| | HB5262 Engrossed | | LRB102 25484 RAM 34772 b |
|
|
1 | | AN ACT concerning transportation.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | Section 1. Short title. This Act may be cited as the |
5 | | Infrastructure Delivery and Program Transparency Act. |
6 | | Section 5. Definitions. As used in this Act:
|
7 | | "Coordinator" means the Infrastructure Implementation |
8 | | Coordinator appointed by the Office of the Secretary of |
9 | | Transportation.
|
10 | | "Department" means the Illinois Department of |
11 | | Transportation.
|
12 | | "Infrastructure" means publicly owned infrastructure |
13 | | located in the State of Illinois including: (1) streets, |
14 | | roadways, pedestrian ways, commuter linkages and circulator |
15 | | transit systems, bridges, tunnels, overpasses, bus ways, and |
16 | | guideways connected to or adjacent to an infrastructure |
17 | | project; (2) utilities systems and related facilities, utility |
18 | | relocations and replacements, utility-line extensions, network |
19 | | and communication systems, streetscape improvements, drainage |
20 | | systems, sewer and water systems, subgrade structures and |
21 | | associated improvements; (3) landscaping, facade construction |
22 | | and restoration, wayfinding, and signage; (4) public |
23 | | transportation and transit facilities and related |
|
| | HB5262 Engrossed | - 2 - | LRB102 25484 RAM 34772 b |
|
|
1 | | infrastructure, vehicle parking facilities, and other |
2 | | facilities that encourage intermodal transportation and public |
3 | | transit connected to or adjacent to a project; (5) railroad |
4 | | infrastructure, stations, maintenance and storage facilities; |
5 | | (6) parks, plazas, atria, cultural facilities, community and |
6 | | recreational facilities, facilities to promote tourism and |
7 | | hospitality, educational facilities, conferencing and |
8 | | convention centers, broadcast and related multimedia |
9 | | infrastructure, and destination and community retail, dining, |
10 | | and entertainment facilities; and (7) other facilities with |
11 | | the primary purpose of attracting and fostering economic |
12 | | development by generating additional tax base.
|
13 | | "Infrastructure" does not include a commercial office, |
14 | | residential or hotel facilities, or any retail, dining, and |
15 | | entertainment space included within such facilities.
|
16 | | "Infrastructure project" means the construction or |
17 | | renovation of publicly owned infrastructure located within the |
18 | | State of Illinois.
|
19 | | "Program" means the Rebuild Illinois Program.
|
20 | | "Secretary" means the Illinois Secretary of |
21 | | Transportation.
|
22 | | Section 10. Infrastructure implementation coordinator.
|
23 | | (a) The Secretary of Transportation shall appoint an |
24 | | Infrastructure Implementation Coordinator who shall administer |
25 | | the Rebuild Illinois Program, disburse and provide an |
|
| | HB5262 Engrossed | - 3 - | LRB102 25484 RAM 34772 b |
|
|
1 | | accounting of capital funding granted to the State by the U.S. |
2 | | Infrastructure Investment Jobs Act, and provide and facilitate |
3 | | regular reporting and communication to the Illinois Department |
4 | | of Transportation, the General Assembly, the Federal Highway |
5 | | Administration, and to key industry and public stakeholders.
|
6 | | (b) The Coordinator shall direct the performance of all |
7 | | program implementation processes and procedures and shall be |
8 | | provided the necessary resources to establish a master |
9 | | program, budget, and schedule; to track and monitor key |
10 | | metrics; to report and communicate all program metrics; to |
11 | | implement program initiatives; and to provide leadership that |
12 | | results in improvement to all process and procedures related |
13 | | to the delivery of infrastructure improvements.
|
14 | | Section 15. Publicly available master program, budget, and |
15 | | construction schedule.
For the purpose of allowing key |
16 | | infrastructure stakeholders to effectively plan and schedule |
17 | | the procurement of required materials and resources and to |
18 | | keep the public informed of project progress, the Office of |
19 | | the Secretary of Transportation shall develop a publicly |
20 | | available project information website that includes the |
21 | | following information:
|
22 | | (1) the name of the infrastructure being constructed |
23 | | or renovated;
|
24 | | (2) the location of each project;
|
25 | | (3) the estimated commencement and completion date of |
|
| | HB5262 Engrossed | - 4 - | LRB102 25484 RAM 34772 b |
|
|
1 | | each project, as well as timely updates on any projected |
2 | | changes to such dates;
|
3 | | (4) the actual cost of each project.
|
4 | | Section 20. Program metrics.
To measure construction and |
5 | | renovation progress and performance, resolve issues, and |
6 | | publicly report on the program's accomplishments, the |
7 | | Coordinator shall track and make publicly available the |
8 | | following program metrics:
|
9 | | (1) the overall program budget, which the Secretary |
10 | | shall track and report by service type (i.e. construction, |
11 | | consultant services, miscellaneous) and which includes the |
12 | | following:
|
13 | | (A) the current program budget;
|
14 | | (B) the original amount of each program funding |
15 | | award;
|
16 | | (C) the cost of each contract change order or |
17 | | supplemental order;
|
18 | | (D) the amount of obligated funding for each |
19 | | project;
and |
20 | | (E) the amount remaining in each project budget at |
21 | | the completion of the project;
|
22 | | (2) each individual project budget, categorized by |
23 | | core work categories (for example, roadway maintenance, |
24 | | bridges, safety and system modernization, system |
25 | | expansion, and system support);
|
|
| | HB5262 Engrossed | - 5 - | LRB102 25484 RAM 34772 b |
|
|
1 | | (3) general program metrics, which may be categorized |
2 | | on a subprogram basis by major corridor or core work type, |
3 | | and include the following:
|
4 | | (A) the number of direct and indirect jobs |
5 | | created;
|
6 | | (B) the number of contracts awarded under |
7 | | $10,000,000;
|
8 | | (C) the number of contracts awarded to |
9 | | construction and engineering firms;
|
10 | | (D) the number of contracts awarded to unique |
11 | | veteran-owned firms;
and |
12 | | (E) the number of contracts awarded to new firms, |
13 | | established within a year before the date of the |
14 | | contract;
|
15 | | (4) diversity metrics, which shall be tracked and |
16 | | reported for construction and consultant services and |
17 | | include the following:
|
18 | | (A) the amount in contract awards and the |
19 | | percentage of total contracts awarded to participants |
20 | | in the Disadvantaged Business Enterprise Program;
|
21 | | (B) the amount in contract awards and the |
22 | | percentage of total contracts awarded to veteran-owned |
23 | | businesses;
|
24 | | (C) the number of contracts awarded under protege |
25 | | agreements;
|
26 | | (D) the number of contracts awarded to prime |
|
| | HB5262 Engrossed | - 6 - | LRB102 25484 RAM 34772 b |
|
|
1 | | contractors that are participants of the Disadvantaged |
2 | | Business Enterprise Program;
and |
3 | | (E) the number of contracts awarded to prime |
4 | | contractors that are veteran-owned businesses;
and |
5 | | (5) program administrative metrics that include:
|
6 | | (A) the average time from selection of a |
7 | | contractor to the contractor's receipt of a Notice to |
8 | | Proceed;
|
9 | | (B) the average time to process a project invoice;
|
10 | | (C) the average time to process a project payment;
|
11 | | (D) the number of actual advertised contracts;
|
12 | | (E) the number of projected advertised contracts;
|
13 | | and |
14 | | (F) the projected need for construction and |
15 | | consultant services for each year, to be published in |
16 | | each issue of the Illinois Department of |
17 | | Transportation Professional Transportation Bulletin |
18 | | and updated quarterly.
|
19 | | Section 25. Program goal development.
After a review of |
20 | | the program metrics, the Coordinator shall implement |
21 | | improvements to the program in accordance with the established |
22 | | overall program budget and project schedule. As a result, |
23 | | individual project budgets and schedules may be adjusted; |
24 | | however, the overall annual expected program expenditures and |
25 | | target delivery dates for major corridor improvements shall |
|
| | HB5262 Engrossed | - 7 - | LRB102 25484 RAM 34772 b |
|
|
1 | | not vary significantly from established goals.
|
2 | | Section 30. Program goals; expedited processes.
|
3 | | (a) The Coordinator shall process a Notice to Proceed |
4 | | within 30 days of a construction bid opening or consultant |
5 | | selection and shall expedite the execution of contracts and |
6 | | the issuance of a Notice to Proceed to meet this goal.
|
7 | | (b) The Secretary shall disburse payments to construction |
8 | | contractors on a biweekly basis and shall expedite payment to |
9 | | meet this goal.
|
10 | | (c) The Secretary shall disburse payments to consultants |
11 | | within 45 days of the completion of services and shall |
12 | | expedite payments to meet this goal.
|
13 | | Section 35. Program initiatives to support program goals.
|
14 | | The Department and the Coordinator shall do the following to |
15 | | assist the Department with meeting program goals:
|
16 | | (1) develop a mechanism to openly identify and elevate |
17 | | issues within the Rebuild Illinois Program so that they |
18 | | may be resolved in a timely manner;
|
19 | | (2) evaluate and improve processes and procedures for |
20 | | State coordination with the Federal Highway Administration |
21 | | to expedite project delivery;
|
22 | | (3) evaluate and improve the State processes and |
23 | | procedures for prioritizing right-of-way issues, utility |
24 | | conflicts, and permits, to expedite project delivery;
|
|
| | HB5262 Engrossed | - 8 - | LRB102 25484 RAM 34772 b |
|
|
1 | | (4) evaluate and improve the State processes and |
2 | | procedures for prioritizing the resolution of construction |
3 | | field issues that require contract change orders;
|
4 | | (5) establish and improve a construction and |
5 | | consultant mentor-protege program to promote significant |
6 | | and sustainable growth for participants of the |
7 | | Disadvantaged Enterprise Program and veteran-owned firms.
|