Introduced 02/05/04, by Dan Reitz SYNOPSIS AS INTRODUCED: |
|
820 ILCS 130/3 |
from Ch. 48, par. 39s-3 |
|
Amends the Prevailing Wage Act. Provides that workers who perform work specifically designated for installation on a public works project shall be deemed to be employed on public works.
|
| |
|
|
| FISCAL NOTE ACT MAY APPLY | |
|
|
A BILL FOR
|
|
|
|
|
HB5134 |
|
LRB093 20815 DRJ 46739 b |
|
|
1 |
| AN ACT concerning employment.
|
2 |
| Be it enacted by the People of the State of Illinois,
|
3 |
| represented in the General Assembly:
|
4 |
| Section 5. The Prevailing Wage Act is amended by changing |
5 |
| Section 3 as follows:
|
6 |
| (820 ILCS 130/3) (from Ch. 48, par. 39s-3)
|
7 |
| Sec. 3. Not less than the general prevailing rate of hourly |
8 |
| wages for
work of a similar character on public works in the |
9 |
| locality in which the
work is performed, and not less than the |
10 |
| general prevailing rate of
hourly wages for legal holiday and |
11 |
| overtime work, shall be paid to all
laborers, workers and |
12 |
| mechanics employed by or on behalf of any public
body engaged |
13 |
| in the construction of public works.
Only such laborers, |
14 |
| workers and mechanics as are
directly employed by contractors |
15 |
| or subcontractors in actual
construction work on the site of |
16 |
| the building or construction job, or who perform work |
17 |
| specifically designated for installation on a public works |
18 |
| project, and
laborers, workers and mechanics engaged in the |
19 |
| transportation of
materials and equipment to or from the site, |
20 |
| but not including the
transportation by the sellers and |
21 |
| suppliers or the manufacture or
processing of materials or |
22 |
| equipment, in the execution of any contract
or contracts for |
23 |
| public works with any public body shall be deemed to be
|
24 |
| employed upon public works. The wage for a tradesman performing |
25 |
| maintenance
is equivalent to that of a tradesman engaged in |
26 |
| construction.
|
27 |
| (Source: P.A. 93-15, eff. 6-11-03; 93-16, eff. 1-1-04.)
|