1 | AN ACT concerning regulation.
| ||||||
2 | Be it enacted by the People of the State of Illinois,
| ||||||
3 | represented in the General Assembly:
| ||||||
4 | Section 5. The Public Utilities Act is amended by adding | ||||||
5 | Section 16-128.1 as follows: | ||||||
6 | (220 ILCS 5/16-128.1 new) | ||||||
7 | Sec. 16-128.1. Electric utility employees; labor | ||||||
8 | displacement or reductions. | ||||||
9 | (a) The General Assembly finds the following: | ||||||
10 | (1) Since the enactment of the Electric Service | ||||||
11 | Customer Choice and Rate Relief Law of 1997, Illinois' | ||||||
12 | electric utilities have reduced their in-house workforce | ||||||
13 | between 20% and 40% through workforce reductions, | ||||||
14 | attrition, and terminations. | ||||||
15 | (2) The reductions have resulted in the electric | ||||||
16 | utilities not maintaining adequate staffing levels to | ||||||
17 | provide safe and reliable electric service to retail | ||||||
18 | customers. | ||||||
19 | (3) It is necessary to prevent additional staffing | ||||||
20 | level reductions in order to protect system reliability and | ||||||
21 | the health and safety of electric utility employees, retail | ||||||
22 | customers, and the public.
| ||||||
23 | (b) For purposes of this Section, "labor displacement or |
| |||||||
| |||||||
1 | reduction" means any decrease in the staffing levels for one or | ||||||
2 | more job classifications, including, but not limited to, | ||||||
3 | layoffs, attrition, voluntary severance, and termination. | ||||||
4 | (c) No electric utility shall be allowed to engage in any | ||||||
5 | labor displacement or reductions below the staffing levels for | ||||||
6 | each job classification in existence on January 1, 2007, unless | ||||||
7 | the electric utility submits a petition to the Commission that | ||||||
8 | sets forth the requested labor displacement or reductions and | ||||||
9 | obtains approval from the Commission in a contested proceeding. | ||||||
10 | The electric utility shall bear the burden of proof and must | ||||||
11 | demonstrate to the Commission based upon clear and convincing | ||||||
12 | evidence that the staffing reductions will not in any manner | ||||||
13 | disrupt or impair the ability of the electric utility to | ||||||
14 | provide safe and reliable electric service that protects and | ||||||
15 | promotes the safety, health, comfort, and convenience of its | ||||||
16 | patrons, employees, and the public. | ||||||
17 | (d) Nothing in this Section shall prevent a labor | ||||||
18 | displacement or reduction due to attrition so long as the | ||||||
19 | electric utility fills the vacancy or vacancies within a | ||||||
20 | reasonable period of time, which in no case shall be greater | ||||||
21 | than 6 months. Nothing in this Section shall prohibit an | ||||||
22 | electric utility from terminating an employee pursuant to the | ||||||
23 | terms of a collective bargaining agreement or other agreement | ||||||
24 | with employees or employee representatives provided that the | ||||||
25 | electric utility shall fill the vacancy or vacancies within a | ||||||
26 | reasonable period of time, which in no case shall be greater |
| |||||||
| |||||||
1 | than 6 months. | ||||||
2 | (e) The employees of an electric utility, including the | ||||||
3 | collective bargaining representative or representatives of the | ||||||
4 | employees, shall have an independent statutory cause of action | ||||||
5 | under State law to file a complaint against an electric utility | ||||||
6 | in circuit court for alleged violations of this Section. | ||||||
7 | The employees of an electric utility, including the | ||||||
8 | collective bargaining representative or representatives of | ||||||
9 | such employees, may file a complaint in the circuit court of | ||||||
10 | Cook, Sangamon, or Madison County or any other circuit court in | ||||||
11 | order to prevent or stop the violation of this Section either | ||||||
12 | by mandamus or injunction. The circuit court shall specify a | ||||||
13 | time, not exceeding 21 days after the service of the copy of | ||||||
14 | the complaint for mandamus or injunction for the filing of any | ||||||
15 | answer, and in the meantime the named defendant shall be | ||||||
16 | restrained from continuing an alleged violation pending a | ||||||
17 | hearing before the court. In the event of default, or after | ||||||
18 | answer, the circuit court shall immediately inquire into the | ||||||
19 | facts and circumstances of the case and enter an appropriate | ||||||
20 | order with respect to the matters in the complaint. An appeal | ||||||
21 | may be taken from the final judgment in the same manner and | ||||||
22 | with the same effect as appeals are taken from judgments of the | ||||||
23 | circuit court in other actions for mandamus or injunction. | ||||||
24 | Nothing in this subsection (e) shall limit the rights of | ||||||
25 | employees of an electric utility, including the collective | ||||||
26 | bargaining representative or representatives of such |
| |||||||
| |||||||
1 | employees, to file a complaint against the electric utility | ||||||
2 | with the Commission for alleged violations of this Section. | ||||||
3 | (f) In any case in which an employee of an electric | ||||||
4 | utility, including the collective bargaining representative or | ||||||
5 | representatives of such employees, demonstrates that an | ||||||
6 | electric utility has violated or is about to violate this | ||||||
7 | Section, the circuit court shall permanently restrain or order | ||||||
8 | the defendant or defendants from continuing the alleged | ||||||
9 | violation and award the party bringing the action the | ||||||
10 | reasonable expenses of the litigation, including all | ||||||
11 | reasonable attorney's fees.
| ||||||
12 | Section 99. Effective date. This Act takes effect upon | ||||||
13 | becoming law.
|