|
|
|
93RD GENERAL ASSEMBLY
State of Illinois
2003 and 2004 HB4619
Introduced 02/04/04, by Jay C. Hoffman SYNOPSIS AS INTRODUCED: |
|
|
Creates the Design-Build Procurement Act. Provides procedures by which certain State agencies may solicit design-build proposals. Requires that each request for design-build proposals include scope and performance criteria. Requires State agencies to establish a committee to evaluate and select design-build firms. Sets forth the procedures for selecting a design-build firm. Sets forth the procedures by which design-build firms may submit proposals. Sets forth the procedures by which a State agency may award a design-build contract. Makes other provisions concerning design-build contracts. Effective immediately.
|
|
|
|
|
| FISCAL NOTE ACT MAY APPLY | |
|
|
A BILL FOR
|
|
|
|
|
HB4619 |
|
LRB093 20721 BDD 46609 b |
|
|
1 |
| AN ACT concerning procurement.
|
2 |
| Be it enacted by the People of the State of |
3 |
| Illinois,represented in the General Assembly:
|
4 |
| Section 1. Short title. This Act may be cited as |
5 |
| the Design-Build
Procurement Act.
|
6 |
| Section 5. Legislative policy. It is the intent of the |
7 |
| General Assembly
that
State construction agencies be allowed to |
8 |
| use the design-build delivery method
for public
projects if it |
9 |
| is shown to be in the State's best interest for that particular
|
10 |
| project. It shall be the policy of State construction agencies |
11 |
| in the
procurement of
design-build services to publicly |
12 |
| announce all requirements for design-build
services and to |
13 |
| procure these services on the basis of demonstrated competence
|
14 |
| and qualifications and with due regard for the principles of |
15 |
| competitive
selection.
|
16 |
| A State construction agency shall, prior to issuing |
17 |
| requests for proposals,
promulgate
and publish procedures for |
18 |
| the solicitation and award of contracts pursuant to
this Act.
|
19 |
| A State construction agency shall, for each public project |
20 |
| or projects
permitted under
this Act, make a written |
21 |
| determination, including a description as to the
particular |
22 |
| advantages of the design-build procurement method, that it is |
23 |
| in the
best interests of this State to enter into a |
24 |
| design-build contract for the
project or projects. In making |
25 |
| that determination, the following factors shall
be considered:
|
26 |
| (1) The probability that the design-build procurement |
27 |
| method will be in
the best interests of the State by |
28 |
| providing a material savings of time or
cost over the |
29 |
| design-bid-build or other delivery system.
|
30 |
| (2) The type and size of the project and its |
31 |
| suitability to the
design-build procurement method.
|
32 |
| (3) The ability of the State construction agency to |
|
|
|
HB4619 |
- 2 - |
LRB093 20721 BDD 46609 b |
|
|
1 |
| define and provide
comprehensive
scope and performance |
2 |
| criteria for the project.
|
3 |
| The State construction agency shall within 15 days after |
4 |
| the initial
determination provide an advisory copy to the |
5 |
| Procurement Policy Board and
maintain the full record of |
6 |
| determination for 5 years.
|
7 |
| Section 10. Definitions. As used in this Act:
|
8 |
| "State construction agency" means and includes
those |
9 |
| agencies as defined in Section 1-15.25 of the Illinois |
10 |
| Procurement Code,
as amended, but does not mean the Illinois |
11 |
| Department of Transportation and the
Illinois State Toll |
12 |
| Highway Authority.
|
13 |
| "Delivery system" means the design and construction |
14 |
| approach used to develop
and construct a project.
|
15 |
| "Design-bid-build" means the traditional delivery system |
16 |
| used on public
projects in this State that incorporates the |
17 |
| Architectural, Engineering, and
Land Surveying Qualification |
18 |
| Based Selection Act (30 ILCS 535/) and the
principles of |
19 |
| competitive selection in the Illinois Procurement Code (30 ILCS
|
20 |
| 500/).
|
21 |
| "Design-build" means a delivery system that provides |
22 |
| responsibility within a
single contract for the furnishing of |
23 |
| architecture, engineering, land surveying
and related services |
24 |
| as required, and the labor, materials, equipment, and
other |
25 |
| construction services for the project.
|
26 |
| "Design-build contract" means a contract for a public |
27 |
| project under this Act
between a State construction agency and |
28 |
| a design-build entity to furnish
architecture,
engineering, |
29 |
| land surveying, and related services as required, and to |
30 |
| furnish
the labor, materials, equipment, and other |
31 |
| construction services for the
project. The design-build |
32 |
| contract may be conditioned upon subsequent
refinements in |
33 |
| scope and price and may allow the State construction agency to
|
34 |
| make
modifications in the project scope without invalidating |
35 |
| the design-build
contract.
|
|
|
|
HB4619 |
- 3 - |
LRB093 20721 BDD 46609 b |
|
|
1 |
| "Design-build entity" means any individual, sole |
2 |
| proprietorship, firm,
partnership, joint venture, corporation, |
3 |
| professional corporation, or other
entity that proposes to |
4 |
| design and construct any public project under this Act.
A |
5 |
| design-build entity and associated design-build professionals |
6 |
| shall conduct
themselves in accordance with the laws of this |
7 |
| State and the related provisions
of the
Illinois
Administrative |
8 |
| Code, as
referenced by the licensed design professional Acts of |
9 |
| this
State, with respect to the solicitation and contracting of |
10 |
| design-build
services.
|
11 |
| "Design professional" means any individual, sole |
12 |
| proprietorship, firm,
partnership, joint venture, corporation, |
13 |
| professional corporation, or other
entity that offers services |
14 |
| under the Illinois Architecture Practice Act of
1989 (225 ILCS |
15 |
| 305/), the Professional Engineering Practice Act of 1989 (225
|
16 |
| ILCS 325/),
the Structural Engineering Licensing Act of 1989 |
17 |
| (225 ILCS 340/), or the
Illinois Professional
Land Surveyor Act |
18 |
| of 1989 (225 ILCS 330/).
|
19 |
| "Evaluation criteria" means the requirements for the |
20 |
| separate phases of the
selection process as defined in this Act |
21 |
| and may include the specialized
experience, technical |
22 |
| qualifications and competence, capacity to perform, past
|
23 |
| performance, experience with similar projects, assignment of |
24 |
| personnel to the
project, and other appropriate factors. Price |
25 |
| may not be used as a factor in
the evaluation of Phase I |
26 |
| proposals.
|
27 |
| "Proposal" means the offer to enter into a design-build |
28 |
| contract as submitted
by a design-build entity in accordance |
29 |
| with this Act.
|
30 |
| "Request for proposal" means the document used by a State |
31 |
| construction agency
to solicit
proposals for a design-build |
32 |
| contract.
|
33 |
| "Scope and performance criteria" means the requirements |
34 |
| for the public
project, including but not limited to, the |
35 |
| intended usage, capacity, size,
scope, quality and performance |
36 |
| standards, life-cycle costs, and other
programmatic criteria |
|
|
|
HB4619 |
- 4 - |
LRB093 20721 BDD 46609 b |
|
|
1 |
| that are expressed in performance-oriented and
quantifiable |
2 |
| specifications and drawings that can be reasonably inferred and
|
3 |
| are suited to allow a design-build entity to develop a |
4 |
| proposal.
|
5 |
| Section 15. Solicitation of proposals.
|
6 |
| (a) A State construction agency that elects to use the |
7 |
| design-build delivery
method must
issue a notice of intent to |
8 |
| receive requests for proposals for the project at
least 14 days |
9 |
| before issuing the request for the proposal. The State
|
10 |
| construction agency
must publish the advance notice in the |
11 |
| official procurement bulletin of the
State or the professional |
12 |
| services bulletin of the State construction agency,
if any. The
|
13 |
| agency is encouraged to use publication of the notice in |
14 |
| related construction
industry service publications. A brief |
15 |
| description of the proposed procurement
must be included in the |
16 |
| notice. The State construction agency must provide a
copy of |
17 |
| the
request for proposal to any party requesting a copy.
|
18 |
| (b) The request for proposal shall be prepared for each |
19 |
| project and must
contain, without limitation, the following |
20 |
| information:
|
21 |
| (1) The State construction agency that will award the |
22 |
| design-build
contract.
|
23 |
| (2) A preliminary schedule for the completion of the |
24 |
| contract.
|
25 |
| (3) The proposed budget for the project, the source of |
26 |
| funds, and the
currently available funds.
|
27 |
| (4) Prequalification criteria for design-build |
28 |
| entities wishing to submit
proposals.
The State |
29 |
| construction agency shall include, at a minimum, its normal
|
30 |
| prequalification, licensing, registration, and other |
31 |
| requirements, but nothing
contained herein precludes the |
32 |
| use of additional prequalification criteria
by the State |
33 |
| construction agency.
|
34 |
| (5) Material requirements of the contract, including |
35 |
| but not limited to,
the proposed terms and conditions, |
|
|
|
HB4619 |
- 5 - |
LRB093 20721 BDD 46609 b |
|
|
1 |
| required performance and payment bonds,
insurance, |
2 |
| affirmative action, and workforce requirements, if any.
|
3 |
| (6) The performance criteria.
|
4 |
| (7) The evaluation criteria for each phase of the |
5 |
| solicitation.
|
6 |
| (8) The number of entities that will be considered for |
7 |
| the technical and
cost
evaluation phase.
|
8 |
| (c) The State construction agency may include any other |
9 |
| relevant information
that it
chooses to supply. The |
10 |
| design-build entity shall be entitled to rely upon the
accuracy |
11 |
| of this documentation in the development of its proposal.
|
12 |
| (d) The date that proposals are due must be at least 21 |
13 |
| calendar days after
the date of the issuance of the request for |
14 |
| proposal. In the event the cost of
the project
is estimated to |
15 |
| exceed $10 million, then the proposal due date must be at least
|
16 |
| 28 calendar days after the date of the issuance of the request |
17 |
| for proposal.
The State construction agency shall include in |
18 |
| the request for proposal a
minimum of 30 days
to develop the |
19 |
| Phase II submissions after the selection of entities
from the |
20 |
| Phase I evaluation is completed.
|
21 |
| (e) Each design-build entity whose proposal proceeds to the |
22 |
| technical and
cost
evaluation phase may be reimbursed by the |
23 |
| State construction agency to defray
costs
associated with the |
24 |
| proposal preparation. If the State construction agency
elects |
25 |
| to provide
reimbursement, it shall specify in the request for |
26 |
| proposal the basis or
overall
reimbursement to be provided.
|
27 |
| Section 20. Development of scope and performance criteria.
|
28 |
| (a) The State construction agency shall develop, at the |
29 |
| direction of a
licensed design professional, a request
for |
30 |
| proposal, which shall include scope and performance criteria.
|
31 |
| The scope and performance criteria must be in sufficient detail |
32 |
| and contain
adequate information to reasonably apprise the |
33 |
| qualified design-build entities
of the State construction |
34 |
| agency's overall programmatic needs and goals,
including |
35 |
| criteria and preliminary design plans,
general budget |
|
|
|
HB4619 |
- 6 - |
LRB093 20721 BDD 46609 b |
|
|
1 |
| parameters, schedule, and delivery requirements.
|
2 |
| (b) Each request for proposal shall also include a |
3 |
| description of the level
of design to be provided in the |
4 |
| proposals. This description must include the
scope and type of |
5 |
| renderings, drawings, and specifications that, at a minimum,
|
6 |
| will be required by the State construction agency to be |
7 |
| produced by the
design-build entities.
|
8 |
| (c) The scope and performance criteria shall be prepared by |
9 |
| a design
professional who is an employee of the State |
10 |
| construction agency, or the State
construction
agency may
|
11 |
| contract with an independent design professional selected |
12 |
| under the
Architectural, Engineering and Land Surveying |
13 |
| Qualification Based Selection Act
(30 ILCS 535/) to provide |
14 |
| these services.
|
15 |
| (d) The design professional that prepares the scope and |
16 |
| performance criteria
is prohibited from participating in any |
17 |
| design-build entity proposal for the
project.
|
18 |
| Section 25. Selection Committee.
|
19 |
| (a) Each State construction agency that elects to use the |
20 |
| design-build
delivery method
shall establish a committee to |
21 |
| evaluate and select the design-build entity. The
committee, |
22 |
| under the discretion of the State construction agency, shall |
23 |
| consist
of 3, 5, or
7 members and shall include at least one |
24 |
| licensed design professional and one
member of the public. The |
25 |
| public
member may not be employed or associated with any firm |
26 |
| holding a contract with
the State construction agency and shall |
27 |
| be nominated by design or construction
industry associations. |
28 |
| The selection committee may be designated for a set term
or
for |
29 |
| the particular project subject to the request for proposal.
|
30 |
| (b) The members of the selection committee must certify for |
31 |
| each request for
proposal that no conflict of interest exists |
32 |
| between the members and the
design-build entities submitting |
33 |
| proposals. If a conflict exists, the member
must
be replaced |
34 |
| before any review of proposals.
|
|
|
|
HB4619 |
- 7 - |
LRB093 20721 BDD 46609 b |
|
|
1 |
| Section 30. Procedures for Selection.
|
2 |
| (a) The State construction agency must use a two-phase |
3 |
| procedure for the
selection of the
successful design-build |
4 |
| entity. Phase I of the procedure will evaluate and
shortlist |
5 |
| the design-build entities based on qualifications, and Phase II
|
6 |
| will
evaluate the technical and cost proposals.
|
7 |
| (b) The State construction agency shall include in the |
8 |
| request for proposal
the
evaluating factors to be used in Phase |
9 |
| I. These factors are in addition to any
prequalification |
10 |
| requirements of design-build entities that the agency has set
|
11 |
| forth. Each request for proposal shall establish the relative |
12 |
| importance
assigned to each evaluation factor and subfactor, |
13 |
| including any weighting of
criteria to be employed by the State |
14 |
| construction agency. The State
construction agency must |
15 |
| maintain a
record of the evaluation scoring to be disclosed in |
16 |
| event of a protest
regarding the solicitation.
|
17 |
| The State construction agency shall include the following |
18 |
| criteria in every
Phase I
evaluation of design-build entities: |
19 |
| (1) experience of personnel; (2)
successful
experience with |
20 |
| similar project types; (3) financial capability; (4) |
21 |
| timeliness
of past performance; (5) experience with similarly |
22 |
| sized projects; (6)
successful reference checks of the firm; |
23 |
| and (7) commitment to assign personnel
for the duration of the |
24 |
| project and qualifications of the entity's consultants.
The |
25 |
| State construction agency may include any additional relevant |
26 |
| criteria in
Phase I that
it deems necessary for a proper |
27 |
| qualification review.
|
28 |
| The State construction agency may not consider any |
29 |
| design-build entity for
evaluation or
award if the entity has |
30 |
| any pecuniary interest in the project or has other
|
31 |
| relationships or circumstances, including but not limited to, |
32 |
| long-term
leasehold, mutual performance, or development |
33 |
| contracts with the State
construction agency,
that may give the |
34 |
| design-build entity a financial or tangible advantage over
|
35 |
| other design-build entities in the preparation, evaluation, or |
36 |
| performance of
the
design-build contract or that create the |
|
|
|
HB4619 |
- 8 - |
LRB093 20721 BDD 46609 b |
|
|
1 |
| appearance of impropriety.
|
2 |
| Upon completion of the qualifications evaluation, the |
3 |
| State construction
agency shall
create a shortlist of the most |
4 |
| highly qualified design-build entities. The
State
construction |
5 |
| agency, in its discretion, is not required to shortlist the
|
6 |
| maximum number of
entities as identified for Phase II |
7 |
| evaluation, provided however, no less than
2
design-build |
8 |
| entities nor more than 6 are selected to submit Phase II
|
9 |
| proposals.
|
10 |
| The State construction agency shall notify the entities |
11 |
| selected for the
shortlist in
writing. This notification shall |
12 |
| commence the period for the preparation of the
Phase II |
13 |
| technical and cost evaluations. The State construction agency |
14 |
| must
allow sufficient
time for the shortlist entities to |
15 |
| prepare their Phase II submittals
considering
the scope and |
16 |
| detail requested by the State agency.
|
17 |
| (c) The State construction agency shall include in the |
18 |
| request for proposal
the
evaluating factors to be used in the |
19 |
| technical and cost submission components
of Phase II. Each |
20 |
| request for proposal shall establish, for both the technical
|
21 |
| and cost submission components of Phase II, the relative |
22 |
| importance assigned to
each evaluation factor and subfactor, |
23 |
| including any weighting of criteria to be
employed by the State |
24 |
| construction agency. The State construction agency must
|
25 |
| maintain a record of the
evaluation scoring to be disclosed in |
26 |
| event of a protest regarding the
solicitation.
|
27 |
| The State construction agency shall include the following |
28 |
| criteria in every
Phase II
technical evaluation of design-build |
29 |
| entities: (1) compliance with objectives
of
the
project; (2) |
30 |
| compliance of proposed services to the request for proposal
|
31 |
| requirements; (3) quality of products or materials proposed; |
32 |
| (4) quality of
design parameters; (5) design concepts; (6) |
33 |
| innovation in meeting the scope and
performance criteria; and |
34 |
| (7) constructability of the
proposed project. The State |
35 |
| construction agency may include any additional
relevant
|
36 |
| technical evaluation factors it deems necessary for proper |
|
|
|
HB4619 |
- 9 - |
LRB093 20721 BDD 46609 b |
|
|
1 |
| selection.
|
2 |
| The State construction agency shall include the following |
3 |
| criteria in every
Phase II cost
evaluation: the total project |
4 |
| cost, the construction costs, and the time of
completion. The |
5 |
| State construction agency may include any additional relevant
|
6 |
| technical
evaluation factors it deems necessary for proper |
7 |
| selection. In no event shall
the total project cost
criteria in |
8 |
| this subsection exceed a weighting factor greater than 25%.
|
9 |
| The State construction agency shall directly employ or |
10 |
| retain a licensed
design
professional to evaluate the technical |
11 |
| and cost submissions to determine if the
technical submissions |
12 |
| are in accordance with generally
accepted industry standards.
|
13 |
| Upon completion of the technical submissions and cost |
14 |
| submissions evaluation,
the State construction agency may |
15 |
| award the design-build contract to the
highest
overall ranked |
16 |
| entity.
|
17 |
| Section 35. Small projects. In any case where the total |
18 |
| overall cost of the
project is estimated to be less than $5 |
19 |
| million, the State construction agency
may combine
the |
20 |
| two-phase procedure for selection described in Section 30 into |
21 |
| one combined
step, provided that all the requirements of |
22 |
| evaluation are performed in
accordance with Section 30.
|
23 |
| Section 40. Submission of proposals. Proposals must be |
24 |
| properly identified
and sealed. Proposals may not be reviewed |
25 |
| until after the deadline for
submission has passed as set forth |
26 |
| in the request for proposals. All
design-build entities |
27 |
| submitting proposals shall be disclosed after the
deadline
for |
28 |
| submission, and all design-build entities who are selected for |
29 |
| Phase II
evaluation shall also be disclosed at the time of that |
30 |
| determination.
|
31 |
| Proposals shall include a bid bond in the form and security |
32 |
| as designated in
the request for proposals. Proposals shall |
33 |
| also contain a separate sealed
envelope with the cost |
34 |
| information within the overall proposal submission.
Proposals |
|
|
|
HB4619 |
- 10 - |
LRB093 20721 BDD 46609 b |
|
|
1 |
| shall include a list of all design professionals and other |
2 |
| entities
to which any work may be subcontracted during the |
3 |
| performance of the contract.
In the event the request for |
4 |
| proposal so designates, these entities must meet
|
5 |
| prequalification standards of the State construction agency.
|
6 |
| Proposals must meet all material requirements of the |
7 |
| request for proposal or
they may be rejected as non-responsive. |
8 |
| The State construction agency shall
have the right
to reject |
9 |
| any and all proposals.
|
10 |
| The drawings and specifications of the proposal shall |
11 |
| remain the property of
the design-build entity.
|
12 |
| The State construction agency shall review the proposals |
13 |
| for compliance with
the
performance criteria and evaluation |
14 |
| factors.
|
15 |
| Proposals may be withdrawn prior to evaluation for any |
16 |
| cause. After
evaluation begins by the State construction |
17 |
| agency, clear and convincing
evidence of error
is required for |
18 |
| withdrawal.
|
19 |
| Section 45. Award. The State construction agency may award |
20 |
| the contract to
the highest
overall ranked entity. Notice of |
21 |
| award shall be made in writing. Unsuccessful
entities shall |
22 |
| also be notified in writing. The State construction agency may
|
23 |
| not request a
best and final offer after the receipt of |
24 |
| proposals. The State construction
agency may
negotiate with the |
25 |
| selected design-build entity after award but prior to
contract
|
26 |
| execution for the purpose of securing better terms than |
27 |
| originally proposed,
provided that the salient features of the |
28 |
| request for proposal are not
diminished.
|
29 |
| Section 50. Administrative Procedure Act. The Illinois
|
30 |
| Administrative Procedure Act (5 ILCS 100/) applies to all
|
31 |
| administrative rules and procedures of the State construction |
32 |
| agency under this
Act.
|
33 |
| Section 53. Federal requirements. In the procurement of |