2023 and 2024 SB0215 Introduced 1/31/2023, by Sen. Ram Villivalam SYNOPSIS AS INTRODUCED: |
| |
Amends the Design-Build
Procurement Act. Provides that "design-build" includes the progressive design-build delivery method. Defines progressive design-build delivery method.
|
| |
| | A BILL FOR |
|
|
| | SB0215 | | LRB103 05061 HLH 50075 b |
|
|
1 | | AN ACT concerning finance.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | Section 5. The Design-Build
Procurement Act is amended by |
5 | | changing Section 10 as follows: |
6 | | (30 ILCS 537/10) |
7 | | (Section scheduled to be repealed on July 1, 2027)
|
8 | | Sec. 10. Definitions. As used in this Act:
|
9 | | "State construction agency" means the Capital Development |
10 | | Board.
|
11 | | "Delivery system" means the design and construction |
12 | | approach used to develop
and construct a project.
|
13 | | "Design-bid-build" means the traditional delivery system |
14 | | used on public
projects in this State that incorporates the |
15 | | Architectural, Engineering, and
Land Surveying Qualification |
16 | | Based Selection Act (30 ILCS 535/) and the
principles of |
17 | | competitive selection in the Illinois Procurement Code (30 |
18 | | ILCS
500/).
|
19 | | "Design-build" means a delivery system that provides |
20 | | responsibility within a
single contract for the furnishing of |
21 | | architecture, engineering, land surveying
and related services |
22 | | as required, and the labor, materials, equipment, and
other |
23 | | construction services for the project.
"Design-build" |
|
| | SB0215 | - 2 - | LRB103 05061 HLH 50075 b |
|
|
1 | | includes, but is not limited to, the progressive design-build |
2 | | delivery method.
|
3 | | "Design-build contract" means a contract for a public |
4 | | project under this Act
between the State construction agency |
5 | | and a design-build entity to furnish
architecture,
|
6 | | engineering, land surveying, and related services as required, |
7 | | and to furnish
the labor, materials, equipment, and other |
8 | | construction services for the
project. The design-build |
9 | | contract may be conditioned upon subsequent
refinements in |
10 | | scope and price and may allow the State construction agency to
|
11 | | make
modifications in the project scope without invalidating |
12 | | the design-build
contract.
|
13 | | "Design-build entity" means any individual, sole |
14 | | proprietorship, firm,
partnership, joint venture, corporation, |
15 | | professional corporation, or other
entity that proposes to |
16 | | design and construct any public project under this Act.
A |
17 | | design-build entity and associated design-build professionals |
18 | | shall conduct themselves in accordance with the laws of this |
19 | | State and the related provisions of the Illinois |
20 | | Administrative Code, as referenced by the licensed design |
21 | | professionals Acts of this State.
|
22 | | "Design professional" means any individual, sole |
23 | | proprietorship, firm,
partnership, joint venture, corporation, |
24 | | professional corporation, or other
entity that offers services |
25 | | under the Illinois Architecture Practice Act of
1989 (225 ILCS |
26 | | 305/), the Professional Engineering Practice Act of 1989 (225
|
|
| | SB0215 | - 3 - | LRB103 05061 HLH 50075 b |
|
|
1 | | ILCS 325/),
the Structural Engineering Licensing Act of 1989 |
2 | | (225 ILCS 340/), or the
Illinois Professional
Land Surveyor |
3 | | Act of 1989 (225 ILCS 330/).
|
4 | | "Evaluation criteria" means the requirements for the |
5 | | separate phases of the
selection process as defined in this |
6 | | Act and may include the specialized
experience, technical |
7 | | qualifications and competence, capacity to perform, past
|
8 | | performance, experience with similar projects, assignment of |
9 | | personnel to the
project, and other appropriate factors. Price |
10 | | may not be used as a factor in
the evaluation of Phase I |
11 | | proposals.
|
12 | | "Progressive design-build delivery method" means a |
13 | | design-build project delivery method that consists of 2 |
14 | | phases. The first phase includes budget-level design |
15 | | development, preconstruction services, and negotiation of a |
16 | | contract price (either lump sum or guaranteed maximum price), |
17 | | and the second phase includes final design, construction, and |
18 | | commissioning of the project. |
19 | | "Proposal" means the offer to enter into a design-build |
20 | | contract as submitted
by a design-build entity in accordance |
21 | | with this Act.
|
22 | | "Request for proposal" means the document used by the |
23 | | State construction agency
to solicit
proposals for a |
24 | | design-build contract.
|
25 | | "Scope and performance criteria" means the requirements |
26 | | for the public
project, including but not limited to, the |
|
| | SB0215 | - 4 - | LRB103 05061 HLH 50075 b |
|
|
1 | | intended usage, capacity, size,
scope, quality and performance |
2 | | standards, life-cycle costs, and other
programmatic criteria |
3 | | that are expressed in performance-oriented and
quantifiable |
4 | | specifications and drawings that can be reasonably inferred |
5 | | and
are suited to allow a design-build entity to develop a |
6 | | proposal.
|
7 | | (Source: P.A. 94-716, eff. 12-13-05 .)
|