3 | | everything after the enacting clause with the following:
|
4 | | "Section 1. Short title. This Act may be cited as the |
5 | | Mechanical Insulation Energy and Safety Assessment Act. |
6 | | Section 5. Legislative findings. The General Assembly |
7 | | finds that the State has an interest in decreasing the carbon |
8 | | footprint of publicly owned buildings. The General Assembly |
9 | | also finds that it is the public policy of this State to ensure |
10 | | that all Illinois residents can use publicly owned buildings |
11 | | for employment, educational purposes, and social services, |
12 | | free from harmful mold and bacteria. This Act is created in |
13 | | recognition of the important role that mechanical insulation |
14 | | plays in lowering operating expenses, reducing energy loss, |
15 | | and decreasing emissions. |
|
| | 10300SB2049sam001 | - 2 - | LRB103 28907 HLH 59389 a |
|
|
1 | | Section 10. Definitions. As used in this Act: |
2 | | "Board" means the Capital Development Board. |
3 | | "Mechanical insulation" means insulation, materials, |
4 | | facings, and accessory products that are applied to mechanical |
5 | | systems, including piping, equipment, vessels, HVAC, boilers, |
6 | | and other similar equipment, or that are used to prevent |
7 | | corrosion of cooling systems. |
8 | | "Mechanical insulation energy and safety assessment" means |
9 | | an assessment that analyzes potential energy savings and any |
10 | | potential public health risks according to the specifications |
11 | | of a building's mechanical equipment. |
12 | | "Public building" means any structure in the State that is |
13 | | owned in whole or in part by the State of Illinois. |
14 | | "Qualified mechanical insulation contractor" means a |
15 | | mechanical insulation contractor who is an active participant |
16 | | in an apprenticeship program approved by the United States |
17 | | Department of Labor. |
18 | | Section 15. Mechanical insulation energy and safety |
19 | | assessments. |
20 | | (a) For the purpose of moving the State closer to its 100% |
21 | | clean energy goal, the Board shall contract with a qualified |
22 | | mechanical insulation contractor on a commission basis to |
23 | | perform a mechanical insulation energy and safety assessment |
24 | | of every public building within 10 years after the effective |
25 | | date of this Act. The assessments' findings shall include any |
|
| | 10300SB2049sam001 | - 3 - | LRB103 28907 HLH 59389 a |
|
|
1 | | and all remediation measures necessary to bring the subject |
2 | | mechanical insulation system up to Code, as defined in Section |
3 | | 10 of the Energy Efficient Building Act, and to ensure that the |
4 | | system functions at a specific operating temperature to |
5 | | minimize energy loss and ensure public health and safety. |
6 | | (b) The findings shall be a matter of public record and |
7 | | shall be posted on the Board's website no later than 30 days |
8 | | after the completion of the assessment. In addition, the Board |
9 | | shall file with the General Assembly an annual report |
10 | | outlining the assessments completed in the previous calendar |
11 | | year. The reports shall be filed by December 31 of the calendar |
12 | | year after the calendar year in which the assessment is |
13 | | performed. |
14 | | (c) If the mechanical insulation energy and safety |
15 | | assessment identifies mechanical insulation remediation |
16 | | measures that would result in a reduction in the carbon |
17 | | footprint for the subject building of more than 30% and a |
18 | | cumulative energy savings for the subject building of more |
19 | | than 30%, then the State shall enter into a contract for those |
20 | | mechanical insulation remediation measures within 12 months |
21 | | after the publication of the assessment findings on the |
22 | | Board's website. If any public health or safety concerns are |
23 | | identified in the mechanical insulation energy and safety |
24 | | assessment, then those concerns are deemed to be a hazard to |
25 | | the public health and safety and shall be contracted out for |
26 | | immediate remediation. Any construction performed under this |