Rep. Jay Hoffman

Filed: 3/9/2021

 

 


 

 


 
10200HB2567ham001LRB102 13430 RJF 23011 a

1
AMENDMENT TO HOUSE BILL 2567

2    AMENDMENT NO. ______. Amend House Bill 2567 by replacing
3everything after the enacting clause with the following:
 
4    "Section 5. The Illinois Procurement Code is amended by
5changing Sections 1-15.93 and 30-30 as follows:
 
6    (30 ILCS 500/1-15.93)
7    (Section scheduled to be repealed on January 1, 2022)
8    Sec. 1-15.93. Single prime. "Single prime" means the
9design-bid-build procurement delivery method for a building
10construction project in which the Capital Development Board is
11the construction agency procuring 2 or more subdivisions of
12work enumerated in paragraphs (1) through (5) of subsection
13(a) of Section 30-30 of this Code under a single contract. This
14Section is repealed on January 1, 2024 2022.
15(Source: P.A. 101-369, eff. 12-15-19; 101-645, eff. 6-26-20.)
 

 

 

10200HB2567ham001- 2 -LRB102 13430 RJF 23011 a

1    (30 ILCS 500/30-30)
2    Sec. 30-30. Design-bid-build construction.
3    (a) The provisions of this subsection are operative
4through December 31, 2023 2021.
5    For building construction contracts in excess of $250,000,
6separate specifications may be prepared for all equipment,
7labor, and materials in connection with the following 5
8subdivisions of the work to be performed:
9        (1) plumbing;
10        (2) heating, piping, refrigeration, and automatic
11    temperature control systems, including the testing and
12    balancing of those systems;
13        (3) ventilating and distribution systems for
14    conditioned air, including the testing and balancing of
15    those systems;
16        (4) electric wiring; and
17        (5) general contract work.
18    The specifications may be so drawn as to permit separate
19and independent bidding upon each of the 5 subdivisions of
20work. All contracts awarded for any part thereof may award the
215 subdivisions of work separately to responsible and reliable
22persons, firms, or corporations engaged in these classes of
23work. The contracts, at the discretion of the construction
24agency, may be assigned to the successful bidder on the
25general contract work or to the successful bidder on the
26subdivision of work designated by the construction agency

 

 

10200HB2567ham001- 3 -LRB102 13430 RJF 23011 a

1before the bidding as the prime subdivision of work, provided
2that all payments will be made directly to the contractors for
3the 5 subdivisions of work upon compliance with the conditions
4of the contract.
5    Beginning on the effective date of this amendatory Act of
6the 101st General Assembly and through December 31, 2023 2020,
7for single prime projects: (i) the bid of the successful low
8bidder shall identify the name of the subcontractor, if any,
9and the bid proposal costs for each of the 5 subdivisions of
10work set forth in this Section; (ii) the contract entered into
11with the successful bidder shall provide that no identified
12subcontractor may be terminated without the written consent of
13the Capital Development Board; (iii) the contract shall comply
14with the disadvantaged business practices of the Business
15Enterprise for Minorities, Women, and Persons with
16Disabilities Act and the equal employment practices of Section
172-105 of the Illinois Human Rights Act; and (iv) the Capital
18Development Board shall submit an annual report to the General
19Assembly and Governor on the bidding, award, and performance
20of all single prime projects.
21    For building construction projects with a total
22construction cost valued at $5,000,000 or less, the Capital
23Development Board shall not use the single prime procurement
24delivery method for more than 50% of the total number of
25projects bid for each fiscal year. Any project with a total
26construction cost valued greater than $5,000,000 may be bid

 

 

10200HB2567ham001- 4 -LRB102 13430 RJF 23011 a

1using single prime at the discretion of the Executive Director
2of the Capital Development Board.
3    (b) The provisions of this subsection are operative on and
4after January 1, 2024 2022. For building construction
5contracts in excess of $250,000, separate specifications shall
6be prepared for all equipment, labor, and materials in
7connection with the following 5 subdivisions of the work to be
8performed:
9        (1) plumbing;
10        (2) heating, piping, refrigeration, and automatic
11    temperature control systems, including the testing and
12    balancing of those systems;
13        (3) ventilating and distribution systems for
14    conditioned air, including the testing and balancing of
15    those systems;
16        (4) electric wiring; and
17        (5) general contract work.
18    The specifications must be so drawn as to permit separate
19and independent bidding upon each of the 5 subdivisions of
20work. All contracts awarded for any part thereof shall award
21the 5 subdivisions of work separately to responsible and
22reliable persons, firms, or corporations engaged in these
23classes of work. The contracts, at the discretion of the
24construction agency, may be assigned to the successful bidder
25on the general contract work or to the successful bidder on the
26subdivision of work designated by the construction agency

 

 

10200HB2567ham001- 5 -LRB102 13430 RJF 23011 a

1before the bidding as the prime subdivision of work, provided
2that all payments will be made directly to the contractors for
3the 5 subdivisions of work upon compliance with the conditions
4of the contract.
5(Source: P.A. 100-391, eff. 8-25-17; 101-369, eff. 12-15-19;
6101-645, eff. 6-26-20.)
 
7    Section 99. Effective date. This Act takes effect upon
8becoming law.".