Amends the Illinois Procurement Code. With respect to construction contracts in excess of $250,000 for which the Capital Development Board is the chief procurement officer, provides that the State shall not be liable for monetary damages due to delay caused by a contractor or subcontractor. Effective immediately.
|
| |
|
|
| FISCAL NOTE ACT MAY APPLY | |
|
|
A BILL FOR
|
|
|
|
|
SB2843 |
|
LRB094 17450 JAM 52745 b |
|
|
1 |
| AN ACT concerning finance.
|
2 |
| Be it enacted by the People of the State of Illinois,
|
3 |
| represented in the General Assembly:
|
4 |
| Section 5. The Illinois Procurement Code is amended by |
5 |
| changing Section 30-30 as follows:
|
6 |
| (30 ILCS 500/30-30)
|
7 |
| Sec. 30-30. Contracts in excess of $250,000.
|
8 |
| (a) For
building construction contracts in excess of
|
9 |
| $250,000, separate specifications shall be prepared for all
|
10 |
| equipment, labor, and materials in
connection with the |
11 |
| following 5 subdivisions of the work to be
performed:
|
12 |
| (1) plumbing;
|
13 |
| (2) heating, piping, refrigeration, and automatic
|
14 |
| temperature control systems,
including the testing and |
15 |
| balancing of those systems;
|
16 |
| (3) ventilating and distribution systems for
|
17 |
| conditioned air, including the testing
and balancing of |
18 |
| those systems;
|
19 |
| (4) electric wiring; and
|
20 |
| (5) general contract work.
|
21 |
| The specifications must be so drawn as to permit separate |
22 |
| and
independent bidding upon
each of the 5 subdivisions of |
23 |
| work. All contracts awarded
for any part thereof shall
award |
24 |
| the 5 subdivisions of work separately to responsible and
|
25 |
| reliable persons, firms, or
corporations engaged in these |
26 |
| classes of work. The contracts, at
the discretion of the
|
27 |
| construction agency, may be assigned to the successful bidder |
28 |
| on
the general contract work or
to the successful bidder on the |
29 |
| subdivision of work designated by
the construction agency |
30 |
| before
the bidding as the prime subdivision of work, provided |
31 |
| that all
payments will be made directly
to the contractors for |
32 |
| the 5 subdivisions of work upon compliance
with the conditions |
|
|
|
SB2843 |
- 2 - |
LRB094 17450 JAM 52745 b |
|
|
1 |
| of the
contract. A contract may be let for one or more |
2 |
| buildings in any
project to the same contractor.
The |
3 |
| specifications shall require, however, that unless the
|
4 |
| buildings are identical, a separate price
shall be submitted |
5 |
| for each building. The contract may be awarded
to the lowest |
6 |
| responsible
bidder for each or all of the buildings included in |
7 |
| the
specifications.
|
8 |
| (b) Until a date 2 years after the effective date of this |
9 |
| amendatory Act of the 93rd General Assembly, the requirements |
10 |
| of this Section , other than subsection (d), do not apply to the |
11 |
| construction of an Emergency Operations Center for the Illinois |
12 |
| Emergency Management Agency if (i) the majority of the funding |
13 |
| for the project is from federal funds, (ii) the bid of the |
14 |
| successful bidder identifies the name of the subcontractor, if |
15 |
| any, and the bid proposal costs for each of the 5 subdivisions |
16 |
| of work set forth in this Section, and (iii) the contract |
17 |
| entered into with the successful bidder provides that no |
18 |
| identified subcontractor may be terminated without the written |
19 |
| consent of the Capital Development Board.
|
20 |
| (c) Until a date 5 years after the effective date of this |
21 |
| amendatory Act of the 94th General Assembly, the requirements |
22 |
| of this Section , other than subsection (d), do not apply to the |
23 |
| Capitol Building HVAC upgrade project if (i) the bid of the |
24 |
| successful bidder identifies the name of the subcontractor, if |
25 |
| any, and the bid proposal costs for each of the 5 subdivisions |
26 |
| of work set forth in this Section, and (ii) the contract |
27 |
| entered into with the successful bidder provides that no |
28 |
| identified subcontractor may be terminated without the written |
29 |
| consent of the Capital Development Board.
|
30 |
| (d) With respect to contracts subject to this Section for |
31 |
| which the Capital Development Board is the chief procurement |
32 |
| officer, the State shall not be liable for monetary damages due |
33 |
| to the delay of a contractor or subcontractor.
|
34 |
| (Source: P.A. 93-1035, eff. 9-10-04; 94-699, eff. 11-29-05.)
|
35 |
| Section 99. Effective date. This Act takes effect upon |