| | HB5555 Engrossed | | LRB102 25480 RJF 34768 b |
|
|
1 | | AN ACT concerning State government.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | Section 5. The Business Assistance and Regulatory Reform |
5 | | Act is amended by changing Sections 5, 10, and 15 and by adding |
6 | | Sections 7, 25, and 30 as follows:
|
7 | | (20 ILCS 608/5)
|
8 | | Sec. 5. Goal. The goal of this Act is to improve the |
9 | | State's business
climate by making it easier for small and |
10 | | mid-size businesses to deal with
State requirements for doing |
11 | | business. This goal will be achieved through
providing quick, |
12 | | accurate information on existing requirements and avoiding
|
13 | | unnecessary requirements , and expedite permit issuance .
|
14 | | (Source: P.A. 88-404.)
|
15 | | (20 ILCS 608/7 new) |
16 | | Sec. 7. Definitions. As used in this Act: |
17 | | "Authorization" means any license, permit, approval, |
18 | | finding, determination, or other administrative decision |
19 | | issued by an agency and any interagency consultation that is |
20 | | required or authorized under State law in order to site, |
21 | | construct, reconstruct, or commence operations of a covered |
22 | | project administered by a State agency or, in the case of a |
|
| | HB5555 Engrossed | - 2 - | LRB102 25480 RJF 34768 b |
|
|
1 | | unit of local government that chooses to participate in the |
2 | | environmental review and authorization process in accordance |
3 | | with subparagraph (A) of paragraph (3) of subsection (c) of |
4 | | Section 30, a local permitting authority. |
5 | | "Committee" means the Interagency Permitting Advisory |
6 | | Committee established under Section 25. |
7 | | "Covered project" means any activity in Illinois with |
8 | | authorization or environmental review by an agency involving |
9 | | construction of infrastructure for renewable or conventional |
10 | | energy production, electricity transmission, surface |
11 | | transportation, aviation, ports and waterways, water resource |
12 | | projects, broadband, pipelines, manufacturing, or any other |
13 | | sector as determined by a majority vote of the Committee that: |
14 | | (1) is subject to permitting requirements pursuant to |
15 | | the Environmental Protection Act, is likely to require a |
16 | | total investment of more than $20,000,000, and does not |
17 | | qualify for abbreviated authorization or environmental |
18 | | review processes under any applicable law; or |
19 | | (2) is subject to permitting requirements pursuant to |
20 | | the Environmental Protection Act and the size and |
21 | | complexity of which, in the opinion of the Committee, |
22 | | makes the project likely to benefit from enhanced |
23 | | oversight and coordination, including a project likely to |
24 | | require authorization from or environmental review |
25 | | involving more than 2 agencies. |
26 | | "Project sponsor" means an entity, including any private, |
|
| | HB5555 Engrossed | - 3 - | LRB102 25480 RJF 34768 b |
|
|
1 | | public, or public-private entity, seeking an authorization for |
2 | | a covered project.
|
3 | | (20 ILCS 608/10)
|
4 | | Sec. 10. Executive Office. There is created an Office of |
5 | | Business
Permits and Regulatory Assistance (hereinafter |
6 | | referred to as "office")
within the Department of Commerce and |
7 | | Community Affairs (now Department of Commerce and Economic |
8 | | Opportunity)
which shall consolidate existing programs
|
9 | | throughout State government, provide assistance to businesses |
10 | | with fewer than
500
employees in meeting State requirements |
11 | | for doing business , consolidate existing programs throughout |
12 | | State government, and perform other
functions specified in |
13 | | this Act. The office shall implement reforms to improve |
14 | | interagency coordination that allow for expeditious permitting |
15 | | issuance. The office shall utilize information technology |
16 | | tools to track project schedules and metrics to improve |
17 | | transparency and accountability of the permitting process, |
18 | | reduce uncertainty and delays, and reduce costs and risks to |
19 | | taxpayers. The
By March 1, 1994, the office shall complete and |
20 | | file with the Governor and the
General Assembly a plan for the |
21 | | implementation of this Act. Thereafter, the
office shall carry |
22 | | out the provisions of this Act, subject to funding
through |
23 | | appropriation.
|
24 | | (Source: P.A. 98-463, eff. 8-16-13.)
|
|
| | HB5555 Engrossed | - 4 - | LRB102 25480 RJF 34768 b |
|
|
1 | | (20 ILCS 608/15)
|
2 | | Sec. 15. Providing Information and Expediting Permit |
3 | | Reviews.
|
4 | | (a) The office shall provide an online information system |
5 | | using a website toll-free
business assistance number. The |
6 | | number shall be advertised throughout the
State. Interested |
7 | | businesses shall If requested, the caller will be sent a basic |
8 | | business kit, describing
the basic requirements and procedures |
9 | | for doing business in Illinois. If
requested, the caller shall |
10 | | be directed to one or more of the additional
services provided |
11 | | by the office. All persons providing advice to callers on
|
12 | | behalf of
the office and all persons responsible for directly |
13 | | providing services to
persons visiting the office or one of |
14 | | its branches shall be persons with small
business experience |
15 | | in an administrative or managerial capacity.
|
16 | | (b) (Blank).
|
17 | | (c) Any applicant for permits required for a business |
18 | | activity may confer
with the office to obtain assistance in |
19 | | the prompt and efficient processing and
review of |
20 | | applications. The office shall may designate an employee of |
21 | | the office to
act as a permit assistance manager to:
|
22 | | (1) facilitate contacts for the applicant with |
23 | | responsible agencies;
|
24 | | (2) arrange conferences to clarify the requirements of |
25 | | interested
agencies;
|
26 | | (3) consider with State agencies the feasibility of |
|
| | HB5555 Engrossed | - 5 - | LRB102 25480 RJF 34768 b |
|
|
1 | | consolidating
hearings and data required of the applicant;
|
2 | | (4) assist the applicant in resolution of outstanding |
3 | | issues identified by
State agencies; and
|
4 | | (5) coordinate federal, State and local regulatory |
5 | | procedures and permit
review actions to the extent |
6 | | possible.
|
7 | | (d) The office shall publish an online a directory of |
8 | | State business permits and State
programs to assist small |
9 | | businesses.
|
10 | | (e) The office shall attempt to establish
agreements with |
11 | | local governments to
allow the office to provide assistance to |
12 | | applicants for permits required by
these local governments.
|
13 | | (f) (Blank). Interested
State agencies shall, to the |
14 | | maximum extent feasible, establish procedures to
expedite |
15 | | applications for infrastructure projects. Applications for |
16 | | permits
for infrastructure projects shall be approved or |
17 | | disapproved within 45 days of
submission, unless law or |
18 | | regulations specify a different period. If the
interested |
19 | | agency is unable to act within that period, the agency shall |
20 | | provide
a written notification to the office specifying |
21 | | reasons for its inability to
act and the date by which approval |
22 | | or disapproval shall be determined. The
office may require any |
23 | | interested State agency to designate an employee who
will |
24 | | coordinate the handling of permits in that area.
|
25 | | (g) In addition to its responsibilities in connection with |
26 | | permit
assistance, the office shall provide general regulatory |
|
| | HB5555 Engrossed | - 6 - | LRB102 25480 RJF 34768 b |
|
|
1 | | information by
directing businesses to appropriate officers in |
2 | | State agencies to supply the
information requested.
|
3 | | (h) The office shall help businesses to locate and apply |
4 | | to training
programs available to train current employees in |
5 | | particular skills, techniques
or areas of knowledge relevant |
6 | | to the employees' present or anticipated job
duties. In |
7 | | pursuit of this objective, the office shall provide businesses |
8 | | with
pertinent information about training programs offered by |
9 | | State agencies, units
of local government, public universities |
10 | | and colleges, community colleges, and
school districts in |
11 | | Illinois.
|
12 | | (i) The office shall help businesses to locate and apply |
13 | | to State programs
offering to businesses grants, loans, loan |
14 | | or bond guarantees, investment
partnerships, technology or |
15 | | productivity consultation, or other forms of
business |
16 | | assistance.
|
17 | | (j) To the extent authorized by federal law, the office |
18 | | shall assist
businesses in ascertaining and complying with the |
19 | | requirements of the federal
Americans with Disabilities Act.
|
20 | | (k) The office shall provide confidential on-site |
21 | | assistance in identifying
problems and solutions in compliance |
22 | | with requirements of State and federal
environmental |
23 | | regulations. The office shall work through and contract with |
24 | | the Illinois Sustainable Technology
Center to provide |
25 | | confidential on-site
consultation audits that (i) assist |
26 | | regulatory compliance and (ii) identify
pollution prevention |
|
| | HB5555 Engrossed | - 7 - | LRB102 25480 RJF 34768 b |
|
|
1 | | opportunities.
|
2 | | (k-5) Until July 1, 2012, the office shall provide |
3 | | confidential on-site assistance, including, but not limited |
4 | | to, consultation audits, to identify
problems and solutions |
5 | | regarding compliance with the requirements of the federal
|
6 | | Occupational Safety and Health Administration. On and after |
7 | | July 1, 2012, the Department of Labor shall provide |
8 | | confidential on-site assistance, including, but not limited |
9 | | to, consultation audits, to identify
problems and solutions |
10 | | regarding compliance with the requirements of the federal
|
11 | | Occupational Safety and Health Administration. |
12 | | (l) The office shall provide information on existing loan |
13 | | and business
assistance programs provided by the State.
|
14 | | (m) Each State agency having jurisdiction to approve or |
15 | | deny a permit shall
have the continuing power heretofore or |
16 | | hereafter vested in it to make such
determinations. The |
17 | | provisions of this Act shall not lessen or reduce such
powers |
18 | | and shall modify the procedures followed in carrying out such |
19 | | powers
only to the extent provided in this Act.
|
20 | | (n) (1) Each State agency shall fully cooperate with the |
21 | | office in
providing information, documentation, personnel or |
22 | | facilities requested by the
office.
|
23 | | (2) Each State agency having jurisdiction of any permit to |
24 | | which the
master application procedure is applicable shall |
25 | | designate an employee to act
as permit liaison office with the |
26 | | office in carrying out the provisions of this
Act.
|
|
| | HB5555 Engrossed | - 8 - | LRB102 25480 RJF 34768 b |
|
|
1 | | (o) (1) The office shall identify, develop, and track |
2 | | metrics for timeliness of permit reviews, permit decisions, |
3 | | and project outcomes has authority, but is not required, to |
4 | | keep and analyze
appropriate statistical data regarding the |
5 | | number of permits issued by State
agencies, the amount of time |
6 | | necessary for the permits to be issued, the cost
of obtaining |
7 | | such permits, the types of projects for which specific permits |
8 | | are
issued, a geographic distribution of permits, and other |
9 | | pertinent data the
office deems appropriate .
|
10 | | The office shall administer and expand the use of online |
11 | | transparency tools providing: |
12 | | (i) tracking and reporting metrics; |
13 | | (ii) development and posting of schedules for permit |
14 | | reviews and permit decisions; |
15 | | (iii) the sharing of best practices relating to |
16 | | efficient project permitting and reviews; and |
17 | | (iv) the visual display of relevant geospatial data to |
18 | | support the permitting process. make such data and any |
19 | | analysis of the data available to
the public.
|
20 | | (2) The office shall has authority, but is not required, |
21 | | to conduct or cause to be
conducted a thorough review of any |
22 | | agency's permit requirements and the need
by the State to |
23 | | require such permits. The office shall draw on the review, on
|
24 | | its direct experience, and on its statistical analyses to |
25 | | prepare
recommendations regarding how to:
|
26 | | (i) eliminate unnecessary or antiquated permit |
|
| | HB5555 Engrossed | - 9 - | LRB102 25480 RJF 34768 b |
|
|
1 | | requirements;
|
2 | | (ii) consolidate duplicative or overlapping permit |
3 | | requirements;
|
4 | | (iii) simplify overly complex or lengthy application |
5 | | procedures;
|
6 | | (iv) expedite time-consuming agency review and |
7 | | approval procedures; or
|
8 | | (v) otherwise improve the permitting processes in the |
9 | | State.
|
10 | | The office shall submit copies of all recommendations |
11 | | within 5 days of
issuance to the affected agency, the |
12 | | Governor, the General Assembly, and the
Joint Committee on |
13 | | Administrative Rules.
|
14 | | (p) The office shall has authority to review State forms |
15 | | on its own initiative or
upon the request of another State |
16 | | agency to ascertain the burden, if any, of
complying with |
17 | | those forms. If the office determines that a form is unduly
|
18 | | burdensome to business, it may recommend to the agency issuing |
19 | | the form either
that the form be eliminated or that specific |
20 | | changes be made in the form.
|
21 | | (q) Not later than March 1 of each year, beginning March 1, |
22 | | 1995, the office
shall submit an annual
report of its |
23 | | activities during the preceding year to the Governor and |
24 | | General
Assembly. The report shall describe the activities of |
25 | | the office during the
preceding year and shall contain |
26 | | statistical information on the permit
assistance activities of |
|
| | HB5555 Engrossed | - 10 - | LRB102 25480 RJF 34768 b |
|
|
1 | | the office.
|
2 | | (Source: P.A. 97-787, eff. 7-13-12; 98-346, eff. 8-14-13.)
|
3 | | (20 ILCS 608/25 new) |
4 | | Sec. 25. Interagency Permitting Advisory Committee. |
5 | | (a) The Director of each permitting agency shall designate |
6 | | a representative of the agency to serve on the committee and |
7 | | represent the agency as agency chief environmental review and |
8 | | permitting officer as required by this Act. |
9 | | (b) The head of each of the following agencies, or his or |
10 | | her designee, shall serve on the committee: |
11 | | (1) the Office of Business Permits and Regulatory |
12 | | Assistance; |
13 | | (2) the Environmental Protection Agency; |
14 | | (3) the Department of Transportation; |
15 | | (4) the Department of Natural Resources; |
16 | | (5) the Illinois Commerce Commission; |
17 | | (6) the Office of State Fire Marshal; and |
18 | | (7) the Department of Public Health. |
19 | | (20 ILCS 608/30 new) |
20 | | Sec. 30. Permitting process improvement. |
21 | | (a) Project initiation and designation of participating |
22 | | agencies. |
23 | | (1) Notice. |
24 | | (A) A project sponsor of a covered project shall |
|
| | HB5555 Engrossed | - 11 - | LRB102 25480 RJF 34768 b |
|
|
1 | | submit to the office notice of the initiation of a |
2 | | proposed covered project. |
3 | | (B) Each notice described in subparagraph (A) |
4 | | shall include: |
5 | | (i) a statement of the purposes and objectives |
6 | | of the proposed project; |
7 | | (ii) a concise description, including the |
8 | | general location of the proposed project and a |
9 | | summary of geospatial information, if available, |
10 | | illustrating the project area and the locations, |
11 | | if any, of environmental, cultural, and historic |
12 | | resources; |
13 | | (iii) a statement regarding the technical and |
14 | | financial ability of the project sponsor to |
15 | | construct the proposed project; |
16 | | (iv) a statement of any financing, and |
17 | | authorizations anticipated to be required to |
18 | | complete the proposed project; and |
19 | | (v) an assessment that the proposed project |
20 | | meets the definition of a covered project under |
21 | | Section 7 and a statement of reasons supporting |
22 | | the assessment. |
23 | | (2) Invitation. |
24 | | (A) Not later than 21 calendar days after the date |
25 | | on which the office makes a specific entry for the |
26 | | project on the Permitting Dashboard under paragraph |
|
| | HB5555 Engrossed | - 12 - | LRB102 25480 RJF 34768 b |
|
|
1 | | (1) of subsection (b), the office, with input from the |
2 | | agency chief environmental review and permitting |
3 | | officer shall: |
4 | | (i) identify agencies and governmental |
5 | | entities likely to have financing, environmental |
6 | | review, authorization, or other responsibilities |
7 | | with respect to the proposed project; and |
8 | | (ii) invite all agencies identified under |
9 | | clause (i) to become a cooperating agency, in the |
10 | | environmental review and authorization management |
11 | | process described in this Section. |
12 | | (B) Each invitation made under subparagraph (A) |
13 | | shall include a 14 calendar day deadline for a |
14 | | response to be submitted to the office. |
15 | | (3) Cooperating agencies. |
16 | | (A) An agency invited under paragraph (2) shall be |
17 | | designated as a cooperating agency for a covered |
18 | | project, unless the agency informs the office in |
19 | | writing before the deadline under subparagraph (B) of |
20 | | paragraph (2) that the agency: |
21 | | (i) has no jurisdiction or authority with |
22 | | respect to the proposed project; or |
23 | | (ii) does not intend to exercise authority |
24 | | related to, or submit comments on, the proposed |
25 | | project. |
26 | | (B) On request and a showing of changed |
|
| | HB5555 Engrossed | - 13 - | LRB102 25480 RJF 34768 b |
|
|
1 | | circumstances, the office may designate an agency that |
2 | | has opted out under subparagraph (A)(ii) of this |
3 | | paragraph (3) to be a cooperating agency. |
4 | | (4) The designation described in paragraph (3) shall |
5 | | not: |
6 | | (A) give the cooperating agency authority or |
7 | | jurisdiction over the covered project; or |
8 | | (B) expand any jurisdiction or authority a |
9 | | cooperating agency may have over the proposed project. |
10 | | (b) Permitting Dashboard. |
11 | | (1) Requirement to maintain. |
12 | | (A) The office, in coordination with the |
13 | | Department of Innovation and Technology, shall |
14 | | maintain an online database to be known as the |
15 | | "Permitting Dashboard" to track the status of |
16 | | environmental reviews and authorizations for any cover |
17 | | project. |
18 | | (B) If the office determines that the project is |
19 | | not a covered project, the project sponsor may submit |
20 | | a further explanation as to why the project is a |
21 | | covered project not later than 14 days after the date |
22 | | of being notified of the determination. |
23 | | (C) Not later than 14 days after receiving an |
24 | | explanation described in subparagraph (B), the office |
25 | | shall: |
26 | | (i) make a final and conclusive determination |
|
| | HB5555 Engrossed | - 14 - | LRB102 25480 RJF 34768 b |
|
|
1 | | as to whether the project is a covered project; |
2 | | and |
3 | | (ii) if the office determines that the project |
4 | | is a covered project, create a specific entry on |
5 | | the Permitting Dashboard for the covered project. |
6 | | (2) Postings by agencies. |
7 | | (A) For each covered project added to the |
8 | | Permitting Dashboard under paragraph (1), the office |
9 | | and each cooperating and agency shall post to the |
10 | | Permitting Dashboard: |
11 | | (i) a hyperlink that directs to a website that |
12 | | contains, to the extent consistent with applicable |
13 | | law: |
14 | | (I) the notification submitted under |
15 | | paragraph (1) of subsection (a); |
16 | | (II) where practicable: (aa) the |
17 | | applications and supporting documents that |
18 | | have been submitted by a project sponsor for |
19 | | any required environmental review or |
20 | | authorization; or (bb) a notice explaining how |
21 | | the public may obtain access to such |
22 | | documents; |
23 | | (III) a description of any agency action |
24 | | taken or decision made that materially affects |
25 | | the status of a covered project; |
26 | | (IV) any significant document that |
|
| | HB5555 Engrossed | - 15 - | LRB102 25480 RJF 34768 b |
|
|
1 | | supports the action or decision described in |
2 | | subclause (III); and |
3 | | (V) a description of the status of any |
4 | | litigation to which the agency is a party that |
5 | | is directly related to the project, including, |
6 | | if practicable, any judicial document made |
7 | | available on an electronic docket maintained |
8 | | by a federal, State, or local court; and |
9 | | (ii) any document described in clause (i) that |
10 | | is not available by hyperlink on another website. |
11 | | (B) The information described in subparagraph (A) |
12 | | shall be posted to the website made available by |
13 | | hyperlink on the Permitting Dashboard not later than 5 |
14 | | business days after the date on which the agency |
15 | | receives the information. |
16 | | (3) Postings by the office. The office shall publish |
17 | | to the Permitting Dashboard: |
18 | | (A) the permitting timetable established under |
19 | | paragraph (2) of subsection (c); |
20 | | (B) the status of the compliance of each agency |
21 | | with the permitting timetable; |
22 | | (C) any modifications of the permitting timetable; |
23 | | (D) an explanation of each modification described |
24 | | in subparagraph (C); and |
25 | | (E) any memorandum of understanding established |
26 | | under subparagraph (C) of paragraph (3) of subsection |
|
| | HB5555 Engrossed | - 16 - | LRB102 25480 RJF 34768 b |
|
|
1 | | (c). |
2 | | (c) Coordination and timetables. |
3 | | (1) Coordinated project plan. |
4 | | (A) Not later than 60 days after the date on which |
5 | | the office makes a specific entry for the project on |
6 | | the Permitting Dashboard, in consultation with each |
7 | | agency chief environmental review and permitting |
8 | | officer, shall establish a concise plan for |
9 | | coordinating public and agency participation in, and |
10 | | completion of, any required environmental review and |
11 | | authorization for the project. |
12 | | (B) The coordinated project plan shall include the |
13 | | following information and be updated by the office, as |
14 | | applicable, at least once per quarter: |
15 | | (i) A list of, and roles and responsibilities |
16 | | for, all entities with environmental review or |
17 | | authorization responsibility for the project. |
18 | | (ii) A permitting timetable, as described in |
19 | | paragraph (2), setting forth a comprehensive |
20 | | schedule of dates by which all environmental |
21 | | reviews and authorizations, and to the maximum |
22 | | extent practicable, other jurisdictions' permits, |
23 | | reviews, and approvals must be made. |
24 | | (iii) A discussion of potential avoidance, |
25 | | minimization, and mitigation strategies, if |
26 | | required by applicable law and known. |
|
| | HB5555 Engrossed | - 17 - | LRB102 25480 RJF 34768 b |
|
|
1 | | (iv) Plans and a schedule for public outreach |
2 | | and coordination, to the extent required by |
3 | | applicable law. |
4 | | (C) The coordinated project plan described in |
5 | | subparagraph (A) may be incorporated into a memorandum |
6 | | of understanding. |
7 | | (2) Permitting timetable. |
8 | | (A) As part of the coordination project plan under |
9 | | paragraph (1), the office, in consultation with each |
10 | | agency chief environmental review and permitting |
11 | | officer, the project sponsor, and any unit of local |
12 | | government in which the project is located, and, |
13 | | subject to subparagraph (C), with the concurrence of |
14 | | each cooperating agency, shall establish a permitting |
15 | | timetable that includes intermediate and final |
16 | | completion dates for action by each cooperating agency |
17 | | on any environmental review or authorization required |
18 | | for the project. The final completion states shall be |
19 | | based on relevant historical data but with the aim of |
20 | | completing all required authorizations within 2 years. |
21 | | (B) In establishing the permitting timetable under |
22 | | subparagraph (A), the office may vary the timetable |
23 | | based on relevant factors including: |
24 | | (i) the size and complexity of the covered |
25 | | project; |
26 | | (ii) the resources available to each |
|
| | HB5555 Engrossed | - 18 - | LRB102 25480 RJF 34768 b |
|
|
1 | | participating agency; |
2 | | (iii) the regional or national economic |
3 | | significance of the project; |
4 | | (iv) the sensitivity of the natural or |
5 | | historic resources that may be affected by the |
6 | | project; |
7 | | (v) the financing plan for the project; and |
8 | | (vi)the extent to which similar projects in |
9 | | geographic proximity to the project were recently |
10 | | subject to environmental review or similar |
11 | | procedures under State law. |
12 | | (C) Dispute resolution. |
13 | | (i) The office, in consultation with |
14 | | appropriate agency chief environmental review and |
15 | | permitting officers and the project sponsor, |
16 | | shall, as necessary, mediate any disputes |
17 | | regarding the permitting timetable referred to |
18 | | under subparagraph (A). |
19 | | (ii) If a dispute remains unresolved 30 days |
20 | | after the date on which the dispute was submitted |
21 | | to the office, the Director of the Governor's |
22 | | Office of Management and Budget shall facilitate a |
23 | | resolution of the dispute and direct the agencies |
24 | | party to the dispute to resolve the dispute by the |
25 | | end of the 60-day period beginning on the date of |
26 | | submission of the dispute to the office. |
|
| | HB5555 Engrossed | - 19 - | LRB102 25480 RJF 34768 b |
|
|
1 | | (iii) Any action taken by the Director of the |
2 | | Governor's Office of Management and Budget in the |
3 | | resolution of a dispute under clause (ii) shall: |
4 | | (I) be final and conclusive; and |
5 | | (II) not be subject to judicial review. |
6 | | (D) Modification after approval. |
7 | | (i) The office may modify a permitting |
8 | | timetable established under subparagraph (A) only |
9 | | if: |
10 | | (I) the affected cooperating agencies, |
11 | | after consultation with the project sponsor, |
12 | | agree to a different completion date; |
13 | | (II) the affected cooperating agency |
14 | | provides a written justification for the |
15 | | modification; and |
16 | | (III) in the case of a modification that |
17 | | would necessitate an extension of a final |
18 | | completion date under a permitting timetable |
19 | | established under subparagraph (A) to a date |
20 | | more than 30 days after the final completion |
21 | | date originally established under subparagraph |
22 | | (A), the office shall consult with the project |
23 | | sponsor and make a determination on the |
24 | | record, based on consideration of the relevant |
25 | | factors described under subparagraph (B), |
26 | | whether to make such modification. |
|
| | HB5555 Engrossed | - 20 - | LRB102 25480 RJF 34768 b |
|
|
1 | | (ii) A completion date in the permitting |
2 | | timetable may not be modified within 30 days after |
3 | | the completion date. |
4 | | (iii) Limitation on length of modifications. |
5 | | (I) Except as provided in subclause (II), |
6 | | the total length of all modifications to a |
7 | | permitting timetable authorized or made under |
8 | | this subparagraph (D), other than for reasons |
9 | | outside the control of federal, State, local, |
10 | | or tribal governments, may not extend the |
11 | | permitting timetable for a period of time |
12 | | greater than half of the amount of time from |
13 | | the establishment of the permitting timetable |
14 | | under subparagraph (A) to the last final |
15 | | completion date originally established under |
16 | | subparagraph (A). |
17 | | (II) The Director of the Governor's Office |
18 | | of Management and Budget, after consultation |
19 | | with the project sponsor, may permit the |
20 | | office to authorize additional extensions of a |
21 | | permitting timetable beyond the limit |
22 | | prescribed by subclause (I). In such a case, |
23 | | the Director of the Governor's Office of |
24 | | Management and Budget shall transmit, not |
25 | | later than 5 days after making a determination |
26 | | to permit an authorization of extension under |
|
| | HB5555 Engrossed | - 21 - | LRB102 25480 RJF 34768 b |
|
|
1 | | this subclause (II), a report to the General |
2 | | Assembly explaining why such modification is |
3 | | required. Such report shall explain to General |
4 | | Assembly with specificity why the original |
5 | | permitting timetable and the modifications |
6 | | authorized by the office failed to be |
7 | | adequate. The office shall transmit to the |
8 | | Director of the Governor's Office of |
9 | | Management and Budget, a supplemental report |
10 | | on progress toward the final completion date |
11 | | each year thereafter, until the permit review |
12 | | is completed or the project sponsor withdraws |
13 | | its notice or application or other request to |
14 | | which this Section applies. |
15 | | (iv) The following shall not be subject to |
16 | | judicial review: |
17 | | (I) A determination by the office under |
18 | | subclause (III) of clause (i). |
19 | | (II) A determination under subclause (II) |
20 | | of clause (iii) by the Director of the |
21 | | Governor's Office of Management and Budget to |
22 | | permit the office to authorize extensions of a |
23 | | permitting timetable. |
24 | | (E) A permitting timetable established under |
25 | | subparagraph (A) shall be consistent with any other |
26 | | relevant time period established under law and shall |
|
| | HB5555 Engrossed | - 22 - | LRB102 25480 RJF 34768 b |
|
|
1 | | not prevent any cooperating agency from discharging |
2 | | any obligation under law in connection with the |
3 | | project. |
4 | | (F) Conforming to permitting timetables. |
5 | | (i) Each agency shall conform to the |
6 | | completion dates set forth in the permitting |
7 | | timetable established under subparagraph (A), or |
8 | | with any completion date modified under |
9 | | subparagraph (D). |
10 | | (ii) If an agency fails to conform with a |
11 | | completion date for agency action on a covered |
12 | | project or is at significant risk of failing to |
13 | | conform with such a completion date, the agency |
14 | | shall: |
15 | | (I) promptly submit to the office for |
16 | | publication on the Permitting Dashboard an |
17 | | explanation of the specific reasons for |
18 | | failing or significantly risking failing to |
19 | | conform to the completion date and a proposal |
20 | | for an
alternative completion date; |
21 | | (II) in consultation with the office |
22 | | establish, an alternative completion date; and |
23 | | (III) each month thereafter until the |
24 | | agency has taken final action on the delayed |
25 | | authorization or review, submit to the office |
26 | | for posting on the Permitting Dashboard a |
|
| | HB5555 Engrossed | - 23 - | LRB102 25480 RJF 34768 b |
|
|
1 | | status report describing any agency activity |
2 | | related to the project. |
3 | | (G) Abandonment of covered project. |
4 | | (i) If the office has a reasonable basis to |
5 | | doubt the continuing technical or financial |
6 | | ability of the project sponsor to construct the |
7 | | covered project, the office may request the |
8 | | project sponsor provide an updated statement |
9 | | regarding the ability of the project sponsor to |
10 | | complete the project. |
11 | | (ii) If the project sponsor fails to respond |
12 | | to a request described in clause (i) by the date |
13 | | that is 30 days after receiving the request, the |
14 | | office shall publish an appropriate notice on the |
15 | | Permitting Dashboard. |
16 | | (iii) On publication of a notice under clause |
17 | | (ii), the completion dates in the permitting |
18 | | timetable shall be tolled and agencies shall be |
19 | | relieved of the obligation to comply with |
20 | | subparagraph (F) until the project sponsor submits |
21 | | to the office an updated statement regarding the |
22 | | technical and financial ability of the project |
23 | | sponsor to construct the project. |
24 | | (3) Cooperating local governments. |
25 | | (A) If the environmental review is being |
26 | | implemented within the boundaries of a unit of local |
|
| | HB5555 Engrossed | - 24 - | LRB102 25480 RJF 34768 b |
|
|
1 | | government, it may choose to participate in the |
2 | | environmental review and authorization process under |
3 | | this subsection and to make subject to the process all |
4 | | local authorities that: |
5 | | (i) have jurisdiction over the covered |
6 | | project; |
7 | | (ii) are required to conduct or issue a |
8 | | review, analysis, opinion, or statement for the |
9 | | covered project; or |
10 | | (iii) are required to make a determination on |
11 | | issuing a permit, license, or other approval or |
12 | | decision for the covered project. |
13 | | (B) To the maximum extent practicable
under |
14 | | applicable law, the office shall coordinate the |
15 | | environmental review and authorization processes under |
16 | | this subsection (c) with any local authority |
17 | | responsible for conducting any separate review or |
18 | | authorization of the covered project to ensure timely |
19 | | and efficient completion of environmental reviews and |
20 | | authorizations. |
21 | | (C) Any coordination plan between the office and |
22 | | any local authority shall, to the maximum extent |
23 | | practicable, be included in a memorandum of |
24 | | understanding. |
25 | | (d) Early consultation. The office shall provide an |
26 | | expeditious process for project sponsors to confer with each |
|
| | HB5555 Engrossed | - 25 - | LRB102 25480 RJF 34768 b |
|
|
1 | | cooperating agency involved and, not later than 60 days after |
2 | | the date on which the project sponsor submits a request under |
3 | | this subsection, to have each such agency provide to the |
4 | | project sponsor information concerning: |
5 | | (1) the availability of information and tools, |
6 | | including pre-application toolkits, to facilitate early |
7 | | planning efforts; |
8 | | (2) key issues of concern to each agency and to the |
9 | | public; and |
10 | | (3) issues that must be addressed before an |
11 | | environmental review or authorization can be completed.
|