve the standards |
21 |
| specified in this Act. |
22 |
| (B) Conduct competitive procurement processes to |
23 |
| procure the supply resources identified in the procurement |
24 |
| plan. |
25 |
| (C) Develop electric generation and co-generation |
26 |
| facilities that use indigenous coal or renewable |
|
|
|
09500SB1987ham001 |
- 4 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| resources, or both, financed with bonds issued by the |
2 |
| Illinois Finance Authority. |
3 |
| (D) Supply electricity from the Agency's facilities at |
4 |
| cost to one or more of the following: municipal electric |
5 |
| systems, governmental aggregators, or rural electric |
6 |
| cooperatives in Illinois.
|
7 |
| (Source: P.A. 95-481, eff. 8-28-07.) |
8 |
| (20 ILCS 3855/1-10)
|
9 |
| Sec. 1-10. Definitions. |
10 |
| "Agency" means the Illinois Power Agency. |
11 |
| "Agency loan agreement" means any agreement pursuant to |
12 |
| which the Illinois Finance Authority agrees to loan the |
13 |
| proceeds of revenue bonds issued with respect to a project to |
14 |
| the Agency upon terms providing for loan repayment installments |
15 |
| at least sufficient to pay when due all principal of, interest |
16 |
| and premium, if any, on those revenue bonds, and providing for |
17 |
| maintenance, insurance, and other matters in respect of the |
18 |
| project. |
19 |
| "Authority" means the Illinois Finance Authority. |
20 |
| "Clean coal facility" means an electric generating |
21 |
| facility that uses primarily coal as a feedstock and that |
22 |
| captures and sequesters carbon emissions at the following |
23 |
| levels: at least 50% of the total carbon emissions that the |
24 |
| facility would otherwise emit if, at the time construction |
25 |
| commences, the facility is scheduled to commence operation |
|
|
|
09500SB1987ham001 |
- 5 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| before 2015, at least 70% of the total carbon emissions that |
2 |
| the facility would otherwise emit if, at the time construction |
3 |
| commences, the facility is scheduled to commence operation |
4 |
| during 2015 or 2016, and at least 90% of the total carbon |
5 |
| emissions that the facility would otherwise emit if, at the |
6 |
| time construction commences, the facility is scheduled to |
7 |
| commence operation after 2016. The power block of the clean |
8 |
| coal facility shall not exceed allowable emission rates for |
9 |
| sulfur dioxide, nitrogen oxides, carbon monoxide, particulates |
10 |
| and mercury for a natural gas-fired combined-cycle facility the |
11 |
| same size as and in the same location as the clean coal |
12 |
| facility at the time the clean coal facility obtains an |
13 |
| approved air permit. All coal used by a clean coal facility |
14 |
| shall have high volatile bituminous rank and greater than 1.7 |
15 |
| pounds of sulfur per million btu content, unless the clean coal |
16 |
| facility does not use gasification technology and was operating |
17 |
| as a conventional coal-fired electric generating facility on |
18 |
| the effective date of this amendatory Act of the 95th General |
19 |
| Assembly. |
20 |
| "Clean coal SNG facility" means a facility that uses a |
21 |
| gasification process to produce substitute natural gas, that |
22 |
| sequesters at least 90% of the total carbon emissions that the |
23 |
| facility would otherwise emit and that uses coal as a |
24 |
| feedstock, with all such coal having a high bituminous rank and |
25 |
| greater than 1.7 pounds of sulfur per million btu content. |
26 |
| "Commission" means the Illinois Commerce Commission. |
|
|
|
09500SB1987ham001 |
- 6 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| "Costs incurred in connection with the development and |
2 |
| construction of a facility" means: |
3 |
| (1) the cost of acquisition of all real property and |
4 |
| improvements in connection therewith and equipment and |
5 |
| other property, rights, and easements acquired that are |
6 |
| deemed necessary for the operation and maintenance of the |
7 |
| facility; |
8 |
| (2) financing costs with respect to bonds, notes, and |
9 |
| other evidences of indebtedness of the Agency; |
10 |
| (3) all origination, commitment, utilization, |
11 |
| facility, placement, underwriting, syndication, credit |
12 |
| enhancement, and rating agency fees; |
13 |
| (4) engineering, design, procurement, consulting, |
14 |
| legal, accounting, title insurance, survey, appraisal, |
15 |
| escrow, trustee, collateral agency, interest rate hedging, |
16 |
| interest rate swap, capitalized interest and other |
17 |
| financing costs, and other expenses for professional |
18 |
| services; and |
19 |
| (5) the costs of plans, specifications, site study and |
20 |
| investigation, installation, surveys, other Agency costs |
21 |
| and estimates of costs, and other expenses necessary or |
22 |
| incidental to determining the feasibility of any project, |
23 |
| together with such other expenses as may be necessary or |
24 |
| incidental to the financing, insuring, acquisition, and |
25 |
| construction of a specific project and placing that project |
26 |
| in operation. |
|
|
|
09500SB1987ham001 |
- 7 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| "Department" means the Department of Commerce and Economic |
2 |
| Opportunity. |
3 |
| "Director" means the Director of the Illinois Power Agency. |
4 |
| "Demand-response" means measures that decrease peak |
5 |
| electricity demand or shift demand from peak to off-peak |
6 |
| periods. |
7 |
| "Energy efficiency" means measures that reduce the amount |
8 |
| of electricity required to achieve a given end use. |
9 |
| "Electric utility" has the same definition as found in |
10 |
| Section 16-102 of the Public Utilities Act. |
11 |
| "Facility" means an electric generating unit or a |
12 |
| co-generating unit that produces electricity along with |
13 |
| related equipment necessary to connect the facility to an |
14 |
| electric transmission or distribution system. |
15 |
| "Governmental aggregator" means one or more units of local |
16 |
| government that individually or collectively procure |
17 |
| electricity to serve residential retail electrical loads |
18 |
| located within its or their jurisdiction. |
19 |
| "Local government" means a unit of local government as |
20 |
| defined in Article VII of Section 1 of the Illinois |
21 |
| Constitution. |
22 |
| "Municipality" means a city, village, or incorporated |
23 |
| town. |
24 |
| "Person" means any natural person, firm, partnership, |
25 |
| corporation, either domestic or foreign, company, association, |
26 |
| limited liability company, joint stock company, or association |
|
|
|
09500SB1987ham001 |
- 8 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| and includes any trustee, receiver, assignee, or personal |
2 |
| representative thereof. |
3 |
| "Project" means the planning, bidding, and construction of |
4 |
| a facility. |
5 |
| "Public utility" has the same definition as found in |
6 |
| Section 3-105 of the Public Utilities Act. |
7 |
| "Real property" means any interest in land together with |
8 |
| all structures, fixtures, and improvements thereon, including |
9 |
| lands under water and riparian rights, any easements, |
10 |
| covenants, licenses, leases, rights-of-way, uses, and other |
11 |
| interests, together with any liens, judgments, mortgages, or |
12 |
| other claims or security interests related to real property. |
13 |
| "Renewable energy credit" means a tradable credit that |
14 |
| represents the environmental attributes of a certain amount of |
15 |
| energy produced from a renewable energy resource. |
16 |
| "Renewable energy resources" includes energy and its |
17 |
| associated renewable energy credit or renewable energy credits |
18 |
| from wind, solar thermal energy, photovoltaic cells and panels, |
19 |
| biodiesel, crops and untreated and unadulterated organic waste |
20 |
| biomass, trees and tree trimmings, hydropower that does not |
21 |
| involve new construction or significant expansion of |
22 |
| hydropower dams, and other alternative sources of |
23 |
| environmentally preferable energy. For purposes of this Act, |
24 |
| landfill gas produced in the State is considered a renewable |
25 |
| energy resource. "Renewable energy resources" does not include |
26 |
| the incineration, burning, or heating of tires, garbage, |
|
|
|
09500SB1987ham001 |
- 9 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| general household, institutional, and commercial waste, |
2 |
| industrial lunchroom or office waste, landscape waste other |
3 |
| than trees and tree trimmings, railroad crossties, utility |
4 |
| poles, and construction or demolition debris, other than |
5 |
| untreated and unadulterated waste wood. |
6 |
| "Revenue bond" means any bond, note, or other evidence of |
7 |
| indebtedness issued by the Authority, the principal and |
8 |
| interest of which is payable solely from revenues or income |
9 |
| derived from any project or activity of the Agency. |
10 |
| "Sequester" means permanent storage of carbon dioxide by |
11 |
| injecting it into a saline aquifer, a depleted gas reservoir, |
12 |
| or an oil reservoir, directly or through an enhanced oil |
13 |
| recovery process that may involve intermediate storage in a |
14 |
| salt dome. |
15 |
| "Substitute natural gas" or "SNG" means a gas manufactured |
16 |
| by gasification of hydrocarbon feedstock, which is |
17 |
| substantially interchangeable in use and distribution with |
18 |
| conventional natural gas. |
19 |
| "Total resource cost test" or "TRC test" means a standard |
20 |
| that is met if, for an investment in energy efficiency or |
21 |
| demand-response measures, the benefit-cost ratio is greater |
22 |
| than one. The benefit-cost ratio is the ratio of the net |
23 |
| present value of the total benefits of the program to the net |
24 |
| present value of the total costs as calculated over the |
25 |
| lifetime of the measures. A total resource cost test compares |
26 |
| the sum of avoided electric utility costs, representing the |
|
|
|
09500SB1987ham001 |
- 10 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| benefits that accrue to the system and the participant in the |
2 |
| delivery of those efficiency measures, to the sum of all |
3 |
| incremental costs of end-use measures that are implemented due |
4 |
| to the program (including both utility and participant |
5 |
| contributions), plus costs to administer, deliver, and |
6 |
| evaluate each demand-side program, to quantify the net savings |
7 |
| obtained by substituting the demand-side program for supply |
8 |
| resources. In calculating avoided costs of power and energy |
9 |
| that an electric utility would otherwise have had to acquire, |
10 |
| reasonable estimates shall be included of financial costs |
11 |
| likely to be imposed by future regulations and legislation on |
12 |
| emissions of greenhouse gases.
|
13 |
| (Source: P.A. 95-481, eff. 8-28-07.) |
14 |
| (20 ILCS 3855/1-75)
|
15 |
| Sec. 1-75. Planning and Procurement Bureau. The Planning |
16 |
| and Procurement Bureau has the following duties and |
17 |
| responsibilities: |
18 |
| (a) The Planning and Procurement Bureau shall each |
19 |
| year, beginning in 2008, develop plans for the procurement |
20 |
| of electricity supply, including electricity generated by |
21 |
| clean coal facilities and facilities that use renewable |
22 |
| resources. The Bureau shall plans and conduct competitive |
23 |
| procurement processes in accordance with the requirements |
24 |
| of Section 16-111.5 of the Public Utilities Act for the |
25 |
| eligible retail customers of electric utilities that on |
|
|
|
09500SB1987ham001 |
- 11 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| December 31, 2005 provided electric service to at least |
2 |
| 100,000 customers in Illinois. For the purposes of this |
3 |
| Section, the term "eligible retail customers" has the same |
4 |
| definition as found in Section 16-111.5(a) of the Public |
5 |
| Utilities Act. |
6 |
| (1) The Agency shall each year, beginning in 2008, |
7 |
| as needed, issue a request for qualifications for |
8 |
| experts or expert consulting firms to develop the |
9 |
| procurement plans in accordance with Section 16-111.5 |
10 |
| of the Public Utilities Act. In order to qualify an |
11 |
| expert or expert consulting firm must have: |
12 |
| (A) direct previous experience assembling |
13 |
| large-scale power supply plans or portfolios for |
14 |
| end-use customers; |
15 |
| (B) an advanced degree in economics, |
16 |
| mathematics, engineering, risk management, or a |
17 |
| related area of study; |
18 |
| (C) 10 years of experience in the electricity |
19 |
| sector, including managing supply risk; |
20 |
| (D) expertise in wholesale electricity market |
21 |
| rules, including those established by the Federal |
22 |
| Energy Regulatory Commission and regional |
23 |
| transmission organizations; |
24 |
| (E) expertise in credit protocols and |
25 |
| familiarity with contract protocols; |
26 |
| (F) adequate resources to perform and fulfill |
|
|
|
09500SB1987ham001 |
- 12 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| the required functions and responsibilities; and |
2 |
| (G) the absence of a conflict of interest and |
3 |
| inappropriate bias for or against potential |
4 |
| bidders or the affected electric utilities. |
5 |
| (2) The Agency shall each year, as needed, issue a |
6 |
| request for qualifications for a procurement |
7 |
| administrator to conduct the competitive procurement |
8 |
| processes in accordance with Section 16-111.5 of the |
9 |
| Public Utilities Act. In order to qualify an expert or |
10 |
| expert consulting firm must have: |
11 |
| (A) direct previous experience administering a |
12 |
| large-scale competitive procurement process; |
13 |
| (B) an advanced degree in economics, |
14 |
| mathematics, engineering, or a related area of |
15 |
| study; |
16 |
| (C) 10 years of experience in the electricity |
17 |
| sector, including risk management experience; |
18 |
| (D) expertise in wholesale electricity market |
19 |
| rules, including those established by the Federal |
20 |
| Energy Regulatory Commission and regional |
21 |
| transmission organizations; |
22 |
| (E) expertise in credit and contract |
23 |
| protocols; |
24 |
| (F) adequate resources to perform and fulfill |
25 |
| the required functions and responsibilities; and |
26 |
| (G) the absence of a conflict of interest and |
|
|
|
09500SB1987ham001 |
- 13 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| inappropriate bias for or against potential |
2 |
| bidders or the affected electric utilities. |
3 |
| (3) The Agency shall provide affected utilities |
4 |
| and other interested parties with the lists of |
5 |
| qualified experts or expert consulting firms |
6 |
| identified through the request for qualifications |
7 |
| processes that are under consideration to develop the |
8 |
| procurement plans and to serve as the procurement |
9 |
| administrator. The Agency shall also provide each |
10 |
| qualified expert's or expert consulting firm's |
11 |
| response to the request for qualifications. All |
12 |
| information provided under this subparagraph shall |
13 |
| also be provided to the Commission. The Agency may |
14 |
| provide by rule for fees associated with supplying the |
15 |
| information to utilities and other interested parties. |
16 |
| These parties shall, within 5 business days, notify the |
17 |
| Agency in writing if they object to any experts or |
18 |
| expert consulting firms on the lists. Objections shall |
19 |
| be based on: |
20 |
| (A) failure to satisfy qualification criteria; |
21 |
| (B) identification of a conflict of interest; |
22 |
| or |
23 |
| (C) evidence of inappropriate bias for or |
24 |
| against potential bidders or the affected |
25 |
| utilities. |
26 |
| The Agency shall remove experts or expert |
|
|
|
09500SB1987ham001 |
- 14 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| consulting firms from the lists within 10 days if there |
2 |
| is a reasonable basis for an objection and provide the |
3 |
| updated lists to the affected utilities and other |
4 |
| interested parties. If the Agency fails to remove an |
5 |
| expert or expert consulting firm from a list, an |
6 |
| objecting party may seek review by the Commission |
7 |
| within 5 days thereafter by filing a petition, and the |
8 |
| Commission shall render a ruling on the petition within |
9 |
| 10 days. There is no right of appeal of the |
10 |
| Commission's ruling. |
11 |
| (4) The Agency shall issue requests for proposals |
12 |
| to the qualified experts or expert consulting firms to |
13 |
| develop a procurement plan for the affected utilities |
14 |
| and to serve as procurement administrator. |
15 |
| (5) The Agency shall select an expert or expert |
16 |
| consulting firm to develop procurement plans based on |
17 |
| the proposals submitted and shall award one-year |
18 |
| contracts to those selected with an option for the |
19 |
| Agency for a one-year renewal. |
20 |
| (6) The Agency shall select an expert or expert |
21 |
| consulting firm, with approval of the Commission, to |
22 |
| serve as procurement administrator based on the |
23 |
| proposals submitted. If the Commission rejects, within |
24 |
| 5 days, the Agency's selection, the Agency shall submit |
25 |
| another recommendation within 3 days based on the |
26 |
| proposals submitted. The Agency shall award a one-year |
|
|
|
09500SB1987ham001 |
- 15 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| contract to the expert or expert consulting firm so |
2 |
| selected with Commission approval with an option for |
3 |
| the Agency for a one-year renewal. |
4 |
| (b) The experts or expert consulting firms retained by |
5 |
| the Agency shall, as appropriate, prepare procurement |
6 |
| plans, and conduct a competitive procurement process as |
7 |
| prescribed in Section 16-111.5 of the Public Utilities Act, |
8 |
| to ensure adequate, reliable, affordable, efficient, and |
9 |
| environmentally sustainable electric service at the lowest |
10 |
| total cost over time, taking into account any benefits of |
11 |
| price stability, for eligible retail customers of electric |
12 |
| utilities that on December 31, 2005 provided electric |
13 |
| service to at least 100,000 customers in the State of |
14 |
| Illinois. |
15 |
| (c) Renewable portfolio standard. |
16 |
| (1) The procurement plans shall include |
17 |
| cost-effective renewable energy resources. A minimum |
18 |
| percentage of each utility's total supply to serve the |
19 |
| load of eligible retail customers, as defined in |
20 |
| Section 16-111.5(a) of the Public Utilities Act, |
21 |
| procured for each of the following years shall be |
22 |
| generated from cost-effective renewable energy |
23 |
| resources: at least 2% by June 1, 2008; at least 4% by |
24 |
| June 1, 2009; at least 5% by June 1, 2010; at least 6% |
25 |
| by June 1, 2011; at least 7% by June 1, 2012; at least |
26 |
| 8% by June 1, 2013; at least 9% by June 1, 2014; at |
|
|
|
09500SB1987ham001 |
- 16 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| least 10% by June 1, 2015; and increasing by at least |
2 |
| 1.5% each year thereafter to at least 25% by June 1, |
3 |
| 2025. To the extent that it is available, at least 75% |
4 |
| of the renewable energy resources used to meet these |
5 |
| standards shall come from wind generation. For |
6 |
| purposes of this Section, "cost-effective" means that |
7 |
| the costs of procuring renewable energy resources do |
8 |
| not cause the limit stated in paragraph (2) of this |
9 |
| subsection (c) to be exceeded and do not exceed |
10 |
| benchmarks based on market prices for renewable |
11 |
| resources in the region, which shall be developed by |
12 |
| the procurement administrator, in consultation with |
13 |
| the Commission staff, Agency staff, and the |
14 |
| procurement monitor and shall be subject to Commission |
15 |
| review and approval . |
16 |
| (2) For purposes of this subsection (c), the |
17 |
| required procurement of cost-effective renewable |
18 |
| energy resources for a particular year shall be |
19 |
| measured as a percentage of the actual amount of |
20 |
| electricity (megawatt-hours) supplied by the electric |
21 |
| utility to eligible retail customers in the planning |
22 |
| year ending immediately prior to the procurement. For |
23 |
| purposes of this subsection (c), the amount per |
24 |
| kilowatthour means the total amount paid for electric |
25 |
| service expressed on a per kilowatthour basis. For |
26 |
| purposes of this subsection (c), the total amount paid |
|
|
|
09500SB1987ham001 |
- 17 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| for electric service includes without limitation |
2 |
| amounts paid for supply, transmission, distribution, |
3 |
| surcharges, and add-on taxes. |
4 |
| Notwithstanding the requirements of this |
5 |
| subsection (c), the total of renewable energy |
6 |
| resources procured pursuant to the procurement plan |
7 |
| for any single year shall be reduced by an amount |
8 |
| necessary to limit the annual estimated average net |
9 |
| increase due to the costs of these resources included |
10 |
| in the amounts paid by eligible retail customers in |
11 |
| connection with electric service to: |
12 |
| (A) in 2008, no more than 0.5% of the amount |
13 |
| paid per kilowatthour by those customers during |
14 |
| the year ending May 31, 2007; |
15 |
| (B) in 2009, the greater of an additional 0.5% |
16 |
| of the amount paid per kilowatthour by those |
17 |
| customers during the year ending May 31, 2008 or 1% |
18 |
| of the amount paid per kilowatthour by those |
19 |
| customers during the year ending May 31, 2007; |
20 |
| (C) in 2010, the greater of an additional 0.5% |
21 |
| of the amount paid per kilowatthour by those |
22 |
| customers during the year ending May 31, 2009 or |
23 |
| 1.5% of the amount paid per kilowatthour by those |
24 |
| customers during the year ending May 31, 2007; |
25 |
| (D) in 2011, the greater of an additional 0.5% |
26 |
| of the amount paid per kilowatthour by those |
|
|
|
09500SB1987ham001 |
- 18 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| customers during the year ending May 31, 2010 or 2% |
2 |
| of the amount paid per kilowatthour by those |
3 |
| customers during the year ending May 31, 2007; and |
4 |
| (E) thereafter, the amount of renewable energy |
5 |
| resources procured pursuant to the procurement |
6 |
| plan for any single year shall be reduced by an |
7 |
| amount necessary to limit the estimated average |
8 |
| net increase due to the cost of these resources |
9 |
| included in the amounts paid by eligible retail |
10 |
| customers in connection with electric service to |
11 |
| no more than the greater of 2.015% of the amount |
12 |
| paid per kilowatthour by those customers during |
13 |
| the year ending May 31, 2007 or the incremental |
14 |
| amount per kilowatthour paid for these resources |
15 |
| in 2011. |
16 |
| No later than June 30, 2011, the Commission shall |
17 |
| review the limitation on the amount of renewable energy |
18 |
| resources procured pursuant to this subsection (c) and |
19 |
| report to the General Assembly its findings as to |
20 |
| whether that limitation unduly constrains the |
21 |
| procurement of cost-effective renewable energy |
22 |
| resources. |
23 |
| (3) Through June 1, 2011, renewable energy |
24 |
| resources shall be counted for the purpose of meeting |
25 |
| the renewable energy standards set forth in paragraph |
26 |
| (1) of this subsection (c) only if they are generated |
|
|
|
09500SB1987ham001 |
- 19 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| from facilities located in the State, provided that |
2 |
| cost-effective renewable energy resources are |
3 |
| available from those facilities. If those |
4 |
| cost-effective resources are not available in |
5 |
| Illinois, they shall be procured in states that adjoin |
6 |
| Illinois and may be counted towards compliance. If |
7 |
| those cost-effective resources are not available in |
8 |
| Illinois or in states that adjoin Illinois, they shall |
9 |
| be purchased elsewhere and shall be counted towards |
10 |
| compliance. After June 1, 2011, cost-effective |
11 |
| renewable energy resources located in Illinois and in |
12 |
| states that adjoin Illinois may be counted towards |
13 |
| compliance with the standards set forth in paragraph |
14 |
| (1) of this subsection (c). If those cost-effective |
15 |
| resources are not available in Illinois or in states |
16 |
| that adjoin Illinois, they shall be purchased |
17 |
| elsewhere and shall be counted towards compliance. |
18 |
| (4) The electric utility shall retire all |
19 |
| renewable energy credits used to comply with the |
20 |
| standard. |
21 |
| (d) Clean coal portfolio standard. |
22 |
| (1) The procurement plans shall include electricity |
23 |
| generated by cost-effective clean coal facilities. At |
24 |
| least 5% of each utility's total supply to serve the load |
25 |
| of eligible retail customers in 2015 and each year |
26 |
| thereafter shall be generated by the initial clean coal |
|
|
|
09500SB1987ham001 |
- 20 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| facility, subject to the limits specified in paragraph (2) |
2 |
| of this subsection (d). It is the goal of the State that by |
3 |
| January 1, 2025, 25% of the electricity used in the State |
4 |
| shall be generated by cost-effective clean coal |
5 |
| facilities. For purposes of this Section, "cost-effective" |
6 |
| means that the costs of procuring electricity generated by |
7 |
| cost-effective clean coal facilities do not cause the limit |
8 |
| stated in paragraph (2) of this subsection (d) to be |
9 |
| exceeded and do not exceed cost-based benchmarks, which |
10 |
| shall be developed to assess all purchases of electricity |
11 |
| generated by clean coal facilities, other than the initial |
12 |
| clean coal facility, by the procurement administrator, in |
13 |
| consultation with the Commission staff, Agency staff, and |
14 |
| the procurement monitor and shall be subject to Commission |
15 |
| review and approval. For purposes of meeting the |
16 |
| requirements of this Section: |
17 |
| (A) A utility need not actually deliver |
18 |
| electricity purchased to comply with this Section to |
19 |
| eligible retail customers, provided that if the |
20 |
| utility claims credit for such purpose, subsequent |
21 |
| purchasers shall not receive any emission credits in |
22 |
| connection with the purchase of such electricity. |
23 |
| Utilities shall maintain adequate records documenting |
24 |
| the contractual disposition of all electricity |
25 |
| purchased to comply with this Section and shall file an |
26 |
| accounting with the load forecast that must be filed |
|
|
|
09500SB1987ham001 |
- 21 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| with the Agency by July 15 of each year, in accordance |
2 |
| with subsection (d) of Section 16-111.5 of the Public |
3 |
| Utilities Act. |
4 |
| (B) A utility shall be deemed to have complied with |
5 |
| this item (1) of the clean coal portfolio standard if, |
6 |
| in any given year, the utility solicits bids for |
7 |
| electricity generated by clean coal facilities but |
8 |
| does not receive acceptable bids for the quantity that |
9 |
| is needed, in combination with any existing contracts, |
10 |
| to comply with the portfolio standard for that year. |
11 |
| (2) For purposes of this subsection (d), the required |
12 |
| procurement of electricity generated by cost-effective |
13 |
| clean coal facilities for a particular year shall be |
14 |
| measured as a percentage of the actual amount of |
15 |
| electricity (megawatt-hours) supplied by the electric |
16 |
| utility to eligible retail customers in the planning year |
17 |
| ending immediately prior to the procurement. For purposes |
18 |
| of this subsection (d) the amount per kilowatt-hour means |
19 |
| the total amount paid for electric service expressed on a |
20 |
| per kilowatt-hour basis. For purposes of this subsection |
21 |
| (d), the total amount paid for electric service includes |
22 |
| without limitation amounts paid for supply, transmission, |
23 |
| distribution, surcharges and add-on taxes. |
24 |
| Notwithstanding the requirements of this subsection |
25 |
| (d), the total amount of electricity generated by clean |
26 |
| coal facilities procured pursuant to the procurement plan |
|
|
|
09500SB1987ham001 |
- 22 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| for any given year shall be reduced by an amount necessary |
2 |
| to limit the annual estimated average net increase due to |
3 |
| the costs of these resources included in the amounts paid |
4 |
| by eligible retail customers in connection with electric |
5 |
| service to: |
6 |
| (i) in 2010, no more than 0.5% of the amount |
7 |
| paid per kilowatthour by those customers during |
8 |
| the year ending May 31, 2009; |
9 |
| (ii) in 2011, the greater of an additional 0.5% |
10 |
| of the amount paid per kilowatthour by those |
11 |
| customers during the year ending May 31, 2010 or 1% |
12 |
| of the amount paid per kilowatthour by those |
13 |
| customers during the year ending May 31, 2009; |
14 |
| (iii) in 2012, the greater of an additional |
15 |
| 0.5% of the amount paid per kilowatthour by those |
16 |
| customers during the year ending May 31, 2011 or |
17 |
| 1.5% of the amount paid per kilowatthour by those |
18 |
| customers during the year ending May 31, 2009; |
19 |
| (iv) in 2013, the greater of an additional 0.5% |
20 |
| of the amount paid per kilowatthour by those |
21 |
| customers during the year ending May 31, 2012 or 2% |
22 |
| of the amount paid per kilowatthour by those |
23 |
| customers during the year ending May 31, 2009; and |
24 |
| (v) thereafter, the amount of electricity |
25 |
| generated by clean coal facilities procured |
26 |
| pursuant to the procurement plan for any single |
|
|
|
09500SB1987ham001 |
- 23 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| year shall be reduced by an amount necessary to |
2 |
| limit the estimated average net increase due to the |
3 |
| cost of these resources included in the amounts |
4 |
| paid by eligible retail customers in connection |
5 |
| with electric service to no more than the greater |
6 |
| of (i) 2.015% of the amount paid per kilowatthour |
7 |
| by those customers during the year ending May 31, |
8 |
| 2009 or (ii) 0.5% of the amount paid per |
9 |
| kilowatt-hour by those customers during the year |
10 |
| ending on the last day of May of the prior year. |
11 |
| These requirements may be altered only as provided |
12 |
| by statute.
No later than June 30, 2015, the |
13 |
| Commission shall review the limitation on the |
14 |
| amount of electricity generated by clean coal |
15 |
| facilities procured pursuant to this subsection |
16 |
| (d) and report to the General Assembly its findings |
17 |
| as to whether that limitation unduly constrains |
18 |
| the procurement of cost-effective clean coal |
19 |
| facilities. |
20 |
| (3) Initial clean coal facility. In order to promote |
21 |
| development of clean coal facilities in Illinois, each |
22 |
| electric utility subject to this Section shall execute a |
23 |
| power purchase agreement to purchase electricity from a |
24 |
| proposed clean coal facility in Illinois (the "initial |
25 |
| clean coal facility") that will have a nameplate capacity |
26 |
| of at least 500 MW when commercial operation commences, |
|
|
|
09500SB1987ham001 |
- 24 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| that has a final Clean Air Act permit on the effective date |
2 |
| of this amendatory Act of the 95th General Assembly, and |
3 |
| that will meet the definition of clean coal facility in |
4 |
| Section 1-10 of this Act when commercial operation |
5 |
| commences. The power purchase agreements with this initial |
6 |
| clean coal facility shall be executed within 60 days after |
7 |
| the later of the effective date of this amendatory Act of |
8 |
| the 95th General Assembly or approval of the agreement by |
9 |
| the Federal Energy Regulatory Commission and shall be |
10 |
| considered pre-existing contracts in the utilities' |
11 |
| procurement plans for eligible retail customers. The |
12 |
| Agency and the Commission shall have authority to inspect |
13 |
| all books and records associated with the initial clean |
14 |
| coal facility during the term of such a power purchase |
15 |
| agreement. A utility's power purchase agreement for the |
16 |
| sale of energy and capacity produced by the initial clean |
17 |
| coal facility shall: |
18 |
| (i) provide for a formula rate, approved |
19 |
| pursuant to paragraph (4) of this subsection (d), |
20 |
| which shall be determined using a cost of service |
21 |
| methodology employing either a level or deferred |
22 |
| capital recovery component, based on a capital |
23 |
| structure consisting of 45% equity and 55% debt, |
24 |
| and a return on equity as may be approved by the |
25 |
| Federal Energy Regulatory Commission, but in any |
26 |
| case not to exceed the lower of 11.5% or the rate |
|
|
|
09500SB1987ham001 |
- 25 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| of return approved by the General Assembly |
2 |
| pursuant to paragraph (4) of this subsection (d); |
3 |
| (ii) provide that all miscellaneous net |
4 |
| revenue, including but not limited to net revenue |
5 |
| from the sale of emission allowances, if any, |
6 |
| substitute natural gas, if any, grants or other |
7 |
| support provided by the State of Illinois or the |
8 |
| United States Government, firm transmission |
9 |
| rights, if any, by-products produced by the |
10 |
| facility, energy or capacity derived from the |
11 |
| facility and not purchased pursuant to paragraph |
12 |
| (3) of this subsection (d) or item (5) of |
13 |
| subsection (d) of Section 16-115 of the Public |
14 |
| Utilities Act, whether generated from the |
15 |
| synthesis gas derived from coal, from substitute |
16 |
| natural gas, or from natural gas, shall be credited |
17 |
| against the revenue requirement for this initial |
18 |
| clean coal facility; |
19 |
| (iii) establish a plant availability target of |
20 |
| 85% starting in the third year of commercial |
21 |
| operation and an incentive structure based on this |
22 |
| target, under which the penalty in any given year |
23 |
| shall not exceed 15% of the amount of return on |
24 |
| equity approved pursuant to paragraph (4) of this |
25 |
| subsection (d) and the bonus shall not exceed 10% |
26 |
| of the amount of return on equity approved pursuant |
|
|
|
09500SB1987ham001 |
- 26 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| to paragraph (4) of this subsection (d); |
2 |
| (iv) require delivery of electricity to the |
3 |
| initial clean coal facility busbar, which shall be |
4 |
| interconnected with transmission facilities |
5 |
| operated by the Midwest Independent System |
6 |
| Operator, the PJM Interconnection or their |
7 |
| successors; |
8 |
| (v) specify a term of no more than 30 years, |
9 |
| commencing on the commercial operation date of the |
10 |
| facility; |
11 |
| (vi) require a utility subject to this Section |
12 |
| to buy from the initial clean coal facility in each |
13 |
| hour an amount of energy equal to all clean coal |
14 |
| energy made available from the initial clean coal |
15 |
| facility during such hour times a fraction, the |
16 |
| numerator of which is such utility's market share |
17 |
| of electricity sold in the utility's service |
18 |
| territory (expressed in kilowatt-hours sold) |
19 |
| during the prior calendar month and the |
20 |
| denominator of which is the total market shares |
21 |
| during the prior month of all utilities and |
22 |
| alternative retail electric suppliers that are |
23 |
| party to a power purchase agreement with the |
24 |
| initial clean coal facility, provided that the |
25 |
| amount purchased by the utility in any year will be |
26 |
| limited by item (2) of this subsection (d); |
|
|
|
09500SB1987ham001 |
- 27 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| (vii) append documentation showing that the |
2 |
| formula rate and contract have been approved by the |
3 |
| Federal Energy Regulatory Commission pursuant to |
4 |
| Section 205 of the Federal Power Act; |
5 |
| (viii) provide that all costs associated with |
6 |
| the initial clean coal project will be |
7 |
| periodically reported to the Federal Energy |
8 |
| Regulatory Commission and to purchasers in |
9 |
| accordance with applicable laws governing |
10 |
| cost-based wholesale power contracts; |
11 |
| (ix) provide that any changes to the terms of |
12 |
| the contract are subject to review under the public |
13 |
| interest standard applied by the Federal Energy |
14 |
| Regulatory Commission pursuant to Sections 205 and |
15 |
| 206 of the Federal Power Act; |
16 |
| (x) conform with customary lender requirements |
17 |
| in power purchase agreements used as the basis for |
18 |
| financing non-utility generators; |
19 |
| (xi) permit the Illinois Power Agency to |
20 |
| assume ownership of the initial clean coal |
21 |
| facility, without monetary consideration and |
22 |
| otherwise on reasonable terms acceptable to the |
23 |
| Agency, if the Agency so requests no less than 3 |
24 |
| years prior to the end of the stated contract term; |
25 |
| (xii) require the owner of the initial clean |
26 |
| coal facility to provide documentation to the |
|
|
|
09500SB1987ham001 |
- 28 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| Commission each year, starting in the facility's |
2 |
| third year of commercial operation, accurately |
3 |
| reporting the quantity of carbon emissions from |
4 |
| the facility that have been captured and |
5 |
| sequestered and report any quantities of carbon |
6 |
| released from the site or sites at which carbon |
7 |
| emissions were sequestered in prior years, based |
8 |
| on continuous monitoring of such sites. If, in any |
9 |
| year after the third year of commercial operation, |
10 |
| the owner of the facility fails to demonstrate that |
11 |
| the initial clean coal facility captured and |
12 |
| sequestered at least 50% of the total carbon |
13 |
| emissions that the facility would otherwise emit |
14 |
| or that sequestration of emissions from prior |
15 |
| years has failed, resulting in the release of |
16 |
| carbon dioxide into the atmosphere, the owner of |
17 |
| the facility must offset excess emissions. Any |
18 |
| such carbon offsets must be permanent, additional, |
19 |
| verifiable, real, located within the state of |
20 |
| Illinois, and legally and practicably enforceable. |
21 |
| The cost of such offsets for the facility that are |
22 |
| not recoverable shall not exceed $15 million in any |
23 |
| given year. No costs of any such purchases of |
24 |
| carbon offsets may be recovered from a utility or |
25 |
| its customers. All carbon offsets purchased for |
26 |
| this purpose and any carbon emission credits |
|
|
|
09500SB1987ham001 |
- 29 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| associated with sequestration of carbon from the |
2 |
| facility must be permanently retired. The initial |
3 |
| clean coal facility shall not forfeit its |
4 |
| designation as a clean coal facility if the |
5 |
| facility fails to fully comply with the applicable |
6 |
| carbon sequestration requirements in any given |
7 |
| year, provided the requisite offsets are |
8 |
| purchased. However, the Attorney General, on |
9 |
| behalf of the People of the State of Illinois, may |
10 |
| specifically enforce the facility's sequestration |
11 |
| requirement and the other terms of this contract |
12 |
| provision; |
13 |
| (xiii) include limits on, and accordingly |
14 |
| provide for modification of, the amount of energy |
15 |
| the utility is required to purchase under the |
16 |
| contract consistent with item (2) of this |
17 |
| subsection (d); |
18 |
| (xiv) limit the utility's obligation to such |
19 |
| amount as the utility is allowed to recover through |
20 |
| tariffs filed with the Commission, provided that |
21 |
| neither the clean coal facility nor the utility |
22 |
| waives any right to assert federal pre-emption or |
23 |
| any other argument in response to a purported |
24 |
| disallowance of recovery costs; |
25 |
| (xv) limit the purchaser's obligation to incur |
26 |
| any liability until such time as the facility is |
|
|
|
09500SB1987ham001 |
- 30 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| generating power and energy and such power and |
2 |
| energy is being delivered to the facility busbar. |
3 |
| (4) Effective date of power purchase agreements for the |
4 |
| initial clean coal facility. Power purchase agreements |
5 |
| with the initial clean coal facility shall not become |
6 |
| effective unless authorizing legislation is enacted to |
7 |
| approve the projected price, stated in cents per |
8 |
| kilowatt-hour, to be charged for electricity generated by |
9 |
| the initial clean coal facility; the projected impact on |
10 |
| residential and small business customers' bills over the |
11 |
| life of the power purchase agreement; and allowable return |
12 |
| on equity for the project, based on a front end engineering |
13 |
| and design study, a facility cost report, and an operating |
14 |
| and maintenance cost quote for the facility, which shall be |
15 |
| prepared as follows: |
16 |
| (A) The facility cost report shall be prepared by |
17 |
| duly licensed engineering and construction firms |
18 |
| detailing the estimated capital costs payable to one or |
19 |
| more contractors or suppliers for the engineering, |
20 |
| procurement and construction of the components |
21 |
| comprising the initial clean coal facility and the |
22 |
| estimated costs of operation and maintenance of the |
23 |
| facility. The facility cost report shall include: |
24 |
| (i) an estimate of the capital cost of the core |
25 |
| plant based on one or more front end engineering |
26 |
| and design studies for the gasification island and |
|
|
|
09500SB1987ham001 |
- 31 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| related facilities. The core plant shall include |
2 |
| all civil, structural, mechanical, electrical, |
3 |
| control, and safety systems. |
4 |
| (ii) an estimate of the capital cost of the |
5 |
| balance of the plant, including any capital costs |
6 |
| associated with sequestration of carbon dioxide |
7 |
| emissions and all interconnects and interfaces |
8 |
| required to operate the facility, such as |
9 |
| transmission of electricity, construction or |
10 |
| backfeed power supply, pipelines to transport |
11 |
| substitute natural gas or carbon dioxide, potable |
12 |
| water supply, natural gas supply, water supply, |
13 |
| water discharge, landfill, access roads, and coal |
14 |
| delivery. |
15 |
| The quoted construction costs shall be expressed |
16 |
| in nominal dollars as of the date that the quote is |
17 |
| prepared and shall include (1) capitalized financing |
18 |
| costs during construction,
(2) taxes, insurance, and |
19 |
| other owners costs, and (3) an assumed escalation in |
20 |
| materials and labor beyond the date as of which the |
21 |
| construction cost quote is expressed. |
22 |
| (B) The front end engineering and design study for |
23 |
| the gasification island and the cost study for the |
24 |
| balance of plant shall include sufficient design work |
25 |
| to permit quantification of major categories of |
26 |
| materials, commodities and labor hours, and receipt of |
|
|
|
09500SB1987ham001 |
- 32 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| quotes from vendors of major equipment required to |
2 |
| construct and operate the clean coal facility. |
3 |
| (C) The facility cost report shall also include an |
4 |
| operating and maintenance cost quote that will provide |
5 |
| the estimated cost of delivered fuel, personnel, |
6 |
| maintenance contracts, chemicals, catalysts, |
7 |
| consumables, spares, and other fixed and variable |
8 |
| operations and maintenance costs. |
9 |
| (a) The delivered fuel cost estimate will be |
10 |
| provided by a recognized third party expert or |
11 |
| experts in the fuel and transportation industries. |
12 |
| (b) The balance of the operating and |
13 |
| maintenance cost quote, excluding delivered fuel |
14 |
| costs will be developed based on the inputs |
15 |
| provided by duly licensed engineering and |
16 |
| construction firms performing the construction |
17 |
| cost quote, potential vendors under long-term |
18 |
| service agreements and plant operating agreements, |
19 |
| or recognized third party plant operator or |
20 |
| operators. |
21 |
| The operating and maintenance cost quote |
22 |
| (including the cost of the front end engineering |
23 |
| and design study) shall be expressed in nominal |
24 |
| dollars as of the date that the quote is prepared |
25 |
| and shall include (1) taxes, insurance, and other |
26 |
| owner's costs, and (2) an assumed escalation in |
|
|
|
09500SB1987ham001 |
- 33 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| materials and labor beyond the date as of which the |
2 |
| operating and maintenance cost quote is expressed. |
3 |
| (D) Amounts paid to third parties unrelated to the |
4 |
| owner or owners of the initial clean coal facility to |
5 |
| prepare the core plant construction cost quote, |
6 |
| including the front end engineering and design study, |
7 |
| and the operating and maintenance cost quote will be |
8 |
| reimbursed through Coal Development Bonds. |
9 |
| (5) Re-powering and retrofitting coal-fired power |
10 |
| plants previously owned by Illinois utilities to qualify as |
11 |
| clean coal facilities. During the 2009 procurement |
12 |
| planning process and thereafter, the Agency and the |
13 |
| Commission shall consider contracts to purchase |
14 |
| electricity generated by power plants that were previously |
15 |
| owned by Illinois utilities and that have been or will be |
16 |
| converted into clean coal facilities, as defined by Section |
17 |
| 1-10 of this Act. The owners of such facilities may propose |
18 |
| long-term power purchase agreements to sell electricity on |
19 |
| a cost of service basis, to utilities and Alternative |
20 |
| Retail Electric Suppliers required, under subsection (d) |
21 |
| of this Section and item (5) of subsection (d) of Section |
22 |
| 16-115 of the Public Utilities Act to comply with the clean |
23 |
| coal portfolio standard. The Agency and the Commission may |
24 |
| approve any such utility contracts that do not exceed |
25 |
| cost-based benchmarks developed by the procurement |
26 |
| administrator, in consultation with the Commission staff, |
|
|
|
09500SB1987ham001 |
- 34 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| Agency staff and the procurement monitor, subject to |
2 |
| Commission review and approval. The Commission shall have |
3 |
| authority to inspect all books and records associated with |
4 |
| these clean coal facilities during the term of any such |
5 |
| contract. |
6 |
| (6) Costs incurred under this subsection (d) or |
7 |
| pursuant to a contract entered into under this subsection |
8 |
| (d) shall be deemed prudently incurred and reasonable in |
9 |
| amount and the electric utility shall be entitled to full |
10 |
| cost recovery pursuant to the tariffs filed with the |
11 |
| Commission. |
12 |
| (e) (d) The draft procurement plans are subject to |
13 |
| public comment, as required by Section 16-111.5 of the |
14 |
| Public Utilities Act. |
15 |
| (f) (e) The Agency shall submit the final procurement |
16 |
| plan to the Commission. The Agency shall revise a |
17 |
| procurement plan if the Commission determines that it does |
18 |
| not meet the standards set forth in Section 16-111.5 of the |
19 |
| Public Utilities Act. |
20 |
| (g) (f) The Agency shall assess fees to each affected |
21 |
| utility to recover the costs incurred in preparation of the |
22 |
| annual procurement plan for the utility. |
23 |
| (h) (g) The Agency shall assess fees to each bidder to |
24 |
| recover the costs incurred in connection with a competitive |
25 |
| procurement process.
|
26 |
| (Source: P.A. 95-481, eff. 8-28-07.) |
|
|
|
09500SB1987ham001 |
- 35 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| (20 ILCS 3855/1-80)
|
2 |
| Sec. 1-80. Resource Development Bureau. The Resource |
3 |
| Development Bureau has the following duties and |
4 |
| responsibilities: |
5 |
| (a) At the Agency's discretion, conduct feasibility |
6 |
| studies on the construction of any facility. Funding for a |
7 |
| study shall come from either: |
8 |
| (i) fees assessed by the Agency on municipal |
9 |
| electric systems, governmental aggregators, unit or |
10 |
| units of local government, or rural electric |
11 |
| cooperatives requesting the feasibility study; or |
12 |
| (ii) an appropriation from the General Assembly. |
13 |
| (b) If the Agency undertakes the construction of a |
14 |
| facility, moneys generated from the sale of revenue bonds |
15 |
| by the Authority for the facility shall be used to |
16 |
| reimburse the source of the money used for the facility's |
17 |
| feasibility study. |
18 |
| (c) The Agency may develop, finance, construct, or |
19 |
| operate electric generation and co-generation facilities |
20 |
| that use indigenous coal or renewable resources, or both, |
21 |
| financed with bonds issued by the Authority on behalf of |
22 |
| the Agency. Any such facility that uses coal must be a |
23 |
| clean coal facility and must be constructed in a location |
24 |
| Preference shall be given to technologies that enable |
25 |
| carbon capture and sites in locations where the geology is |
|
|
|
09500SB1987ham001 |
- 36 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| suitable for carbon sequestration. The Agency may also |
2 |
| develop, finance, construct, or operate a carbon |
3 |
| sequestration facility. |
4 |
| (1) The Agency may enter into contractual |
5 |
| arrangements with private and public entities, |
6 |
| including but not limited to municipal electric |
7 |
| systems, governmental aggregators, and rural electric |
8 |
| cooperatives, to plan, site, construct, improve, |
9 |
| rehabilitate, and operate those electric generation |
10 |
| and co-generation facilities. No contract shall be |
11 |
| entered into by the Agency that would jeopardize the |
12 |
| tax-exempt status of any bond issued in connection with |
13 |
| a project for which the Agency entered into the |
14 |
| contract. |
15 |
| (2) The Agency shall hold at least one public |
16 |
| hearing before entering into any such contractual |
17 |
| arrangements. At least 30-days' notice of the hearing |
18 |
| shall be given by publication once in each week during |
19 |
| that period in 6 newspapers within the State, at least |
20 |
| one of which has a circulation area that includes the |
21 |
| location of the proposed facility. |
22 |
| (3) The first facility that the Agency develops, |
23 |
| finances, or constructs shall be a facility that uses |
24 |
| coal produced in Illinois. The Agency may, however, |
25 |
| also develop, finance, or construct renewable energy |
26 |
| facilities after work on the first facility has |
|
|
|
09500SB1987ham001 |
- 37 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| commenced. |
2 |
| (4) The Agency may not develop, finance, or |
3 |
| construct a nuclear power plant. |
4 |
| (5) The Agency shall assess fees to applicants |
5 |
| seeking to partner with the Agency on projects. |
6 |
| (d) Use of electricity generated by the Agency's |
7 |
| facilities. The Agency may supply electricity produced by |
8 |
| the Agency's facilities to municipal electric systems, |
9 |
| governmental aggregators, or rural electric cooperatives |
10 |
| in Illinois. The electricity shall be supplied at cost. |
11 |
| (1) Contracts to supply power and energy from the |
12 |
| Agency's facilities shall provide for the effectuation |
13 |
| of the policies set forth in this Act. |
14 |
| (2) The contracts shall also provide that, |
15 |
| notwithstanding any provision in the Public Utilities |
16 |
| Act, entities supplied with power and energy from an |
17 |
| Agency facility shall supply the power and energy to |
18 |
| retail customers at the same price paid to purchase |
19 |
| power and energy from the Agency. |
20 |
| (e) Electric utilities shall not be required to purchase |
21 |
| electricity directly or indirectly from facilities developed |
22 |
| or sponsored by the Agency. |
23 |
| (f) The Agency may sell excess capacity and excess energy |
24 |
| into the wholesale electric market at prevailing market rates; |
25 |
| provided, however, the Agency may not sell excess capacity or |
26 |
| excess energy through the procurement process described in |
|
|
|
09500SB1987ham001 |
- 38 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| Section 16-111.5 of the Public Utilities Act. |
2 |
| (g) The Agency shall not directly sell electric power and |
3 |
| energy to retail customers. Nothing in this paragraph shall be |
4 |
| construed to prohibit sales to municipal electric systems, |
5 |
| governmental aggregators, or rural electric cooperatives.
|
6 |
| (Source: P.A. 95-481, eff. 8-28-07.) |
7 |
| Section 1-10. The Public Utilities Act is amended by |
8 |
| changing Sections 9-220, 16-101A, and 16-115 as follows:
|
9 |
| (220 ILCS 5/9-220) (from Ch. 111 2/3, par. 9-220)
|
10 |
| Sec. 9-220. Rate changes based on changes in fuel costs.
|
11 |
| (a) Notwithstanding the provisions of Section 9-201, the
|
12 |
| Commission may authorize the increase or decrease of rates and |
13 |
| charges
based upon changes in the cost of fuel used in the |
14 |
| generation or production
of electric power, changes in the cost |
15 |
| of purchased power, or changes in
the cost of purchased gas |
16 |
| through the application of fuel adjustment
clauses or purchased |
17 |
| gas adjustment clauses. The Commission may also
authorize the |
18 |
| increase or decrease of rates and charges based upon |
19 |
| expenditures
or revenues resulting from the purchase or sale of |
20 |
| emission allowances created
under the federal Clean Air Act |
21 |
| Amendments of 1990,
through such fuel adjustment clauses, as a |
22 |
| cost of fuel. For the purposes of
this paragraph, cost of fuel |
23 |
| used in the generation or production of electric
power shall |
24 |
| include the amount of any fees paid by the utility for the
|
|
|
|
09500SB1987ham001 |
- 39 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| implementation and operation of a process for the |
2 |
| desulfurization of the
flue gas when burning high sulfur coal |
3 |
| at any location within the State of
Illinois irrespective of |
4 |
| the attainment status designation of such
location; but shall |
5 |
| not include transportation costs
of coal
(i) except to the |
6 |
| extent that for contracts entered into on
and after the |
7 |
| effective date of this amendatory Act of 1997,
the cost of the |
8 |
| coal, including transportation costs,
constitutes the lowest |
9 |
| cost for adequate and reliable fuel
supply reasonably available |
10 |
| to the public utility in
comparison to the cost, including |
11 |
| transportation costs, of
other adequate and reliable sources of |
12 |
| fuel supply reasonably
available to the public utility, or (ii)
|
13 |
| except as otherwise provided in the next 3 sentences of this |
14 |
| paragraph.
Such costs of fuel
shall, when requested by a |
15 |
| utility or at the conclusion of the utility's
next general |
16 |
| electric rate proceeding, whichever shall first occur, include
|
17 |
| transportation costs of coal purchased under existing coal |
18 |
| purchase
contracts. For purposes of this paragraph "existing |
19 |
| coal purchase
contracts" means contracts for the purchase of |
20 |
| coal in effect on the
effective date of this amendatory Act of |
21 |
| 1991, as such contracts may
thereafter be amended, but only to |
22 |
| the extent that any such amendment does
not increase the |
23 |
| aggregate quantity of coal to be purchased under such
contract.
|
24 |
| Nothing herein shall authorize an electric utility
to recover |
25 |
| through its fuel adjustment clause any amounts of
|
26 |
| transportation costs of coal that were included in the revenue
|
|
|
|
09500SB1987ham001 |
- 40 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| requirement used to set base rates in its most recent general
|
2 |
| rate proceeding.
Cost shall be based upon uniformly applied |
3 |
| accounting
principles. Annually, the Commission shall initiate |
4 |
| public hearings to
determine whether the clauses reflect actual |
5 |
| costs of fuel, gas, power, or
coal transportation purchased to |
6 |
| determine whether such purchases were
prudent, and to reconcile |
7 |
| any amounts collected with the actual costs of
fuel, power, |
8 |
| gas, or coal transportation prudently purchased. In each such
|
9 |
| proceeding, the burden of proof shall be upon the utility to |
10 |
| establish the
prudence of its cost of fuel, power, gas, or coal
|
11 |
| transportation purchases
and costs.
The Commission shall
issue |
12 |
| its final order in each such annual proceeding for an
electric |
13 |
| utility by December 31 of the year immediately
following the |
14 |
| year to which the proceeding pertains, provided,
that the |
15 |
| Commission shall issue its final order with respect
to such |
16 |
| annual proceeding for the years 1996 and earlier by December |
17 |
| 31, 1998.
|
18 |
| (b) A public utility providing electric service, other than |
19 |
| a public utility
described in subsections (e) or (f) of this |
20 |
| Section, may at
any time during the mandatory transition period |
21 |
| file with the
Commission proposed tariff sheets that eliminate |
22 |
| the public
utility's fuel adjustment clause and adjust the |
23 |
| public
utility's base rate tariffs by the amount necessary for |
24 |
| the
base fuel component of the base rates to recover the public
|
25 |
| utility's average fuel and power supply costs per kilowatt-hour |
26 |
| for the 2
most recent years for which the Commission
has issued |
|
|
|
09500SB1987ham001 |
- 41 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| final orders in annual proceedings pursuant to
subsection (a), |
2 |
| where the average fuel and power supply costs
per kilowatt-hour |
3 |
| shall be calculated as the sum of the public
utility's prudent |
4 |
| and allowable fuel and power supply costs as
found by the |
5 |
| Commission in the 2 proceedings divided by the
public utility's |
6 |
| actual jurisdictional kilowatt-hour sales for
those 2 years. |
7 |
| Notwithstanding any contrary or inconsistent
provisions in |
8 |
| Section 9-201 of this Act, in subsection (a) of
this Section or |
9 |
| in any rules or regulations promulgated by the
Commission |
10 |
| pursuant to subsection (g) of this Section, the
Commission |
11 |
| shall review and shall by order approve, or approve
as |
12 |
| modified, the proposed tariff sheets within 60 days after
the |
13 |
| date of the public utility's filing. The Commission may
modify |
14 |
| the public utility's proposed tariff sheets only to the
extent |
15 |
| the Commission finds necessary to achieve conformance
to the |
16 |
| requirements of this subsection (b). During the 5
years |
17 |
| following the date of the Commission's order, but in any
event |
18 |
| no earlier than January 1, 2007, a public utility whose
fuel |
19 |
| adjustment clause has been eliminated pursuant to this
|
20 |
| subsection shall not file proposed tariff sheets seeking, or
|
21 |
| otherwise petition the Commission for, reinstatement of a fuel
|
22 |
| adjustment clause.
|
23 |
| (c) Notwithstanding any contrary or inconsistent
|
24 |
| provisions in Section 9-201 of this Act, in subsection (a) of
|
25 |
| this Section or in any rules or regulations promulgated by the
|
26 |
| Commission pursuant to subsection (g) of this Section, a
public |
|
|
|
09500SB1987ham001 |
- 42 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| utility providing electric service, other than a public utility
|
2 |
| described
in subsection (e) or (f) of this Section, may at any |
3 |
| time
during the mandatory transition period file with the
|
4 |
| Commission proposed tariff sheets that establish the rate per
|
5 |
| kilowatt-hour to be applied pursuant to the public utility's
|
6 |
| fuel adjustment clause at the average value for such rate
|
7 |
| during the preceding 24 months, provided that such average
rate |
8 |
| results in a credit to customers' bills, without making
any |
9 |
| revisions to the public utility's base rate tariffs. The
|
10 |
| proposed tariff sheets shall establish the fuel adjustment
rate |
11 |
| for a specific time period of at least 3 years but not
more |
12 |
| than 5 years, provided that the terms and conditions for
any |
13 |
| reinstatement earlier than 5 years shall be set forth in
the |
14 |
| proposed tariff sheets and subject to modification or
approval |
15 |
| by the Commission. The Commission shall review and
shall by |
16 |
| order approve the proposed tariff sheets if it finds
that the |
17 |
| requirements of this subsection are met. The
Commission shall |
18 |
| not conduct the annual hearings specified in the
last 3 |
19 |
| sentences of subsection (a) of this Section for the
utility for |
20 |
| the period that the factor established pursuant to
this |
21 |
| subsection is in effect.
|
22 |
| (d) A public utility providing electric service, or a |
23 |
| public utility
providing gas service
may file with the |
24 |
| Commission proposed tariff sheets that
eliminate the public |
25 |
| utility's fuel or purchased gas
adjustment clause and adjust |
26 |
| the public utility's base rate
tariffs to provide for recovery |
|
|
|
09500SB1987ham001 |
- 43 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| of power supply costs or gas
supply costs that would have been |
2 |
| recovered through such
clause; provided, that the provisions of |
3 |
| this subsection (d) shall not be
available to a public utility |
4 |
| described in subsections (e) or (f) of this
Section to |
5 |
| eliminate its fuel adjustment clause. Notwithstanding any |
6 |
| contrary
or inconsistent
provisions in Section 9-201 of this |
7 |
| Act, in subsection (a) of
this Section, or in any rules or |
8 |
| regulations promulgated by
the Commission pursuant to |
9 |
| subsection (g) of this Section, the
Commission shall review and |
10 |
| shall by order approve, or approve
as modified in the |
11 |
| Commission's order, the proposed tariff
sheets within 240 days |
12 |
| after the date of the public utility's
filing. The Commission's |
13 |
| order shall approve rates and
charges that the Commission, |
14 |
| based on information in the
public utility's filing or on the |
15 |
| record if a hearing is held
by the Commission, finds will |
16 |
| recover the reasonable, prudent
and necessary jurisdictional |
17 |
| power supply costs or gas supply
costs incurred or to be |
18 |
| incurred by the public utility during
a 12 month period found |
19 |
| by the Commission to be appropriate
for these purposes, |
20 |
| provided, that such period shall be either
(i) a 12 month |
21 |
| historical period occurring during the 15
months ending on the |
22 |
| date of the public utility's filing, or
(ii) a 12 month future |
23 |
| period ending no later than 15 months
following the date of the |
24 |
| public utility's filing. The public
utility shall include with |
25 |
| its tariff filing information
showing both (1) its actual |
26 |
| jurisdictional power supply costs
or gas supply costs for a 12 |
|
|
|
09500SB1987ham001 |
- 44 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| month historical period
conforming to (i) above and (2) its |
2 |
| projected jurisdictional
power supply costs or gas supply costs |
3 |
| for a future 12 month
period conforming to (ii) above. If the |
4 |
| Commission's order
requires modifications in the tariff sheets |
5 |
| filed by the
public utility, the public utility shall have 7 |
6 |
| days following
the date of the order to notify the Commission |
7 |
| whether the
public utility will implement the modified tariffs |
8 |
| or elect to
continue its fuel or purchased gas adjustment |
9 |
| clause in force
as though no order had been entered. The |
10 |
| Commission's order
shall provide for any reconciliation of |
11 |
| power supply costs or
gas supply costs, as the case may be, and |
12 |
| associated revenues
through the date that the public utility's |
13 |
| fuel or purchased
gas adjustment clause is eliminated. During |
14 |
| the 5 years
following the date of the Commission's order, a |
15 |
| public utility
whose fuel or purchased gas adjustment clause |
16 |
| has been
eliminated pursuant to this subsection shall not file |
17 |
| proposed
tariff sheets seeking, or otherwise petition the |
18 |
| Commission
for, reinstatement or adoption of a fuel or |
19 |
| purchased gas
adjustment clause. Nothing in this subsection (d) |
20 |
| shall be
construed as limiting the Commission's authority to |
21 |
| eliminate
a public utility's fuel adjustment clause or |
22 |
| purchased gas
adjustment clause in accordance with any other |
23 |
| applicable
provisions of this Act.
|
24 |
| (e) Notwithstanding any contrary or inconsistent |
25 |
| provisions in
Section 9-201 of this Act, in subsection (a) of |
26 |
| this Section, or in
any rules promulgated by the Commission |
|
|
|
09500SB1987ham001 |
- 45 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| pursuant
to subsection (g) of this Section, a public utility |
2 |
| providing
electric service to more than 1,000,000 customers in |
3 |
| this State may, within the
first 6 months after the
effective |
4 |
| date of this amendatory Act of 1997, file with the
Commission |
5 |
| proposed tariff sheets that eliminate, effective
January 1, |
6 |
| 1997, the public utility's fuel adjustment clause
without |
7 |
| adjusting its base rates, and such tariff sheets shall be
|
8 |
| effective upon filing. To the extent the application of the |
9 |
| fuel
adjustment clause had resulted in net charges to customers |
10 |
| after
January 1, 1997, the utility shall also file a tariff |
11 |
| sheet that
provides for a refund stated on a per kilowatt-hour |
12 |
| basis of such
charges over a period not to exceed 6 months; |
13 |
| provided
however, that such refund shall not include the |
14 |
| proportional
amounts of taxes paid under the Use Tax Act, |
15 |
| Service Use Tax Act,
Service Occupation Tax Act, and Retailers' |
16 |
| Occupation Tax Act on
fuel used in generation. The Commission |
17 |
| shall issue an order
within 45 days after the date of the |
18 |
| public utility's filing
approving or approving as modified such |
19 |
| tariff sheet. If the fuel
adjustment clause is eliminated |
20 |
| pursuant to this subsection, the
Commission shall not conduct |
21 |
| the annual hearings specified in the
last 3 sentences of |
22 |
| subsection (a) of this Section for the
utility for any period |
23 |
| after December 31, 1996 and prior to any
reinstatement of such |
24 |
| clause. A public utility whose fuel
adjustment clause has been |
25 |
| eliminated pursuant to this subsection
shall not file a |
26 |
| proposed tariff sheet seeking, or otherwise
petition the |
|
|
|
09500SB1987ham001 |
- 46 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| Commission for, reinstatement of the fuel adjustment
clause |
2 |
| prior to January 1, 2007.
|
3 |
| (f) Notwithstanding any contrary or inconsistent |
4 |
| provisions in Section
9-201 of this Act, in subsection (a) of |
5 |
| this Section, or in any rules or
regulations promulgated by the |
6 |
| Commission pursuant to subsection (g) of this
Section, a public |
7 |
| utility providing electric service to more than 500,000
|
8 |
| customers but fewer than 1,000,000 customers in this State may, |
9 |
| within the
first
6 months after the effective date of this |
10 |
| amendatory Act of 1997, file with the
Commission proposed |
11 |
| tariff sheets that eliminate, effective January 1, 1997,
the |
12 |
| public utility's fuel adjustment clause and adjust its base |
13 |
| rates by the
amount necessary for the base fuel component of |
14 |
| the base rates to recover
91% of the public utility's average |
15 |
| fuel and power supply costs for the 2 most
recent years for |
16 |
| which the Commission, as of January 1, 1997, has issued final
|
17 |
| orders in annual proceedings pursuant to subsection (a), where |
18 |
| the average fuel
and power supply costs per kilowatt-hour shall |
19 |
| be calculated as the sum of the
public utility's prudent and |
20 |
| allowable fuel and power supply costs as found by
the |
21 |
| Commission in the 2 proceedings divided by the public utility's |
22 |
| actual
jurisdictional kilowatt-hour sales for those 2 years, |
23 |
| provided, that such
tariff sheets shall be effective upon |
24 |
| filing. To the extent the application of
the fuel adjustment |
25 |
| clause had resulted in net charges to customers after
January |
26 |
| 1, 1997, the utility shall also file a tariff sheet that |
|
|
|
09500SB1987ham001 |
- 47 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| provides for a
refund stated on a per kilowatt-hour basis of |
2 |
| such charges over a period not to
exceed 6 months. Provided |
3 |
| however, that such refund shall not include the
proportional |
4 |
| amounts of taxes paid under the Use Tax Act, Service Use Tax |
5 |
| Act,
Service Occupation Tax Act, and Retailers' Occupation Tax |
6 |
| Act on fuel used in
generation. The Commission shall issue an |
7 |
| order within 45 days after the date
of the public utility's |
8 |
| filing approving or approving as modified such tariff
sheet. If |
9 |
| the fuel adjustment clause is eliminated pursuant to this
|
10 |
| subsection, the Commission shall not conduct the annual |
11 |
| hearings specified in
the last 3 sentences of subsection (a) of |
12 |
| this Section for the utility for any
period after December 31, |
13 |
| 1996 and prior to any reinstatement of such clause.
A public |
14 |
| utility whose fuel adjustment clause has been eliminated |
15 |
| pursuant to
this subsection shall not file a proposed tariff |
16 |
| sheet seeking, or otherwise
petition the Commission for, |
17 |
| reinstatement of the fuel adjustment clause prior
to January 1, |
18 |
| 2007.
|
19 |
| (g) The Commission shall have authority to promulgate rules |
20 |
| and
regulations to
carry out the provisions of this Section.
|
21 |
| (h) Any gas utility may enter into a contract for up to 20 |
22 |
| years of supply with any company for the purchase of substitute |
23 |
| natural gas (SNG) produced from coal through the gasification |
24 |
| process if the company has commenced construction of a coal |
25 |
| gasification facility by July 1, 2010. The cost for the SNG is |
26 |
| reasonable and prudent and recoverable through the purchased |
|
|
|
09500SB1987ham001 |
- 48 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| gas adjustment clause for years one through 10 of the contract |
2 |
| if: (i) the only coal used in the gasification process has high |
3 |
| volatile bituminous rank and greater than 1.7 pounds of sulfur |
4 |
| per million Btu content; (ii) at the time the contract term |
5 |
| commences, the price per million Btu does not exceed $7.95 in |
6 |
| 2008 dollars, adjusted annually based on the change in the |
7 |
| Annual Consumer Price Index for All Urban Consumers for the |
8 |
| Midwest Region as published in April by the United States |
9 |
| Department of Labor, Bureau of Labor Statistics (or a suitable |
10 |
| Consumer Price Index calculation if this Consumer Price Index |
11 |
| is not available) for the previous calendar year; provided that |
12 |
| the price per million Btu shall not exceed $8.95 at any time |
13 |
| during the contract; (iii) the utility's aggregate long-term |
14 |
| supply contracts for the purchase of SNG does not exceed 25% of |
15 |
| the annual system supply requirements of the utility at the |
16 |
| time the contract is entered into and the quantity of SNG |
17 |
| supplied to a utility by any one producer may not exceed 20 |
18 |
| billion cubic feet per year; and (iv) the contract is entered |
19 |
| into within 120 days after the effective date of this |
20 |
| amendatory Act of the 95th General Assembly and terminates no |
21 |
| more than 20 years after the commencement of the commercial |
22 |
| production of synthetic natural gas at the facility. Contracts |
23 |
| greater than 10 years shall provide that if, at any time during |
24 |
| supply years 11 through 20 of the contract, the Commission |
25 |
| determines that the cost for the synthetic natural gas |
26 |
| purchased under the contract during supply years 11 through 20 |
|
|
|
09500SB1987ham001 |
- 49 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| is not reasonable and prudent, then the company shall reimburse |
2 |
| the utility for the difference between the cost deemed |
3 |
| reasonable and prudent by the Commission and the cost imposed |
4 |
| under the contract. All such contracts, regardless of duration, |
5 |
| shall require the owner of any facility supplying SNG under the |
6 |
| contract to provide documentation to the Commission each year, |
7 |
| starting in the facility's third year of commercial operation, |
8 |
| accurately reporting the quantity of carbon dioxide emissions |
9 |
| from the facility that have been captured and sequestered and |
10 |
| reporting any quantities of carbon dioxide released from the |
11 |
| site or sites at which carbon dioxide emissions were |
12 |
| sequestered in prior years, based on continuous monitoring of |
13 |
| those sites. If, in any year, the owner of the facility fails |
14 |
| to demonstrate that the SNG facility captured and sequestered |
15 |
| at least 90% of the total carbon dioxide emissions that the |
16 |
| facility would otherwise emit or that sequestration of |
17 |
| emissions from prior years has failed, resulting in the release |
18 |
| of carbon dioxide into the atmosphere, the owner of the |
19 |
| facility must offset excess emissions. Any such carbon dioxide |
20 |
| offsets must be permanent, additional, verifiable, real, |
21 |
| located within the State of Illinois, and legally and |
22 |
| practicably enforceable. The costs of such offsets that are not |
23 |
| recoverable shall not exceed $30 million in any given year. No |
24 |
| costs of any such purchases of carbon offsets may be recovered |
25 |
| from a utility or its customers. All carbon offsets purchased |
26 |
| for this purpose must be permanently retired. In addition, 50% |
|
|
|
09500SB1987ham001 |
- 50 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| of the carbon dioxide emission credits associated with the |
2 |
| required sequestration of carbon dioxide from the facility must |
3 |
| be permanently retired. An SNG facility operating pursuant to |
4 |
| this subsection (h) shall not forfeit its designation as a |
5 |
| clean coal SNG facility if the facility fails to fully comply |
6 |
| with the applicable carbon sequestration requirements in any |
7 |
| given year, provided the requisite offsets are purchased. |
8 |
| However, the Attorney General, on behalf of the People of the |
9 |
| State of Illinois, may specifically enforce the facility's |
10 |
| sequestration requirements. Any gas utility may enter into a |
11 |
| 20-year supply contract with any company for synthetic natural |
12 |
| gas produced from coal through the gasification process if the |
13 |
| company has commenced construction of a coal gasification |
14 |
| facility by July 1, 2008. The cost for the synthetic natural |
15 |
| gas is reasonable and prudent and recoverable through the |
16 |
| purchased gas adjustment clause for years one through 10 of the |
17 |
| contract if: (i) the only coal used in the gasification process |
18 |
| has high volatile bituminous rank and greater than 1.7 pounds |
19 |
| of sulfur per million Btu content; (ii) at the time the |
20 |
| contract term commences, the price per million Btu does not |
21 |
| exceed $5 in 2004 dollars, adjusted annually based on the |
22 |
| change in the Annual Consumer Price Index for All Urban |
23 |
| Consumers for the Midwest Region as published in April by the |
24 |
| United States Department of Labor, Bureau of Labor Statistics |
25 |
| (or a suitable Consumer Price Index calculation if this |
26 |
| Consumer Price Index is not available) for the previous |
|
|
|
09500SB1987ham001 |
- 51 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| calendar year; provided that the price per million Btu shall |
2 |
| not exceed $5.50 at any time during the contract; (iii) the |
3 |
| utility's aggregate long-term supply contracts for the |
4 |
| purchase of synthetic natural gas produced from coal through |
5 |
| the gasification process does not exceed 25% of the annual |
6 |
| system supply requirements of the utility at the time the |
7 |
| contract is entered into; and (iv) the contract is entered into |
8 |
| within one year after the effective date of this amendatory Act |
9 |
| of the 94th General Assembly and terminates 20 years after the |
10 |
| commencement of the production of synthetic natural gas. The |
11 |
| contract shall provide that if, at any time during years 11 |
12 |
| through 20 of the contract, the Commission determines that the |
13 |
| cost for the synthetic natural gas under the contract is not |
14 |
| reasonable and prudent, then the company shall reimburse the |
15 |
| utility for the difference between the cost deemed reasonable |
16 |
| and prudent by the Commission and the cost imposed under the |
17 |
| contract. |
18 |
| (i) If a gas utility or an affiliate of a gas utility has |
19 |
| an ownership interest in any entity that produces or sells |
20 |
| synthetic natural gas, Article VII of this Act shall apply.
|
21 |
| (Source: P.A. 94-63, eff. 6-21-05.)
|
22 |
| (220 ILCS 5/16-101A)
|
23 |
| Sec. 16-101A. Legislative findings.
|
24 |
| (a) The citizens and businesses of the State of Illinois
|
25 |
| have been well-served by a comprehensive electrical utility
|
|
|
|
09500SB1987ham001 |
- 52 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| system which has provided safe, reliable, and affordable
|
2 |
| service. The electrical utility system in the State of
Illinois |
3 |
| has historically been subject to State and federal
regulation, |
4 |
| aimed at assuring the citizens and businesses of
the State of |
5 |
| safe, reliable, and affordable service, while at
the same time |
6 |
| assuring the utility system of a return on its
investment.
|
7 |
| (b) Competitive forces are affecting the market for
|
8 |
| electricity as a result of recent federal regulatory and
|
9 |
| statutory changes and the activities of other states.
|
10 |
| Competition in the electric services market may create
|
11 |
| opportunities for new products and services for customers and
|
12 |
| lower costs for users of electricity. Long-standing regulatory
|
13 |
| relationships need to be altered to accommodate the
competition |
14 |
| that could fundamentally alter the structure of
the electric |
15 |
| services market.
|
16 |
| (c) With the advent of increasing competition in this
|
17 |
| industry, the State has a continued interest in assuring that
|
18 |
| the safety, reliability, and affordability of electrical power
|
19 |
| is not sacrificed to competitive pressures, and to that end,
|
20 |
| intends to implement safeguards to assure that the industry
|
21 |
| continues to operate the electrical system in a manner that
|
22 |
| will serve the public's interest. Under the existing
regulatory |
23 |
| framework, the industry has been encouraged to
undertake |
24 |
| certain investments in its physical plant and
personnel to |
25 |
| enhance its efficient operation, the cost of
which it has been |
26 |
| permitted to pass on to consumers. The
State has an interest in |
|
|
|
09500SB1987ham001 |
- 53 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| providing the existing utilities a
reasonable opportunity to |
2 |
| obtain a return on certain
investments on which they depended |
3 |
| in undertaking those
commitments in the first instance while, |
4 |
| at the same time, not
permitting new entrants into the industry |
5 |
| to take unreasonable
advantage of the investments made by the |
6 |
| formerly regulated
industry.
|
7 |
| (d) A competitive wholesale and retail market must
benefit |
8 |
| all Illinois citizens. The Illinois Commerce
Commission should |
9 |
| act to promote the development of an
effectively competitive |
10 |
| electricity market that operates
efficiently and is equitable |
11 |
| to all consumers. Consumer
protections must be in place to |
12 |
| ensure that all customers
continue to receive safe, reliable, |
13 |
| affordable, and
environmentally safe electric service.
|
14 |
| (e) All consumers must benefit in an equitable and timely
|
15 |
| fashion from the lower costs for electricity that result from
|
16 |
| retail and wholesale competition and receive sufficient
|
17 |
| information to make informed choices among suppliers and
|
18 |
| services. The use of renewable resources and energy efficiency
|
19 |
| resources should be encouraged in competitive markets.
|
20 |
| (f) The efficiency of electric markets depends both upon |
21 |
| the competitiveness of supply and upon the |
22 |
| price-responsiveness of the demand for service. Therefore, to |
23 |
| ensure the lowest total cost of service and to enhance the |
24 |
| reliability of service, all classes of the electricity |
25 |
| customers of electric utilities should have access to and be |
26 |
| able to voluntarily use real-time pricing and other |
|
|
|
09500SB1987ham001 |
- 54 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| price-response and demand-response mechanisms.
|
2 |
| (g) Including cost-effective renewable resources in a |
3 |
| diverse electricity supply portfolio will reduce long-term |
4 |
| direct and indirect costs to consumers by decreasing |
5 |
| environmental impacts and by avoiding or delaying the need for |
6 |
| new generation, transmission, and distribution infrastructure. |
7 |
| It serves the public interest to allow electric utilities to |
8 |
| recover costs for reasonably and prudently incurred expenses |
9 |
| for electricity generated by renewable resources.
|
10 |
| (h) Including electricity generated by clean coal |
11 |
| facilities, as defined under Section 1-10 of the Illinois Power |
12 |
| Agency Act, in a diverse electricity procurement portfolio will |
13 |
| reduce the need to purchase, directly or indirectly, carbon |
14 |
| dioxide emission credits and will decrease environmental |
15 |
| impacts. It serves the public interest to allow electric |
16 |
| utilities to recover costs for reasonably and prudently |
17 |
| incurred expenses for electricity generated by clean coal |
18 |
| facilities. |
19 |
| (Source: P.A. 94-977, eff. 6-30-06; 95-481, eff. 8-28-07.)
|
20 |
| (220 ILCS 5/16-115)
|
21 |
| Sec. 16-115. Certification of alternative retail
electric |
22 |
| suppliers. |
23 |
| (a) Any alternative retail electric supplier must obtain
a |
24 |
| certificate of service authority from the Commission in
|
25 |
| accordance with this Section before serving any retail
customer |
|
|
|
09500SB1987ham001 |
- 55 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| or other user located in this State. An alternative
retail |
2 |
| electric supplier may request, and the Commission may
grant, a |
3 |
| certificate of service authority for the entire State
or for a |
4 |
| specified geographic area of the State.
|
5 |
| (b) An alternative retail electric supplier seeking a
|
6 |
| certificate of service authority shall file with the
Commission |
7 |
| a verified application containing information
showing that the |
8 |
| applicant meets the requirements of this
Section. The |
9 |
| alternative retail electric supplier shall
publish notice of |
10 |
| its application in the official State
newspaper within 10 days |
11 |
| following the date of its filing. No
later than 45 days after |
12 |
| the application is properly filed
with the Commission, and such |
13 |
| notice is published, the
Commission shall issue its order |
14 |
| granting or denying the
application.
|
15 |
| (c) An application for a certificate of service
authority |
16 |
| shall identify the area or areas in which the
applicant intends |
17 |
| to offer service and the types of services
it intends to offer. |
18 |
| Applicants that seek to serve
residential or small commercial |
19 |
| retail customers within a
geographic area that is smaller than |
20 |
| an electric utility's
service area shall submit evidence |
21 |
| demonstrating that the
designation of this smaller area does |
22 |
| not violate Section 16-115A. An applicant
that seeks to serve |
23 |
| residential or small
commercial retail customers may state in |
24 |
| its application for
certification any limitations that will be |
25 |
| imposed on the
number of customers or maximum load to be |
26 |
| served.
|
|
|
|
09500SB1987ham001 |
- 56 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| (d) The Commission shall grant the application for a
|
2 |
| certificate of service authority if it makes the findings set
|
3 |
| forth in this subsection
based on the verified
application and |
4 |
| such other information as the applicant may
submit:
|
5 |
| (1) That the applicant possesses sufficient
technical, |
6 |
| financial and managerial resources and
abilities to |
7 |
| provide the service for which it seeks a
certificate of |
8 |
| service authority. In determining the
level of technical, |
9 |
| financial and managerial resources
and abilities which the |
10 |
| applicant must demonstrate, the
Commission shall consider |
11 |
| (i) the characteristics,
including the size and financial |
12 |
| sophistication, of the
customers that the applicant seeks |
13 |
| to serve, and (ii)
whether the applicant seeks to provide |
14 |
| electric power and
energy using property, plant and |
15 |
| equipment which it owns,
controls or operates;
|
16 |
| (2) That the applicant will comply with all
applicable |
17 |
| federal, State, regional and industry rules,
policies, |
18 |
| practices and procedures for the use,
operation, and |
19 |
| maintenance of the safety, integrity and
reliability, of |
20 |
| the interconnected electric transmission
system;
|
21 |
| (3) That the applicant will only provide service to
|
22 |
| retail customers in an electric utility's service area
that |
23 |
| are eligible to take delivery services under this
Act;
|
24 |
| (4) That the applicant will comply with such
|
25 |
| informational or reporting requirements as the Commission
|
26 |
| may by rule establish and provide the information required |
|
|
|
09500SB1987ham001 |
- 57 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| by Section 16-112.
Any data related to
contracts for the |
2 |
| purchase and sale of electric power and
energy shall be |
3 |
| made available for review by the Staff of
the Commission on |
4 |
| a confidential and proprietary basis
and only to the extent |
5 |
| and for the purposes which the
Commission determines are |
6 |
| reasonably necessary in order
to carry out the purposes of |
7 |
| this Act;
|
8 |
| (5) That the applicant will supply electricity |
9 |
| generated by renewable energy resources and clean coal |
10 |
| facilities, as defined in Section 1-10 of the Illinois |
11 |
| Power Agency Act, to all of the applicant's Illinois |
12 |
| customers in amounts at least equal to the percentages set |
13 |
| forth in subsections (c) and (d) of Section 1-72 of the |
14 |
| Illinois Power Agency Act. For purposes of this Section:
|
15 |
| (i) The required procurement of electricity |
16 |
| generated by renewable energy resources and clean coal |
17 |
| facilities shall be measured as a percentage of the |
18 |
| actual amount of electricity (megawatt-hours) supplied |
19 |
| by the alternative retail electric supplier in the |
20 |
| prior calendar year, as reported for that year to the |
21 |
| Commission. This purchase obligation applies to all |
22 |
| electricity sold pursuant to retail contracts |
23 |
| executed, extended, or otherwise revised after the |
24 |
| effective date of this amendatory Act, provided the |
25 |
| alternative retail electric supplier submits all |
26 |
| documentation needed by the Commission to determine |
|
|
|
09500SB1987ham001 |
- 58 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| the actual amount of electricity supplied under |
2 |
| contracts that may be excluded under this limitation. |
3 |
| (ii) An alternative retail electric supplier need |
4 |
| not actually deliver electricity purchased to comply |
5 |
| with this Section to its customers, provided that if |
6 |
| the alternative retail electric supplier claims credit |
7 |
| for such purpose, subsequent purchasers shall not |
8 |
| receive any emission credits or renewable energy |
9 |
| credits in connection with the purchase of such |
10 |
| electricity. Alternative retail electric suppliers |
11 |
| shall maintain adequate records documenting the |
12 |
| contractual disposition of all electricity purchased |
13 |
| to comply with this Section and shall file an |
14 |
| accounting in the report which must be filed with the |
15 |
| Commission on August 1 of each year, starting in 2009, |
16 |
| in accordance with subsection (e) of this Section. |
17 |
| (iii) The required procurement of electricity |
18 |
| generated by renewable resources and clean coal |
19 |
| facilities, other than the initial clean coal |
20 |
| facility, shall be limited to the amount of electricity |
21 |
| that can be purchased at a price at or below the |
22 |
| benchmarks approved by the Commission each year in |
23 |
| accordance with item (1) of subsection (c) and items |
24 |
| (1) and (5) of subsection (d) of Section 1-75 of the |
25 |
| Illinois Power Agency Act. |
26 |
| (iv) all alternative retail electric suppliers |
|
|
|
09500SB1987ham001 |
- 59 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| shall execute a power purchase agreement to purchase |
2 |
| electricity from the initial clean coal facility, on |
3 |
| the terms set forth in items (3) and (4) of subsection |
4 |
| (d) of Section 1-75 of the Illinois Power Agency Act, |
5 |
| except that in lieu of the requirements in items |
6 |
| (3)(vi), (xiii), and (xiv) of that subsection (d), the |
7 |
| applicant shall contract to purchase in each hour an |
8 |
| amount of electricity equal to all clean coal energy |
9 |
| made available from the initial clean coal facility to |
10 |
| all alternative retail electric suppliers, multiplied |
11 |
| by a fraction, the numerator of which is the |
12 |
| alternative electricity retail electric supplier's |
13 |
| Illinois market share, expressed in kilowatt-hours |
14 |
| sold during the prior month and the denominator of |
15 |
| which is the total market shares during the prior month |
16 |
| of all alternative retail electric suppliers that are |
17 |
| party to power purchase agreements with the initial |
18 |
| clean coal facility. |
19 |
| (v) if, in any year after the third year of |
20 |
| commercial operation, the owner of the clean coal |
21 |
| facility fails to demonstrate to the Commission that |
22 |
| the initial clean coal facility captured and |
23 |
| sequestered at least 50% of the total carbon emissions |
24 |
| that the facility would otherwise emit or that |
25 |
| sequestration of emissions from prior years has |
26 |
| failed, resulting in the release of carbon into the |
|
|
|
09500SB1987ham001 |
- 60 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| atmosphere, the owner of the facility must offset |
2 |
| excess emissions. Any such carbon offsets must be |
3 |
| permanent, additional, verifiable, real, located |
4 |
| within the State of Illinois, and legally and |
5 |
| practicably enforceable. The costs of any such offsets |
6 |
| that are not recoverable shall not exceed $15 million |
7 |
| in any given year. No costs of any such purchases of |
8 |
| carbon offsets may be recovered from an alternative |
9 |
| retail electric supplier or its customers. All carbon |
10 |
| offsets purchased for this purpose and any carbon |
11 |
| emission credits associated with sequestration of |
12 |
| carbon from the facility must be permanently retired. |
13 |
| The initial clean coal facility shall not forfeit its |
14 |
| designation as a clean coal facility if the facility |
15 |
| fails to fully comply with the applicable carbon |
16 |
| sequestration requirements in any given year, provided |
17 |
| the requisite offsets are purchased. However, the |
18 |
| Attorney General, on behalf of the People of the State |
19 |
| of Illinois, may specifically enforce the facility's |
20 |
| sequestration requirement and the other terms of this |
21 |
| contract provision (Blank) ;
|
22 |
| (6) With respect to an applicant that seeks to serve
|
23 |
| residential or small commercial retail customers, that
the |
24 |
| area to be served by the applicant and any
limitations it |
25 |
| proposes on the number of customers or
maximum amount of |
26 |
| load to be served meet the provisions
of Section 16-115A, |
|
|
|
09500SB1987ham001 |
- 61 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| provided, that the Commission can
extend the time for |
2 |
| considering such a certificate
request by up to 90 days, |
3 |
| and can schedule hearings on
such a request;
|
4 |
| (7) That the applicant meets the requirements of |
5 |
| subsection (a) of Section
16-128; and
|
6 |
| (8) That the applicant will comply with all other
|
7 |
| applicable laws and regulations.
|
8 |
| (d-5) The Commission shall revoke the certification of any |
9 |
| alternative retail electric supplier that fails to execute a |
10 |
| power purchase agreement to purchase electricity from the |
11 |
| initial clean coal facility, as required by item (5) of |
12 |
| subsection (d) of this Section, within 60 days after the later |
13 |
| of the effective date of this amendatory Act or approval of the |
14 |
| agreement by the Federal Energy Regulatory Commission, and |
15 |
| that, on August 1, 2009 and each year thereafter, fails to |
16 |
| demonstrate that the electricity provided to the alternative |
17 |
| retail electricity supplier's Illinois customers during the |
18 |
| previous year was generated by renewable energy resources and |
19 |
| clean coal facilities in amounts at least equal to the |
20 |
| percentages set forth in subsections (c) and (d) of Section |
21 |
| 1-75 of the Illinois Power Agency Act, as limited by subsection |
22 |
| (d)(5)(iii) of this Section. The Commission shall not accept an |
23 |
| application for certification from an alternative retail |
24 |
| electric supplier that has lost certification under this |
25 |
| subsection (d-5), or any corporate affiliate thereof, for at |
26 |
| least one year from the date of revocation. |
|
|
|
09500SB1987ham001 |
- 62 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| (e) A retail customer that owns a cogeneration or |
2 |
| self-generation facility
and that seeks certification only to
|
3 |
| provide electric power and energy from such facility to
retail |
4 |
| customers at separate locations which customers are
both (i) |
5 |
| owned by, or a subsidiary or other corporate
affiliate of, such |
6 |
| applicant and
(ii) eligible for delivery services, shall be |
7 |
| granted a
certificate of service authority upon filing an |
8 |
| application
and notifying the Commission that it has entered |
9 |
| into an
agreement with the relevant electric utilities pursuant |
10 |
| to
Section 16-118.
Provided, however, that if the retail |
11 |
| customer owning such cogeneration or
self-generation facility |
12 |
| would not be charged a transition charge due to the
exemption |
13 |
| provided under subsection (f) of Section 16-108 prior to the
|
14 |
| certification, and the retail customers at separate locations |
15 |
| are taking
delivery services in conjunction with purchasing |
16 |
| power and energy from the
facility, the retail customer on |
17 |
| whose premises the facility is located shall
not thereafter be |
18 |
| required to pay transition charges on the power and energy
that |
19 |
| such retail customer takes from the facility.
|
20 |
| (f) The Commission shall have the authority to
promulgate |
21 |
| rules and regulations to carry out the provisions
of this |
22 |
| Section. On or before May 1, 1999, the Commission
shall adopt a |
23 |
| rule or rules applicable to the certification of
those |
24 |
| alternative retail electric suppliers that seek to serve
only |
25 |
| nonresidential retail customers with maximum electrical
|
26 |
| demands of one megawatt or more which shall provide for (i)
|
|
|
|
09500SB1987ham001 |
- 63 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| expedited and streamlined procedures
for certification of such |
2 |
| alternative
retail electric suppliers and (ii) specific |
3 |
| criteria which,
if met by any such alternative retail electric |
4 |
| supplier, shall
constitute the demonstration of technical, |
5 |
| financial and
managerial resources and abilities to provide |
6 |
| service required
by subsection (d) (1) of this Section, such as |
7 |
| a requirement
to post a bond or letter of credit, from a |
8 |
| responsible surety
or financial institution, of sufficient |
9 |
| size for the nature
and scope of the services to be provided; |
10 |
| demonstration of
adequate insurance for the scope and nature of |
11 |
| the services to
be provided; and experience in providing |
12 |
| similar services in
other jurisdictions.
|
13 |
| (Source: P.A. 95-130, eff. 1-1-08.)
|
14 |
| ARTICLE 5 |
15 |
| Section 5-5. The Public Utilities Act is amended by |
16 |
| changing Section 2-203 as follows:
|
17 |
| (220 ILCS 5/2-203)
|
18 |
| (Section scheduled to be repealed on January 1, 2009)
|
19 |
| Sec. 2-203. Public Utility Fund base maintenance |
20 |
| contribution. Each For each of the years 2003 through 2008, |
21 |
| each electric
utility as defined in Section 16-102 of this Act |
22 |
| providing service to more than
12,500 customers in this State |
23 |
| on January 1, 1995 shall contribute annually a
pro rata share |
|
|
|
09500SB1987ham001 |
- 64 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| of a total amount of $5,500,000 based upon the number of
|
2 |
| kilowatt-hours delivered to retail customers within this State |
3 |
| by each such
electric utility in the 12 months preceding the |
4 |
| year of contribution. On or
before May 1 of each year, the |
5 |
| Illinois Commerce Commission shall determine and
notify the |
6 |
| Illinois Department of Revenue of the pro rata share owed by |
7 |
| each
electric utility based upon information supplied annually |
8 |
| to the Commission. On
or before June 1 of each year, the |
9 |
| Department of Revenue shall send written
notification to each |
10 |
| electric utility of the amount of pro rata share they owe.
|
11 |
| These contributions shall be remitted to the Department of |
12 |
| Revenue no earlier
that July 1 and no later than July 31 of |
13 |
| each year the contribution is due on a
return prescribed and
|
14 |
| furnished by the Department of Revenue showing such information |
15 |
| as the
Department of Revenue may reasonably require. The |
16 |
| Department of Revenue shall
place the funds remitted under this |
17 |
| Section in the Public Utility Fund in the
State treasury. The |
18 |
| funds received pursuant to this Section shall be subject to
|
19 |
| appropriation by the General Assembly. If an electric utility |
20 |
| does
not remit its pro rata share to the Department of Revenue, |
21 |
| the Department of
Revenue must inform the Illinois Commerce |
22 |
| Commission of such failure. The
Illinois Commerce Commission |
23 |
| may then revoke the certification of that electric
utility. |
24 |
| This Section is repealed on January 1, 2014 2009 .
|
25 |
| (Source: P.A. 92-600, eff. 6-28-02.)
|
|
|
|
09500SB1987ham001 |
- 65 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| ARTICLE 10. |
2 |
| Section 10-5. The Public Utilities Act is amended by |
3 |
| changing Section 16-125 as follows:
|
4 |
| (220 ILCS 5/16-125)
|
5 |
| Sec. 16-125. Transmission and distribution reliability
|
6 |
| requirements.
|
7 |
| (a) To assure the reliable delivery of electricity to all
|
8 |
| customers in this State and the effective implementation of
the |
9 |
| provisions of this Article, the Commission shall, within
180 |
10 |
| days of the effective date of this Article, adopt rules
and |
11 |
| regulations for assessing and assuring the reliability of
the |
12 |
| transmission and distribution systems and facilities that
are |
13 |
| under the Commission's jurisdiction.
|
14 |
| (b) These rules and regulations shall require each electric |
15 |
| utility or
alternative retail electric supplier owning, |
16 |
| controlling, or operating
transmission and distribution |
17 |
| facilities and equipment subject to the
Commission's |
18 |
| jurisdiction, referred to in this Section as "jurisdictional
|
19 |
| entities", to adopt and implement procedures for restoring |
20 |
| transmission and
distribution services to customers after |
21 |
| transmission or distribution outages
on a nondiscriminatory |
22 |
| basis without regard to whether a customer has chosen
the |
23 |
| electric utility, an affiliate of the electric utility, or |
24 |
| another entity
as its provider of electric power and energy. |
|
|
|
09500SB1987ham001 |
- 66 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| These rules and regulations
shall also, at a minimum, |
2 |
| specifically require each jurisdictional entity to
submit |
3 |
| annually to the Commission.
|
4 |
| (1) the number and duration of planned and
unplanned |
5 |
| outages during the prior year and their impacts
on |
6 |
| customers;
|
7 |
| (2) outages that were controllable and outages that
|
8 |
| were exacerbated in scope or duration by the condition of
|
9 |
| facilities, equipment or premises or by the actions or
|
10 |
| inactions of operating personnel or agents;
|
11 |
| (3) customer service interruptions that were due
|
12 |
| solely to the actions or inactions of an alternative
retail |
13 |
| electric supplier or a public utility in supplying
power or |
14 |
| energy;
|
15 |
| (4) a detailed report of the age, current
condition, |
16 |
| reliability and performance of the
jurisdictional entity's |
17 |
| existing transmission and
distribution facilities, which |
18 |
| shall include, without
limitation, the following data:
|
19 |
| (i) a summary of the jurisdictional entity's
|
20 |
| outages and voltage variances reportable under the
|
21 |
| Commission's rules;
|
22 |
| (ii) the jurisdictional entity's expenditures
for |
23 |
| transmission construction and maintenance, the
ratio |
24 |
| of those expenditures to the jurisdictional
entity's |
25 |
| transmission investment, and the average
remaining |
26 |
| depreciation lives of the entity's
transmission |
|
|
|
09500SB1987ham001 |
- 67 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| facilities, expressed as a percentage
of total |
2 |
| depreciation lives;
|
3 |
| (iii) the jurisdictional entity's expenditures
for |
4 |
| distribution construction and maintenance, the
ratio |
5 |
| of those expenditures to the jurisdictional
entity's |
6 |
| distribution investment, and the average
remaining |
7 |
| depreciation lives of the entity's
distribution |
8 |
| facilities, expressed as a percentage
of total |
9 |
| depreciation lives;
|
10 |
| (iv) a customer satisfaction survey covering,
|
11 |
| among other areas identified in Commission rules,
|
12 |
| reliability, customer service, and understandability
|
13 |
| of the jurisdictional entity's services and prices;
|
14 |
| and
|
15 |
| (v) the corresponding information, in the same
|
16 |
| format, for the previous 3 years, if available;
|
17 |
| (5) a plan for future investment and reliability
|
18 |
| improvements for the jurisdictional entity's transmission
|
19 |
| and distribution facilities that will ensure continued
|
20 |
| reliable delivery of energy to customers and provide the
|
21 |
| delivery reliability needed for fair and open competition; |
22 |
| and
|
23 |
| (6) a report of the jurisdictional entity's
|
24 |
| implementation of its plan filed pursuant to subparagraph |
25 |
| (5)
for the previous reporting period.
|
26 |
| (c) The Commission rules shall set forth the criteria
that |
|
|
|
09500SB1987ham001 |
- 68 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| will be used to assess each jurisdictional entity's annual |
2 |
| report and
evaluate its reliability performance. Such criteria
|
3 |
| must take into account, at a minimum: the items required to be
|
4 |
| reported in subsection (b); the relevant characteristics of
the |
5 |
| area served; the age and condition of the system's
equipment |
6 |
| and facilities; good engineering practices; the
costs of |
7 |
| potential actions; and the benefits of avoiding the
risks of |
8 |
| service disruption.
|
9 |
| (d) At least every 3 years, beginning in the year
the |
10 |
| Commission issues the rules required by subsection
(a) or the |
11 |
| following year if the rules are issued after June
1, the |
12 |
| Commission shall assess the annual report of each
|
13 |
| jurisdictional entity and evaluate its reliability |
14 |
| performance. The
Commission's evaluation shall
include |
15 |
| specific identification of, and recommendations
concerning, |
16 |
| any potential reliability problems that it has
identified as a |
17 |
| result of its evaluation.
|
18 |
| (e) In the event that more than either (i) 30,000 (or some |
19 |
| other number, but only as provided by statute) of the total |
20 |
| customers or (ii) 0.8% (or some other percentage, but only as |
21 |
| provided by statute) of the total customers , whichever is less, |
22 |
| of an electric
utility are subjected to a continuous power |
23 |
| interruption of
4 hours or more that results in the |
24 |
| transmission of power
at less than 50% of the standard voltage, |
25 |
| or that results in
the total loss of power transmission, the |
26 |
| utility shall be
responsible for compensating customers |
|
|
|
09500SB1987ham001 |
- 69 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| affected by that interruption for 4
hours or more for all
|
2 |
| actual damages, which shall not include consequential
damages, |
3 |
| suffered as a result of the power interruption.
The utility |
4 |
| shall also reimburse the affected municipality,
county, or |
5 |
| other unit of local government in which the power
interruption |
6 |
| has taken place for all
emergency and contingency expenses |
7 |
| incurred by the unit of
local government as a result of the |
8 |
| interruption. A waiver
of the requirements of this subsection |
9 |
| may be granted by the
Commission in instances in which the |
10 |
| utility can show that
the power interruption was a result of |
11 |
| any
one or more of the following causes:
|
12 |
| (1) Unpreventable damage due to weather events or
|
13 |
| conditions.
|
14 |
| (2) Customer tampering.
|
15 |
| (3) Unpreventable damage due to civil or
international |
16 |
| unrest or animals.
|
17 |
| (4) Damage to utility equipment or other actions by a |
18 |
| party other
than the utility, its employees, agents, or
|
19 |
| contractors.
|
20 |
| Loss of revenue and expenses incurred in complying with this
|
21 |
| subsection may not be recovered from ratepayers.
|
22 |
| (f) In the event of a power surge or other fluctuation
that |
23 |
| causes damage and affects more than either (i) 30,000 (or some |
24 |
| other number, but only as provided by statute) of the total |
25 |
| customers or (ii) 0.8% (or some other percentage, but only as |
26 |
| provided by statute) of the total customers, whichever is less, |
|
|
|
09500SB1987ham001 |
- 70 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| the electric utility
shall pay to
affected customers the |
2 |
| replacement value of all goods
damaged as a result of the power |
3 |
| surge or other fluctuation
unless the utility can show that the |
4 |
| power surge or other
fluctuation was due to one or more of the |
5 |
| following causes:
|
6 |
| (1) Unpreventable damage due to weather events or
|
7 |
| conditions.
|
8 |
| (2) Customer tampering.
|
9 |
| (3) Unpreventable damage due to civil or
international |
10 |
| unrest or animals.
|
11 |
| (4) Damage to utility equipment or other actions by a |
12 |
| party other
than the utility, its employees, agents, or
|
13 |
| contractors.
|
14 |
| Loss of revenue and expenses incurred in complying with this
|
15 |
| subsection may not be recovered from ratepayers. Customers with |
16 |
| respect to
whom a waiver has been granted by the Commission |
17 |
| pursuant to subparagraphs
(1)-(4) of subsections (e) and (f) |
18 |
| shall not count toward the either (i) 30,000 (or some other |
19 |
| number, but only as provided by statute) of the total customers |
20 |
| or (ii) 0.8% (or some other percentage, but only as provided by |
21 |
| statute) of the total customers
required therein.
|
22 |
| (g) Whenever an electric utility must perform
planned or |
23 |
| routine maintenance or repairs on its equipment
that will |
24 |
| result in transmission of power at less than 50%
of the |
25 |
| standard voltage, loss of power, or power fluctuation
(as |
26 |
| defined in subsection (f)), the utility shall make
reasonable |
|
|
|
09500SB1987ham001 |
- 71 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| efforts to notify potentially affected customers
no less than |
2 |
| 24 hours in advance of performance of the
repairs or |
3 |
| maintenance.
|
4 |
| (h) Remedies provided for under this Section may be
sought |
5 |
| exclusively through the Illinois Commerce Commission
as |
6 |
| provided under Section 10-109 of this Act. Damages
awarded |
7 |
| under this Section for a power interruption shall be
limited to |
8 |
| actual damages, which shall not include
consequential damages, |
9 |
| and litigation costs. A utility's request for a waiver of this |
10 |
| Section shall be timely if filed no later than 30 days after |
11 |
| the date on which a claim is filed with the Commission seeking |
12 |
| damages or expense reimbursement under this Section. No utility |
13 |
| shall be liable under this Section while a request for waiver |
14 |
| is pending. Damage awards
may not be paid out of utility rate |
15 |
| funds.
|
16 |
| (i) The provisions of this Section shall not in any way
|
17 |
| diminish or replace other civil or administrative remedies
|
18 |
| available to a customer or a class of customers.
|
19 |
| (j) The Commission shall by rule require an electric
|
20 |
| utility to maintain service records detailing
information on |
21 |
| each instance of transmission of power at
less than 50% of the |
22 |
| standard voltage, loss of power, or
power fluctuation (as |
23 |
| defined in subsection (f)), that
affects 10 or more customers. |
24 |
| Occurrences that are
momentary shall not be required to be |
25 |
| recorded or reported.
The service record shall include, for |
26 |
| each occurrence, the
following information:
|
|
|
|
09500SB1987ham001 |
- 72 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| (1) The date.
|
2 |
| (2) The time of occurrence.
|
3 |
| (3) The duration of the incident.
|
4 |
| (4) The number of customers affected.
|
5 |
| (5) A description of the cause.
|
6 |
| (6) The geographic area affected.
|
7 |
| (7) The specific equipment involved in the
fluctuation |
8 |
| or interruption.
|
9 |
| (8) A description of measures taken to restore
service.
|
10 |
| (9) A description of measures taken to remedy the
cause |
11 |
| of the power interruption or fluctuation.
|
12 |
| (10) A description of measures taken to prevent
future |
13 |
| occurrence.
|
14 |
| (11) The amount of remuneration, if any, paid to
|
15 |
| affected customers.
|
16 |
| (12) A statement of whether the fixed charge was
waived |
17 |
| for affected customers.
|
18 |
| Copies of the records containing this information shall
be |
19 |
| available for public inspection at the utility's offices,
and |
20 |
| copies thereof may be obtained upon payment of a fee not
|
21 |
| exceeding the reasonable cost of reproduction. A copy of
each |
22 |
| record shall be filed with the Commission and shall be
|
23 |
| available for public inspection. Copies of the records may
be |
24 |
| obtained upon payment of a fee not exceeding the
reasonable |
25 |
| cost of reproduction.
|
26 |
| (k) The requirements of subsections (e) through (j) of
this |
|
|
|
09500SB1987ham001 |
- 73 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| Section shall apply only to an electric public utility
having |
2 |
| 100,000 1,000,000 or more customers.
|
3 |
| (Source: P.A. 90-561, eff. 12-16-97.)
|
4 |
| ARTICLE 15 |
5 |
| Section 15-5. The Public Utilities Act is amended by |
6 |
| changing Section 2-202 as follows:
|
7 |
| (220 ILCS 5/2-202) (from Ch. 111 2/3, par. 2-202)
|
8 |
| Sec. 2-202. Policy; Public Utility Fund; tax.
|
9 |
| (a) It is declared to be the public policy of this State |
10 |
| that
in order to maintain and foster the effective regulation |
11 |
| of public
utilities under this Act in the interests of the |
12 |
| People of the State of
Illinois and the public utilities as |
13 |
| well, the public utilities subject
to regulation under this Act |
14 |
| and which enjoy the privilege of operating
as public utilities |
15 |
| in this State, shall bear the expense of
administering this Act |
16 |
| by means of a tax on such privilege measured by the
annual |
17 |
| gross revenue of such public utilities in the manner provided |
18 |
| in
this Section. For purposes of this Section, "expense of
|
19 |
| administering this Act" includes any costs incident to studies, |
20 |
| whether
made by the Commission or under contract entered into |
21 |
| by the Commission,
concerning environmental pollution problems |
22 |
| caused or contributed to by
public utilities and the means for |
23 |
| eliminating or abating those
problems. Such proceeds shall be |
|
|
|
09500SB1987ham001 |
- 74 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| deposited in the Public Utility Fund in
the State treasury.
|
2 |
| (b) All of the ordinary and contingent expenses of the
|
3 |
| Commission incident to the administration of this Act shall be |
4 |
| paid out
of the Public Utility Fund except the compensation of |
5 |
| the members of the
Commission which shall be paid from the |
6 |
| General Revenue Fund.
Notwithstanding other provisions of this |
7 |
| Act to the contrary, the
ordinary and contingent expenses of |
8 |
| the Commission incident to the
administration of the Illinois |
9 |
| Commercial Transportation Law may be paid
from appropriations |
10 |
| from the Public Utility Fund through the end of fiscal
year |
11 |
| 1986.
|
12 |
| (c) A tax is imposed upon each public utility subject to |
13 |
| the
provisions of this Act equal to .08% of its gross revenue |
14 |
| for each
calendar year commencing with the calendar year |
15 |
| beginning January 1, 1982,
except that the Commission may, by |
16 |
| rule, establish a different rate no
greater than 0.1%.
For |
17 |
| purposes of this Section, "gross revenue" shall not include
|
18 |
| revenue from the production, transmission, distribution, sale,
|
19 |
| delivery, or furnishing of electricity.
"Gross revenue" shall |
20 |
| not include amounts paid by telecommunications retailers
under |
21 |
| the Telecommunications Infrastructure Maintenance Fee Act.
|
22 |
| (d) Annual gross revenue returns shall be filed in |
23 |
| accordance with
paragraph (1) or (2) of this subsection (d).
|
24 |
| (1) Except as provided in paragraph (2) of this |
25 |
| subsection (d), on
or before January 10 of each year each |
26 |
| public utility
subject to the provisions of this Act shall |
|
|
|
09500SB1987ham001 |
- 75 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| file with the Commission an
estimated annual gross revenue |
2 |
| return containing an estimate of the amount
of its gross |
3 |
| revenue for the calendar year commencing January 1 of said
|
4 |
| year and a statement of the amount of tax due for said |
5 |
| calendar year on the
basis of that estimate. Public |
6 |
| utilities may also file revised returns
containing updated |
7 |
| estimates and updated amounts of tax due during the
|
8 |
| calendar year. These revised returns, if filed, shall form |
9 |
| the basis for
quarterly payments due during the remainder |
10 |
| of the calendar year. In
addition, on or before March 31 of |
11 |
| each year, each public
utility shall
file an amended return |
12 |
| showing the actual amount of gross revenues shown by
the |
13 |
| company's books and records as of December 31 of the |
14 |
| previous year.
Forms and instructions for such estimated, |
15 |
| revised, and amended returns
shall be devised and supplied |
16 |
| by the Commission.
|
17 |
| (2) Beginning with returns due after January 1, 2002, |
18 |
| the
requirements of paragraph (1) of
this subsection (d) |
19 |
| shall not apply to any public utility in any calendar year
|
20 |
| for which the total tax the public utility owes under this |
21 |
| Section is less than
$10,000. For such public utilities |
22 |
| with respect to such years,
the public
utility shall file |
23 |
| with the Commission, on or before March 31
of the
following |
24 |
| year, an annual gross revenue return for the year and a |
25 |
| statement of
the amount of tax due for that year on the |
26 |
| basis of such a return. Forms and
instructions for such |
|
|
|
09500SB1987ham001 |
- 76 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| returns and corrected returns shall be devised and
supplied |
2 |
| by the Commission.
|
3 |
| (e) All returns submitted to the Commission by a public |
4 |
| utility as
provided in this subsection (e) or subsection (d) of |
5 |
| this Section shall contain
or be verified by a written |
6 |
| declaration by an appropriate officer of the public
utility |
7 |
| that the return is made under the penalties of perjury. The |
8 |
| Commission
may audit each such return submitted and may, under |
9 |
| the provisions of Section
5-101 of this Act, take such measures |
10 |
| as are necessary to ascertain the
correctness of the returns |
11 |
| submitted. The Commission has the power to direct
the filing of |
12 |
| a corrected return by any utility which has filed an incorrect
|
13 |
| return and to direct the filing of a return by any utility |
14 |
| which has failed to
submit a return. A taxpayer's signing a |
15 |
| fraudulent return under this Section
is perjury, as defined in |
16 |
| Section 32-2 of the Criminal Code of 1961.
|
17 |
| (f) (1) For all public utilities subject to paragraph (1) |
18 |
| of
subsection (d), at least one quarter of the annual amount of |
19 |
| tax due
under subsection (c) shall be paid to the Commission on |
20 |
| or before the tenth day
of January, April, July, and October of |
21 |
| the calendar year subject to tax. In
the event that an |
22 |
| adjustment in the amount of tax due should be necessary as a
|
23 |
| result of the filing of an amended or corrected return under |
24 |
| subsection (d) or
subsection (e) of this Section, the amount of |
25 |
| any deficiency shall be paid by
the public utility together |
26 |
| with the amended or corrected return and the amount
of any |
|
|
|
09500SB1987ham001 |
- 77 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| excess shall, after the filing of a claim for credit by the |
2 |
| public
utility, be returned to the public utility in the form |
3 |
| of a credit memorandum
in the amount of such excess or be |
4 |
| refunded to the public utility in accordance
with the |
5 |
| provisions of subsection (k) of this Section. However, if such
|
6 |
| deficiency or excess is less than $1, then the public utility |
7 |
| need not pay the
deficiency and may not claim a credit.
|
8 |
| (2) Any public utility subject to paragraph (2) of |
9 |
| subsection (d)
shall pay the amount of tax due under subsection |
10 |
| (c) on or before March
31 next following the end of the |
11 |
| calendar year subject to tax. In the
event that an adjustment |
12 |
| in the amount of tax due should be necessary as a
result of the |
13 |
| filing of a corrected return under subsection (e), the amount
|
14 |
| of any deficiency shall be paid by the public utility at the |
15 |
| time the
corrected return is filed. Any excess tax payment by |
16 |
| the public utility shall
be returned to it after the filing of |
17 |
| a claim for credit, in the form of a
credit memorandum in the |
18 |
| amount of the excess. However, if such deficiency or
excess is |
19 |
| less than $1, the public utility need not pay the deficiency |
20 |
| and may
not claim a credit.
|
21 |
| (g) Each installment or required payment of the tax imposed |
22 |
| by
subsection (c) becomes delinquent at midnight of the date |
23 |
| that it is due.
Failure to make a payment as required by this |
24 |
| Section shall result in the
imposition of a late payment |
25 |
| penalty, an underestimation penalty, or both,
as provided by |
26 |
| this subsection. The late payment penalty shall be the
greater |
|
|
|
09500SB1987ham001 |
- 78 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| of:
|
2 |
| (1) $25 for each month or portion of a month that the |
3 |
| installment or
required payment is unpaid or
|
4 |
| (2) an amount equal to the difference between what |
5 |
| should have been paid
on the due date, based upon the most |
6 |
| recently filed estimated, annual, or
amended return, and |
7 |
| what was
actually paid, times 1%, for each month or portion |
8 |
| of a
month that
the installment or required payment goes |
9 |
| unpaid. This penalty may be
assessed as soon as the |
10 |
| installment or required payment becomes delinquent.
|
11 |
| The underestimation penalty shall apply to those public |
12 |
| utilities
subject to paragraph (1) of subsection (d) and shall |
13 |
| be calculated after
the filing of the amended return. It shall |
14 |
| be imposed if the amount actually
paid on any of the dates |
15 |
| specified in subsection (f) is not equal to at least
one-fourth |
16 |
| of the amount actually due for the year, and shall equal the |
17 |
| greater
of:
|
18 |
| (1) $25 for each month or portion of a month that the |
19 |
| amount due is unpaid
or
|
20 |
| (2) an amount equal to the difference between what |
21 |
| should have been
paid, based on the amended return, and |
22 |
| what was actually paid as of the
date specified in |
23 |
| subsection (f), times a percentage equal to 1/12 of the
sum |
24 |
| of 10% and the percentage most recently established by the |
25 |
| Commission
for interest to be paid on customer deposits |
26 |
| under 83 Ill. Adm. Code
280.70(e)(1), for each month or |
|
|
|
09500SB1987ham001 |
- 79 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| portion of a month that the amount due goes
unpaid, except |
2 |
| that no underestimation penalty shall be assessed if the
|
3 |
| amount actually paid on or before each of the dates |
4 |
| specified in subsection
(f) was
based on an estimate of |
5 |
| gross revenues at least equal to the actual gross
revenues |
6 |
| for the previous year. The Commission may enforce the |
7 |
| collection
of any delinquent installment or payment, or |
8 |
| portion thereof by legal
action or in any other manner by |
9 |
| which the collection of debts due the
State of Illinois may |
10 |
| be enforced under the laws of this State. The
executive |
11 |
| director or his designee may excuse the payment of an
|
12 |
| assessed penalty or a portion of an assessed penalty if he |
13 |
| determines that
enforced collection of the penalty as |
14 |
| assessed
would be unjust.
|
15 |
| (h) All sums collected by the Commission under the |
16 |
| provisions of
this Section shall be paid promptly after the |
17 |
| receipt of the same, accompanied
by a detailed statement |
18 |
| thereof, into the Public Utility Fund in the State
treasury.
|
19 |
| (i) During the month of October of each odd-numbered year |
20 |
| the
Commission shall:
|
21 |
| (1) determine the amount of all moneys deposited in the |
22 |
| Public Utility
Fund during the preceding fiscal biennium |
23 |
| plus the balance, if any, in that
fund at the beginning of |
24 |
| that biennium;
|
25 |
| (2) determine the sum total of the following items: (A) |
26 |
| all moneys
expended or obligated against appropriations |
|
|
|
09500SB1987ham001 |
- 80 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| made from the Public Utility
Fund during the preceding |
2 |
| fiscal biennium, plus (B) the sum of the credit
memoranda |
3 |
| then outstanding against the Public Utility Fund, if any; |
4 |
| and
|
5 |
| (3) determine the amount, if any, by which the sum |
6 |
| determined as
provided in item (1) exceeds the amount |
7 |
| determined as provided in item (2).
|
8 |
| If the amount determined as provided in item (3) of this |
9 |
| subsection exceeds
50% of the previous fiscal year's |
10 |
| appropriation level $5,000,000 , the Commission shall then |
11 |
| compute the
proportionate amount, if
any, which (x) the tax |
12 |
| paid hereunder by each utility during the preceding
biennium, |
13 |
| and (y) the amount paid into the Public Utility Fund during the
|
14 |
| preceding biennium by the Department of Revenue pursuant to |
15 |
| Sections 2-9 and
2-11
of the Electricity Excise Tax Law, bears |
16 |
| to the difference between the amount
determined as
provided in |
17 |
| item (3) of this subsection (i) and 50% of the previous fiscal |
18 |
| year's appropriation level $5,000,000 .
The
Commission
shall |
19 |
| cause the proportionate amount determined with respect to |
20 |
| payments
made under the Electricity Excise Tax Law to be |
21 |
| transferred into the General
Revenue Fund in the State |
22 |
| Treasury, and notify each
public utility that it may file |
23 |
| during the 3 month period after the date of
notification a |
24 |
| claim for credit for the proportionate amount
determined with |
25 |
| respect to payments made hereunder by the public utility.
If |
26 |
| the
proportionate amount is less than $10, no notification will |
|
|
|
09500SB1987ham001 |
- 81 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| be sent by the
Commission, and no right to a claim exists as to |
2 |
| that amount. Upon the
filing of a claim for credit within the |
3 |
| period provided, the Commission
shall issue a credit memorandum |
4 |
| in such amount to such public utility. Any
claim for credit |
5 |
| filed after the period provided for in this Section is void.
|
6 |
| (j) Credit memoranda issued pursuant to subsection (f)
and |
7 |
| credit memoranda issued after notification and filing pursuant |
8 |
| to
subsection (i) may be applied for the 2 year period from the |
9 |
| date of issuance,
against the payment of any amount due during |
10 |
| that period under
the tax imposed by subsection (c), or, |
11 |
| subject to reasonable rule of the
Commission including |
12 |
| requirement of notification, may be assigned to any
other |
13 |
| public utility subject to regulation under this Act. Any |
14 |
| application
of credit memoranda after the period provided for |
15 |
| in this Section is void.
|
16 |
| (k) The chairman or executive director may make refund of |
17 |
| fees, taxes or
other charges whenever he shall determine that |
18 |
| the person or public utility
will not be liable for payment of |
19 |
| such fees, taxes or charges during the
next 24 months and he |
20 |
| determines that the issuance of a credit memorandum
would be |
21 |
| unjust.
|
22 |
| (Source: P.A. 92-11, eff. 6-11-01; 92-22, eff. 6-30-01; 92-526, |
23 |
| eff.
1-1-03.)
|
24 |
| Section 15-10. The Illinois Vehicle Code is amended by |
25 |
| changing Section 18c-1503 as follows:
|
|
|
|
09500SB1987ham001 |
- 82 - |
LRB095 14199 MJR 51793 a |
|
|
1 |
| (625 ILCS 5/18c-1503) (from Ch. 95 1/2, par. 18c-1503)
|
2 |
| Sec. 18c-1503. Legislative Intent. It is the intent of the |
3 |
| Legislature that the exercise of powers
under Sections 18c-1501 |
4 |
| and 18c-1502 of this Chapter shall not
diminish revenues to the |
5 |
| Commission, and that any surplus or
deficit of revenues in the |
6 |
| Transportation Regulatory Fund,
together with any projected |
7 |
| changes in the cost of administering
and enforcing this |
8 |
| Chapter, should be considered in establishing or
adjusting fees |
9 |
| and taxes in succeeding years. The Commission
shall administer |
10 |
| fees and taxes under this Chapter in such a manner
as to insure |
11 |
| that any surplus generated or accumulated in the
Transportation |
12 |
| Regulatory Fund does not exceed 50% of the previous fiscal |
13 |
| year's appropriation the surplus
accumulated in the Motor |
14 |
| Vehicle Fund during fiscal year 1984, and
shall adjust the |
15 |
| level of such fees and taxes to insure
compliance with this |
16 |
| provision.
|
17 |
| (Source: P.A. 84-796.)
|
18 |
| ARTICLE 99 |
19 |
| Section 99-97. Severability. The provisions of this Act are |
20 |
| severable under Section 1.31 of the Statute on Statutes.
|
21 |
| Section 99-99. Effective date. This Act takes effect upon |
22 |
| becoming law.".
|