1 | AN ACT concerning construction contracts.
| ||||||
2 | Be it enacted by the People of the State of Illinois,
| ||||||
3 | represented in the General Assembly:
| ||||||
4 | Section 1. Short title. This Act may be cited as the | ||||||
5 | Contractor Prompt Payment Act. | ||||||
6 | Section 5. Definitions. In this Act: | ||||||
7 | (a) "Payment application" means, in accordance with the | ||||||
8 | terms and definitions of
the applicable contract, any invoice, | ||||||
9 | bill or other request for periodic payment, final payment, | ||||||
10 | payment of change order or request for release of retainage | ||||||
11 | from the contractor to the owner. | ||||||
12 | (b) "Construction contract" means a contract or | ||||||
13 | subcontract, entered into after the effective date of this Act, | ||||||
14 | for the design, construction, alteration, improvement, or | ||||||
15 | repair of Illinois real property, except for contracts that | ||||||
16 | require the expenditure of public funds and contracts for the | ||||||
17 | design, construction, alteration, improvement, or repair of | ||||||
18 | single family residences or multiple family residences with 12 | ||||||
19 | or fewer units in a single building. | ||||||
20 | (c) "Contractor" and "subcontractor" shall have the | ||||||
21 | meanings ascribed to them by the Illinois Mechanics Lien Act | ||||||
22 | and cases decided under that Act. |
| |||||||
| |||||||
1 | Section 10. Construction contracts. All construction | ||||||
2 | contracts shall be deemed to provide the following: | ||||||
3 | (1) If a contractor has performed in accordance with the | ||||||
4 | provisions of a construction contract and the payment | ||||||
5 | application has been approved by the owner or the owner's | ||||||
6 | agent, the owner shall pay the amount due to the contractor | ||||||
7 | pursuant to the payment application not more than 15 calendar | ||||||
8 | days after the approval. The payment application shall be | ||||||
9 | deemed approved 25 days after the owner receives it unless the | ||||||
10 | owner provides, before the end of the 25-day period, a written | ||||||
11 | statement of the amount withheld and the reason for withholding | ||||||
12 | payment. If the owner finds that a portion of the work not in | ||||||
13 | accordance with the contract, payment may be withheld for the | ||||||
14 | reasonable value of that portion only. Payment shall be made | ||||||
15 | for any portion of the contract for which the work has been | ||||||
16 | performed in accordance with the provisions of the contract. | ||||||
17 | Instructions or notification from an owner to his or her lender | ||||||
18 | or architect to process or pay a payment application does not | ||||||
19 | constitute approval of the payment application under this Act. | ||||||
20 | (2) If a subcontractor has performed in accordance with the | ||||||
21 | provisions of his or her contract with the contractor or | ||||||
22 | subcontractor and the work has been accepted by the owner, the | ||||||
23 | owner's agent, or the contractor, the contractor shall pay to | ||||||
24 | his or her subcontractor and the subcontractor shall pay to his | ||||||
25 | or her subcontractor, within 15 calendar days of the | ||||||
26 | contractor's receipt from the owner or the subcontractor's |
| |||||||
| |||||||
1 | receipt from the contractor of each periodic payment, final | ||||||
2 | payment, or receipt of retainage monies, the full amount | ||||||
3 | received for the work of the subcontractor based on the work | ||||||
4 | completed or the services rendered under the construction | ||||||
5 | contract. | ||||||
6 | Section 15. Interest; suspension of performance. | ||||||
7 | (a) If a payment due pursuant to the provisions of this Act | ||||||
8 | is not made in a timely manner, the delinquent party shall be | ||||||
9 | liable for the amount of that payment, plus interest at a rate | ||||||
10 | equal to 10% per annum. | ||||||
11 | (b) A contractor or subcontractor who is not paid as | ||||||
12 | required by this Act may, after providing 7 calendar days' | ||||||
13 | written notice to the party failing to make the required | ||||||
14 | payment, suspend performance of a construction contract | ||||||
15 | without penalty for breach of contract, until the payment | ||||||
16 | required pursuant to this Act is made. | ||||||
17 | (c) The interest imposed by this Act shall not be | ||||||
18 | duplicative of the interest charged under the Mechanics Lien | ||||||
19 | Act.
| ||||||
20 | Section 99. Effective date. This Act shall take effect upon | ||||||
21 | becoming law.
|