Sen. Gary Forby
Filed: 4/11/2005
|
|
09400SB1989sam001 |
|
LRB094 11937 LCB 44630 a |
|
|
1 |
| AMENDMENT TO SENATE BILL 1989
|
2 |
| AMENDMENT NO. ______. Amend Senate Bill 1989 by replacing |
3 |
| everything after the enacting clause with the following:
|
4 |
| "Section 5. The Drilling Operations Act is amended by |
5 |
| changing Section 6 as follows:
|
6 |
| (765 ILCS 530/6) (from Ch. 96 1/2, par. 9656)
|
7 |
| Sec. 6. Compensation of surface owners for drilling and |
8 |
| producing
operations and duties after cessation of production.
|
9 |
| (A) The surface owner shall be entitled to reasonable |
10 |
| compensation from
the operator for damages as follows: |
11 |
| (1) To
to growing crops, trees, shrubs, fences, roads,
|
12 |
| structures, improvements , personal property, and livestock |
13 |
| thereon caused by the drilling of a new
well. The surface |
14 |
| owner shall also be entitled to reasonable compensation
|
15 |
| from the operator for subsequent damages |
16 |
| (2) To
to growing crops, trees, shrubs,
fences, roads, |
17 |
| structures, improvements , personal property, and livestock |
18 |
| thereon .
|
19 |
| (3) For the loss of the value of a commercial crop |
20 |
| corresponding to lands taken out of production because of |
21 |
| the use thereof by the operator for roads and production |
22 |
| equipment. Any recovery shall only be applicable if the |
23 |
| area adjacent to said roads and production equipment are |
24 |
| planted and harvested. The value of the crop shall be |
|
|
|
09400SB1989sam001 |
- 2 - |
LRB094 11937 LCB 44630 a |
|
|
1 |
| calculated by: (i) determining the average per acre yield |
2 |
| for the crop on adjacent lands; (ii) determining the price |
3 |
| received for the sale of the crop on adjacent lands less |
4 |
| the cost of seed planting, chemicals, fertilizers and |
5 |
| harvesting; (iii) determining the acreage of the area |
6 |
| utilized for roads and production equipment; and (iv) |
7 |
| attributing the determined crop yield to the determined |
8 |
| acreage utilized and applying the determined price. The |
9 |
| initial determination of the value of the crop shall be |
10 |
| determined by the surface owner and submitted to the |
11 |
| operator. The surface owner and operator shall mutually |
12 |
| agree as to the value of the crop.
caused by
subsequent |
13 |
| production operations of the operator thereon. The surface
|
14 |
| owner shall also be entitled to reasonable compensation
|
15 |
| (4) For
for all negligent
acts of operator that cause |
16 |
| measurable damage to the productive capacity of
the soil. |
17 |
| In addition, |
18 |
| (B) The
the operator shall not utilize any more of the
|
19 |
| surface estate than is reasonably necessary for the |
20 |
| exploration, production
and development of the mineral estate.
|
21 |
|
|
22 |
| (B) The compensation required pursuant to paragraph (A) |
23 |
| above shall be
paid in any manner mutually agreed upon by the |
24 |
| operator and the surface
owner, but the failure to agree upon, |
25 |
| or make the compensation required,
shall not prevent the |
26 |
| operator from commencement of drilling operations;
provided, |
27 |
| however, that operator shall tender to the surface owner |
28 |
| payment by
check or draft in accordance with the provisions |
29 |
| herein no later than 90 days
after completion of the well. The |
30 |
| surface owner's remedy shall be an
action for compensation in |
31 |
| the circuit court in which the lands or the
greater part |
32 |
| thereof are located on which drilling operations were
|
33 |
| conducted; provided, however, that if operator fails to tender |
34 |
| payment
within the 90-day period or if the tender is not |
|
|
|
09400SB1989sam001 |
- 3 - |
LRB094 11937 LCB 44630 a |
|
|
1 |
| reasonable, surface owner
shall be entitled to reasonable |
2 |
| compensation as provided herein as well as
attorney's fees.
|
3 |
| If operator relies on a third party appraiser or fair |
4 |
| market value, such
amount shall be conclusively deemed to be |
5 |
| reasonable, and there shall be no
award of attorney's fees.
|
6 |
| (C) Blank.
In conjunction with the plugging and abandonment |
7 |
| of any well, the
operator shall restore the surface to a |
8 |
| condition as near as practicable to
the condition of the |
9 |
| surface prior to commencement of drilling operations;
|
10 |
| provided, however, that the surface owner and operator may |
11 |
| waive this
requirement in writing, subject to the approval of |
12 |
| the Department of Natural
Resources that the waiver is in |
13 |
| accordance with its
rules.
|
14 |
| (D) Blank.
Where practicable and absent a written agreement |
15 |
| to the contrary
with the surface owner, all flow lines and |
16 |
| other underground structures
must be buried to a depth not less |
17 |
| than 36 inches from the surface.
|
18 |
| (Source: P.A. 89-445, eff. 2-7-96.)".
|