Sen. Gary Forby
Filed: 5/16/2007
|
|
09500SB1041sam001 |
|
LRB095 05940 AJO 36428 a |
|
|
1 |
| AMENDMENT TO SENATE BILL 1041
|
2 |
| AMENDMENT NO. ______. Amend Senate Bill 1041 by replacing |
3 |
| everything after the enacting clause with the following:
|
4 |
| "Section 5. The Drilling Operations Act is amended by |
5 |
| changing Sections 4 and 6 as follows:
|
6 |
| (765 ILCS 530/4) (from Ch. 96 1/2, par. 9654)
|
7 |
| Sec. 4. Notice.
|
8 |
| (a) Prior to commencement of the drilling of a well, the |
9 |
| operator shall
give a copy of the Act with a written notice to |
10 |
| the surface owner of the operator's intent to commence
drilling |
11 |
| operations.
|
12 |
| (b) The operator shall, for the purpose of giving notice as |
13 |
| herein
required, secure from the assessor's office within 90 |
14 |
| days prior to the
giving of the notice, a certification which |
15 |
| shall identify the person in
whose name the lands on which |
16 |
| drilling operations are to be commenced and who
is assessed at |
|
|
|
09500SB1041sam001 |
- 2 - |
LRB095 05940 AJO 36428 a |
|
|
1 |
| the time the certification is made. The written certification
|
2 |
| made by the assessor of the surface owner shall be conclusive |
3 |
| evidence of
the surface ownership and of the operator's |
4 |
| compliance with the provisions of
this Act.
|
5 |
| (c) The notice required to be given by the operator to the |
6 |
| surface owner
shall identify the following:
|
7 |
| (1) The location of the proposed entry on the
surface |
8 |
| for drilling operations, and the date on or after which |
9 |
| drilling
operations shall be commenced.
|
10 |
| (2) A photocopy of the drilling application to the |
11 |
| Department
of Natural Resources for
the well to be drilled.
|
12 |
| (3) The name, address and telephone number of the |
13 |
| operator.
|
14 |
| (4) An offer to discuss with the surface owner those |
15 |
| matters set forth
in Section 5 hereof prior to commencement |
16 |
| of drilling operations.
|
17 |
| (5) If the surface owner elects to meet the operator, the |
18 |
| surface owner
shall request the operator to schedule a meeting |
19 |
| at a mutually agreed time
and place within the limitations set |
20 |
| forth herein. Failure of the surface
owner to contact the |
21 |
| operator at least 5 days prior to the proposed
commencement of |
22 |
| drilling operations shall be conclusively deemed a waiver
of |
23 |
| the right to meet by the surface owner.
|
24 |
| (6) The meeting shall be scheduled between the hours of |
25 |
| 9:00 in the
morning
and the setting of the sun of the same day |
26 |
| and shall be at least 3 days prior
to commencement of drilling |
|
|
|
09500SB1041sam001 |
- 3 - |
LRB095 05940 AJO 36428 a |
|
|
1 |
| operations. Unless agreed to otherwise, the
place shall be |
2 |
| located within the county in which drilling operations are
to |
3 |
| be commenced where the operator or his agent shall be available |
4 |
| to
discuss with the surface owner or his agent those matters |
5 |
| set forth in Section
5 hereof.
|
6 |
| (7) The notice and a copy of the Act as herein required |
7 |
| shall be given to the surface owner by
either:
|
8 |
| (A) certified mail addressed to the surface owner at |
9 |
| the address shown
in the certification obtained from the |
10 |
| assessor, which shall be postmarked
at least 10 days prior |
11 |
| to the commencement of drilling operations; or
|
12 |
| (B) personal delivery to the surface owner at least 8 |
13 |
| days prior to the
commencement of drilling operations.
|
14 |
| (C) Notice to the surface owner as defined in this Act |
15 |
| shall be deemed
conclusive notice to the record owners of |
16 |
| all interest in the surface.
|
17 |
| (Source: P.A. 89-445, eff. 2-7-96; revised 10-19-05.)
|
18 |
| (765 ILCS 530/6) (from Ch. 96 1/2, par. 9656)
|
19 |
| Sec. 6. Compensation of surface owners for drilling and |
20 |
| producing
operations and duties after cessation of production.
|
21 |
| (A) The surface owner shall be entitled to reasonable |
22 |
| compensation from
the operator for damages as follows: |
23 |
| (1) To
to growing crops, trees, shrubs, fences, roads,
|
24 |
| structures, improvements , personal property, and livestock |
25 |
| thereon caused by the drilling of a new
well. The surface |
|
|
|
09500SB1041sam001 |
- 4 - |
LRB095 05940 AJO 36428 a |
|
|
1 |
| owner shall also be entitled to reasonable compensation
|
2 |
| from the operator for subsequent damages .
|
3 |
| (2) To
to growing crops, trees, shrubs,
fences, roads, |
4 |
| structures, improvements , personal property, and livestock |
5 |
| thereon .
|
6 |
| (3) For the loss of the value of a commercial crop |
7 |
| corresponding to lands taken out of production because of |
8 |
| the use thereof by the operator for roads and production |
9 |
| equipment. Any recovery shall only be applicable if the |
10 |
| area adjacent to said roads and production equipment are |
11 |
| planted and harvested. The value of the crop shall be |
12 |
| calculated by: (i) determining the average per acre yield |
13 |
| for the crop on adjacent lands; (ii) determining the price |
14 |
| received for the sale of the crop on adjacent lands less |
15 |
| the cost of seed planting, chemicals, fertilizers and |
16 |
| harvesting; (iii) determining the acreage of the area |
17 |
| utilized for roads and production equipment; and (iv) |
18 |
| attributing the determined crop yield to the determined |
19 |
| acreage utilized and applying the determined price. The |
20 |
| initial determination of the value of the crop shall be |
21 |
| determined by the surface owner and submitted to the |
22 |
| operator. The surface owner and operator shall mutually |
23 |
| agree as to the value of the crop utilizing the above |
24 |
| referenced formula for the initial crop year and all
caused |
25 |
| by
subsequent crop years
production operations of the |
26 |
| operator thereon . The surface
owner shall also be entitled |
|
|
|
09500SB1041sam001 |
- 5 - |
LRB095 05940 AJO 36428 a |
|
|
1 |
| to reasonable compensation
|
2 |
| (4) For
for all negligent
acts of operator that cause |
3 |
| measurable damage to the productive capacity of
the soil. |
4 |
| In addition, |
5 |
| (A-5) The
the operator shall not utilize any more of the
|
6 |
| surface estate than is reasonably necessary for the |
7 |
| exploration, production
and development of the mineral estate.
|
8 |
| (B) The compensation required pursuant to paragraph (A) |
9 |
| above shall be
paid in any manner mutually agreed upon by the |
10 |
| operator and the surface
owner, but the failure to agree upon, |
11 |
| or make the compensation required,
shall not prevent the |
12 |
| operator from commencement of drilling operations;
provided, |
13 |
| however, that operator shall tender to the surface owner |
14 |
| payment by
check or draft in accordance with the provisions |
15 |
| herein no later than 90 days
after completion of the well. The |
16 |
| surface owner's remedy shall be an
action for compensation in |
17 |
| the circuit court in which the lands or the
greater part |
18 |
| thereof are located on which drilling operations were
|
19 |
| conducted; provided, however, that if operator fails to tender |
20 |
| payment
within the 90-day period or if the tender is not |
21 |
| reasonable, surface owner
shall be entitled to reasonable |
22 |
| compensation as provided herein as well as
attorney's fees.
|
23 |
| If operator relies on a third party appraiser or fair |
24 |
| market value, such
amount shall be conclusively deemed to be |
25 |
| reasonable, and there shall be no
award of attorney's fees.
|
26 |
| (C)
In conjunction with the plugging and abandonment of any |
|
|
|
09500SB1041sam001 |
- 6 - |
LRB095 05940 AJO 36428 a |
|
|
1 |
| well, the
operator shall restore the surface to a condition as |
2 |
| near as practicable to
the condition of the surface prior to |
3 |
| commencement of drilling operations;
provided, however, that |
4 |
| the surface owner and operator may waive this
requirement in |
5 |
| writing, subject to the approval of the Department of Natural
|
6 |
| Resources that the waiver is in accordance with its
rules.
|
7 |
| (D)
Where practicable and absent a written agreement to the |
8 |
| contrary
with the surface owner, all flow lines and other |
9 |
| underground structures
must be buried to a depth not less than |
10 |
| 36 inches from the surface.
|
11 |
| (Source: P.A. 89-445, eff. 2-7-96.)".
|