94TH GENERAL ASSEMBLY
State of Illinois
2005 and 2006 SB2742
Introduced 1/20/2006, by Sen. Terry Link SYNOPSIS AS INTRODUCED: |
|
50 ILCS 505/3.5 new |
|
50 ILCS 505/8 new |
|
50 ILCS 505/9 |
from Ch. 85, par. 5609 |
|
Amends the Local Government Prompt Payment Act to authorize construction related contracts covered by the Act to include retainage provisions. Sets forth certain conditions for these retainage provisions. Provides that if the local government entity fails to pay any invoice within 30 days of approval or fails to approve or disapprove the invoice within the time required to approve or disapprove a bill, plus an additional 30 days, the contractor and subcontractors not paid may suspend performance under the construction contract or subcontracts without penalty until the overdue payment or payments are made. Sets forth that interest payments received pursuant this Act shall be disbursed to subcontractors and material suppliers to whom payment has been delayed on a pro rata basis. Authorizes contractors, subcontractors, and material suppliers to recover the interest payable under this Act in any action pursuant to Section 23 of the Mechanics Lien Act or pursuant to the Public Construction Bond Act.
|
| |
|
|
FISCAL NOTE ACT MAY APPLY | |
STATE MANDATES ACT MAY REQUIRE REIMBURSEMENT |
|
|
A BILL FOR
|
|
|
|
|
SB2742 |
|
LRB094 16233 RSP 51477 b |
|
|
1 |
| AN ACT concerning local government.
|
2 |
| Be it enacted by the People of the State of Illinois,
|
3 |
| represented in the General Assembly:
|
4 |
| Section 5. The Local Government Prompt Payment Act is |
5 |
| amended by changing Section 9 and by adding Sections 3.5 and 8 |
6 |
| as follows: |
7 |
| (50 ILCS 505/3.5 new) |
8 |
| Sec. 3.5. Retainage provisions. A construction related |
9 |
| contract covered by this Act may include a provision for |
10 |
| retainage of a portion, not to exceed 10%, of the payment due. |
11 |
| When the gross invoice of the contractor, payable under the |
12 |
| contract, equals or exceeds 50% of the value of the contract, |
13 |
| the retainage withheld thereafter shall not exceed 5% of the |
14 |
| total amounts invoiced. A construction contractor shall not |
15 |
| withhold from any subcontractor a greater percentage of |
16 |
| retainage than is withheld under the prime contract. |
17 |
| (50 ILCS 505/8 new) |
18 |
| Sec. 8. Cessation of work for nonpayment. If the local |
19 |
| government entity fails to pay any invoice within 30 days of |
20 |
| approval or fails to approve or disapprove the invoice within |
21 |
| the time set forth in Section 5 of this Act, plus an additional |
22 |
| 30 days, the contractor and subcontractors not paid may suspend |
23 |
| performance under the construction contract or subcontracts |
24 |
| without penalty until the overdue payment or payments are made.
|
25 |
| (50 ILCS 505/9) (from Ch. 85, par. 5609)
|
26 |
| Sec. 9. When a contractor receives any payment, the |
27 |
| contractor shall
pay each subcontractor and material supplier |
28 |
| in proportion to the work
completed by each subcontractor and |
29 |
| material supplier their application
less any retention. If the |
30 |
| contractor receives less than the full payment
due under the |