94TH GENERAL ASSEMBLY
State of Illinois
2005 and 2006 SB1685
Introduced 2/24/2005, by Sen. William R. Haine SYNOPSIS AS INTRODUCED: |
|
|
Amends the Illinois Procurement Code. Requires that construction contracts in excess of $1,000,000 (now, $250,000) must be separately bid in categories for plumbing, heating, ventilation, electrical, and general contract work. Provides that if a bid for one of the categories would be less than $250,000, that category's bid may be combined with the bid for one or more of the other categories of work. Effective immediately.
|
| |
|
|
| FISCAL NOTE ACT MAY APPLY | |
|
|
A BILL FOR
|
|
|
|
|
SB1685 |
|
LRB094 03462 JAM 33465 b |
|
|
1 |
| AN ACT concerning finance.
|
2 |
| Be it enacted by the People of the State of Illinois,
|
3 |
| represented in the General Assembly:
|
4 |
| Section 5. The Illinois Procurement Code is amended by |
5 |
| changing Section 30-30 as follows:
|
6 |
| (30 ILCS 500/30-30)
|
7 |
| Sec. 30-30. Contracts in excess of $1,000,000
$250,000 . For
|
8 |
| building construction contracts in excess of
$1,000,000
|
9 |
| $250,000 , separate specifications shall be prepared for all
|
10 |
| equipment, labor, and materials in
connection with the |
11 |
| following 5 subdivisions of the work to be
performed:
|
12 |
| (1) plumbing;
|
13 |
| (2) heating, piping, refrigeration, and automatic
|
14 |
| temperature control systems,
including the testing and |
15 |
| balancing of those systems;
|
16 |
| (3) ventilating and distribution systems for
|
17 |
| conditioned air, including the testing
and balancing of |
18 |
| those systems;
|
19 |
| (4) electric wiring; and
|
20 |
| (5) general contract work.
|
21 |
| The specifications must be so drawn as to permit separate |
22 |
| and
independent bidding upon
each of the 5 subdivisions of |
23 |
| work. All contracts awarded
for any part thereof shall
award |
24 |
| the 5 subdivisions of work separately to responsible and
|
25 |
| reliable persons, firms, or
corporations engaged in these |
26 |
| classes of work. The contracts, at
the discretion of the
|
27 |
| construction agency, may be assigned to the successful bidder |
28 |
| on
the general contract work or
to the successful bidder on the |
29 |
| subdivision of work designated by
the construction agency |
30 |
| before
the bidding as the prime subdivision of work, provided |
31 |
| that all
payments will be made directly
to the contractors for |
32 |
| the 5 subdivisions of work upon compliance
with the conditions |