102ND GENERAL ASSEMBLY
State of Illinois
2021 and 2022
SB2161

 

Introduced 2/26/2021, by Sen. Brian W. Stewart

 

SYNOPSIS AS INTRODUCED:
 
20 ILCS 3855/1-10
20 ILCS 3855/1-20
20 ILCS 3855/1-75
220 ILCS 5/16-111.5

    Amends the Illinois Power Agency Act. Authorizes the Illinois Power Agency to develop capacity procurement plans and conduct competitive procurement processes for the procurement of capacity to meet the capacity requirements of all retail customers of electric utilities that serve at least 3,000,000 retail customers in this State. Provides for the goal that no later than the delivery year commencing June 1, 2033, the Agency's procurement plans and processes shall include bundled clean capacity in an amount equal to 100% of the electric load measured in megawatt-hours for all retail customers of electric utilities that serve more than 3,000,000 customers in this State. Requires the Planning and Procurement Bureau to develop plans and processes and conduct competitive procurement events to procure capacity for all retail customers of electric utilities that serve at least 3,000,000 retail customers in this State that are located in the Applicable Fixed Resource Requirement Service Area of PJM Interconnection, LLC. Amends the Public Utilities Act. Establishes requirements for procurement of contracts for capacity by the Agency for electric utilities serving at least 3,000,000 retail customers in this State located in the Applicable Fixed Resource Requirement Service Area of PJM Interconnection, LLC.


LRB102 15735 SPS 21099 b

FISCAL NOTE ACT MAY APPLY

 

 

A BILL FOR

 

SB2161LRB102 15735 SPS 21099 b

1    AN ACT concerning State government.
 
2    Be it enacted by the People of the State of Illinois,
3represented in the General Assembly:
 
4    Section 5. The Illinois Power Agency Act is amended by
5changing Sections 1-10, 1-20, and 1-75 as follows:
 
6    (20 ILCS 3855/1-10)
7    Sec. 1-10. Definitions.
8    "Agency" means the Illinois Power Agency.
9    "Agency loan agreement" means any agreement pursuant to
10which the Illinois Finance Authority agrees to loan the
11proceeds of revenue bonds issued with respect to a project to
12the Agency upon terms providing for loan repayment
13installments at least sufficient to pay when due all principal
14of, interest and premium, if any, on those revenue bonds, and
15providing for maintenance, insurance, and other matters in
16respect of the project.
17    "Authority" means the Illinois Finance Authority.
18    "Brownfield site photovoltaic project" means photovoltaics
19that are:
20        (1) interconnected to an electric utility as defined
21    in this Section, a municipal utility as defined in this
22    Section, a public utility as defined in Section 3-105 of
23    the Public Utilities Act, or an electric cooperative, as

 

 

SB2161- 2 -LRB102 15735 SPS 21099 b

1    defined in Section 3-119 of the Public Utilities Act; and
2        (2) located at a site that is regulated by any of the
3    following entities under the following programs:
4            (A) the United States Environmental Protection
5        Agency under the federal Comprehensive Environmental
6        Response, Compensation, and Liability Act of 1980, as
7        amended;
8            (B) the United States Environmental Protection
9        Agency under the Corrective Action Program of the
10        federal Resource Conservation and Recovery Act, as
11        amended;
12            (C) the Illinois Environmental Protection Agency
13        under the Illinois Site Remediation Program; or
14            (D) the Illinois Environmental Protection Agency
15        under the Illinois Solid Waste Program.
16    "Bundled clean capacity" means the combination of capacity
17and zero emission attributes from clean energy resources.
18    "Clean coal facility" means an electric generating
19facility that uses primarily coal as a feedstock and that
20captures and sequesters carbon dioxide emissions at the
21following levels: at least 50% of the total carbon dioxide
22emissions that the facility would otherwise emit if, at the
23time construction commences, the facility is scheduled to
24commence operation before 2016, at least 70% of the total
25carbon dioxide emissions that the facility would otherwise
26emit if, at the time construction commences, the facility is

 

 

SB2161- 3 -LRB102 15735 SPS 21099 b

1scheduled to commence operation during 2016 or 2017, and at
2least 90% of the total carbon dioxide emissions that the
3facility would otherwise emit if, at the time construction
4commences, the facility is scheduled to commence operation
5after 2017. The power block of the clean coal facility shall
6not exceed allowable emission rates for sulfur dioxide,
7nitrogen oxides, carbon monoxide, particulates and mercury for
8a natural gas-fired combined-cycle facility the same size as
9and in the same location as the clean coal facility at the time
10the clean coal facility obtains an approved air permit. All
11coal used by a clean coal facility shall have high volatile
12bituminous rank and greater than 1.7 pounds of sulfur per
13million btu content, unless the clean coal facility does not
14use gasification technology and was operating as a
15conventional coal-fired electric generating facility on June
161, 2009 (the effective date of Public Act 95-1027).
17    "Clean coal SNG brownfield facility" means a facility that
18(1) has commenced construction by July 1, 2015 on an urban
19brownfield site in a municipality with at least 1,000,000
20residents; (2) uses a gasification process to produce
21substitute natural gas; (3) uses coal as at least 50% of the
22total feedstock over the term of any sourcing agreement with a
23utility and the remainder of the feedstock may be either
24petroleum coke or coal, with all such coal having a high
25bituminous rank and greater than 1.7 pounds of sulfur per
26million Btu content unless the facility reasonably determines

 

 

SB2161- 4 -LRB102 15735 SPS 21099 b

1that it is necessary to use additional petroleum coke to
2deliver additional consumer savings, in which case the
3facility shall use coal for at least 35% of the total feedstock
4over the term of any sourcing agreement; and (4) captures and
5sequesters at least 85% of the total carbon dioxide emissions
6that the facility would otherwise emit.
7    "Clean coal SNG facility" means a facility that uses a
8gasification process to produce substitute natural gas, that
9sequesters at least 90% of the total carbon dioxide emissions
10that the facility would otherwise emit, that uses at least 90%
11coal as a feedstock, with all such coal having a high
12bituminous rank and greater than 1.7 pounds of sulfur per
13million btu content, and that has a valid and effective permit
14to construct emission sources and air pollution control
15equipment and approval with respect to the federal regulations
16for Prevention of Significant Deterioration of Air Quality
17(PSD) for the plant pursuant to the federal Clean Air Act;
18provided, however, a clean coal SNG brownfield facility shall
19not be a clean coal SNG facility.
20    "Clean energy resources" means: (1) energy efficiency
21measures that are implemented pursuant to plans approved by
22the Commission under Sections 8-103, 8-103B, and 8-104 of the
23Public Utilities Act; (2) renewable energy resources; and (3)
24resources from zero emission facilities.
25    "Commission" means the Illinois Commerce Commission.
26    "Community renewable generation project" means an electric

 

 

SB2161- 5 -LRB102 15735 SPS 21099 b

1generating facility that:
2        (1) is powered by wind, solar thermal energy,
3    photovoltaic cells or panels, biodiesel, crops and
4    untreated and unadulterated organic waste biomass, tree
5    waste, and hydropower that does not involve new
6    construction or significant expansion of hydropower dams;
7        (2) is interconnected at the distribution system level
8    of an electric utility as defined in this Section, a
9    municipal utility as defined in this Section that owns or
10    operates electric distribution facilities, a public
11    utility as defined in Section 3-105 of the Public
12    Utilities Act, or an electric cooperative, as defined in
13    Section 3-119 of the Public Utilities Act;
14        (3) credits the value of electricity generated by the
15    facility to the subscribers of the facility; and
16        (4) is limited in nameplate capacity to less than or
17    equal to 2,000 kilowatts.
18    "Costs incurred in connection with the development and
19construction of a facility" means:
20        (1) the cost of acquisition of all real property,
21    fixtures, and improvements in connection therewith and
22    equipment, personal property, and other property, rights,
23    and easements acquired that are deemed necessary for the
24    operation and maintenance of the facility;
25        (2) financing costs with respect to bonds, notes, and
26    other evidences of indebtedness of the Agency;

 

 

SB2161- 6 -LRB102 15735 SPS 21099 b

1        (3) all origination, commitment, utilization,
2    facility, placement, underwriting, syndication, credit
3    enhancement, and rating agency fees;
4        (4) engineering, design, procurement, consulting,
5    legal, accounting, title insurance, survey, appraisal,
6    escrow, trustee, collateral agency, interest rate hedging,
7    interest rate swap, capitalized interest, contingency, as
8    required by lenders, and other financing costs, and other
9    expenses for professional services; and
10        (5) the costs of plans, specifications, site study and
11    investigation, installation, surveys, other Agency costs
12    and estimates of costs, and other expenses necessary or
13    incidental to determining the feasibility of any project,
14    together with such other expenses as may be necessary or
15    incidental to the financing, insuring, acquisition, and
16    construction of a specific project and starting up,
17    commissioning, and placing that project in operation.
18    "Delivery services" has the same definition as found in
19Section 16-102 of the Public Utilities Act.
20    "Delivery year" means the consecutive 12-month period
21beginning June 1 of a given year and ending May 31 of the
22following year.
23    "Department" means the Department of Commerce and Economic
24Opportunity.
25    "Director" means the Director of the Illinois Power
26Agency.

 

 

SB2161- 7 -LRB102 15735 SPS 21099 b

1    "Demand-response" means measures that decrease peak
2electricity demand or shift demand from peak to off-peak
3periods.
4    "Distributed renewable energy generation device" means a
5device that is:
6        (1) powered by wind, solar thermal energy,
7    photovoltaic cells or panels, biodiesel, crops and
8    untreated and unadulterated organic waste biomass, tree
9    waste, and hydropower that does not involve new
10    construction or significant expansion of hydropower dams;
11        (2) interconnected at the distribution system level of
12    either an electric utility as defined in this Section, a
13    municipal utility as defined in this Section that owns or
14    operates electric distribution facilities, or a rural
15    electric cooperative as defined in Section 3-119 of the
16    Public Utilities Act;
17        (3) located on the customer side of the customer's
18    electric meter and is primarily used to offset that
19    customer's electricity load; and
20        (4) limited in nameplate capacity to less than or
21    equal to 2,000 kilowatts.
22    "Energy efficiency" means measures that reduce the amount
23of electricity or natural gas consumed in order to achieve a
24given end use. "Energy efficiency" includes voltage
25optimization measures that optimize the voltage at points on
26the electric distribution voltage system and thereby reduce

 

 

SB2161- 8 -LRB102 15735 SPS 21099 b

1electricity consumption by electric customers' end use
2devices. "Energy efficiency" also includes measures that
3reduce the total Btus of electricity, natural gas, and other
4fuels needed to meet the end use or uses.
5    "Electric utility" has the same definition as found in
6Section 16-102 of the Public Utilities Act.
7    "Facility" means an electric generating unit or a
8co-generating unit that produces electricity along with
9related equipment necessary to connect the facility to an
10electric transmission or distribution system.
11    "Governmental aggregator" means one or more units of local
12government that individually or collectively procure
13electricity to serve residential retail electrical loads
14located within its or their jurisdiction.
15    "Local government" means a unit of local government as
16defined in Section 1 of Article VII of the Illinois
17Constitution.
18    "Municipality" means a city, village, or incorporated
19town.
20    "Municipal utility" means a public utility owned and
21operated by any subdivision or municipal corporation of this
22State.
23    "Nameplate capacity" means the aggregate inverter
24nameplate capacity in kilowatts AC.
25    "Person" means any natural person, firm, partnership,
26corporation, either domestic or foreign, company, association,

 

 

SB2161- 9 -LRB102 15735 SPS 21099 b

1limited liability company, joint stock company, or association
2and includes any trustee, receiver, assignee, or personal
3representative thereof.
4    "Project" means the planning, bidding, and construction of
5a facility.
6    "Public utility" has the same definition as found in
7Section 3-105 of the Public Utilities Act.
8    "Real property" means any interest in land together with
9all structures, fixtures, and improvements thereon, including
10lands under water and riparian rights, any easements,
11covenants, licenses, leases, rights-of-way, uses, and other
12interests, together with any liens, judgments, mortgages, or
13other claims or security interests related to real property.
14    "Renewable energy credit" means a tradable credit that
15represents the environmental attributes of one megawatt hour
16of energy produced from a renewable energy resource.
17    "Renewable energy resources" includes energy and its
18associated renewable energy credit or renewable energy credits
19from wind, solar thermal energy, photovoltaic cells and
20panels, biodiesel, anaerobic digestion, crops and untreated
21and unadulterated organic waste biomass, tree waste, and
22hydropower that does not involve new construction or
23significant expansion of hydropower dams. For purposes of this
24Act, landfill gas produced in the State is considered a
25renewable energy resource. "Renewable energy resources" does
26not include the incineration or burning of tires, garbage,

 

 

SB2161- 10 -LRB102 15735 SPS 21099 b

1general household, institutional, and commercial waste,
2industrial lunchroom or office waste, landscape waste other
3than tree waste, railroad crossties, utility poles, or
4construction or demolition debris, other than untreated and
5unadulterated waste wood.
6    "Retail customer" has the same definition as found in
7Section 16-102 of the Public Utilities Act.
8    "Revenue bond" means any bond, note, or other evidence of
9indebtedness issued by the Authority, the principal and
10interest of which is payable solely from revenues or income
11derived from any project or activity of the Agency.
12    "Sequester" means permanent storage of carbon dioxide by
13injecting it into a saline aquifer, a depleted gas reservoir,
14or an oil reservoir, directly or through an enhanced oil
15recovery process that may involve intermediate storage,
16regardless of whether these activities are conducted by a
17clean coal facility, a clean coal SNG facility, a clean coal
18SNG brownfield facility, or a party with which a clean coal
19facility, clean coal SNG facility, or clean coal SNG
20brownfield facility has contracted for such purposes.
21    "Service area" has the same definition as found in Section
2216-102 of the Public Utilities Act.
23    "Sourcing agreement" means (i) in the case of an electric
24utility, an agreement between the owner of a clean coal
25facility and such electric utility, which agreement shall have
26terms and conditions meeting the requirements of paragraph (3)

 

 

SB2161- 11 -LRB102 15735 SPS 21099 b

1of subsection (d) of Section 1-75, (ii) in the case of an
2alternative retail electric supplier, an agreement between the
3owner of a clean coal facility and such alternative retail
4electric supplier, which agreement shall have terms and
5conditions meeting the requirements of Section 16-115(d)(5) of
6the Public Utilities Act, and (iii) in case of a gas utility,
7an agreement between the owner of a clean coal SNG brownfield
8facility and the gas utility, which agreement shall have the
9terms and conditions meeting the requirements of subsection
10(h-1) of Section 9-220 of the Public Utilities Act.
11    "Subscriber" means a person who (i) takes delivery service
12from an electric utility, and (ii) has a subscription of no
13less than 200 watts to a community renewable generation
14project that is located in the electric utility's service
15area. No subscriber's subscriptions may total more than 40% of
16the nameplate capacity of an individual community renewable
17generation project. Entities that are affiliated by virtue of
18a common parent shall not represent multiple subscriptions
19that total more than 40% of the nameplate capacity of an
20individual community renewable generation project.
21    "Subscription" means an interest in a community renewable
22generation project expressed in kilowatts, which is sized
23primarily to offset part or all of the subscriber's
24electricity usage.
25    "Substitute natural gas" or "SNG" means a gas manufactured
26by gasification of hydrocarbon feedstock, which is

 

 

SB2161- 12 -LRB102 15735 SPS 21099 b

1substantially interchangeable in use and distribution with
2conventional natural gas.
3    "Total resource cost test" or "TRC test" means a standard
4that is met if, for an investment in energy efficiency or
5demand-response measures, the benefit-cost ratio is greater
6than one. The benefit-cost ratio is the ratio of the net
7present value of the total benefits of the program to the net
8present value of the total costs as calculated over the
9lifetime of the measures. A total resource cost test compares
10the sum of avoided electric utility costs, representing the
11benefits that accrue to the system and the participant in the
12delivery of those efficiency measures and including avoided
13costs associated with reduced use of natural gas or other
14fuels, avoided costs associated with reduced water
15consumption, and avoided costs associated with reduced
16operation and maintenance costs, as well as other quantifiable
17societal benefits, to the sum of all incremental costs of
18end-use measures that are implemented due to the program
19(including both utility and participant contributions), plus
20costs to administer, deliver, and evaluate each demand-side
21program, to quantify the net savings obtained by substituting
22the demand-side program for supply resources. In calculating
23avoided costs of power and energy that an electric utility
24would otherwise have had to acquire, reasonable estimates
25shall be included of financial costs likely to be imposed by
26future regulations and legislation on emissions of greenhouse

 

 

SB2161- 13 -LRB102 15735 SPS 21099 b

1gases. In discounting future societal costs and benefits for
2the purpose of calculating net present values, a societal
3discount rate based on actual, long-term Treasury bond yields
4should be used. Notwithstanding anything to the contrary, the
5TRC test shall not include or take into account a calculation
6of market price suppression effects or demand reduction
7induced price effects.
8    "Utility-scale solar project" means an electric generating
9facility that:
10        (1) generates electricity using photovoltaic cells;
11    and
12        (2) has a nameplate capacity that is greater than
13    2,000 kilowatts.
14    "Utility-scale wind project" means an electric generating
15facility that:
16        (1) generates electricity using wind; and
17        (2) has a nameplate capacity that is greater than
18    2,000 kilowatts.
19    "Zero emission credit" means a tradable credit that
20represents the environmental attributes of one megawatt hour
21of energy produced from a zero emission facility.
22    "Zero emission facility" means a facility that: (1) is
23fueled by nuclear power; and (2) is interconnected with PJM
24Interconnection, LLC or the Midcontinent Independent System
25Operator, Inc., or their successors.
26(Source: P.A. 98-90, eff. 7-15-13; 99-906, eff. 6-1-17.)
 

 

 

SB2161- 14 -LRB102 15735 SPS 21099 b

1    (20 ILCS 3855/1-20)
2    Sec. 1-20. General powers of the Agency.
3    (a) The Agency is authorized to do each of the following:
4        (1) Develop electricity procurement plans to ensure
5    adequate, reliable, affordable, efficient, and
6    environmentally sustainable electric service at the lowest
7    total cost over time, taking into account any benefits of
8    price stability, for electric utilities that on December
9    31, 2005 provided electric service to at least 100,000
10    customers in Illinois and for small multi-jurisdictional
11    electric utilities that (A) on December 31, 2005 served
12    less than 100,000 customers in Illinois and (B) request a
13    procurement plan for their Illinois jurisdictional load.
14    Except as provided in paragraph (1.5) of this subsection
15    (a), the electricity procurement plans shall be updated on
16    an annual basis and shall include electricity generated
17    from renewable resources sufficient to achieve the
18    standards specified in this Act. Beginning with the
19    delivery year commencing June 1, 2017, develop procurement
20    plans to include zero emission credits generated from zero
21    emission facilities sufficient to achieve the standards
22    specified in this Act.
23        (1.5) Develop a long-term renewable resources
24    procurement plan in accordance with subsection (c) of
25    Section 1-75 of this Act for renewable energy credits in

 

 

SB2161- 15 -LRB102 15735 SPS 21099 b

1    amounts sufficient to achieve the standards specified in
2    this Act for delivery years commencing June 1, 2017 and
3    for the programs and renewable energy credits specified in
4    Section 1-56 of this Act. Electricity procurement plans
5    for delivery years commencing after May 31, 2017, shall
6    not include procurement of renewable energy resources.
7        (2) Conduct competitive procurement processes to
8    procure the supply resources identified in the electricity
9    procurement plan, pursuant to Section 16-111.5 of the
10    Public Utilities Act, and, for the delivery year
11    commencing June 1, 2017, conduct procurement processes to
12    procure zero emission credits from zero emission
13    facilities, under subsection (d-5) of Section 1-75 of this
14    Act.
15        (2.5) Beginning with the procurement for the 2017
16    delivery year, conduct competitive procurement processes
17    and implement programs to procure renewable energy credits
18    identified in the long-term renewable resources
19    procurement plan developed and approved under subsection
20    (c) of Section 1-75 of this Act and Section 16-111.5 of the
21    Public Utilities Act.
22        (2.10) Beginning immediately after the effective date
23    of this amendatory Act of the 102nd General Assembly,
24    develop capacity procurement plans and conduct competitive
25    procurement processes for the procurement of capacity to
26    meet the capacity requirements of all retail customers of

 

 

SB2161- 16 -LRB102 15735 SPS 21099 b

1    electric utilities that serve at least 3,000,000 retail
2    customers in this State, as prescribed by Section 1-75 of
3    this Act and Section 16-111.5 of the Public Utilities Act.
4        (3) Develop electric generation and co-generation
5    facilities that use indigenous coal or renewable
6    resources, or both, financed with bonds issued by the
7    Illinois Finance Authority.
8        (4) Supply electricity from the Agency's facilities at
9    cost to one or more of the following: municipal electric
10    systems, governmental aggregators, or rural electric
11    cooperatives in Illinois.
12    (b) Except as otherwise limited by this Act, the Agency
13has all of the powers necessary or convenient to carry out the
14purposes and provisions of this Act, including without
15limitation, each of the following:
16        (1) To have a corporate seal, and to alter that seal at
17    pleasure, and to use it by causing it or a facsimile to be
18    affixed or impressed or reproduced in any other manner.
19        (2) To use the services of the Illinois Finance
20    Authority necessary to carry out the Agency's purposes.
21        (3) To negotiate and enter into loan agreements and
22    other agreements with the Illinois Finance Authority.
23        (4) To obtain and employ personnel and hire
24    consultants that are necessary to fulfill the Agency's
25    purposes, and to make expenditures for that purpose within
26    the appropriations for that purpose.

 

 

SB2161- 17 -LRB102 15735 SPS 21099 b

1        (5) To purchase, receive, take by grant, gift, devise,
2    bequest, or otherwise, lease, or otherwise acquire, own,
3    hold, improve, employ, use, and otherwise deal in and
4    with, real or personal property whether tangible or
5    intangible, or any interest therein, within the State.
6        (6) To acquire real or personal property, whether
7    tangible or intangible, including without limitation
8    property rights, interests in property, franchises,
9    obligations, contracts, and debt and equity securities,
10    and to do so by the exercise of the power of eminent domain
11    in accordance with Section 1-21; except that any real
12    property acquired by the exercise of the power of eminent
13    domain must be located within the State.
14        (7) To sell, convey, lease, exchange, transfer,
15    abandon, or otherwise dispose of, or mortgage, pledge, or
16    create a security interest in, any of its assets,
17    properties, or any interest therein, wherever situated.
18        (8) To purchase, take, receive, subscribe for, or
19    otherwise acquire, hold, make a tender offer for, vote,
20    employ, sell, lend, lease, exchange, transfer, or
21    otherwise dispose of, mortgage, pledge, or grant a
22    security interest in, use, and otherwise deal in and with,
23    bonds and other obligations, shares, or other securities
24    (or interests therein) issued by others, whether engaged
25    in a similar or different business or activity.
26        (9) To make and execute agreements, contracts, and

 

 

SB2161- 18 -LRB102 15735 SPS 21099 b

1    other instruments necessary or convenient in the exercise
2    of the powers and functions of the Agency under this Act,
3    including contracts with any person, including personal
4    service contracts, or with any local government, State
5    agency, or other entity; and all State agencies and all
6    local governments are authorized to enter into and do all
7    things necessary to perform any such agreement, contract,
8    or other instrument with the Agency. No such agreement,
9    contract, or other instrument shall exceed 40 years.
10        (10) To lend money, invest and reinvest its funds in
11    accordance with the Public Funds Investment Act, and take
12    and hold real and personal property as security for the
13    payment of funds loaned or invested.
14        (11) To borrow money at such rate or rates of interest
15    as the Agency may determine, issue its notes, bonds, or
16    other obligations to evidence that indebtedness, and
17    secure any of its obligations by mortgage or pledge of its
18    real or personal property, machinery, equipment,
19    structures, fixtures, inventories, revenues, grants, and
20    other funds as provided or any interest therein, wherever
21    situated.
22        (12) To enter into agreements with the Illinois
23    Finance Authority to issue bonds whether or not the income
24    therefrom is exempt from federal taxation.
25        (13) To procure insurance against any loss in
26    connection with its properties or operations in such

 

 

SB2161- 19 -LRB102 15735 SPS 21099 b

1    amount or amounts and from such insurers, including the
2    federal government, as it may deem necessary or desirable,
3    and to pay any premiums therefor.
4        (14) To negotiate and enter into agreements with
5    trustees or receivers appointed by United States
6    bankruptcy courts or federal district courts or in other
7    proceedings involving adjustment of debts and authorize
8    proceedings involving adjustment of debts and authorize
9    legal counsel for the Agency to appear in any such
10    proceedings.
11        (15) To file a petition under Chapter 9 of Title 11 of
12    the United States Bankruptcy Code or take other similar
13    action for the adjustment of its debts.
14        (16) To enter into management agreements for the
15    operation of any of the property or facilities owned by
16    the Agency.
17        (17) To enter into an agreement to transfer and to
18    transfer any land, facilities, fixtures, or equipment of
19    the Agency to one or more municipal electric systems,
20    governmental aggregators, or rural electric agencies or
21    cooperatives, for such consideration and upon such terms
22    as the Agency may determine to be in the best interest of
23    the citizens of Illinois.
24        (18) To enter upon any lands and within any building
25    whenever in its judgment it may be necessary for the
26    purpose of making surveys and examinations to accomplish

 

 

SB2161- 20 -LRB102 15735 SPS 21099 b

1    any purpose authorized by this Act.
2        (19) To maintain an office or offices at such place or
3    places in the State as it may determine.
4        (20) To request information, and to make any inquiry,
5    investigation, survey, or study that the Agency may deem
6    necessary to enable it effectively to carry out the
7    provisions of this Act.
8        (21) To accept and expend appropriations.
9        (22) To engage in any activity or operation that is
10    incidental to and in furtherance of efficient operation to
11    accomplish the Agency's purposes, including hiring
12    employees that the Director deems essential for the
13    operations of the Agency.
14        (23) To adopt, revise, amend, and repeal rules with
15    respect to its operations, properties, and facilities as
16    may be necessary or convenient to carry out the purposes
17    of this Act, subject to the provisions of the Illinois
18    Administrative Procedure Act and Sections 1-22 and 1-35 of
19    this Act.
20        (24) To establish and collect charges and fees as
21    described in this Act.
22        (25) To conduct competitive gasification feedstock
23    procurement processes to procure the feedstocks for the
24    clean coal SNG brownfield facility in accordance with the
25    requirements of Section 1-78 of this Act.
26        (26) To review, revise, and approve sourcing

 

 

SB2161- 21 -LRB102 15735 SPS 21099 b

1    agreements and mediate and resolve disputes between gas
2    utilities and the clean coal SNG brownfield facility
3    pursuant to subsection (h-1) of Section 9-220 of the
4    Public Utilities Act.
5        (27) To request, review and accept proposals, execute
6    contracts, purchase renewable energy credits and otherwise
7    dedicate funds from the Illinois Power Agency Renewable
8    Energy Resources Fund to create and carry out the
9    objectives of the Illinois Solar for All program in
10    accordance with Section 1-56 of this Act.
11(Source: P.A. 99-906, eff. 6-1-17.)
 
12    (20 ILCS 3855/1-75)
13    Sec. 1-75. Planning and Procurement Bureau. The Planning
14and Procurement Bureau has the following duties and
15responsibilities:
16    (a) The Planning and Procurement Bureau shall each year,
17beginning in 2008, develop procurement plans and conduct
18competitive procurement processes in accordance with the
19requirements of Section 16-111.5 of the Public Utilities Act
20for the eligible retail customers of electric utilities that
21on December 31, 2005 provided electric service to at least
22100,000 customers in Illinois. Beginning with the delivery
23year commencing on June 1, 2017, the Planning and Procurement
24Bureau shall develop plans and processes for the procurement
25of zero emission credits from zero emission facilities in

 

 

SB2161- 22 -LRB102 15735 SPS 21099 b

1accordance with the requirements of subsection (d-5) of this
2Section. The Planning and Procurement Bureau shall also
3develop procurement plans and conduct competitive procurement
4processes in accordance with the requirements of Section
516-111.5 of the Public Utilities Act for the eligible retail
6customers of small multi-jurisdictional electric utilities
7that (i) on December 31, 2005 served less than 100,000
8customers in Illinois and (ii) request a procurement plan for
9their Illinois jurisdictional load. This Section shall not
10apply to a small multi-jurisdictional utility until such time
11as a small multi-jurisdictional utility requests the Agency to
12prepare a procurement plan for their Illinois jurisdictional
13load. For the purposes of this Section, the term "eligible
14retail customers" has the same definition as found in Section
1516-111.5(a) of the Public Utilities Act.
16    Beginning with the plan or plans to be implemented in the
172017 delivery year, the Agency shall no longer include the
18procurement of renewable energy resources in the annual
19procurement plans required by this subsection (a), except as
20provided in subsection (q) of Section 16-111.5 of the Public
21Utilities Act, and shall instead develop a long-term renewable
22resources procurement plan in accordance with subsection (c)
23of this Section and Section 16-111.5 of the Public Utilities
24Act.
25    It is a goal of the State that, no later than the delivery
26year commencing June 1, 2033, the Agency's procurement plans

 

 

SB2161- 23 -LRB102 15735 SPS 21099 b

1and processes implemented under this Section shall include
2bundled clean capacity in an amount equal to 100% of the
3electric load measured in megawatt-hours for all retail
4customers of electric utilities that serve more than 3,000,000
5customers in this State. The Agency shall, to the extent not
6inconsistent with the provisions of this Act and the Public
7Utilities Act, develop procurement plans and conduct
8competitive procurements consistent with that goal beginning
9with the delivery year commencing June 1, 2024.
10    Beginning immediately after the effective date of this
11amendatory Act of the 102nd General Assembly, the Planning and
12Procurement Bureau shall develop plans and processes and
13conduct competitive procurement events to procure capacity for
14all retail customers of electric utilities that serve at least
153,000,000 retail customers in this State in accordance with
16subsection (b-5) of Section 16-111.5 of the Public Utilities
17Act that are located in the Applicable Fixed Resource
18Requirement Service Area of PJM Interconnection, LLC, or its
19successor. For purposes of this Section, "Fixed Resource
20Requirement Service Area" shall have the meaning set forth in
21the Reliability Assurance Agreement of PJM Interconnection,
22LLC, or its successor, as that Agreement may be updated from
23time to time. For the purposes of this Section, "Applicable
24Fixed Resource Requirement Service Area" means the Fixed
25Resource Requirement Service Area within PJM Interconnection,
26LLC, or its successor, that incorporates all retail customers

 

 

SB2161- 24 -LRB102 15735 SPS 21099 b

1of electric utilities that serve at least 3,000,000 retail
2customers in the State.
3        (1) The Agency shall each year, beginning in 2008, as
4    needed, issue a request for qualifications for experts or
5    expert consulting firms to develop the procurement plans
6    in accordance with Section 16-111.5 of the Public
7    Utilities Act. In order to qualify an expert or expert
8    consulting firm must have:
9            (A) direct previous experience assembling
10        large-scale power supply plans or portfolios for
11        end-use customers;
12            (B) an advanced degree in economics, mathematics,
13        engineering, risk management, or a related area of
14        study;
15            (C) 10 years of experience in the electricity
16        sector, including managing supply risk;
17            (D) expertise in wholesale electricity market
18        rules, including those established by the Federal
19        Energy Regulatory Commission and regional transmission
20        organizations;
21            (E) expertise in credit protocols and familiarity
22        with contract protocols;
23            (F) adequate resources to perform and fulfill the
24        required functions and responsibilities; and
25            (G) the absence of a conflict of interest and
26        inappropriate bias for or against potential bidders or

 

 

SB2161- 25 -LRB102 15735 SPS 21099 b

1        the affected electric utilities.
2        (2) The Agency shall each year, as needed, issue a
3    request for qualifications for a procurement administrator
4    to conduct the competitive procurement processes in
5    accordance with Section 16-111.5 of the Public Utilities
6    Act. In order to qualify an expert or expert consulting
7    firm must have:
8            (A) direct previous experience administering a
9        large-scale competitive procurement process;
10            (B) an advanced degree in economics, mathematics,
11        engineering, or a related area of study;
12            (C) 10 years of experience in the electricity
13        sector, including risk management experience;
14            (D) expertise in wholesale electricity market
15        rules, including those established by the Federal
16        Energy Regulatory Commission and regional transmission
17        organizations;
18            (E) expertise in credit and contract protocols;
19            (F) adequate resources to perform and fulfill the
20        required functions and responsibilities; and
21            (G) the absence of a conflict of interest and
22        inappropriate bias for or against potential bidders or
23        the affected electric utilities.
24        (3) The Agency shall provide affected utilities and
25    other interested parties with the lists of qualified
26    experts or expert consulting firms identified through the

 

 

SB2161- 26 -LRB102 15735 SPS 21099 b

1    request for qualifications processes that are under
2    consideration to develop the procurement plans and to
3    serve as the procurement administrator. The Agency shall
4    also provide each qualified expert's or expert consulting
5    firm's response to the request for qualifications. All
6    information provided under this subparagraph shall also be
7    provided to the Commission. The Agency may provide by rule
8    for fees associated with supplying the information to
9    utilities and other interested parties. These parties
10    shall, within 5 business days, notify the Agency in
11    writing if they object to any experts or expert consulting
12    firms on the lists. Objections shall be based on:
13            (A) failure to satisfy qualification criteria;
14            (B) identification of a conflict of interest; or
15            (C) evidence of inappropriate bias for or against
16        potential bidders or the affected utilities.
17        The Agency shall remove experts or expert consulting
18    firms from the lists within 10 days if there is a
19    reasonable basis for an objection and provide the updated
20    lists to the affected utilities and other interested
21    parties. If the Agency fails to remove an expert or expert
22    consulting firm from a list, an objecting party may seek
23    review by the Commission within 5 days thereafter by
24    filing a petition, and the Commission shall render a
25    ruling on the petition within 10 days. There is no right of
26    appeal of the Commission's ruling.

 

 

SB2161- 27 -LRB102 15735 SPS 21099 b

1        (4) The Agency shall issue requests for proposals to
2    the qualified experts or expert consulting firms to
3    develop a procurement plan for the affected utilities and
4    to serve as procurement administrator.
5        (5) The Agency shall select an expert or expert
6    consulting firm to develop procurement plans based on the
7    proposals submitted and shall award contracts of up to 5
8    years to those selected.
9        (6) The Agency shall select an expert or expert
10    consulting firm, with approval of the Commission, to serve
11    as procurement administrator based on the proposals
12    submitted. If the Commission rejects, within 5 days, the
13    Agency's selection, the Agency shall submit another
14    recommendation within 3 days based on the proposals
15    submitted. The Agency shall award a 5-year contract to the
16    expert or expert consulting firm so selected with
17    Commission approval.
18    (b) The experts or expert consulting firms retained by the
19Agency shall, as appropriate, prepare procurement plans, and
20conduct a competitive procurement process as prescribed in
21Section 16-111.5 of the Public Utilities Act, to ensure
22adequate, reliable, affordable, efficient, and environmentally
23sustainable electric service at the lowest total cost over
24time, taking into account any benefits of price stability, for
25eligible retail customers of electric utilities that on
26December 31, 2005 provided electric service to at least

 

 

SB2161- 28 -LRB102 15735 SPS 21099 b

1100,000 customers in the State of Illinois, and for eligible
2Illinois retail customers of small multi-jurisdictional
3electric utilities that (i) on December 31, 2005 served less
4than 100,000 customers in Illinois and (ii) request a
5procurement plan for their Illinois jurisdictional load.
6    (c) Renewable portfolio standard.
7        (1)(A) The Agency shall develop a long-term renewable
8    resources procurement plan that shall include procurement
9    programs and competitive procurement events necessary to
10    meet the goals set forth in this subsection (c). The
11    initial long-term renewable resources procurement plan
12    shall be released for comment no later than 160 days after
13    June 1, 2017 (the effective date of Public Act 99-906).
14    The Agency shall review, and may revise on an expedited
15    basis, the long-term renewable resources procurement plan
16    at least every 2 years, which shall be conducted in
17    conjunction with the procurement plan under Section
18    16-111.5 of the Public Utilities Act to the extent
19    practicable to minimize administrative expense. The
20    long-term renewable resources procurement plans shall be
21    subject to review and approval by the Commission under
22    Section 16-111.5 of the Public Utilities Act.
23        (B) Subject to subparagraph (F) of this paragraph (1),
24    the long-term renewable resources procurement plan shall
25    include the goals for procurement of renewable energy
26    credits to meet at least the following overall

 

 

SB2161- 29 -LRB102 15735 SPS 21099 b

1    percentages: 13% by the 2017 delivery year; increasing by
2    at least 1.5% each delivery year thereafter to at least
3    25% by the 2025 delivery year; and continuing at no less
4    than 25% for each delivery year thereafter. In the event
5    of a conflict between these goals and the new wind and new
6    photovoltaic procurement requirements described in items
7    (i) through (iii) of subparagraph (C) of this paragraph
8    (1), the long-term plan shall prioritize compliance with
9    the new wind and new photovoltaic procurement requirements
10    described in items (i) through (iii) of subparagraph (C)
11    of this paragraph (1) over the annual percentage targets
12    described in this subparagraph (B).
13        For the delivery year beginning June 1, 2017, the
14    procurement plan shall include cost-effective renewable
15    energy resources equal to at least 13% of each utility's
16    load for eligible retail customers and 13% of the
17    applicable portion of each utility's load for retail
18    customers who are not eligible retail customers, which
19    applicable portion shall equal 50% of the utility's load
20    for retail customers who are not eligible retail customers
21    on February 28, 2017.
22        For the delivery year beginning June 1, 2018, the
23    procurement plan shall include cost-effective renewable
24    energy resources equal to at least 14.5% of each utility's
25    load for eligible retail customers and 14.5% of the
26    applicable portion of each utility's load for retail

 

 

SB2161- 30 -LRB102 15735 SPS 21099 b

1    customers who are not eligible retail customers, which
2    applicable portion shall equal 75% of the utility's load
3    for retail customers who are not eligible retail customers
4    on February 28, 2017.
5        For the delivery year beginning June 1, 2019, and for
6    each year thereafter, the procurement plans shall include
7    cost-effective renewable energy resources equal to a
8    minimum percentage of each utility's load for all retail
9    customers as follows: 16% by June 1, 2019; increasing by
10    1.5% each year thereafter to 25% by June 1, 2025; and 25%
11    by June 1, 2026 and each year thereafter.
12        For each delivery year, the Agency shall first
13    recognize each utility's obligations for that delivery
14    year under existing contracts. Any renewable energy
15    credits under existing contracts, including renewable
16    energy credits as part of renewable energy resources,
17    shall be used to meet the goals set forth in this
18    subsection (c) for the delivery year.
19        (C) Of the renewable energy credits procured under
20    this subsection (c), at least 75% shall come from wind and
21    photovoltaic projects. The long-term renewable resources
22    procurement plan described in subparagraph (A) of this
23    paragraph (1) shall include the procurement of renewable
24    energy credits in amounts equal to at least the following:
25            (i) By the end of the 2020 delivery year:
26                At least 2,000,000 renewable energy credits

 

 

SB2161- 31 -LRB102 15735 SPS 21099 b

1            for each delivery year shall come from new wind
2            projects; and
3                At least 2,000,000 renewable energy credits
4            for each delivery year shall come from new
5            photovoltaic projects; of that amount, to the
6            extent possible, the Agency shall procure: at
7            least 50% from solar photovoltaic projects using
8            the program outlined in subparagraph (K) of this
9            paragraph (1) from distributed renewable energy
10            generation devices or community renewable
11            generation projects; at least 40% from
12            utility-scale solar projects; at least 2% from
13            brownfield site photovoltaic projects that are not
14            community renewable generation projects; and the
15            remainder shall be determined through the
16            long-term planning process described in
17            subparagraph (A) of this paragraph (1).
18            (ii) By the end of the 2025 delivery year:
19                At least 3,000,000 renewable energy credits
20            for each delivery year shall come from new wind
21            projects; and
22                At least 3,000,000 renewable energy credits
23            for each delivery year shall come from new
24            photovoltaic projects; of that amount, to the
25            extent possible, the Agency shall procure: at
26            least 50% from solar photovoltaic projects using

 

 

SB2161- 32 -LRB102 15735 SPS 21099 b

1            the program outlined in subparagraph (K) of this
2            paragraph (1) from distributed renewable energy
3            devices or community renewable generation
4            projects; at least 40% from utility-scale solar
5            projects; at least 2% from brownfield site
6            photovoltaic projects that are not community
7            renewable generation projects; and the remainder
8            shall be determined through the long-term planning
9            process described in subparagraph (A) of this
10            paragraph (1).
11            (iii) By the end of the 2030 delivery year:
12                At least 4,000,000 renewable energy credits
13            for each delivery year shall come from new wind
14            projects; and
15                At least 4,000,000 renewable energy credits
16            for each delivery year shall come from new
17            photovoltaic projects; of that amount, to the
18            extent possible, the Agency shall procure: at
19            least 50% from solar photovoltaic projects using
20            the program outlined in subparagraph (K) of this
21            paragraph (1) from distributed renewable energy
22            devices or community renewable generation
23            projects; at least 40% from utility-scale solar
24            projects; at least 2% from brownfield site
25            photovoltaic projects that are not community
26            renewable generation projects; and the remainder

 

 

SB2161- 33 -LRB102 15735 SPS 21099 b

1            shall be determined through the long-term planning
2            process described in subparagraph (A) of this
3            paragraph (1).
4            (iv) By the end of the 2033 delivery year,
5        renewable energy credits for each delivery year shall
6        come from new wind projects and from new photovoltaic
7        projects in sufficient quantities to meet the clean
8        capacity requirements for electric utilities that
9        serve more than 3,000,000 customers established under
10        subsection (a).
11            For purposes of this Section:
12                "New wind projects" means wind renewable
13            energy facilities that are energized after June 1,
14            2017 for the delivery year commencing June 1, 2017
15            or within 3 years after the date the Commission
16            approves contracts for subsequent delivery years.
17                "New photovoltaic projects" means photovoltaic
18            renewable energy facilities that are energized
19            after June 1, 2017. Photovoltaic projects
20            developed under Section 1-56 of this Act shall not
21            apply towards the new photovoltaic project
22            requirements in this subparagraph (C).
23        (D) Renewable energy credits shall be cost effective.
24    For purposes of this subsection (c), "cost effective"
25    means that the costs of procuring renewable energy
26    resources do not cause the limit stated in subparagraph

 

 

SB2161- 34 -LRB102 15735 SPS 21099 b

1    (E) of this paragraph (1) to be exceeded and, for
2    renewable energy credits procured through a competitive
3    procurement event, do not exceed benchmarks based on
4    market prices for like products in the region. For
5    purposes of this subsection (c), "like products" means
6    contracts for renewable energy credits from the same or
7    substantially similar technology, same or substantially
8    similar vintage (new or existing), the same or
9    substantially similar quantity, and the same or
10    substantially similar contract length and structure.
11    Benchmarks shall be developed by the procurement
12    administrator, in consultation with the Commission staff,
13    Agency staff, and the procurement monitor and shall be
14    subject to Commission review and approval. If price
15    benchmarks for like products in the region are not
16    available, the procurement administrator shall establish
17    price benchmarks based on publicly available data on
18    regional technology costs and expected current and future
19    regional energy prices. The benchmarks in this Section
20    shall not be used to curtail or otherwise reduce
21    contractual obligations entered into by or through the
22    Agency prior to June 1, 2017 (the effective date of Public
23    Act 99-906).
24        (E) For purposes of this subsection (c), the required
25    procurement of cost-effective renewable energy resources
26    for a particular year commencing prior to June 1, 2017

 

 

SB2161- 35 -LRB102 15735 SPS 21099 b

1    shall be measured as a percentage of the actual amount of
2    electricity (megawatt-hours) supplied by the electric
3    utility to eligible retail customers in the delivery year
4    ending immediately prior to the procurement, and, for
5    delivery years commencing on and after June 1, 2017, the
6    required procurement of cost-effective renewable energy
7    resources for a particular year shall be measured as a
8    percentage of the actual amount of electricity
9    (megawatt-hours) delivered by the electric utility in the
10    delivery year ending immediately prior to the procurement,
11    to all retail customers in its service territory. For
12    purposes of this subsection (c), the amount paid per
13    kilowatthour means the total amount paid for electric
14    service expressed on a per kilowatthour basis. For
15    purposes of this subsection (c), the total amount paid for
16    electric service includes without limitation amounts paid
17    for supply, transmission, distribution, surcharges, and
18    add-on taxes.
19        Notwithstanding the requirements of this subsection
20    (c), the total of renewable energy resources procured
21    under the procurement plan for any single year shall be
22    subject to the limitations of this subparagraph (E). Such
23    procurement shall be reduced for all retail customers
24    based on the amount necessary to limit the annual
25    estimated average net increase due to the costs of these
26    resources included in the amounts paid by eligible retail

 

 

SB2161- 36 -LRB102 15735 SPS 21099 b

1    customers in connection with electric service to no more
2    than the greater of 2.015% of the amount paid per
3    kilowatthour by those customers during the year ending May
4    31, 2007 or the incremental amount per kilowatthour paid
5    for these resources in 2011. To arrive at a maximum dollar
6    amount of renewable energy resources to be procured for
7    the particular delivery year, the resulting per
8    kilowatthour amount shall be applied to the actual amount
9    of kilowatthours of electricity delivered, or applicable
10    portion of such amount as specified in paragraph (1) of
11    this subsection (c), as applicable, by the electric
12    utility in the delivery year immediately prior to the
13    procurement to all retail customers in its service
14    territory. The calculations required by this subparagraph
15    (E) shall be made only once for each delivery year at the
16    time that the renewable energy resources are procured.
17    Once the determination as to the amount of renewable
18    energy resources to procure is made based on the
19    calculations set forth in this subparagraph (E) and the
20    contracts procuring those amounts are executed, no
21    subsequent rate impact determinations shall be made and no
22    adjustments to those contract amounts shall be allowed.
23    All costs incurred under such contracts shall be fully
24    recoverable by the electric utility as provided in this
25    Section.
26        (F) If the limitation on the amount of renewable

 

 

SB2161- 37 -LRB102 15735 SPS 21099 b

1    energy resources procured in subparagraph (E) of this
2    paragraph (1) prevents the Agency from meeting all of the
3    goals in this subsection (c), the Agency's long-term plan
4    shall prioritize compliance with the requirements of this
5    subsection (c) regarding renewable energy credits in the
6    following order:
7            (i) renewable energy credits under existing
8        contractual obligations;
9            (i-5) funding for the Illinois Solar for All
10        Program, as described in subparagraph (O) of this
11        paragraph (1);
12            (ii) renewable energy credits necessary to comply
13        with the new wind and new photovoltaic procurement
14        requirements described in items (i) through (iii) of
15        subparagraph (C) of this paragraph (1); and
16            (iii) renewable energy credits necessary to meet
17        the remaining requirements of this subsection (c).
18        (G) The following provisions shall apply to the
19    Agency's procurement of renewable energy credits under
20    this subsection (c):
21            (i) Notwithstanding whether a long-term renewable
22        resources procurement plan has been approved, the
23        Agency shall conduct an initial forward procurement
24        for renewable energy credits from new utility-scale
25        wind projects within 160 days after June 1, 2017 (the
26        effective date of Public Act 99-906). For the purposes

 

 

SB2161- 38 -LRB102 15735 SPS 21099 b

1        of this initial forward procurement, the Agency shall
2        solicit 15-year contracts for delivery of 1,000,000
3        renewable energy credits delivered annually from new
4        utility-scale wind projects to begin delivery on June
5        1, 2019, if available, but not later than June 1, 2021,
6        unless the project has delays in the establishment of
7        an operating interconnection with the applicable
8        transmission or distribution system as a result of the
9        actions or inactions of the transmission or
10        distribution provider, or other causes for force
11        majeure as outlined in the procurement contract, in
12        which case, not later than June 1, 2022. Payments to
13        suppliers of renewable energy credits shall commence
14        upon delivery. Renewable energy credits procured under
15        this initial procurement shall be included in the
16        Agency's long-term plan and shall apply to all
17        renewable energy goals in this subsection (c).
18            (ii) Notwithstanding whether a long-term renewable
19        resources procurement plan has been approved, the
20        Agency shall conduct an initial forward procurement
21        for renewable energy credits from new utility-scale
22        solar projects and brownfield site photovoltaic
23        projects within one year after June 1, 2017 (the
24        effective date of Public Act 99-906). For the purposes
25        of this initial forward procurement, the Agency shall
26        solicit 15-year contracts for delivery of 1,000,000

 

 

SB2161- 39 -LRB102 15735 SPS 21099 b

1        renewable energy credits delivered annually from new
2        utility-scale solar projects and brownfield site
3        photovoltaic projects to begin delivery on June 1,
4        2019, if available, but not later than June 1, 2021,
5        unless the project has delays in the establishment of
6        an operating interconnection with the applicable
7        transmission or distribution system as a result of the
8        actions or inactions of the transmission or
9        distribution provider, or other causes for force
10        majeure as outlined in the procurement contract, in
11        which case, not later than June 1, 2022. The Agency may
12        structure this initial procurement in one or more
13        discrete procurement events. Payments to suppliers of
14        renewable energy credits shall commence upon delivery.
15        Renewable energy credits procured under this initial
16        procurement shall be included in the Agency's
17        long-term plan and shall apply to all renewable energy
18        goals in this subsection (c).
19            (iii) Subsequent forward procurements for
20        utility-scale wind projects shall solicit at least
21        1,000,000 renewable energy credits delivered annually
22        per procurement event and shall be planned, scheduled,
23        and designed such that the cumulative amount of
24        renewable energy credits delivered from all new wind
25        projects in each delivery year shall not exceed the
26        Agency's projection of the cumulative amount of

 

 

SB2161- 40 -LRB102 15735 SPS 21099 b

1        renewable energy credits that will be delivered from
2        all new photovoltaic projects, including utility-scale
3        and distributed photovoltaic devices, in the same
4        delivery year at the time scheduled for wind contract
5        delivery.
6            (iv) If, at any time after the time set for
7        delivery of renewable energy credits pursuant to the
8        initial procurements in items (i) and (ii) of this
9        subparagraph (G), the cumulative amount of renewable
10        energy credits projected to be delivered from all new
11        wind projects in a given delivery year exceeds the
12        cumulative amount of renewable energy credits
13        projected to be delivered from all new photovoltaic
14        projects in that delivery year by 200,000 or more
15        renewable energy credits, then the Agency shall within
16        60 days adjust the procurement programs in the
17        long-term renewable resources procurement plan to
18        ensure that the projected cumulative amount of
19        renewable energy credits to be delivered from all new
20        wind projects does not exceed the projected cumulative
21        amount of renewable energy credits to be delivered
22        from all new photovoltaic projects by 200,000 or more
23        renewable energy credits, provided that nothing in
24        this Section shall preclude the projected cumulative
25        amount of renewable energy credits to be delivered
26        from all new photovoltaic projects from exceeding the

 

 

SB2161- 41 -LRB102 15735 SPS 21099 b

1        projected cumulative amount of renewable energy
2        credits to be delivered from all new wind projects in
3        each delivery year and provided further that nothing
4        in this item (iv) shall require the curtailment of an
5        executed contract. The Agency shall update, on a
6        quarterly basis, its projection of the renewable
7        energy credits to be delivered from all projects in
8        each delivery year. Notwithstanding anything to the
9        contrary, the Agency may adjust the timing of
10        procurement events conducted under this subparagraph
11        (G). The long-term renewable resources procurement
12        plan shall set forth the process by which the
13        adjustments may be made.
14            (v) All procurements under this subparagraph (G)
15        shall comply with the geographic requirements in
16        subparagraph (I) of this paragraph (1) and shall
17        follow the procurement processes and procedures
18        described in this Section and Section 16-111.5 of the
19        Public Utilities Act to the extent practicable, and
20        these processes and procedures may be expedited to
21        accommodate the schedule established by this
22        subparagraph (G).
23        (H) The procurement of renewable energy resources for
24    a given delivery year shall be reduced as described in
25    this subparagraph (H) if an alternative retail electric
26    supplier meets the requirements described in this

 

 

SB2161- 42 -LRB102 15735 SPS 21099 b

1    subparagraph (H).
2            (i) Within 45 days after June 1, 2017 (the
3        effective date of Public Act 99-906), an alternative
4        retail electric supplier or its successor shall submit
5        an informational filing to the Illinois Commerce
6        Commission certifying that, as of December 31, 2015,
7        the alternative retail electric supplier owned one or
8        more electric generating facilities that generates
9        renewable energy resources as defined in Section 1-10
10        of this Act, provided that such facilities are not
11        powered by wind or photovoltaics, and the facilities
12        generate one renewable energy credit for each
13        megawatthour of energy produced from the facility.
14            The informational filing shall identify each
15        facility that was eligible to satisfy the alternative
16        retail electric supplier's obligations under Section
17        16-115D of the Public Utilities Act as described in
18        this item (i).
19            (ii) For a given delivery year, the alternative
20        retail electric supplier may elect to supply its
21        retail customers with renewable energy credits from
22        the facility or facilities described in item (i) of
23        this subparagraph (H) that continue to be owned by the
24        alternative retail electric supplier.
25            (iii) The alternative retail electric supplier
26        shall notify the Agency and the applicable utility, no

 

 

SB2161- 43 -LRB102 15735 SPS 21099 b

1        later than February 28 of the year preceding the
2        applicable delivery year or 15 days after June 1, 2017
3        (the effective date of Public Act 99-906), whichever
4        is later, of its election under item (ii) of this
5        subparagraph (H) to supply renewable energy credits to
6        retail customers of the utility. Such election shall
7        identify the amount of renewable energy credits to be
8        supplied by the alternative retail electric supplier
9        to the utility's retail customers and the source of
10        the renewable energy credits identified in the
11        informational filing as described in item (i) of this
12        subparagraph (H), subject to the following
13        limitations:
14                For the delivery year beginning June 1, 2018,
15            the maximum amount of renewable energy credits to
16            be supplied by an alternative retail electric
17            supplier under this subparagraph (H) shall be 68%
18            multiplied by 25% multiplied by 14.5% multiplied
19            by the amount of metered electricity
20            (megawatt-hours) delivered by the alternative
21            retail electric supplier to Illinois retail
22            customers during the delivery year ending May 31,
23            2016.
24                For delivery years beginning June 1, 2019 and
25            each year thereafter, the maximum amount of
26            renewable energy credits to be supplied by an

 

 

SB2161- 44 -LRB102 15735 SPS 21099 b

1            alternative retail electric supplier under this
2            subparagraph (H) shall be 68% multiplied by 50%
3            multiplied by 16% multiplied by the amount of
4            metered electricity (megawatt-hours) delivered by
5            the alternative retail electric supplier to
6            Illinois retail customers during the delivery year
7            ending May 31, 2016, provided that the 16% value
8            shall increase by 1.5% each delivery year
9            thereafter to 25% by the delivery year beginning
10            June 1, 2025, and thereafter the 25% value shall
11            apply to each delivery year.
12            For each delivery year, the total amount of
13        renewable energy credits supplied by all alternative
14        retail electric suppliers under this subparagraph (H)
15        shall not exceed 9% of the Illinois target renewable
16        energy credit quantity. The Illinois target renewable
17        energy credit quantity for the delivery year beginning
18        June 1, 2018 is 14.5% multiplied by the total amount of
19        metered electricity (megawatt-hours) delivered in the
20        delivery year immediately preceding that delivery
21        year, provided that the 14.5% shall increase by 1.5%
22        each delivery year thereafter to 25% by the delivery
23        year beginning June 1, 2025, and thereafter the 25%
24        value shall apply to each delivery year.
25            If the requirements set forth in items (i) through
26        (iii) of this subparagraph (H) are met, the charges

 

 

SB2161- 45 -LRB102 15735 SPS 21099 b

1        that would otherwise be applicable to the retail
2        customers of the alternative retail electric supplier
3        under paragraph (6) of this subsection (c) for the
4        applicable delivery year shall be reduced by the ratio
5        of the quantity of renewable energy credits supplied
6        by the alternative retail electric supplier compared
7        to that supplier's target renewable energy credit
8        quantity. The supplier's target renewable energy
9        credit quantity for the delivery year beginning June
10        1, 2018 is 14.5% multiplied by the total amount of
11        metered electricity (megawatt-hours) delivered by the
12        alternative retail supplier in that delivery year,
13        provided that the 14.5% shall increase by 1.5% each
14        delivery year thereafter to 25% by the delivery year
15        beginning June 1, 2025, and thereafter the 25% value
16        shall apply to each delivery year.
17            On or before April 1 of each year, the Agency shall
18        annually publish a report on its website that
19        identifies the aggregate amount of renewable energy
20        credits supplied by alternative retail electric
21        suppliers under this subparagraph (H).
22        (I) The Agency shall design its long-term renewable
23    energy procurement plan to maximize the State's interest
24    in the health, safety, and welfare of its residents,
25    including but not limited to minimizing sulfur dioxide,
26    nitrogen oxide, particulate matter and other pollution

 

 

SB2161- 46 -LRB102 15735 SPS 21099 b

1    that adversely affects public health in this State,
2    increasing fuel and resource diversity in this State,
3    enhancing the reliability and resiliency of the
4    electricity distribution system in this State, meeting
5    goals to limit carbon dioxide emissions under federal or
6    State law, and contributing to a cleaner and healthier
7    environment for the citizens of this State. In order to
8    further these legislative purposes, renewable energy
9    credits shall be eligible to be counted toward the
10    renewable energy requirements of this subsection (c) if
11    they are generated from facilities located in this State.
12    The Agency may qualify renewable energy credits from
13    facilities located in states adjacent to Illinois if the
14    generator demonstrates and the Agency determines that the
15    operation of such facility or facilities will help promote
16    the State's interest in the health, safety, and welfare of
17    its residents based on the public interest criteria
18    described above. To ensure that the public interest
19    criteria are applied to the procurement and given full
20    effect, the Agency's long-term procurement plan shall
21    describe in detail how each public interest factor shall
22    be considered and weighted for facilities located in
23    states adjacent to Illinois.
24        (J) In order to promote the competitive development of
25    renewable energy resources in furtherance of the State's
26    interest in the health, safety, and welfare of its

 

 

SB2161- 47 -LRB102 15735 SPS 21099 b

1    residents, renewable energy credits shall not be eligible
2    to be counted toward the renewable energy requirements of
3    this subsection (c) if they are sourced from a generating
4    unit whose costs were being recovered through rates
5    regulated by this State or any other state or states on or
6    after January 1, 2017. Each contract executed to purchase
7    renewable energy credits under this subsection (c) shall
8    provide for the contract's termination if the costs of the
9    generating unit supplying the renewable energy credits
10    subsequently begin to be recovered through rates regulated
11    by this State or any other state or states; and each
12    contract shall further provide that, in that event, the
13    supplier of the credits must return 110% of all payments
14    received under the contract. Amounts returned under the
15    requirements of this subparagraph (J) shall be retained by
16    the utility and all of these amounts shall be used for the
17    procurement of additional renewable energy credits from
18    new wind or new photovoltaic resources as defined in this
19    subsection (c). The long-term plan shall provide that
20    these renewable energy credits shall be procured in the
21    next procurement event.
22        Notwithstanding the limitations of this subparagraph
23    (J), renewable energy credits sourced from generating
24    units that are constructed, purchased, owned, or leased by
25    an electric utility as part of an approved project,
26    program, or pilot under Section 1-56 of this Act shall be

 

 

SB2161- 48 -LRB102 15735 SPS 21099 b

1    eligible to be counted toward the renewable energy
2    requirements of this subsection (c), regardless of how the
3    costs of these units are recovered.
4        (K) The long-term renewable resources procurement plan
5    developed by the Agency in accordance with subparagraph
6    (A) of this paragraph (1) shall include an Adjustable
7    Block program for the procurement of renewable energy
8    credits from new photovoltaic projects that are
9    distributed renewable energy generation devices or new
10    photovoltaic community renewable generation projects. The
11    Adjustable Block program shall be designed to provide a
12    transparent schedule of prices and quantities to enable
13    the photovoltaic market to scale up and for renewable
14    energy credit prices to adjust at a predictable rate over
15    time. The prices set by the Adjustable Block program can
16    be reflected as a set value or as the product of a formula.
17        The Adjustable Block program shall include for each
18    category of eligible projects: a schedule of standard
19    block purchase prices to be offered; a series of steps,
20    with associated nameplate capacity and purchase prices
21    that adjust from step to step; and automatic opening of
22    the next step as soon as the nameplate capacity and
23    available purchase prices for an open step are fully
24    committed or reserved. Only projects energized on or after
25    June 1, 2017 shall be eligible for the Adjustable Block
26    program. For each block group the Agency shall determine

 

 

SB2161- 49 -LRB102 15735 SPS 21099 b

1    the number of blocks, the amount of generation capacity in
2    each block, and the purchase price for each block,
3    provided that the purchase price provided and the total
4    amount of generation in all blocks for all block groups
5    shall be sufficient to meet the goals in this subsection
6    (c). The Agency may periodically review its prior
7    decisions establishing the number of blocks, the amount of
8    generation capacity in each block, and the purchase price
9    for each block, and may propose, on an expedited basis,
10    changes to these previously set values, including but not
11    limited to redistributing these amounts and the available
12    funds as necessary and appropriate, subject to Commission
13    approval as part of the periodic plan revision process
14    described in Section 16-111.5 of the Public Utilities Act.
15    The Agency may define different block sizes, purchase
16    prices, or other distinct terms and conditions for
17    projects located in different utility service territories
18    if the Agency deems it necessary to meet the goals in this
19    subsection (c).
20        The Adjustable Block program shall include at least
21    the following block groups in at least the following
22    amounts, which may be adjusted upon review by the Agency
23    and approval by the Commission as described in this
24    subparagraph (K):
25            (i) At least 25% from distributed renewable energy
26        generation devices with a nameplate capacity of no

 

 

SB2161- 50 -LRB102 15735 SPS 21099 b

1        more than 10 kilowatts.
2            (ii) At least 25% from distributed renewable
3        energy generation devices with a nameplate capacity of
4        more than 10 kilowatts and no more than 2,000
5        kilowatts. The Agency may create sub-categories within
6        this category to account for the differences between
7        projects for small commercial customers, large
8        commercial customers, and public or non-profit
9        customers.
10            (iii) At least 25% from photovoltaic community
11        renewable generation projects.
12            (iv) The remaining 25% shall be allocated as
13        specified by the Agency in the long-term renewable
14        resources procurement plan.
15        The Adjustable Block program shall be designed to
16    ensure that renewable energy credits are procured from
17    photovoltaic distributed renewable energy generation
18    devices and new photovoltaic community renewable energy
19    generation projects in diverse locations and are not
20    concentrated in a few geographic areas.
21        (L) The procurement of photovoltaic renewable energy
22    credits under items (i) through (iv) of subparagraph (K)
23    of this paragraph (1) shall be subject to the following
24    contract and payment terms:
25            (i) The Agency shall procure contracts of at least
26        15 years in length.

 

 

SB2161- 51 -LRB102 15735 SPS 21099 b

1            (ii) For those renewable energy credits that
2        qualify and are procured under item (i) of
3        subparagraph (K) of this paragraph (1), the renewable
4        energy credit purchase price shall be paid in full by
5        the contracting utilities at the time that the
6        facility producing the renewable energy credits is
7        interconnected at the distribution system level of the
8        utility and energized. The electric utility shall
9        receive and retire all renewable energy credits
10        generated by the project for the first 15 years of
11        operation.
12            (iii) For those renewable energy credits that
13        qualify and are procured under item (ii) and (iii) of
14        subparagraph (K) of this paragraph (1) and any
15        additional categories of distributed generation
16        included in the long-term renewable resources
17        procurement plan and approved by the Commission, 20
18        percent of the renewable energy credit purchase price
19        shall be paid by the contracting utilities at the time
20        that the facility producing the renewable energy
21        credits is interconnected at the distribution system
22        level of the utility and energized. The remaining
23        portion shall be paid ratably over the subsequent
24        4-year period. The electric utility shall receive and
25        retire all renewable energy credits generated by the
26        project for the first 15 years of operation.

 

 

SB2161- 52 -LRB102 15735 SPS 21099 b

1            (iv) Each contract shall include provisions to
2        ensure the delivery of the renewable energy credits
3        for the full term of the contract.
4            (v) The utility shall be the counterparty to the
5        contracts executed under this subparagraph (L) that
6        are approved by the Commission under the process
7        described in Section 16-111.5 of the Public Utilities
8        Act. No contract shall be executed for an amount that
9        is less than one renewable energy credit per year.
10            (vi) If, at any time, approved applications for
11        the Adjustable Block program exceed funds collected by
12        the electric utility or would cause the Agency to
13        exceed the limitation described in subparagraph (E) of
14        this paragraph (1) on the amount of renewable energy
15        resources that may be procured, then the Agency shall
16        consider future uncommitted funds to be reserved for
17        these contracts on a first-come, first-served basis,
18        with the delivery of renewable energy credits required
19        beginning at the time that the reserved funds become
20        available.
21            (vii) Nothing in this Section shall require the
22        utility to advance any payment or pay any amounts that
23        exceed the actual amount of revenues collected by the
24        utility under paragraph (6) of this subsection (c) and
25        subsection (k) of Section 16-108 of the Public
26        Utilities Act, and contracts executed under this

 

 

SB2161- 53 -LRB102 15735 SPS 21099 b

1        Section shall expressly incorporate this limitation.
2        (M) The Agency shall be authorized to retain one or
3    more experts or expert consulting firms to develop,
4    administer, implement, operate, and evaluate the
5    Adjustable Block program described in subparagraph (K) of
6    this paragraph (1), and the Agency shall retain the
7    consultant or consultants in the same manner, to the
8    extent practicable, as the Agency retains others to
9    administer provisions of this Act, including, but not
10    limited to, the procurement administrator. The selection
11    of experts and expert consulting firms and the procurement
12    process described in this subparagraph (M) are exempt from
13    the requirements of Section 20-10 of the Illinois
14    Procurement Code, under Section 20-10 of that Code. The
15    Agency shall strive to minimize administrative expenses in
16    the implementation of the Adjustable Block program.
17        The Agency and its consultant or consultants shall
18    monitor block activity, share program activity with
19    stakeholders and conduct regularly scheduled meetings to
20    discuss program activity and market conditions. If
21    necessary, the Agency may make prospective administrative
22    adjustments to the Adjustable Block program design, such
23    as redistributing available funds or making adjustments to
24    purchase prices as necessary to achieve the goals of this
25    subsection (c). Program modifications to any price,
26    capacity block, or other program element that do not

 

 

SB2161- 54 -LRB102 15735 SPS 21099 b

1    deviate from the Commission's approved value by more than
2    25% shall take effect immediately and are not subject to
3    Commission review and approval. Program modifications to
4    any price, capacity block, or other program element that
5    deviate more than 25% from the Commission's approved value
6    must be approved by the Commission as a long-term plan
7    amendment under Section 16-111.5 of the Public Utilities
8    Act. The Agency shall consider stakeholder feedback when
9    making adjustments to the Adjustable Block design and
10    shall notify stakeholders in advance of any planned
11    changes.
12        (N) The long-term renewable resources procurement plan
13    required by this subsection (c) shall include a community
14    renewable generation program. The Agency shall establish
15    the terms, conditions, and program requirements for
16    community renewable generation projects with a goal to
17    expand renewable energy generating facility access to a
18    broader group of energy consumers, to ensure robust
19    participation opportunities for residential and small
20    commercial customers and those who cannot install
21    renewable energy on their own properties. Any plan
22    approved by the Commission shall allow subscriptions to
23    community renewable generation projects to be portable and
24    transferable. For purposes of this subparagraph (N),
25    "portable" means that subscriptions may be retained by the
26    subscriber even if the subscriber relocates or changes its

 

 

SB2161- 55 -LRB102 15735 SPS 21099 b

1    address within the same utility service territory; and
2    "transferable" means that a subscriber may assign or sell
3    subscriptions to another person within the same utility
4    service territory.
5        Electric utilities shall provide a monetary credit to
6    a subscriber's subsequent bill for service for the
7    proportional output of a community renewable generation
8    project attributable to that subscriber as specified in
9    Section 16-107.5 of the Public Utilities Act.
10        The Agency shall purchase renewable energy credits
11    from subscribed shares of photovoltaic community renewable
12    generation projects through the Adjustable Block program
13    described in subparagraph (K) of this paragraph (1) or
14    through the Illinois Solar for All Program described in
15    Section 1-56 of this Act. The electric utility shall
16    purchase any unsubscribed energy from community renewable
17    generation projects that are Qualifying Facilities ("QF")
18    under the electric utility's tariff for purchasing the
19    output from QFs under Public Utilities Regulatory Policies
20    Act of 1978.
21        The owners of and any subscribers to a community
22    renewable generation project shall not be considered
23    public utilities or alternative retail electricity
24    suppliers under the Public Utilities Act solely as a
25    result of their interest in or subscription to a community
26    renewable generation project and shall not be required to

 

 

SB2161- 56 -LRB102 15735 SPS 21099 b

1    become an alternative retail electric supplier by
2    participating in a community renewable generation project
3    with a public utility.
4        (O) For the delivery year beginning June 1, 2018, the
5    long-term renewable resources procurement plan required by
6    this subsection (c) shall provide for the Agency to
7    procure contracts to continue offering the Illinois Solar
8    for All Program described in subsection (b) of Section
9    1-56 of this Act, and the contracts approved by the
10    Commission shall be executed by the utilities that are
11    subject to this subsection (c). The long-term renewable
12    resources procurement plan shall allocate 5% of the funds
13    available under the plan for the applicable delivery year,
14    or $10,000,000 per delivery year, whichever is greater, to
15    fund the programs, and the plan shall determine the amount
16    of funding to be apportioned to the programs identified in
17    subsection (b) of Section 1-56 of this Act; provided that
18    for the delivery years beginning June 1, 2017, June 1,
19    2021, and June 1, 2025, the long-term renewable resources
20    procurement plan shall allocate 10% of the funds available
21    under the plan for the applicable delivery year, or
22    $20,000,000 per delivery year, whichever is greater, and
23    $10,000,000 of such funds in such year shall be used by an
24    electric utility that serves more than 3,000,000 retail
25    customers in the State to implement a Commission-approved
26    plan under Section 16-108.12 of the Public Utilities Act.

 

 

SB2161- 57 -LRB102 15735 SPS 21099 b

1    In making the determinations required under this
2    subparagraph (O), the Commission shall consider the
3    experience and performance under the programs and any
4    evaluation reports. The Commission shall also provide for
5    an independent evaluation of those programs on a periodic
6    basis that are funded under this subparagraph (O).
7        (2) (Blank).
8        (3) (Blank).
9        (4) The electric utility shall retire all renewable
10    energy credits used to comply with the renewable portfolio
11    standard.
12        (5) Beginning with the 2010 delivery year and ending
13    June 1, 2017, an electric utility subject to this
14    subsection (c) shall apply the lesser of the maximum
15    alternative compliance payment rate or the most recent
16    estimated alternative compliance payment rate for its
17    service territory for the corresponding compliance period,
18    established pursuant to subsection (d) of Section 16-115D
19    of the Public Utilities Act to its retail customers that
20    take service pursuant to the electric utility's hourly
21    pricing tariff or tariffs. The electric utility shall
22    retain all amounts collected as a result of the
23    application of the alternative compliance payment rate or
24    rates to such customers, and, beginning in 2011, the
25    utility shall include in the information provided under
26    item (1) of subsection (d) of Section 16-111.5 of the

 

 

SB2161- 58 -LRB102 15735 SPS 21099 b

1    Public Utilities Act the amounts collected under the
2    alternative compliance payment rate or rates for the prior
3    year ending May 31. Notwithstanding any limitation on the
4    procurement of renewable energy resources imposed by item
5    (2) of this subsection (c), the Agency shall increase its
6    spending on the purchase of renewable energy resources to
7    be procured by the electric utility for the next plan year
8    by an amount equal to the amounts collected by the utility
9    under the alternative compliance payment rate or rates in
10    the prior year ending May 31.
11        (6) The electric utility shall be entitled to recover
12    all of its costs associated with the procurement of
13    renewable energy credits under plans approved under this
14    Section and Section 16-111.5 of the Public Utilities Act.
15    These costs shall include associated reasonable expenses
16    for implementing the procurement programs, including, but
17    not limited to, the costs of administering and evaluating
18    the Adjustable Block program, through an automatic
19    adjustment clause tariff in accordance with subsection (k)
20    of Section 16-108 of the Public Utilities Act.
21        (7) Renewable energy credits procured from new
22    photovoltaic projects or new distributed renewable energy
23    generation devices under this Section after June 1, 2017
24    (the effective date of Public Act 99-906) must be procured
25    from devices installed by a qualified person in compliance
26    with the requirements of Section 16-128A of the Public

 

 

SB2161- 59 -LRB102 15735 SPS 21099 b

1    Utilities Act and any rules or regulations adopted
2    thereunder.
3        In meeting the renewable energy requirements of this
4    subsection (c), to the extent feasible and consistent with
5    State and federal law, the renewable energy credit
6    procurements, Adjustable Block solar program, and
7    community renewable generation program shall provide
8    employment opportunities for all segments of the
9    population and workforce, including minority-owned and
10    female-owned business enterprises, and shall not,
11    consistent with State and federal law, discriminate based
12    on race or socioeconomic status.
13    (d) Clean coal portfolio standard.
14        (1) The procurement plans shall include electricity
15    generated using clean coal. Each utility shall enter into
16    one or more sourcing agreements with the initial clean
17    coal facility, as provided in paragraph (3) of this
18    subsection (d), covering electricity generated by the
19    initial clean coal facility representing at least 5% of
20    each utility's total supply to serve the load of eligible
21    retail customers in 2015 and each year thereafter, as
22    described in paragraph (3) of this subsection (d), subject
23    to the limits specified in paragraph (2) of this
24    subsection (d). It is the goal of the State that by January
25    1, 2025, 25% of the electricity used in the State shall be
26    generated by cost-effective clean coal facilities. For

 

 

SB2161- 60 -LRB102 15735 SPS 21099 b

1    purposes of this subsection (d), "cost-effective" means
2    that the expenditures pursuant to such sourcing agreements
3    do not cause the limit stated in paragraph (2) of this
4    subsection (d) to be exceeded and do not exceed cost-based
5    benchmarks, which shall be developed to assess all
6    expenditures pursuant to such sourcing agreements covering
7    electricity generated by clean coal facilities, other than
8    the initial clean coal facility, by the procurement
9    administrator, in consultation with the Commission staff,
10    Agency staff, and the procurement monitor and shall be
11    subject to Commission review and approval.
12        A utility party to a sourcing agreement shall
13    immediately retire any emission credits that it receives
14    in connection with the electricity covered by such
15    agreement.
16        Utilities shall maintain adequate records documenting
17    the purchases under the sourcing agreement to comply with
18    this subsection (d) and shall file an accounting with the
19    load forecast that must be filed with the Agency by July 15
20    of each year, in accordance with subsection (d) of Section
21    16-111.5 of the Public Utilities Act.
22        A utility shall be deemed to have complied with the
23    clean coal portfolio standard specified in this subsection
24    (d) if the utility enters into a sourcing agreement as
25    required by this subsection (d).
26        (2) For purposes of this subsection (d), the required

 

 

SB2161- 61 -LRB102 15735 SPS 21099 b

1    execution of sourcing agreements with the initial clean
2    coal facility for a particular year shall be measured as a
3    percentage of the actual amount of electricity
4    (megawatt-hours) supplied by the electric utility to
5    eligible retail customers in the planning year ending
6    immediately prior to the agreement's execution. For
7    purposes of this subsection (d), the amount paid per
8    kilowatthour means the total amount paid for electric
9    service expressed on a per kilowatthour basis. For
10    purposes of this subsection (d), the total amount paid for
11    electric service includes without limitation amounts paid
12    for supply, transmission, distribution, surcharges and
13    add-on taxes.
14        Notwithstanding the requirements of this subsection
15    (d), the total amount paid under sourcing agreements with
16    clean coal facilities pursuant to the procurement plan for
17    any given year shall be reduced by an amount necessary to
18    limit the annual estimated average net increase due to the
19    costs of these resources included in the amounts paid by
20    eligible retail customers in connection with electric
21    service to:
22            (A) in 2010, no more than 0.5% of the amount paid
23        per kilowatthour by those customers during the year
24        ending May 31, 2009;
25            (B) in 2011, the greater of an additional 0.5% of
26        the amount paid per kilowatthour by those customers

 

 

SB2161- 62 -LRB102 15735 SPS 21099 b

1        during the year ending May 31, 2010 or 1% of the amount
2        paid per kilowatthour by those customers during the
3        year ending May 31, 2009;
4            (C) in 2012, the greater of an additional 0.5% of
5        the amount paid per kilowatthour by those customers
6        during the year ending May 31, 2011 or 1.5% of the
7        amount paid per kilowatthour by those customers during
8        the year ending May 31, 2009;
9            (D) in 2013, the greater of an additional 0.5% of
10        the amount paid per kilowatthour by those customers
11        during the year ending May 31, 2012 or 2% of the amount
12        paid per kilowatthour by those customers during the
13        year ending May 31, 2009; and
14            (E) thereafter, the total amount paid under
15        sourcing agreements with clean coal facilities
16        pursuant to the procurement plan for any single year
17        shall be reduced by an amount necessary to limit the
18        estimated average net increase due to the cost of
19        these resources included in the amounts paid by
20        eligible retail customers in connection with electric
21        service to no more than the greater of (i) 2.015% of
22        the amount paid per kilowatthour by those customers
23        during the year ending May 31, 2009 or (ii) the
24        incremental amount per kilowatthour paid for these
25        resources in 2013. These requirements may be altered
26        only as provided by statute.

 

 

SB2161- 63 -LRB102 15735 SPS 21099 b

1        No later than June 30, 2015, the Commission shall
2    review the limitation on the total amount paid under
3    sourcing agreements, if any, with clean coal facilities
4    pursuant to this subsection (d) and report to the General
5    Assembly its findings as to whether that limitation unduly
6    constrains the amount of electricity generated by
7    cost-effective clean coal facilities that is covered by
8    sourcing agreements.
9        (3) Initial clean coal facility. In order to promote
10    development of clean coal facilities in Illinois, each
11    electric utility subject to this Section shall execute a
12    sourcing agreement to source electricity from a proposed
13    clean coal facility in Illinois (the "initial clean coal
14    facility") that will have a nameplate capacity of at least
15    500 MW when commercial operation commences, that has a
16    final Clean Air Act permit on June 1, 2009 (the effective
17    date of Public Act 95-1027), and that will meet the
18    definition of clean coal facility in Section 1-10 of this
19    Act when commercial operation commences. The sourcing
20    agreements with this initial clean coal facility shall be
21    subject to both approval of the initial clean coal
22    facility by the General Assembly and satisfaction of the
23    requirements of paragraph (4) of this subsection (d) and
24    shall be executed within 90 days after any such approval
25    by the General Assembly. The Agency and the Commission
26    shall have authority to inspect all books and records

 

 

SB2161- 64 -LRB102 15735 SPS 21099 b

1    associated with the initial clean coal facility during the
2    term of such a sourcing agreement. A utility's sourcing
3    agreement for electricity produced by the initial clean
4    coal facility shall include:
5            (A) a formula contractual price (the "contract
6        price") approved pursuant to paragraph (4) of this
7        subsection (d), which shall:
8                (i) be determined using a cost of service
9            methodology employing either a level or deferred
10            capital recovery component, based on a capital
11            structure consisting of 45% equity and 55% debt,
12            and a return on equity as may be approved by the
13            Federal Energy Regulatory Commission, which in any
14            case may not exceed the lower of 11.5% or the rate
15            of return approved by the General Assembly
16            pursuant to paragraph (4) of this subsection (d);
17            and
18                (ii) provide that all miscellaneous net
19            revenue, including but not limited to net revenue
20            from the sale of emission allowances, if any,
21            substitute natural gas, if any, grants or other
22            support provided by the State of Illinois or the
23            United States Government, firm transmission
24            rights, if any, by-products produced by the
25            facility, energy or capacity derived from the
26            facility and not covered by a sourcing agreement

 

 

SB2161- 65 -LRB102 15735 SPS 21099 b

1            pursuant to paragraph (3) of this subsection (d)
2            or item (5) of subsection (d) of Section 16-115 of
3            the Public Utilities Act, whether generated from
4            the synthesis gas derived from coal, from SNG, or
5            from natural gas, shall be credited against the
6            revenue requirement for this initial clean coal
7            facility;
8            (B) power purchase provisions, which shall:
9                (i) provide that the utility party to such
10            sourcing agreement shall pay the contract price
11            for electricity delivered under such sourcing
12            agreement;
13                (ii) require delivery of electricity to the
14            regional transmission organization market of the
15            utility that is party to such sourcing agreement;
16                (iii) require the utility party to such
17            sourcing agreement to buy from the initial clean
18            coal facility in each hour an amount of energy
19            equal to all clean coal energy made available from
20            the initial clean coal facility during such hour
21            times a fraction, the numerator of which is such
22            utility's retail market sales of electricity
23            (expressed in kilowatthours sold) in the State
24            during the prior calendar month and the
25            denominator of which is the total retail market
26            sales of electricity (expressed in kilowatthours

 

 

SB2161- 66 -LRB102 15735 SPS 21099 b

1            sold) in the State by utilities during such prior
2            month and the sales of electricity (expressed in
3            kilowatthours sold) in the State by alternative
4            retail electric suppliers during such prior month
5            that are subject to the requirements of this
6            subsection (d) and paragraph (5) of subsection (d)
7            of Section 16-115 of the Public Utilities Act,
8            provided that the amount purchased by the utility
9            in any year will be limited by paragraph (2) of
10            this subsection (d); and
11                (iv) be considered pre-existing contracts in
12            such utility's procurement plans for eligible
13            retail customers;
14            (C) contract for differences provisions, which
15        shall:
16                (i) require the utility party to such sourcing
17            agreement to contract with the initial clean coal
18            facility in each hour with respect to an amount of
19            energy equal to all clean coal energy made
20            available from the initial clean coal facility
21            during such hour times a fraction, the numerator
22            of which is such utility's retail market sales of
23            electricity (expressed in kilowatthours sold) in
24            the utility's service territory in the State
25            during the prior calendar month and the
26            denominator of which is the total retail market

 

 

SB2161- 67 -LRB102 15735 SPS 21099 b

1            sales of electricity (expressed in kilowatthours
2            sold) in the State by utilities during such prior
3            month and the sales of electricity (expressed in
4            kilowatthours sold) in the State by alternative
5            retail electric suppliers during such prior month
6            that are subject to the requirements of this
7            subsection (d) and paragraph (5) of subsection (d)
8            of Section 16-115 of the Public Utilities Act,
9            provided that the amount paid by the utility in
10            any year will be limited by paragraph (2) of this
11            subsection (d);
12                (ii) provide that the utility's payment
13            obligation in respect of the quantity of
14            electricity determined pursuant to the preceding
15            clause (i) shall be limited to an amount equal to
16            (1) the difference between the contract price
17            determined pursuant to subparagraph (A) of
18            paragraph (3) of this subsection (d) and the
19            day-ahead price for electricity delivered to the
20            regional transmission organization market of the
21            utility that is party to such sourcing agreement
22            (or any successor delivery point at which such
23            utility's supply obligations are financially
24            settled on an hourly basis) (the "reference
25            price") on the day preceding the day on which the
26            electricity is delivered to the initial clean coal

 

 

SB2161- 68 -LRB102 15735 SPS 21099 b

1            facility busbar, multiplied by (2) the quantity of
2            electricity determined pursuant to the preceding
3            clause (i); and
4                (iii) not require the utility to take physical
5            delivery of the electricity produced by the
6            facility;
7            (D) general provisions, which shall:
8                (i) specify a term of no more than 30 years,
9            commencing on the commercial operation date of the
10            facility;
11                (ii) provide that utilities shall maintain
12            adequate records documenting purchases under the
13            sourcing agreements entered into to comply with
14            this subsection (d) and shall file an accounting
15            with the load forecast that must be filed with the
16            Agency by July 15 of each year, in accordance with
17            subsection (d) of Section 16-111.5 of the Public
18            Utilities Act;
19                (iii) provide that all costs associated with
20            the initial clean coal facility will be
21            periodically reported to the Federal Energy
22            Regulatory Commission and to purchasers in
23            accordance with applicable laws governing
24            cost-based wholesale power contracts;
25                (iv) permit the Illinois Power Agency to
26            assume ownership of the initial clean coal

 

 

SB2161- 69 -LRB102 15735 SPS 21099 b

1            facility, without monetary consideration and
2            otherwise on reasonable terms acceptable to the
3            Agency, if the Agency so requests no less than 3
4            years prior to the end of the stated contract
5            term;
6                (v) require the owner of the initial clean
7            coal facility to provide documentation to the
8            Commission each year, starting in the facility's
9            first year of commercial operation, accurately
10            reporting the quantity of carbon emissions from
11            the facility that have been captured and
12            sequestered and report any quantities of carbon
13            released from the site or sites at which carbon
14            emissions were sequestered in prior years, based
15            on continuous monitoring of such sites. If, in any
16            year after the first year of commercial operation,
17            the owner of the facility fails to demonstrate
18            that the initial clean coal facility captured and
19            sequestered at least 50% of the total carbon
20            emissions that the facility would otherwise emit
21            or that sequestration of emissions from prior
22            years has failed, resulting in the release of
23            carbon dioxide into the atmosphere, the owner of
24            the facility must offset excess emissions. Any
25            such carbon offsets must be permanent, additional,
26            verifiable, real, located within the State of

 

 

SB2161- 70 -LRB102 15735 SPS 21099 b

1            Illinois, and legally and practicably enforceable.
2            The cost of such offsets for the facility that are
3            not recoverable shall not exceed $15 million in
4            any given year. No costs of any such purchases of
5            carbon offsets may be recovered from a utility or
6            its customers. All carbon offsets purchased for
7            this purpose and any carbon emission credits
8            associated with sequestration of carbon from the
9            facility must be permanently retired. The initial
10            clean coal facility shall not forfeit its
11            designation as a clean coal facility if the
12            facility fails to fully comply with the applicable
13            carbon sequestration requirements in any given
14            year, provided the requisite offsets are
15            purchased. However, the Attorney General, on
16            behalf of the People of the State of Illinois, may
17            specifically enforce the facility's sequestration
18            requirement and the other terms of this contract
19            provision. Compliance with the sequestration
20            requirements and offset purchase requirements
21            specified in paragraph (3) of this subsection (d)
22            shall be reviewed annually by an independent
23            expert retained by the owner of the initial clean
24            coal facility, with the advance written approval
25            of the Attorney General. The Commission may, in
26            the course of the review specified in item (vii),

 

 

SB2161- 71 -LRB102 15735 SPS 21099 b

1            reduce the allowable return on equity for the
2            facility if the facility willfully fails to comply
3            with the carbon capture and sequestration
4            requirements set forth in this item (v);
5                (vi) include limits on, and accordingly
6            provide for modification of, the amount the
7            utility is required to source under the sourcing
8            agreement consistent with paragraph (2) of this
9            subsection (d);
10                (vii) require Commission review: (1) to
11            determine the justness, reasonableness, and
12            prudence of the inputs to the formula referenced
13            in subparagraphs (A)(i) through (A)(iii) of
14            paragraph (3) of this subsection (d), prior to an
15            adjustment in those inputs including, without
16            limitation, the capital structure and return on
17            equity, fuel costs, and other operations and
18            maintenance costs and (2) to approve the costs to
19            be passed through to customers under the sourcing
20            agreement by which the utility satisfies its
21            statutory obligations. Commission review shall
22            occur no less than every 3 years, regardless of
23            whether any adjustments have been proposed, and
24            shall be completed within 9 months;
25                (viii) limit the utility's obligation to such
26            amount as the utility is allowed to recover

 

 

SB2161- 72 -LRB102 15735 SPS 21099 b

1            through tariffs filed with the Commission,
2            provided that neither the clean coal facility nor
3            the utility waives any right to assert federal
4            pre-emption or any other argument in response to a
5            purported disallowance of recovery costs;
6                (ix) limit the utility's or alternative retail
7            electric supplier's obligation to incur any
8            liability until such time as the facility is in
9            commercial operation and generating power and
10            energy and such power and energy is being
11            delivered to the facility busbar;
12                (x) provide that the owner or owners of the
13            initial clean coal facility, which is the
14            counterparty to such sourcing agreement, shall
15            have the right from time to time to elect whether
16            the obligations of the utility party thereto shall
17            be governed by the power purchase provisions or
18            the contract for differences provisions;
19                (xi) append documentation showing that the
20            formula rate and contract, insofar as they relate
21            to the power purchase provisions, have been
22            approved by the Federal Energy Regulatory
23            Commission pursuant to Section 205 of the Federal
24            Power Act;
25                (xii) provide that any changes to the terms of
26            the contract, insofar as such changes relate to

 

 

SB2161- 73 -LRB102 15735 SPS 21099 b

1            the power purchase provisions, are subject to
2            review under the public interest standard applied
3            by the Federal Energy Regulatory Commission
4            pursuant to Sections 205 and 206 of the Federal
5            Power Act; and
6                (xiii) conform with customary lender
7            requirements in power purchase agreements used as
8            the basis for financing non-utility generators.
9        (4) Effective date of sourcing agreements with the
10    initial clean coal facility. Any proposed sourcing
11    agreement with the initial clean coal facility shall not
12    become effective unless the following reports are prepared
13    and submitted and authorizations and approvals obtained:
14            (i) Facility cost report. The owner of the initial
15        clean coal facility shall submit to the Commission,
16        the Agency, and the General Assembly a front-end
17        engineering and design study, a facility cost report,
18        method of financing (including but not limited to
19        structure and associated costs), and an operating and
20        maintenance cost quote for the facility (collectively
21        "facility cost report"), which shall be prepared in
22        accordance with the requirements of this paragraph (4)
23        of subsection (d) of this Section, and shall provide
24        the Commission and the Agency access to the work
25        papers, relied upon documents, and any other backup
26        documentation related to the facility cost report.

 

 

SB2161- 74 -LRB102 15735 SPS 21099 b

1            (ii) Commission report. Within 6 months following
2        receipt of the facility cost report, the Commission,
3        in consultation with the Agency, shall submit a report
4        to the General Assembly setting forth its analysis of
5        the facility cost report. Such report shall include,
6        but not be limited to, a comparison of the costs
7        associated with electricity generated by the initial
8        clean coal facility to the costs associated with
9        electricity generated by other types of generation
10        facilities, an analysis of the rate impacts on
11        residential and small business customers over the life
12        of the sourcing agreements, and an analysis of the
13        likelihood that the initial clean coal facility will
14        commence commercial operation by and be delivering
15        power to the facility's busbar by 2016. To assist in
16        the preparation of its report, the Commission, in
17        consultation with the Agency, may hire one or more
18        experts or consultants, the costs of which shall be
19        paid for by the owner of the initial clean coal
20        facility. The Commission and Agency may begin the
21        process of selecting such experts or consultants prior
22        to receipt of the facility cost report.
23            (iii) General Assembly approval. The proposed
24        sourcing agreements shall not take effect unless,
25        based on the facility cost report and the Commission's
26        report, the General Assembly enacts authorizing

 

 

SB2161- 75 -LRB102 15735 SPS 21099 b

1        legislation approving (A) the projected price, stated
2        in cents per kilowatthour, to be charged for
3        electricity generated by the initial clean coal
4        facility, (B) the projected impact on residential and
5        small business customers' bills over the life of the
6        sourcing agreements, and (C) the maximum allowable
7        return on equity for the project; and
8            (iv) Commission review. If the General Assembly
9        enacts authorizing legislation pursuant to
10        subparagraph (iii) approving a sourcing agreement, the
11        Commission shall, within 90 days of such enactment,
12        complete a review of such sourcing agreement. During
13        such time period, the Commission shall implement any
14        directive of the General Assembly, resolve any
15        disputes between the parties to the sourcing agreement
16        concerning the terms of such agreement, approve the
17        form of such agreement, and issue an order finding
18        that the sourcing agreement is prudent and reasonable.
19        The facility cost report shall be prepared as follows:
20            (A) The facility cost report shall be prepared by
21        duly licensed engineering and construction firms
22        detailing the estimated capital costs payable to one
23        or more contractors or suppliers for the engineering,
24        procurement and construction of the components
25        comprising the initial clean coal facility and the
26        estimated costs of operation and maintenance of the

 

 

SB2161- 76 -LRB102 15735 SPS 21099 b

1        facility. The facility cost report shall include:
2                (i) an estimate of the capital cost of the
3            core plant based on one or more front end
4            engineering and design studies for the
5            gasification island and related facilities. The
6            core plant shall include all civil, structural,
7            mechanical, electrical, control, and safety
8            systems.
9                (ii) an estimate of the capital cost of the
10            balance of the plant, including any capital costs
11            associated with sequestration of carbon dioxide
12            emissions and all interconnects and interfaces
13            required to operate the facility, such as
14            transmission of electricity, construction or
15            backfeed power supply, pipelines to transport
16            substitute natural gas or carbon dioxide, potable
17            water supply, natural gas supply, water supply,
18            water discharge, landfill, access roads, and coal
19            delivery.
20            The quoted construction costs shall be expressed
21        in nominal dollars as of the date that the quote is
22        prepared and shall include capitalized financing costs
23        during construction, taxes, insurance, and other
24        owner's costs, and an assumed escalation in materials
25        and labor beyond the date as of which the construction
26        cost quote is expressed.

 

 

SB2161- 77 -LRB102 15735 SPS 21099 b

1            (B) The front end engineering and design study for
2        the gasification island and the cost study for the
3        balance of plant shall include sufficient design work
4        to permit quantification of major categories of
5        materials, commodities and labor hours, and receipt of
6        quotes from vendors of major equipment required to
7        construct and operate the clean coal facility.
8            (C) The facility cost report shall also include an
9        operating and maintenance cost quote that will provide
10        the estimated cost of delivered fuel, personnel,
11        maintenance contracts, chemicals, catalysts,
12        consumables, spares, and other fixed and variable
13        operations and maintenance costs. The delivered fuel
14        cost estimate will be provided by a recognized third
15        party expert or experts in the fuel and transportation
16        industries. The balance of the operating and
17        maintenance cost quote, excluding delivered fuel
18        costs, will be developed based on the inputs provided
19        by duly licensed engineering and construction firms
20        performing the construction cost quote, potential
21        vendors under long-term service agreements and plant
22        operating agreements, or recognized third party plant
23        operator or operators.
24            The operating and maintenance cost quote
25        (including the cost of the front end engineering and
26        design study) shall be expressed in nominal dollars as

 

 

SB2161- 78 -LRB102 15735 SPS 21099 b

1        of the date that the quote is prepared and shall
2        include taxes, insurance, and other owner's costs, and
3        an assumed escalation in materials and labor beyond
4        the date as of which the operating and maintenance
5        cost quote is expressed.
6            (D) The facility cost report shall also include an
7        analysis of the initial clean coal facility's ability
8        to deliver power and energy into the applicable
9        regional transmission organization markets and an
10        analysis of the expected capacity factor for the
11        initial clean coal facility.
12            (E) Amounts paid to third parties unrelated to the
13        owner or owners of the initial clean coal facility to
14        prepare the core plant construction cost quote,
15        including the front end engineering and design study,
16        and the operating and maintenance cost quote will be
17        reimbursed through Coal Development Bonds.
18        (5) Re-powering and retrofitting coal-fired power
19    plants previously owned by Illinois utilities to qualify
20    as clean coal facilities. During the 2009 procurement
21    planning process and thereafter, the Agency and the
22    Commission shall consider sourcing agreements covering
23    electricity generated by power plants that were previously
24    owned by Illinois utilities and that have been or will be
25    converted into clean coal facilities, as defined by
26    Section 1-10 of this Act. Pursuant to such procurement

 

 

SB2161- 79 -LRB102 15735 SPS 21099 b

1    planning process, the owners of such facilities may
2    propose to the Agency sourcing agreements with utilities
3    and alternative retail electric suppliers required to
4    comply with subsection (d) of this Section and item (5) of
5    subsection (d) of Section 16-115 of the Public Utilities
6    Act, covering electricity generated by such facilities. In
7    the case of sourcing agreements that are power purchase
8    agreements, the contract price for electricity sales shall
9    be established on a cost of service basis. In the case of
10    sourcing agreements that are contracts for differences,
11    the contract price from which the reference price is
12    subtracted shall be established on a cost of service
13    basis. The Agency and the Commission may approve any such
14    utility sourcing agreements that do not exceed cost-based
15    benchmarks developed by the procurement administrator, in
16    consultation with the Commission staff, Agency staff and
17    the procurement monitor, subject to Commission review and
18    approval. The Commission shall have authority to inspect
19    all books and records associated with these clean coal
20    facilities during the term of any such contract.
21        (6) Costs incurred under this subsection (d) or
22    pursuant to a contract entered into under this subsection
23    (d) shall be deemed prudently incurred and reasonable in
24    amount and the electric utility shall be entitled to full
25    cost recovery pursuant to the tariffs filed with the
26    Commission.

 

 

SB2161- 80 -LRB102 15735 SPS 21099 b

1    (d-5) Zero emission standard.
2        (1) Beginning with the delivery year commencing on
3    June 1, 2017, the Agency shall, for electric utilities
4    that serve at least 100,000 retail customers in this
5    State, procure contracts with zero emission facilities
6    that are reasonably capable of generating cost-effective
7    zero emission credits in an amount approximately equal to
8    16% of the actual amount of electricity delivered by each
9    electric utility to retail customers in the State during
10    calendar year 2014. For an electric utility serving fewer
11    than 100,000 retail customers in this State that
12    requested, under Section 16-111.5 of the Public Utilities
13    Act, that the Agency procure power and energy for all or a
14    portion of the utility's Illinois load for the delivery
15    year commencing June 1, 2016, the Agency shall procure
16    contracts with zero emission facilities that are
17    reasonably capable of generating cost-effective zero
18    emission credits in an amount approximately equal to 16%
19    of the portion of power and energy to be procured by the
20    Agency for the utility. The duration of the contracts
21    procured under this subsection (d-5) shall be for a term
22    of 10 years ending May 31, 2027. The quantity of zero
23    emission credits to be procured under the contracts shall
24    be all of the zero emission credits generated by the zero
25    emission facility in each delivery year; however, if the
26    zero emission facility is owned by more than one entity,

 

 

SB2161- 81 -LRB102 15735 SPS 21099 b

1    then the quantity of zero emission credits to be procured
2    under the contracts shall be the amount of zero emission
3    credits that are generated from the portion of the zero
4    emission facility that is owned by the winning supplier.
5        The 16% value identified in this paragraph (1) is the
6    average of the percentage targets in subparagraph (B) of
7    paragraph (1) of subsection (c) of this Section for the 5
8    delivery years beginning June 1, 2017.
9        The procurement process shall be subject to the
10    following provisions:
11            (A) Those zero emission facilities that intend to
12        participate in the procurement shall submit to the
13        Agency the following eligibility information for each
14        zero emission facility on or before the date
15        established by the Agency:
16                (i) the in-service date and remaining useful
17            life of the zero emission facility;
18                (ii) the amount of power generated annually
19            for each of the years 2005 through 2015, and the
20            projected zero emission credits to be generated
21            over the remaining useful life of the zero
22            emission facility, which shall be used to
23            determine the capability of each facility;
24                (iii) the annual zero emission facility cost
25            projections, expressed on a per megawatthour
26            basis, over the next 6 delivery years, which shall

 

 

SB2161- 82 -LRB102 15735 SPS 21099 b

1            include the following: operation and maintenance
2            expenses; fully allocated overhead costs, which
3            shall be allocated using the methodology developed
4            by the Institute for Nuclear Power Operations;
5            fuel expenditures; non-fuel capital expenditures;
6            spent fuel expenditures; a return on working
7            capital; the cost of operational and market risks
8            that could be avoided by ceasing operation; and
9            any other costs necessary for continued
10            operations, provided that "necessary" means, for
11            purposes of this item (iii), that the costs could
12            reasonably be avoided only by ceasing operations
13            of the zero emission facility; and
14                (iv) a commitment to continue operating, for
15            the duration of the contract or contracts executed
16            under the procurement held under this subsection
17            (d-5), the zero emission facility that produces
18            the zero emission credits to be procured in the
19            procurement.
20            The information described in item (iii) of this
21        subparagraph (A) may be submitted on a confidential
22        basis and shall be treated and maintained by the
23        Agency, the procurement administrator, and the
24        Commission as confidential and proprietary and exempt
25        from disclosure under subparagraphs (a) and (g) of
26        paragraph (1) of Section 7 of the Freedom of

 

 

SB2161- 83 -LRB102 15735 SPS 21099 b

1        Information Act. The Office of Attorney General shall
2        have access to, and maintain the confidentiality of,
3        such information pursuant to Section 6.5 of the
4        Attorney General Act.
5            (B) The price for each zero emission credit
6        procured under this subsection (d-5) for each delivery
7        year shall be in an amount that equals the Social Cost
8        of Carbon, expressed on a price per megawatthour
9        basis. However, to ensure that the procurement remains
10        affordable to retail customers in this State if
11        electricity prices increase, the price in an
12        applicable delivery year shall be reduced below the
13        Social Cost of Carbon by the amount ("Price
14        Adjustment") by which the market price index for the
15        applicable delivery year exceeds the baseline market
16        price index for the consecutive 12-month period ending
17        May 31, 2016. If the Price Adjustment is greater than
18        or equal to the Social Cost of Carbon in an applicable
19        delivery year, then no payments shall be due in that
20        delivery year. The components of this calculation are
21        defined as follows:
22                (i) Social Cost of Carbon: The Social Cost of
23            Carbon is $16.50 per megawatthour, which is based
24            on the U.S. Interagency Working Group on Social
25            Cost of Carbon's price in the August 2016
26            Technical Update using a 3% discount rate,

 

 

SB2161- 84 -LRB102 15735 SPS 21099 b

1            adjusted for inflation for each year of the
2            program. Beginning with the delivery year
3            commencing June 1, 2023, the price per
4            megawatthour shall increase by $1 per
5            megawatthour, and continue to increase by an
6            additional $1 per megawatthour each delivery year
7            thereafter.
8                (ii) Baseline market price index: The baseline
9            market price index for the consecutive 12-month
10            period ending May 31, 2016 is $31.40 per
11            megawatthour, which is based on the sum of (aa)
12            the average day-ahead energy price across all
13            hours of such 12-month period at the PJM
14            Interconnection LLC Northern Illinois Hub, (bb)
15            50% multiplied by the Base Residual Auction, or
16            its successor, capacity price for the rest of the
17            RTO zone group determined by PJM Interconnection
18            LLC, divided by 24 hours per day, and (cc) 50%
19            multiplied by the Planning Resource Auction, or
20            its successor, capacity price for Zone 4
21            determined by the Midcontinent Independent System
22            Operator, Inc., divided by 24 hours per day.
23                (iii) Market price index: The market price
24            index for a delivery year shall be the sum of
25            projected energy prices and projected capacity
26            prices determined as follows:

 

 

SB2161- 85 -LRB102 15735 SPS 21099 b

1                    (aa) Projected energy prices: the
2                projected energy prices for the applicable
3                delivery year shall be calculated once for the
4                year using the forward market price for the
5                PJM Interconnection, LLC Northern Illinois
6                Hub. The forward market price shall be
7                calculated as follows: the energy forward
8                prices for each month of the applicable
9                delivery year averaged for each trade date
10                during the calendar year immediately preceding
11                that delivery year to produce a single energy
12                forward price for the delivery year. The
13                forward market price calculation shall use
14                data published by the Intercontinental
15                Exchange, or its successor.
16                    (bb) Projected capacity prices:
17                        (I) For the delivery years commencing
18                    June 1, 2017, June 1, 2018, and June 1,
19                    2019, the projected capacity price shall
20                    be equal to the sum of (1) 50% multiplied
21                    by the Base Residual Auction, or its
22                    successor, price for the rest of the RTO
23                    zone group as determined by PJM
24                    Interconnection LLC, divided by 24 hours
25                    per day and, (2) 50% multiplied by the
26                    resource auction price determined in the

 

 

SB2161- 86 -LRB102 15735 SPS 21099 b

1                    resource auction administered by the
2                    Midcontinent Independent System Operator,
3                    Inc., in which the largest percentage of
4                    load cleared for Local Resource Zone 4,
5                    divided by 24 hours per day, and where
6                    such price is determined by the
7                    Midcontinent Independent System Operator,
8                    Inc.
9                        (II) For the delivery year commencing
10                    June 1, 2020, and each year thereafter,
11                    the projected capacity price shall be
12                    equal to the sum of (1) 50% multiplied by
13                    the Base Residual Auction, or its
14                    successor, price for the ComEd zone as
15                    determined by PJM Interconnection LLC,
16                    divided by 24 hours per day, and (2) 50%
17                    multiplied by the resource auction price
18                    determined in the resource auction
19                    administered by the Midcontinent
20                    Independent System Operator, Inc., in
21                    which the largest percentage of load
22                    cleared for Local Resource Zone 4, divided
23                    by 24 hours per day, and where such price
24                    is determined by the Midcontinent
25                    Independent System Operator, Inc.
26            For purposes of this subsection (d-5):

 

 

SB2161- 87 -LRB102 15735 SPS 21099 b

1                "Rest of the RTO" and "ComEd Zone" shall have
2            the meaning ascribed to them by PJM
3            Interconnection, LLC.
4                "RTO" means regional transmission
5            organization.
6            (C) No later than 45 days after June 1, 2017 (the
7        effective date of Public Act 99-906), the Agency shall
8        publish its proposed zero emission standard
9        procurement plan. The plan shall be consistent with
10        the provisions of this paragraph (1) and shall provide
11        that winning bids shall be selected based on public
12        interest criteria that include, but are not limited
13        to, minimizing carbon dioxide emissions that result
14        from electricity consumed in Illinois and minimizing
15        sulfur dioxide, nitrogen oxide, and particulate matter
16        emissions that adversely affect the citizens of this
17        State. In particular, the selection of winning bids
18        shall take into account the incremental environmental
19        benefits resulting from the procurement, such as any
20        existing environmental benefits that are preserved by
21        the procurements held under Public Act 99-906 and
22        would cease to exist if the procurements were not
23        held, including the preservation of zero emission
24        facilities. The plan shall also describe in detail how
25        each public interest factor shall be considered and
26        weighted in the bid selection process to ensure that

 

 

SB2161- 88 -LRB102 15735 SPS 21099 b

1        the public interest criteria are applied to the
2        procurement and given full effect.
3            For purposes of developing the plan, the Agency
4        shall consider any reports issued by a State agency,
5        board, or commission under House Resolution 1146 of
6        the 98th General Assembly and paragraph (4) of
7        subsection (d) of this Section, as well as publicly
8        available analyses and studies performed by or for
9        regional transmission organizations that serve the
10        State and their independent market monitors.
11            Upon publishing of the zero emission standard
12        procurement plan, copies of the plan shall be posted
13        and made publicly available on the Agency's website.
14        All interested parties shall have 10 days following
15        the date of posting to provide comment to the Agency on
16        the plan. All comments shall be posted to the Agency's
17        website. Following the end of the comment period, but
18        no more than 60 days later than June 1, 2017 (the
19        effective date of Public Act 99-906), the Agency shall
20        revise the plan as necessary based on the comments
21        received and file its zero emission standard
22        procurement plan with the Commission.
23            If the Commission determines that the plan will
24        result in the procurement of cost-effective zero
25        emission credits, then the Commission shall, after
26        notice and hearing, but no later than 45 days after the

 

 

SB2161- 89 -LRB102 15735 SPS 21099 b

1        Agency filed the plan, approve the plan or approve
2        with modification. For purposes of this subsection
3        (d-5), "cost effective" means the projected costs of
4        procuring zero emission credits from zero emission
5        facilities do not cause the limit stated in paragraph
6        (2) of this subsection to be exceeded.
7            (C-5) As part of the Commission's review and
8        acceptance or rejection of the procurement results,
9        the Commission shall, in its public notice of
10        successful bidders:
11                (i) identify how the winning bids satisfy the
12            public interest criteria described in subparagraph
13            (C) of this paragraph (1) of minimizing carbon
14            dioxide emissions that result from electricity
15            consumed in Illinois and minimizing sulfur
16            dioxide, nitrogen oxide, and particulate matter
17            emissions that adversely affect the citizens of
18            this State;
19                (ii) specifically address how the selection of
20            winning bids takes into account the incremental
21            environmental benefits resulting from the
22            procurement, including any existing environmental
23            benefits that are preserved by the procurements
24            held under Public Act 99-906 and would have ceased
25            to exist if the procurements had not been held,
26            such as the preservation of zero emission

 

 

SB2161- 90 -LRB102 15735 SPS 21099 b

1            facilities;
2                (iii) quantify the environmental benefit of
3            preserving the resources identified in item (ii)
4            of this subparagraph (C-5), including the
5            following:
6                    (aa) the value of avoided greenhouse gas
7                emissions measured as the product of the zero
8                emission facilities' output over the contract
9                term multiplied by the U.S. Environmental
10                Protection Agency eGrid subregion carbon
11                dioxide emission rate and the U.S. Interagency
12                Working Group on Social Cost of Carbon's price
13                in the August 2016 Technical Update using a 3%
14                discount rate, adjusted for inflation for each
15                delivery year; and
16                    (bb) the costs of replacement with other
17                zero carbon dioxide resources, including wind
18                and photovoltaic, based upon the simple
19                average of the following:
20                        (I) the price, or if there is more
21                    than one price, the average of the prices,
22                    paid for renewable energy credits from new
23                    utility-scale wind projects in the
24                    procurement events specified in item (i)
25                    of subparagraph (G) of paragraph (1) of
26                    subsection (c) of this Section; and

 

 

SB2161- 91 -LRB102 15735 SPS 21099 b

1                        (II) the price, or if there is more
2                    than one price, the average of the prices,
3                    paid for renewable energy credits from new
4                    utility-scale solar projects and
5                    brownfield site photovoltaic projects in
6                    the procurement events specified in item
7                    (ii) of subparagraph (G) of paragraph (1)
8                    of subsection (c) of this Section and,
9                    after January 1, 2015, renewable energy
10                    credits from photovoltaic distributed
11                    generation projects in procurement events
12                    held under subsection (c) of this Section.
13            Each utility shall enter into binding contractual
14        arrangements with the winning suppliers.
15            The procurement described in this subsection
16        (d-5), including, but not limited to, the execution of
17        all contracts procured, shall be completed no later
18        than May 10, 2017. Based on the effective date of
19        Public Act 99-906, the Agency and Commission may, as
20        appropriate, modify the various dates and timelines
21        under this subparagraph and subparagraphs (C) and (D)
22        of this paragraph (1). The procurement and plan
23        approval processes required by this subsection (d-5)
24        shall be conducted in conjunction with the procurement
25        and plan approval processes required by subsection (c)
26        of this Section and Section 16-111.5 of the Public

 

 

SB2161- 92 -LRB102 15735 SPS 21099 b

1        Utilities Act, to the extent practicable.
2        Notwithstanding whether a procurement event is
3        conducted under Section 16-111.5 of the Public
4        Utilities Act, the Agency shall immediately initiate a
5        procurement process on June 1, 2017 (the effective
6        date of Public Act 99-906).
7            (D) Following the procurement event described in
8        this paragraph (1) and consistent with subparagraph
9        (B) of this paragraph (1), the Agency shall calculate
10        the payments to be made under each contract for the
11        next delivery year based on the market price index for
12        that delivery year. The Agency shall publish the
13        payment calculations no later than May 25, 2017 and
14        every May 25 thereafter.
15            (E) Notwithstanding the requirements of this
16        subsection (d-5), the contracts executed under this
17        subsection (d-5) shall provide that the zero emission
18        facility may, as applicable, suspend or terminate
19        performance under the contracts in the following
20        instances:
21                (i) A zero emission facility shall be excused
22            from its performance under the contract for any
23            cause beyond the control of the resource,
24            including, but not restricted to, acts of God,
25            flood, drought, earthquake, storm, fire,
26            lightning, epidemic, war, riot, civil disturbance

 

 

SB2161- 93 -LRB102 15735 SPS 21099 b

1            or disobedience, labor dispute, labor or material
2            shortage, sabotage, acts of public enemy,
3            explosions, orders, regulations or restrictions
4            imposed by governmental, military, or lawfully
5            established civilian authorities, which, in any of
6            the foregoing cases, by exercise of commercially
7            reasonable efforts the zero emission facility
8            could not reasonably have been expected to avoid,
9            and which, by the exercise of commercially
10            reasonable efforts, it has been unable to
11            overcome. In such event, the zero emission
12            facility shall be excused from performance for the
13            duration of the event, including, but not limited
14            to, delivery of zero emission credits, and no
15            payment shall be due to the zero emission facility
16            during the duration of the event.
17                (ii) A zero emission facility shall be
18            permitted to terminate the contract if legislation
19            is enacted into law by the General Assembly that
20            imposes or authorizes a new tax, special
21            assessment, or fee on the generation of
22            electricity, the ownership or leasehold of a
23            generating unit, or the privilege or occupation of
24            such generation, ownership, or leasehold of
25            generation units by a zero emission facility.
26            However, the provisions of this item (ii) do not

 

 

SB2161- 94 -LRB102 15735 SPS 21099 b

1            apply to any generally applicable tax, special
2            assessment or fee, or requirements imposed by
3            federal law.
4                (iii) A zero emission facility shall be
5            permitted to terminate the contract in the event
6            that the resource requires capital expenditures in
7            excess of $40,000,000 that were neither known nor
8            reasonably foreseeable at the time it executed the
9            contract and that a prudent owner or operator of
10            such resource would not undertake.
11                (iv) A zero emission facility shall be
12            permitted to terminate the contract in the event
13            the Nuclear Regulatory Commission terminates the
14            resource's license.
15            (F) If the zero emission facility elects to
16        terminate a contract under subparagraph (E) of this
17        paragraph (1), then the Commission shall reopen the
18        docket in which the Commission approved the zero
19        emission standard procurement plan under subparagraph
20        (C) of this paragraph (1) and, after notice and
21        hearing, enter an order acknowledging the contract
22        termination election if such termination is consistent
23        with the provisions of this subsection (d-5).
24        (2) For purposes of this subsection (d-5), the amount
25    paid per kilowatthour means the total amount paid for
26    electric service expressed on a per kilowatthour basis.

 

 

SB2161- 95 -LRB102 15735 SPS 21099 b

1    For purposes of this subsection (d-5), the total amount
2    paid for electric service includes, without limitation,
3    amounts paid for supply, transmission, distribution,
4    surcharges, and add-on taxes.
5        Notwithstanding the requirements of this subsection
6    (d-5), the contracts executed under this subsection (d-5)
7    shall provide that the total of zero emission credits
8    procured under a procurement plan shall be subject to the
9    limitations of this paragraph (2). For each delivery year,
10    the contractual volume receiving payments in such year
11    shall be reduced for all retail customers based on the
12    amount necessary to limit the net increase that delivery
13    year to the costs of those credits included in the amounts
14    paid by eligible retail customers in connection with
15    electric service to no more than 1.65% of the amount paid
16    per kilowatthour by eligible retail customers during the
17    year ending May 31, 2009. The result of this computation
18    shall apply to and reduce the procurement for all retail
19    customers, and all those customers shall pay the same
20    single, uniform cents per kilowatthour charge under
21    subsection (k) of Section 16-108 of the Public Utilities
22    Act. To arrive at a maximum dollar amount of zero emission
23    credits to be paid for the particular delivery year, the
24    resulting per kilowatthour amount shall be applied to the
25    actual amount of kilowatthours of electricity delivered by
26    the electric utility in the delivery year immediately

 

 

SB2161- 96 -LRB102 15735 SPS 21099 b

1    prior to the procurement, to all retail customers in its
2    service territory. Unpaid contractual volume for any
3    delivery year shall be paid in any subsequent delivery
4    year in which such payments can be made without exceeding
5    the amount specified in this paragraph (2). The
6    calculations required by this paragraph (2) shall be made
7    only once for each procurement plan year. Once the
8    determination as to the amount of zero emission credits to
9    be paid is made based on the calculations set forth in this
10    paragraph (2), no subsequent rate impact determinations
11    shall be made and no adjustments to those contract amounts
12    shall be allowed. All costs incurred under those contracts
13    and in implementing this subsection (d-5) shall be
14    recovered by the electric utility as provided in this
15    Section.
16        No later than June 30, 2019, the Commission shall
17    review the limitation on the amount of zero emission
18    credits procured under this subsection (d-5) and report to
19    the General Assembly its findings as to whether that
20    limitation unduly constrains the procurement of
21    cost-effective zero emission credits.
22        (3) Six years after the execution of a contract under
23    this subsection (d-5), the Agency shall determine whether
24    the actual zero emission credit payments received by the
25    supplier over the 6-year period exceed the Average ZEC
26    Payment. In addition, at the end of the term of a contract

 

 

SB2161- 97 -LRB102 15735 SPS 21099 b

1    executed under this subsection (d-5), or at the time, if
2    any, a zero emission facility's contract is terminated
3    under subparagraph (E) of paragraph (1) of this subsection
4    (d-5), then the Agency shall determine whether the actual
5    zero emission credit payments received by the supplier
6    over the term of the contract exceed the Average ZEC
7    Payment, after taking into account any amounts previously
8    credited back to the utility under this paragraph (3). If
9    the Agency determines that the actual zero emission credit
10    payments received by the supplier over the relevant period
11    exceed the Average ZEC Payment, then the supplier shall
12    credit the difference back to the utility. The amount of
13    the credit shall be remitted to the applicable electric
14    utility no later than 120 days after the Agency's
15    determination, which the utility shall reflect as a credit
16    on its retail customer bills as soon as practicable;
17    however, the credit remitted to the utility shall not
18    exceed the total amount of payments received by the
19    facility under its contract.
20        For purposes of this Section, the Average ZEC Payment
21    shall be calculated by multiplying the quantity of zero
22    emission credits delivered under the contract times the
23    average contract price. The average contract price shall
24    be determined by subtracting the amount calculated under
25    subparagraph (B) of this paragraph (3) from the amount
26    calculated under subparagraph (A) of this paragraph (3),

 

 

SB2161- 98 -LRB102 15735 SPS 21099 b

1    as follows:
2            (A) The average of the Social Cost of Carbon, as
3        defined in subparagraph (B) of paragraph (1) of this
4        subsection (d-5), during the term of the contract.
5            (B) The average of the market price indices, as
6        defined in subparagraph (B) of paragraph (1) of this
7        subsection (d-5), during the term of the contract,
8        minus the baseline market price index, as defined in
9        subparagraph (B) of paragraph (1) of this subsection
10        (d-5).
11        If the subtraction yields a negative number, then the
12    Average ZEC Payment shall be zero.
13        (4) Cost-effective zero emission credits procured from
14    zero emission facilities shall satisfy the applicable
15    definitions set forth in Section 1-10 of this Act.
16        (5) The electric utility shall retire all zero
17    emission credits used to comply with the requirements of
18    this subsection (d-5).
19        (6) Electric utilities shall be entitled to recover
20    all of the costs associated with the procurement of zero
21    emission credits through an automatic adjustment clause
22    tariff in accordance with subsection (k) and (m) of
23    Section 16-108 of the Public Utilities Act, and the
24    contracts executed under this subsection (d-5) shall
25    provide that the utilities' payment obligations under such
26    contracts shall be reduced if an adjustment is required

 

 

SB2161- 99 -LRB102 15735 SPS 21099 b

1    under subsection (m) of Section 16-108 of the Public
2    Utilities Act.
3        (7) This subsection (d-5) shall become inoperative on
4    January 1, 2028.
5    (e) The draft procurement plans are subject to public
6comment, as required by Section 16-111.5 of the Public
7Utilities Act.
8    (f) The Agency shall submit the final procurement plan to
9the Commission. The Agency shall revise a procurement plan if
10the Commission determines that it does not meet the standards
11set forth in Section 16-111.5 of the Public Utilities Act.
12    (g) The Agency shall assess fees to each affected utility
13to recover the costs incurred in preparation of the annual
14procurement plan for the utility.
15    (h) The Agency shall assess fees to each bidder to recover
16the costs incurred in connection with a competitive
17procurement process.
18    (i) A renewable energy credit, carbon emission credit, or
19zero emission credit can only be used once to comply with a
20single portfolio or other standard as set forth in subsection
21(c), subsection (d), or subsection (d-5) of this Section,
22respectively. A renewable energy credit, carbon emission
23credit, or zero emission credit cannot be used to satisfy the
24requirements of more than one standard. If more than one type
25of credit is issued for the same megawatt hour of energy, only
26one credit can be used to satisfy the requirements of a single

 

 

SB2161- 100 -LRB102 15735 SPS 21099 b

1standard. After such use, the credit must be retired together
2with any other credits issued for the same megawatt hour of
3energy.
4(Source: P.A. 100-863, eff. 8-14-18; 101-81, eff. 7-12-19;
5101-113, eff. 1-1-20.)
 
6    Section 10. The Public Utilities Act is amended by
7changing Section 16-111.5 as follows:
 
8    (220 ILCS 5/16-111.5)
9    Sec. 16-111.5. Provisions relating to procurement.
10    (a) An electric utility that on December 31, 2005 served
11at least 100,000 customers in Illinois shall procure power and
12energy for its eligible retail customers in accordance with
13the applicable provisions set forth in Section 1-75 of the
14Illinois Power Agency Act and this Section. Beginning with the
15delivery year commencing on June 1, 2017, such electric
16utility shall also procure zero emission credits from zero
17emission facilities in accordance with the applicable
18provisions set forth in Section 1-75 of the Illinois Power
19Agency Act, and, for years beginning on or after June 1, 2017,
20the utility shall procure renewable energy resources in
21accordance with the applicable provisions set forth in Section
221-75 of the Illinois Power Agency Act and this Section.
23Pursuant to the procurement plans and processes approved by
24the Commission under subsection (b-5), an electric utility

 

 

SB2161- 101 -LRB102 15735 SPS 21099 b

1that serves at least 3,000,000 retail customers in Illinois
2shall procure capacity in accordance with subsection (b-5) for
3the delivery year commencing June 1, 2024, and each delivery
4year thereafter through the delivery year commencing June 1,
52033.
6    A small multi-jurisdictional electric utility that on
7December 31, 2005 served less than 100,000 customers in
8Illinois may elect to procure power and energy for all or a
9portion of its eligible Illinois retail customers in
10accordance with the applicable provisions set forth in this
11Section and Section 1-75 of the Illinois Power Agency Act.
12This Section shall not apply to a small multi-jurisdictional
13utility until such time as a small multi-jurisdictional
14utility requests the Illinois Power Agency to prepare a
15procurement plan for its eligible retail customers. "Eligible
16retail customers" for the purposes of this Section means those
17retail customers that purchase power and energy from the
18electric utility under fixed-price bundled service tariffs,
19other than those retail customers whose service is declared or
20deemed competitive under Section 16-113 and those other
21customer groups specified in this Section, including
22self-generating customers, customers electing hourly pricing,
23or those customers who are otherwise ineligible for
24fixed-price bundled tariff service. For those customers that
25are excluded from the procurement plan's electric supply
26service requirements, and the utility shall procure any supply

 

 

SB2161- 102 -LRB102 15735 SPS 21099 b

1requirements, including capacity, ancillary services, and
2hourly priced energy, in the applicable markets as needed to
3serve those customers, provided that the utility may include
4in its procurement plan load requirements for the load that is
5associated with those retail customers whose service has been
6declared or deemed competitive pursuant to Section 16-113 of
7this Act to the extent that those customers are purchasing
8power and energy during one of the transition periods
9identified in subsection (b) of Section 16-113 of this Act.
10    (b) A procurement plan shall be prepared for each electric
11utility consistent with the applicable requirements of the
12Illinois Power Agency Act and this Section. For purposes of
13this Section, Illinois electric utilities that are affiliated
14by virtue of a common parent company are considered to be a
15single electric utility. Small multi-jurisdictional utilities
16may request a procurement plan for a portion of or all of its
17Illinois load. Each procurement plan shall analyze the
18projected balance of supply and demand for those retail
19customers to be included in the plan's electric supply service
20requirements over a 5-year period, with the first planning
21year beginning on June 1 of the year following the year in
22which the plan is filed. The plan shall specifically identify
23the wholesale products to be procured following plan approval,
24and shall follow all the requirements set forth in the Public
25Utilities Act and all applicable State and federal laws,
26statutes, rules, or regulations, as well as Commission orders.

 

 

SB2161- 103 -LRB102 15735 SPS 21099 b

1Nothing in this Section precludes consideration of contracts
2longer than 5 years and related forecast data. Unless
3specified otherwise in this Section, in the procurement plan
4or in the implementing tariff, any procurement occurring in
5accordance with this plan shall be competitively bid through a
6request for proposals process. Approval and implementation of
7the procurement plan shall be subject to review and approval
8by the Commission according to the provisions set forth in
9this Section. A procurement plan shall include each of the
10following components:
11        (1) Hourly load analysis. This analysis shall include:
12            (i) multi-year historical analysis of hourly
13        loads;
14            (ii) switching trends and competitive retail
15        market analysis;
16            (iii) known or projected changes to future loads;
17        and
18            (iv) growth forecasts by customer class.
19        (2) Analysis of the impact of any demand side and
20    renewable energy initiatives. This analysis shall include:
21            (i) the impact of demand response programs and
22        energy efficiency programs, both current and
23        projected; for small multi-jurisdictional utilities,
24        the impact of demand response and energy efficiency
25        programs approved pursuant to Section 8-408 of this
26        Act, both current and projected; and

 

 

SB2161- 104 -LRB102 15735 SPS 21099 b

1            (ii) supply side needs that are projected to be
2        offset by purchases of renewable energy resources, if
3        any.
4        (3) A plan for meeting the expected load requirements
5    that will not be met through preexisting contracts. This
6    plan shall include:
7            (i) definitions of the different Illinois retail
8        customer classes for which supply is being purchased;
9            (ii) the proposed mix of demand-response products
10        for which contracts will be executed during the next
11        year. For small multi-jurisdictional electric
12        utilities that on December 31, 2005 served fewer than
13        100,000 customers in Illinois, these shall be defined
14        as demand-response products offered in an energy
15        efficiency plan approved pursuant to Section 8-408 of
16        this Act. The cost-effective demand-response measures
17        shall be procured whenever the cost is lower than
18        procuring comparable capacity products, provided that
19        such products shall:
20                (A) be procured by a demand-response provider
21            from those retail customers included in the plan's
22            electric supply service requirements;
23                (B) at least satisfy the demand-response
24            requirements of the regional transmission
25            organization market in which the utility's service
26            territory is located, including, but not limited

 

 

SB2161- 105 -LRB102 15735 SPS 21099 b

1            to, any applicable capacity or dispatch
2            requirements;
3                (C) provide for customers' participation in
4            the stream of benefits produced by the
5            demand-response products;
6                (D) provide for reimbursement by the
7            demand-response provider of the utility for any
8            costs incurred as a result of the failure of the
9            supplier of such products to perform its
10            obligations thereunder; and
11                (E) meet the same credit requirements as apply
12            to suppliers of capacity, in the applicable
13            regional transmission organization market;
14            (iii) monthly forecasted system supply
15        requirements, including expected minimum, maximum, and
16        average values for the planning period;
17            (iv) the proposed mix and selection of standard
18        wholesale products for which contracts will be
19        executed during the next year, separately or in
20        combination, to meet that portion of its load
21        requirements not met through pre-existing contracts,
22        including but not limited to monthly 5 x 16 peak period
23        block energy, monthly off-peak wrap energy, monthly 7
24        x 24 energy, annual 5 x 16 energy, annual off-peak wrap
25        energy, annual 7 x 24 energy, monthly capacity, annual
26        capacity, peak load capacity obligations, capacity

 

 

SB2161- 106 -LRB102 15735 SPS 21099 b

1        purchase plan, and ancillary services;
2            (v) proposed term structures for each wholesale
3        product type included in the proposed procurement plan
4        portfolio of products; and
5            (vi) an assessment of the price risk, load
6        uncertainty, and other factors that are associated
7        with the proposed procurement plan; this assessment,
8        to the extent possible, shall include an analysis of
9        the following factors: contract terms, time frames for
10        securing products or services, fuel costs, weather
11        patterns, transmission costs, market conditions, and
12        the governmental regulatory environment; the proposed
13        procurement plan shall also identify alternatives for
14        those portfolio measures that are identified as having
15        significant price risk.
16        (4) Proposed procedures for balancing loads. The
17    procurement plan shall include, for load requirements
18    included in the procurement plan, the process for (i)
19    hourly balancing of supply and demand and (ii) the
20    criteria for portfolio re-balancing in the event of
21    significant shifts in load.
22        (5) Long-Term Renewable Resources Procurement Plan.
23    The Agency shall prepare a long-term renewable resources
24    procurement plan for the procurement of renewable energy
25    credits under Sections 1-56 and 1-75 of the Illinois Power
26    Agency Act for delivery beginning in the 2017 delivery

 

 

SB2161- 107 -LRB102 15735 SPS 21099 b

1    year.
2            (i) The initial long-term renewable resources
3        procurement plan and all subsequent revisions shall be
4        subject to review and approval by the Commission. For
5        the purposes of this Section, "delivery year" has the
6        same meaning as in Section 1-10 of the Illinois Power
7        Agency Act. For purposes of this Section, "Agency"
8        shall mean the Illinois Power Agency.
9            (ii) The long-term renewable resources planning
10        process shall be conducted as follows:
11                (A) Electric utilities shall provide a range
12            of load forecasts to the Illinois Power Agency
13            within 45 days of the Agency's request for
14            forecasts, which request shall specify the length
15            and conditions for the forecasts including, but
16            not limited to, the quantity of distributed
17            generation expected to be interconnected for each
18            year.
19                (B) The Agency shall publish for comment the
20            initial long-term renewable resources procurement
21            plan no later than 120 days after the effective
22            date of this amendatory Act of the 99th General
23            Assembly and shall review, and may revise, the
24            plan at least every 2 years thereafter. To the
25            extent practicable, the Agency shall review and
26            propose any revisions to the long-term renewable

 

 

SB2161- 108 -LRB102 15735 SPS 21099 b

1            energy resources procurement plan in conjunction
2            with the Agency's other planning and approval
3            processes conducted under this Section. The
4            initial long-term renewable resources procurement
5            plan shall:
6                    (aa) Identify the procurement programs and
7                competitive procurement events consistent with
8                the applicable requirements of the Illinois
9                Power Agency Act and shall be designed to
10                achieve the goals set forth in subsection (c)
11                of Section 1-75 of that Act.
12                    (bb) Include a schedule for procurements
13                for renewable energy credits from
14                utility-scale wind projects, utility-scale
15                solar projects, and brownfield site
16                photovoltaic projects consistent with
17                subparagraph (G) of paragraph (1) of
18                subsection (c) of Section 1-75 of the Illinois
19                Power Agency Act.
20                    (cc) Identify the process whereby the
21                Agency will submit to the Commission for
22                review and approval the proposed contracts to
23                implement the programs required by such plan.
24                Copies of the initial long-term renewable
25            resources procurement plan and all subsequent
26            revisions shall be posted and made publicly

 

 

SB2161- 109 -LRB102 15735 SPS 21099 b

1            available on the Agency's and Commission's
2            websites, and copies shall also be provided to
3            each affected electric utility. An affected
4            utility and other interested parties shall have 45
5            days following the date of posting to provide
6            comment to the Agency on the initial long-term
7            renewable resources procurement plan and all
8            subsequent revisions. All comments submitted to
9            the Agency shall be specific, supported by data or
10            other detailed analyses, and, if objecting to all
11            or a portion of the procurement plan, accompanied
12            by specific alternative wording or proposals. All
13            comments shall be posted on the Agency's and
14            Commission's websites. During this 45-day comment
15            period, the Agency shall hold at least one public
16            hearing within each utility's service area that is
17            subject to the requirements of this paragraph (5)
18            for the purpose of receiving public comment.
19            Within 21 days following the end of the 45-day
20            review period, the Agency may revise the long-term
21            renewable resources procurement plan based on the
22            comments received and shall file the plan with the
23            Commission for review and approval.
24                (C) Within 14 days after the filing of the
25            initial long-term renewable resources procurement
26            plan or any subsequent revisions, any person

 

 

SB2161- 110 -LRB102 15735 SPS 21099 b

1            objecting to the plan may file an objection with
2            the Commission. Within 21 days after the filing of
3            the plan, the Commission shall determine whether a
4            hearing is necessary. The Commission shall enter
5            its order confirming or modifying the initial
6            long-term renewable resources procurement plan or
7            any subsequent revisions within 120 days after the
8            filing of the plan by the Illinois Power Agency.
9                (D) The Commission shall approve the initial
10            long-term renewable resources procurement plan and
11            any subsequent revisions, including expressly the
12            forecast used in the plan and taking into account
13            that funding will be limited to the amount of
14            revenues actually collected by the utilities, if
15            the Commission determines that the plan will
16            reasonably and prudently accomplish the
17            requirements of Section 1-56 and subsection (c) of
18            Section 1-75 of the Illinois Power Agency Act. The
19            Commission shall also approve the process for the
20            submission, review, and approval of the proposed
21            contracts to procure renewable energy credits or
22            implement the programs authorized by the
23            Commission pursuant to a long-term renewable
24            resources procurement plan approved under this
25            Section.
26            (iii) The Agency or third parties contracted by

 

 

SB2161- 111 -LRB102 15735 SPS 21099 b

1        the Agency shall implement all programs authorized by
2        the Commission in an approved long-term renewable
3        resources procurement plan without further review and
4        approval by the Commission. Third parties shall not
5        begin implementing any programs or receive any payment
6        under this Section until the Commission has approved
7        the contract or contracts under the process authorized
8        by the Commission in item (D) of subparagraph (ii) of
9        paragraph (5) of this subsection (b) and the third
10        party and the Agency or utility, as applicable, have
11        executed the contract. For those renewable energy
12        credits subject to procurement through a competitive
13        bid process under the plan or under the initial
14        forward procurements for wind and solar resources
15        described in subparagraph (G) of paragraph (1) of
16        subsection (c) of Section 1-75 of the Illinois Power
17        Agency Act, the Agency shall follow the procurement
18        process specified in the provisions relating to
19        electricity procurement in subsections (e) through (i)
20        of this Section.
21            (iv) An electric utility shall recover its costs
22        associated with the procurement of renewable energy
23        credits under this Section through an automatic
24        adjustment clause tariff under subsection (k) of
25        Section 16-108 of this Act. A utility shall not be
26        required to advance any payment or pay any amounts

 

 

SB2161- 112 -LRB102 15735 SPS 21099 b

1        under this Section that exceed the actual amount of
2        revenues collected by the utility under paragraph (6)
3        of subsection (c) of Section 1-75 of the Illinois
4        Power Agency Act and subsection (k) of Section 16-108
5        of this Act, and contracts executed under this Section
6        shall expressly incorporate this limitation.
7            (v) For the public interest, safety, and welfare,
8        the Agency and the Commission may adopt rules to carry
9        out the provisions of this Section on an emergency
10        basis immediately following the effective date of this
11        amendatory Act of the 99th General Assembly.
12            (vi) On or before July 1 of each year, the
13        Commission shall hold an informal hearing for the
14        purpose of receiving comments on the prior year's
15        procurement process and any recommendations for
16        change.
17    (b-5)(1) Notwithstanding any other provision of this Act
18or the Illinois Power Agency Act, the Agency shall, for each
19electric utility that serves at least 3,000,000 retail
20customers in this State, procure contracts for capacity for
21all of the utility's retail customers located in the
22Applicable Fixed Resource Requirement Service Area of PJM
23Interconnection, LLC, or its successor, in accordance with
24this subsection (b-5). Capacity procured under this subsection
25(b-5) shall not include capacity for the load associated with
26customers served by a municipal utility or electric

 

 

SB2161- 113 -LRB102 15735 SPS 21099 b

1cooperative.
2    If PJM Interconnection, LLC tariffs permit a
3resource-specific Fixed Resource Requirement, the Illinois
4Power Agency shall procure contracts for clean capacity as
5provided in this subsection (b-5). Additionally, the Illinois
6Power Agency's procurement plan shall evaluate whether a
7supplemental capacity procurement, in an amount sufficient to
8meet such electric utility's Unforced Capacity Obligation, is
9in the public interest. Upon a Commission determination that
10it is in the public interest to pursue a Fixed Resource
11Requirement rather than a resource-specific Fixed Resource
12Requirement, the Illinois Power Agency shall conduct
13procurements for such additional capacity. The Commission, the
14Illinois Power Agency, and the utility shall take all
15necessary steps in accordance with the PJM Interconnection,
16LLC tariffs to effectuate the Commission determination to
17pursue a resource-specific Fixed Resource Requirement, or a
18Fixed Resource Requirement.
19        (i) Prior to the Base Residual Auction of PJM
20    Interconnection, LLC for the procurement of capacity for
21    the delivery year commencing June 1, 2024, each such
22    electric utility shall make timely written notification to
23    PJM Interconnection, LLC, or its successor, that it is
24    electing the Fixed Resource Requirement Alternative under
25    the Reliability Assurance Agreement of PJM
26    Interconnection, LLC, or its successor, by which the

 

 

SB2161- 114 -LRB102 15735 SPS 21099 b

1    electric utility will procure its Unforced Capacity
2    Obligation for the delivery year commencing June 1, 2024,
3    and ending with the delivery year commencing June 1, 2033,
4    as prescribed by this subsection (b-5).
5        (ii) Following PJM Interconnection, LLC's, or its
6    successor's, validation of the electric utility's
7    eligibility to participate in the Fixed Resource
8    Requirement, the utility shall timely submit its Fixed
9    Resource Requirement Capacity Plan under the requirements
10    set forth in, and as defined by, the Reliability Assurance
11    Agreement of PJM Interconnection, LLC, or its successor,
12    as the Agreement may be updated from time to time. The
13    utility shall timely update its Plan on an annual basis,
14    as required by the Agreement. The utility's submission of
15    its Fixed Resource Requirement Capacity Plan, and updates
16    thereto, under this paragraph (1) and the Agreement shall
17    be consistent with the results of the Illinois Power
18    Agency's procurement or procurements of capacity for the
19    applicable delivery year.
20        (iii) For purposes of this subsection (b-5), "Agency",
21    "bundled clean capacity", "clean energy resources", "zero
22    emission credit", and "zero emission facility" shall have
23    the meanings set forth in Section 1-10 of the Illinois
24    Power Agency Act. "Applicable Fixed Resource Requirement
25    Service Area" shall have the meaning set forth in
26    subsection (a) of Section 1-75 of the Illinois Power

 

 

SB2161- 115 -LRB102 15735 SPS 21099 b

1    Agency Act. "Obligation Peak Load" shall have the meaning
2    set forth in PJM Manual 18: PJM Capacity Market, of PJM
3    Interconnection, LLC, or its successor, as such Manual may
4    be updated from time to time. "Fixed Resource Requirement
5    Alternative", "Fixed Resource Requirement Capacity Plan",
6    "Fixed Resource Requirement Service Area", "Load Serving
7    Entities", "Locational Deliverability Area", "Open Access
8    Transmission Tariff", and "Unforced Capacity Obligation"
9    shall have the meanings set forth in the Reliability
10    Assurance Agreement of PJM Interconnection, LLC, or its
11    successor, as that Agreement may be updated from time to
12    time.
13    (2)(i) The Agency shall prepare capacity procurement plans
14and conduct capacity procurement events to procure capacity to
15satisfy the Unforced Capacity Obligation attributable to the
16electric load of all of the retail customers of electric
17utilities that serve at least 3,000,000 retail customers in
18this State and that are located in the Applicable Fixed
19Resource Requirement Service Area. This obligation shall
20commence with the procurement of capacity for the delivery
21year beginning June 1, 2024, and shall require that the Agency
22hold one or more procurement events no later than January 31,
232021 to procure capacity for that delivery year. Except as
24provided in paragraph (1), the Agency's obligation to procure
25capacity shall continue in force and effect for each delivery
26year thereafter until the obligation terminates with the

 

 

SB2161- 116 -LRB102 15735 SPS 21099 b

1delivery year commencing June 1, 2033. To the extent
2practicable, the procurements should be conducted in
3conjunction with the other procurement processes and events
4set forth in this Section. If the effective date of this
5amendatory Act of the 102nd General Assembly would make
6coordination with other procurement planning, processes, and
7events impracticable for the initial capacity procurement to
8be held under this subsection (b-5), then the Agency is
9authorized to conduct a separate procurement process and
10events no later than January 2021 to procure capacity for the
11delivery year commencing June 1, 2024, or as required to meet
12PJM requirements.
13    (ii) The capacity procured for the delivery year
14commencing June 1, 2024 shall include at least 55% of the
15applicable electric utility's 2019 peak of unforced bundled
16clean capacity.
17    If the Agency is unable to procure contracts for bundled
18clean capacity in the full amounts specified in this
19subparagraph (ii), then the Agency shall procure the
20additional capacity as is necessary to satisfy its Unforced
21Capacity Obligations.
22    (3) Capacity resources are eligible to participate in the
23capacity procurements conducted by the Agency pursuant to this
24subsection (b-5) provided that they meet all applicable
25requirements related to participating in a Fixed Resource
26Requirement as set forth in the approved Fixed Resource

 

 

SB2161- 117 -LRB102 15735 SPS 21099 b

1Requirement Plan, Reliability Assurance Agreement, and any
2other requirements of PJM Interconnection LLC, or its
3successor, as that Plan and Agreement may be updated from time
4to time.
5    The owner of any electric generating unit or resource that
6participates in a capacity procurement conducted under this
7subsection (b-5) must commit to pay any fees assessed by the
8Agency to recover the Agency's costs of conducting the
9procurement events and any related activities.
10    (4) Clean energy resources that satisfy the requirements
11of this subsection (b-5) may offer their bundled clean
12capacity into the bundled clean capacity procurements
13conducted by the Agency to satisfy the requirements of
14subparagraph (ii) of paragraph (2). Bundled clean capacity
15selection shall be based on the following:
16        (i) For the delivery year commencing June 1, 2024, the
17    Agency shall procure bundled clean capacity from clean
18    capacity from the following clean energy resources, unless
19    such resource has notified the Agency that it wishes to
20    opt out of the procurement: (A) resources that have
21    contracted to sell zero emission credits and (B) renewable
22    resources that have contracted to sell renewable energy
23    credits through Agency procurements prior to the date of
24    this amendatory Act.
25        For the delivery year commencing June 1, 2024, the
26    Agency shall procure bundled clean capacity from

 

 

SB2161- 118 -LRB102 15735 SPS 21099 b

1    additional clean energy resources, based on the following
2    public interest criteria, as well as price. The public
3    interest criteria include, but are not limited to,
4    minimizing carbon dioxide emissions that result from
5    electricity consumed in Illinois and minimizing sulfur
6    dioxide, nitrogen oxide, and particulate matter emissions
7    that adversely affect the citizens of this State.
8        (ii) The Agency shall conduct additional clean
9    capacity procurements for delivery years commencing after
10    June 1, 2024. The Agency shall procure all bundled clean
11    capacity from renewable resources that are capable of
12    meeting the Fixed Resource Requirements for a utility that
13    serves at least 3,000,000 customers in Illinois, and has
14    contracted to sell renewable energy credits through Agency
15    procurements conducted after the effective date of this
16    amendatory Act of the 102nd General Assembly, subject to
17    the customer protection mechanisms in paragraph (5),
18    unless such resource has notified the Agency that it
19    wishes to opt out of the procurement.
20        (iii) The price for all bundled clean capacity from
21    selected clean energy resources in the initial capacity
22    procurement that do not separately receive payment for
23    zero emission credits under subsection (d-5) of Section
24    1-75 of the Illinois Power Agency Act and that have not
25    separately received payment for renewable energy credits
26    prior to the effective date of this amendatory Act of the

 

 

SB2161- 119 -LRB102 15735 SPS 21099 b

1    102nd General Assembly, shall be the resource's offer
2    price, expressed on a dollar per megawatt-day basis, and
3    subject to the customer protection mechanisms in paragraph
4    (5).
5        Resources that opt to sell capacity when executing
6    contracts to sell renewable energy credits through Agency
7    procurements after the effective date of this amendatory
8    Act of the 102nd General Assembly shall be paid the
9    weighted average price of selected bundled clean capacity
10    offers in the initial capacity procurement for the
11    delivery year commencing June 1, 2024, expressed on a
12    dollar per megawatt-day basis, and subject to the customer
13    protection mechanisms in paragraph (5), as applicable.
14        Renewable resources that have sold renewable energy
15    credits prior to the effective date of this amendatory Act
16    of the 102nd General Assembly, shall receive the price
17    from the Base Residual Auction or its successor, for the
18    applicable utility zone as determined by PJM
19    Interconnection, LLC or its successor.
20        Clean energy resources that have sold zero emission
21    credits shall receive the price from the Base Residual
22    Auction or its successor, for the applicable utility zone
23    as determined by PJM Interconnection, LLC or its
24    successor, for the delivery year commencing June 1, 2024
25    and continuing through the delivery year commencing June
26    1, 2027. For the delivery year commencing June 1, 2028 and

 

 

SB2161- 120 -LRB102 15735 SPS 21099 b

1    thereafter, the resource shall be paid the weighted
2    average price of selected bundled clean capacity offers in
3    the procurement for the delivery year commencing June 1,
4    2024, expressed on a dollar per megawatt-day basis, and
5    subject to customer protection mechanisms in paragraph
6    (5), as applicable.
7    (5) Customer protections and prudence review.
8        (i) Clean energy resources shall be subject to a bid
9    cap.
10        (ii) Clean capacity resources shall be cost effective.
11    Payments to procured bundled clean capacity resources
12    shall be subject to a cap.
13        (iii) The sum of total capacity costs plus projected
14    energy costs for each delivery year commencing June 1,
15    2024 through the delivery year commencing June 1, 2033,
16    for the Applicable Fixed Resource Requirement Service Area
17    shall be a minimum of a fixed percentage less than the
18    capacity costs plus energy costs for the Locational
19    Deliverability Area for the delivery year commencing June
20    1, 2019, adjusted for inflation beginning with the
21    delivery year commencing June 1, 2025.
22    For purposes of this subsection (b-5), "total capacity
23costs" includes all capacity and bundled clean capacity
24procured for the Applicable Fixed Resource Requirement Service
25Area for a given delivery year pursuant to procurements
26conducted under this subsection (b-5).

 

 

SB2161- 121 -LRB102 15735 SPS 21099 b

1    (6) The capacity procurement plans described in this
2subsection (b-5) and approved by the Commission shall address
3load forecasting, billing, and settlement as follows:
4        (i) The plan shall identify whether PJM
5    Interconnection, LLC or the electric utility for which the
6    capacity is being procured shall serve as the
7    administrator for billing and settlement purposes. PJM
8    Interconnection, LLC, or its successor, shall be given the
9    right of first refusal to serve as the administrator for
10    billing and settlement purposes. The administrator for
11    billing and settlement purposes shall perform its role in
12    a competitively neutral manner among all Load Serving
13    Entities.
14        (ii) Electric utilities subject to the requirements of
15    this subsection (b-5) shall forecast the capacity
16    requirements to be covered by the procurement.
17    (7) No later than 45 days after the effective date of this
18amendatory Act of the 102nd General Assembly, the Agency shall
19publish its proposed capacity procurement plan for the
20delivery year commencing June 1, 2024. The plan shall be
21consistent with the provisions of this subsection (b-5) and
22shall describe in detail how each public interest factor shall
23be considered and weighted in the bid selection process to
24ensure that the public interest criteria are applied to the
25procurement and given full effect.
26    Upon publishing of the capacity procurement plan, copies

 

 

SB2161- 122 -LRB102 15735 SPS 21099 b

1of the plan shall be posted and made publicly available on the
2Illinois Power Agency's website. All interested parties shall
3have 10 days following the date of posting to provide comment
4to the Agency on the plan. All comments shall be posted to the
5Agency's website. Following the end of the comment period, but
6no more than 60 days later than the effective date of this
7amendatory Act of the 102nd General Assembly, the Agency shall
8revise the plan as necessary based on the comments received
9and file its capacity procurement plan with the Commission.
10    If the Commission determines that the plan will result in
11the procurement of capacity consistent with the requirements
12of this subsection (b-5), then the Commission shall, after
13notice and hearing, but no later than 45 days after the
14Illinois Power Agency filed the plan, approve the plan or
15approve with modification.
16    Those capacity procurement plans applicable to delivery
17years commencing after June 1, 2024, shall be published,
18filed, and approved consistent with the timelines and dates
19set forth in subsection (d).
20    (8) The Illinois Power Agency shall procure contracts for
21capacity as required under this subsection (b-5) pursuant to
22the procurement events described in paragraph (2), and the
23results of each procurement event shall be subject to approval
24by the Commission. Upon Commission approval of the results of
25a procurement event, the electric utility shall enter into
26binding contractual arrangements with the winning suppliers.

 

 

SB2161- 123 -LRB102 15735 SPS 21099 b

1Contracts for capacity shall conform to any terms and
2conditions established by PJM Interconnection, LLC, or its
3successor, for a Fixed Resource Requirement Capacity Plan.
4    Bundled clean capacity contracts for renewable resources
5that have executed contracts to sell renewable energy credits
6through Agency procurements after the effective date of this
7amendatory Act shall have a term of 10 years unless the
8electric utility that serves at least 3,000,000 retail
9customers in this State is no longer operating pursuant to a
10Fixed Resource Requirement election. Other contracts for
11capacity under this subsection (b-5) shall terminate at the
12end of the delivery year commencing June 1, 2033, or the date
13upon which any federal authorization to operate the clean
14energy resource expires, whichever is earlier.
15    (9) It is the intent of this subsection (b-5) that the
16Agency's and the Commission's implementation of this
17subsection (b-5), including, but not limited to, the timing
18and number of procurement events and the duration of
19contracts, shall conform, at a minimum, to any applicable
20requirements of the Open Access Transmission Tariff,
21Reliability Assurance Agreement, Operating Agreement, and
22Capacity Market Manual of PJM Interconnection LLC, or its
23successor, as such Tariff, Agreements, and Manuals may be
24changed, replaced, or superseded from time to time, that are
25necessary for Load Serving Entities to exercise and implement
26the Fixed Resource Requirement Alternative capacity

 

 

SB2161- 124 -LRB102 15735 SPS 21099 b

1procurement option, or a successor capacity procurement
2mechanism. Notwithstanding anything to the contrary, the
3Agency and the Commission shall have the authority to take all
4steps necessary to implement this subsection (b-5) consistent
5with applicable federal tariffs, and as those tariffs may be
6changed, replaced, or superseded from time to time, to procure
7capacity for the electric load of all retail customers of
8electric utilities subject to the requirements of this
9subsection (b-5).
10    (c) The procurement process set forth in Section 1-75 of
11the Illinois Power Agency Act and subsection (e) of this
12Section shall be administered by a procurement administrator
13and monitored by a procurement monitor.
14        (1) The procurement administrator shall:
15            (i) design the final procurement process in
16        accordance with Section 1-75 of the Illinois Power
17        Agency Act and subsection (e) of this Section
18        following Commission approval of the procurement plan;
19            (ii) develop benchmarks in accordance with
20        subsection (e)(3) to be used to evaluate bids; these
21        benchmarks shall be submitted to the Commission for
22        review and approval on a confidential basis prior to
23        the procurement event;
24            (iii) serve as the interface between the electric
25        utility and suppliers;
26            (iv) manage the bidder pre-qualification and

 

 

SB2161- 125 -LRB102 15735 SPS 21099 b

1        registration process;
2            (v) obtain the electric utilities' agreement to
3        the final form of all supply contracts and credit
4        collateral agreements;
5            (vi) administer the request for proposals process;
6            (vii) have the discretion to negotiate to
7        determine whether bidders are willing to lower the
8        price of bids that meet the benchmarks approved by the
9        Commission; any post-bid negotiations with bidders
10        shall be limited to price only and shall be completed
11        within 24 hours after opening the sealed bids and
12        shall be conducted in a fair and unbiased manner; in
13        conducting the negotiations, there shall be no
14        disclosure of any information derived from proposals
15        submitted by competing bidders; if information is
16        disclosed to any bidder, it shall be provided to all
17        competing bidders;
18            (viii) maintain confidentiality of supplier and
19        bidding information in a manner consistent with all
20        applicable laws, rules, regulations, and tariffs;
21            (ix) submit a confidential report to the
22        Commission recommending acceptance or rejection of
23        bids;
24            (x) notify the utility of contract counterparties
25        and contract specifics; and
26            (xi) administer related contingency procurement

 

 

SB2161- 126 -LRB102 15735 SPS 21099 b

1        events.
2        (2) The procurement monitor, who shall be retained by
3    the Commission, shall:
4            (i) monitor interactions among the procurement
5        administrator, suppliers, and utility;
6            (ii) monitor and report to the Commission on the
7        progress of the procurement process;
8            (iii) provide an independent confidential report
9        to the Commission regarding the results of the
10        procurement event;
11            (iv) assess compliance with the procurement plans
12        approved by the Commission for each utility that on
13        December 31, 2005 provided electric service to at
14        least 100,000 customers in Illinois and for each small
15        multi-jurisdictional utility that on December 31, 2005
16        served less than 100,000 customers in Illinois;
17            (v) preserve the confidentiality of supplier and
18        bidding information in a manner consistent with all
19        applicable laws, rules, regulations, and tariffs;
20            (vi) provide expert advice to the Commission and
21        consult with the procurement administrator regarding
22        issues related to procurement process design, rules,
23        protocols, and policy-related matters; and
24            (vii) consult with the procurement administrator
25        regarding the development and use of benchmark
26        criteria, standard form contracts, credit policies,

 

 

SB2161- 127 -LRB102 15735 SPS 21099 b

1        and bid documents.
2    (d) Except as provided in subsection (j), the planning
3process shall be conducted as follows:
4        (1) Beginning in 2008, each Illinois utility procuring
5    power pursuant to this Section shall annually provide a
6    range of load forecasts to the Illinois Power Agency by
7    July 15 of each year, or such other date as may be required
8    by the Commission or Agency. The load forecasts shall
9    cover the 5-year procurement planning period for the next
10    procurement plan and shall include hourly data
11    representing a high-load, low-load, and expected-load
12    scenario for the load of those retail customers included
13    in the plan's electric supply service requirements. The
14    utility shall provide supporting data and assumptions for
15    each of the scenarios.
16        (2) Beginning in 2008, the Illinois Power Agency shall
17    prepare a procurement plan by August 15th of each year, or
18    such other date as may be required by the Commission. The
19    procurement plan shall identify the portfolio of
20    demand-response and power and energy products to be
21    procured. Cost-effective demand-response measures shall be
22    procured as set forth in item (iii) of subsection (b) of
23    this Section. Copies of the procurement plan shall be
24    posted and made publicly available on the Agency's and
25    Commission's websites, and copies shall also be provided
26    to each affected electric utility. An affected utility

 

 

SB2161- 128 -LRB102 15735 SPS 21099 b

1    shall have 30 days following the date of posting to
2    provide comment to the Agency on the procurement plan.
3    Other interested entities also may comment on the
4    procurement plan. All comments submitted to the Agency
5    shall be specific, supported by data or other detailed
6    analyses, and, if objecting to all or a portion of the
7    procurement plan, accompanied by specific alternative
8    wording or proposals. All comments shall be posted on the
9    Agency's and Commission's websites. During this 30-day
10    comment period, the Agency shall hold at least one public
11    hearing within each utility's service area for the purpose
12    of receiving public comment on the procurement plan.
13    Within 14 days following the end of the 30-day review
14    period, the Agency shall revise the procurement plan as
15    necessary based on the comments received and file the
16    procurement plan with the Commission and post the
17    procurement plan on the websites.
18        (3) Within 5 days after the filing of the procurement
19    plan, any person objecting to the procurement plan shall
20    file an objection with the Commission. Within 10 days
21    after the filing, the Commission shall determine whether a
22    hearing is necessary. The Commission shall enter its order
23    confirming or modifying the procurement plan within 90
24    days after the filing of the procurement plan by the
25    Illinois Power Agency.
26        (4) The Commission shall approve the procurement plan,

 

 

SB2161- 129 -LRB102 15735 SPS 21099 b

1    including expressly the forecast used in the procurement
2    plan, if the Commission determines that it will ensure
3    adequate, reliable, affordable, efficient, and
4    environmentally sustainable electric service at the lowest
5    total cost over time, taking into account any benefits of
6    price stability.
7    (e) The procurement process shall include each of the
8following components:
9        (1) Solicitation, pre-qualification, and registration
10    of bidders. The procurement administrator shall
11    disseminate information to potential bidders to promote a
12    procurement event, notify potential bidders that the
13    procurement administrator may enter into a post-bid price
14    negotiation with bidders that meet the applicable
15    benchmarks, provide supply requirements, and otherwise
16    explain the competitive procurement process. In addition
17    to such other publication as the procurement administrator
18    determines is appropriate, this information shall be
19    posted on the Illinois Power Agency's and the Commission's
20    websites. The procurement administrator shall also
21    administer the prequalification process, including
22    evaluation of credit worthiness, compliance with
23    procurement rules, and agreement to the standard form
24    contract developed pursuant to paragraph (2) of this
25    subsection (e). The procurement administrator shall then
26    identify and register bidders to participate in the

 

 

SB2161- 130 -LRB102 15735 SPS 21099 b

1    procurement event.
2        (2) Standard contract forms and credit terms and
3    instruments. The procurement administrator, in
4    consultation with the utilities, the Commission, and other
5    interested parties and subject to Commission oversight,
6    shall develop and provide standard contract forms for the
7    supplier contracts that meet generally accepted industry
8    practices. Standard credit terms and instruments that meet
9    generally accepted industry practices shall be similarly
10    developed. The procurement administrator shall make
11    available to the Commission all written comments it
12    receives on the contract forms, credit terms, or
13    instruments. If the procurement administrator cannot reach
14    agreement with the applicable electric utility as to the
15    contract terms and conditions, the procurement
16    administrator must notify the Commission of any disputed
17    terms and the Commission shall resolve the dispute. The
18    terms of the contracts shall not be subject to negotiation
19    by winning bidders, and the bidders must agree to the
20    terms of the contract in advance so that winning bids are
21    selected solely on the basis of price.
22        (3) Establishment of a market-based price benchmark.
23    As part of the development of the procurement process, the
24    procurement administrator, in consultation with the
25    Commission staff, Agency staff, and the procurement
26    monitor, shall establish benchmarks for evaluating the

 

 

SB2161- 131 -LRB102 15735 SPS 21099 b

1    final prices in the contracts for each of the products
2    that will be procured through the procurement process. The
3    benchmarks shall be based on price data for similar
4    products for the same delivery period and same delivery
5    hub, or other delivery hubs after adjusting for that
6    difference. The price benchmarks may also be adjusted to
7    take into account differences between the information
8    reflected in the underlying data sources and the specific
9    products and procurement process being used to procure
10    power for the Illinois utilities. The benchmarks shall be
11    confidential but shall be provided to, and will be subject
12    to Commission review and approval, prior to a procurement
13    event.
14        (4) Request for proposals competitive procurement
15    process. The procurement administrator shall design and
16    issue a request for proposals to supply electricity in
17    accordance with each utility's procurement plan, as
18    approved by the Commission. The request for proposals
19    shall set forth a procedure for sealed, binding commitment
20    bidding with pay-as-bid settlement, and provision for
21    selection of bids on the basis of price.
22        (5) A plan for implementing contingencies in the event
23    of supplier default or failure of the procurement process
24    to fully meet the expected load requirement due to
25    insufficient supplier participation, Commission rejection
26    of results, or any other cause.

 

 

SB2161- 132 -LRB102 15735 SPS 21099 b

1            (i) Event of supplier default: In the event of
2        supplier default, the utility shall review the
3        contract of the defaulting supplier to determine if
4        the amount of supply is 200 megawatts or greater, and
5        if there are more than 60 days remaining of the
6        contract term. If both of these conditions are met,
7        and the default results in termination of the
8        contract, the utility shall immediately notify the
9        Illinois Power Agency that a request for proposals
10        must be issued to procure replacement power, and the
11        procurement administrator shall run an additional
12        procurement event. If the contracted supply of the
13        defaulting supplier is less than 200 megawatts or
14        there are less than 60 days remaining of the contract
15        term, the utility shall procure power and energy from
16        the applicable regional transmission organization
17        market, including ancillary services, capacity, and
18        day-ahead or real time energy, or both, for the
19        duration of the contract term to replace the
20        contracted supply; provided, however, that if a needed
21        product is not available through the regional
22        transmission organization market it shall be purchased
23        from the wholesale market.
24            (ii) Failure of the procurement process to fully
25        meet the expected load requirement: If the procurement
26        process fails to fully meet the expected load

 

 

SB2161- 133 -LRB102 15735 SPS 21099 b

1        requirement due to insufficient supplier participation
2        or due to a Commission rejection of the procurement
3        results, the procurement administrator, the
4        procurement monitor, and the Commission staff shall
5        meet within 10 days to analyze potential causes of low
6        supplier interest or causes for the Commission
7        decision. If changes are identified that would likely
8        result in increased supplier participation, or that
9        would address concerns causing the Commission to
10        reject the results of the prior procurement event, the
11        procurement administrator may implement those changes
12        and rerun the request for proposals process according
13        to a schedule determined by those parties and
14        consistent with Section 1-75 of the Illinois Power
15        Agency Act and this subsection. In any event, a new
16        request for proposals process shall be implemented by
17        the procurement administrator within 90 days after the
18        determination that the procurement process has failed
19        to fully meet the expected load requirement.
20            (iii) In all cases where there is insufficient
21        supply provided under contracts awarded through the
22        procurement process to fully meet the electric
23        utility's load requirement, the utility shall meet the
24        load requirement by procuring power and energy from
25        the applicable regional transmission organization
26        market, including ancillary services, capacity, and

 

 

SB2161- 134 -LRB102 15735 SPS 21099 b

1        day-ahead or real time energy, or both; provided,
2        however, that if a needed product is not available
3        through the regional transmission organization market
4        it shall be purchased from the wholesale market.
5        (6) The procurement process described in this
6    subsection is exempt from the requirements of the Illinois
7    Procurement Code, pursuant to Section 20-10 of that Code.
8    (f) Within 2 business days after opening the sealed bids,
9the procurement administrator shall submit a confidential
10report to the Commission. The report shall contain the results
11of the bidding for each of the products along with the
12procurement administrator's recommendation for the acceptance
13and rejection of bids based on the price benchmark criteria
14and other factors observed in the process. The procurement
15monitor also shall submit a confidential report to the
16Commission within 2 business days after opening the sealed
17bids. The report shall contain the procurement monitor's
18assessment of bidder behavior in the process as well as an
19assessment of the procurement administrator's compliance with
20the procurement process and rules. The Commission shall review
21the confidential reports submitted by the procurement
22administrator and procurement monitor, and shall accept or
23reject the recommendations of the procurement administrator
24within 2 business days after receipt of the reports.
25    (g) Within 3 business days after the Commission decision
26approving the results of a procurement event, the utility

 

 

SB2161- 135 -LRB102 15735 SPS 21099 b

1shall enter into binding contractual arrangements with the
2winning suppliers using the standard form contracts; except
3that the utility shall not be required either directly or
4indirectly to execute the contracts if a tariff that is
5consistent with subsection (l) of this Section has not been
6approved and placed into effect for that utility.
7    (h) The names of the successful bidders and the load
8weighted average of the winning bid prices for each contract
9type and for each contract term shall be made available to the
10public at the time of Commission approval of a procurement
11event. The Commission, the procurement monitor, the
12procurement administrator, the Illinois Power Agency, and all
13participants in the procurement process shall maintain the
14confidentiality of all other supplier and bidding information
15in a manner consistent with all applicable laws, rules,
16regulations, and tariffs. Confidential information, including
17the confidential reports submitted by the procurement
18administrator and procurement monitor pursuant to subsection
19(f) of this Section, shall not be made publicly available and
20shall not be discoverable by any party in any proceeding,
21absent a compelling demonstration of need, nor shall those
22reports be admissible in any proceeding other than one for law
23enforcement purposes.
24    (i) Within 2 business days after a Commission decision
25approving the results of a procurement event or such other
26date as may be required by the Commission from time to time,

 

 

SB2161- 136 -LRB102 15735 SPS 21099 b

1the utility shall file for informational purposes with the
2Commission its actual or estimated retail supply charges, as
3applicable, by customer supply group reflecting the costs
4associated with the procurement and computed in accordance
5with the tariffs filed pursuant to subsection (l) of this
6Section and approved by the Commission.
7    (j) Within 60 days following August 28, 2007 (the
8effective date of Public Act 95-481), each electric utility
9that on December 31, 2005 provided electric service to at
10least 100,000 customers in Illinois shall prepare and file
11with the Commission an initial procurement plan, which shall
12conform in all material respects to the requirements of the
13procurement plan set forth in subsection (b); provided,
14however, that the Illinois Power Agency Act shall not apply to
15the initial procurement plan prepared pursuant to this
16subsection. The initial procurement plan shall identify the
17portfolio of power and energy products to be procured and
18delivered for the period June 2008 through May 2009, and shall
19identify the proposed procurement administrator, who shall
20have the same experience and expertise as is required of a
21procurement administrator hired pursuant to Section 1-75 of
22the Illinois Power Agency Act. Copies of the procurement plan
23shall be posted and made publicly available on the
24Commission's website. The initial procurement plan may include
25contracts for renewable resources that extend beyond May 2009.
26        (i) Within 14 days following filing of the initial

 

 

SB2161- 137 -LRB102 15735 SPS 21099 b

1    procurement plan, any person may file a detailed objection
2    with the Commission contesting the procurement plan
3    submitted by the electric utility. All objections to the
4    electric utility's plan shall be specific, supported by
5    data or other detailed analyses. The electric utility may
6    file a response to any objections to its procurement plan
7    within 7 days after the date objections are due to be
8    filed. Within 7 days after the date the utility's response
9    is due, the Commission shall determine whether a hearing
10    is necessary. If it determines that a hearing is
11    necessary, it shall require the hearing to be completed
12    and issue an order on the procurement plan within 60 days
13    after the filing of the procurement plan by the electric
14    utility.
15        (ii) The order shall approve or modify the procurement
16    plan, approve an independent procurement administrator,
17    and approve or modify the electric utility's tariffs that
18    are proposed with the initial procurement plan. The
19    Commission shall approve the procurement plan if the
20    Commission determines that it will ensure adequate,
21    reliable, affordable, efficient, and environmentally
22    sustainable electric service at the lowest total cost over
23    time, taking into account any benefits of price stability.
24    (k) (Blank).
25    (k-5) (Blank).
26    (l) An electric utility shall recover its costs incurred

 

 

SB2161- 138 -LRB102 15735 SPS 21099 b

1under this Section, including, but not limited to, the costs
2of procuring power and energy demand-response resources under
3this Section. The utility shall file with the initial
4procurement plan its proposed tariffs through which its costs
5of procuring power that are incurred pursuant to a
6Commission-approved procurement plan and those other costs
7identified in this subsection (l), will be recovered. The
8tariffs shall include a formula rate or charge designed to
9pass through both the costs incurred by the utility in
10procuring a supply of electric power and energy for the
11applicable customer classes with no mark-up or return on the
12price paid by the utility for that supply, plus any just and
13reasonable costs that the utility incurs in arranging and
14providing for the supply of electric power and energy. The
15formula rate or charge shall also contain provisions that
16ensure that its application does not result in over or under
17recovery due to changes in customer usage and demand patterns,
18and that provide for the correction, on at least an annual
19basis, of any accounting errors that may occur. A utility
20shall recover through the tariff all reasonable costs incurred
21to implement or comply with any procurement plan that is
22developed and put into effect pursuant to Section 1-75 of the
23Illinois Power Agency Act and this Section, including any fees
24assessed by the Illinois Power Agency, costs associated with
25load balancing, and contingency plan costs. The electric
26utility shall also recover its full costs of procuring

 

 

SB2161- 139 -LRB102 15735 SPS 21099 b

1electric supply for which it contracted before the effective
2date of this Section in conjunction with the provision of full
3requirements service under fixed-price bundled service tariffs
4subsequent to December 31, 2006. All such costs shall be
5deemed to have been prudently incurred. The pass-through
6tariffs that are filed and approved pursuant to this Section
7shall not be subject to review under, or in any way limited by,
8Section 16-111(i) of this Act. All of the costs incurred by the
9electric utility associated with the purchase of zero emission
10credits in accordance with subsection (d-5) of Section 1-75 of
11the Illinois Power Agency Act and, beginning June 1, 2017, all
12of the costs incurred by the electric utility associated with
13the purchase of renewable energy resources in accordance with
14Sections 1-56 and 1-75 of the Illinois Power Agency Act, shall
15be recovered through the electric utility's tariffed charges
16applicable to all of its retail customers, as specified in
17subsection (k) of Section 16-108 of this Act, and shall not be
18recovered through the electric utility's tariffed charges for
19electric power and energy supply to its eligible retail
20customers.
21    (m) The Commission has the authority to adopt rules to
22carry out the provisions of this Section. For the public
23interest, safety, and welfare, the Commission also has
24authority to adopt rules to carry out the provisions of this
25Section on an emergency basis immediately following August 28,
262007 (the effective date of Public Act 95-481).

 

 

SB2161- 140 -LRB102 15735 SPS 21099 b

1    (n) Notwithstanding any other provision of this Act, any
2affiliated electric utilities that submit a single procurement
3plan covering their combined needs may procure for those
4combined needs in conjunction with that plan, and may enter
5jointly into power supply contracts, purchases, and other
6procurement arrangements, and allocate capacity and energy and
7cost responsibility therefor among themselves in proportion to
8their requirements.
9    (o) On or before June 1 of each year, the Commission shall
10hold an informal hearing for the purpose of receiving comments
11on the prior year's procurement process and any
12recommendations for change.
13    (p) An electric utility subject to this Section may
14propose to invest, lease, own, or operate an electric
15generation facility as part of its procurement plan, provided
16the utility demonstrates that such facility is the least-cost
17option to provide electric service to those retail customers
18included in the plan's electric supply service requirements.
19If the facility is shown to be the least-cost option and is
20included in a procurement plan prepared in accordance with
21Section 1-75 of the Illinois Power Agency Act and this
22Section, then the electric utility shall make a filing
23pursuant to Section 8-406 of this Act, and may request of the
24Commission any statutory relief required thereunder. If the
25Commission grants all of the necessary approvals for the
26proposed facility, such supply shall thereafter be considered

 

 

SB2161- 141 -LRB102 15735 SPS 21099 b

1as a pre-existing contract under subsection (b) of this
2Section. The Commission shall in any order approving a
3proposal under this subsection specify how the utility will
4recover the prudently incurred costs of investing in, leasing,
5owning, or operating such generation facility through just and
6reasonable rates charged to those retail customers included in
7the plan's electric supply service requirements. Cost recovery
8for facilities included in the utility's procurement plan
9pursuant to this subsection shall not be subject to review
10under or in any way limited by the provisions of Section
1116-111(i) of this Act. Nothing in this Section is intended to
12prohibit a utility from filing for a fuel adjustment clause as
13is otherwise permitted under Section 9-220 of this Act.
14    (q) If the Illinois Power Agency filed with the
15Commission, under Section 16-111.5 of this Act, its proposed
16procurement plan for the period commencing June 1, 2017, and
17the Commission has not yet entered its final order approving
18the plan on or before the effective date of this amendatory Act
19of the 99th General Assembly, then the Illinois Power Agency
20shall file a notice of withdrawal with the Commission, after
21the effective date of this amendatory Act of the 99th General
22Assembly, to withdraw the proposed procurement of renewable
23energy resources to be approved under the plan, other than the
24procurement of renewable energy credits from distributed
25renewable energy generation devices using funds previously
26collected from electric utilities' retail customers that take

 

 

SB2161- 142 -LRB102 15735 SPS 21099 b

1service pursuant to electric utilities' hourly pricing tariff
2or tariffs and, for an electric utility that serves less than
3100,000 retail customers in the State, other than the
4procurement of renewable energy credits from distributed
5renewable energy generation devices. Upon receipt of the
6notice, the Commission shall enter an order that approves the
7withdrawal of the proposed procurement of renewable energy
8resources from the plan. The initially proposed procurement of
9renewable energy resources shall not be approved or be the
10subject of any further hearing, investigation, proceeding, or
11order of any kind.
12    This amendatory Act of the 99th General Assembly preempts
13and supersedes any order entered by the Commission that
14approved the Illinois Power Agency's procurement plan for the
15period commencing June 1, 2017, to the extent it is
16inconsistent with the provisions of this amendatory Act of the
1799th General Assembly. To the extent any previously entered
18order approved the procurement of renewable energy resources,
19the portion of that order approving the procurement shall be
20void, other than the procurement of renewable energy credits
21from distributed renewable energy generation devices using
22funds previously collected from electric utilities' retail
23customers that take service under electric utilities' hourly
24pricing tariff or tariffs and, for an electric utility that
25serves less than 100,000 retail customers in the State, other
26than the procurement of renewable energy credits for

 

 

SB2161- 143 -LRB102 15735 SPS 21099 b

1distributed renewable energy generation devices.
2(Source: P.A. 99-906, eff. 6-1-17.)