|
Rep. Michael J. Zalewski
Filed: 3/20/2019
| | 10100HB3412ham001 | | LRB101 08764 HLH 57768 a |
|
|
1 | | AMENDMENT TO HOUSE BILL 3412
|
2 | | AMENDMENT NO. ______. Amend House Bill 3412 on page 1, |
3 | | immediately below line 16, by inserting the following:
|
4 | | " "ASHRAE Standard 90.4-2016" means the Energy Standard |
5 | | for Data Centers published by the American Society of |
6 | | Heating, Refrigerating, and Air-Conditioning Engineers. "; |
7 | | and |
8 | | on page 5, immediately below line 12, by inserting the |
9 | | following: |
10 | | " (d) New and existing data centers seeking a certificate of |
11 | | exemption for new or existing facilities shall submit, with |
12 | | respect to each application, a response in a form and manner |
13 | | specified by the Department, which includes the following: |
14 | | (1) An energy usage plan that provides the following |
15 | | information: |
16 | | (A) the expected quantity of electrical energy, in |
17 | | kilowatt-hours, needed to fulfill 100% of the |
|
| | 10100HB3412ham001 | - 2 - | LRB101 08764 HLH 57768 a |
|
|
1 | | anticipated electrical energy needs of the data |
2 | | center: |
3 | | (i) over the course of the first 12 consecutive |
4 | | months of operation; and |
5 | | (ii) on average, over the course of 12 |
6 | | consecutive months, excluding the first 12 months |
7 | | of operation; and |
8 | | (B) documentation of the expected quantity of |
9 | | renewable energy to be generated on site or purchased |
10 | | by the data center through renewable energy credits or |
11 | | otherwise delivered to the site. |
12 | | (2) A water resources plan that provides the following |
13 | | information: |
14 | | (A) the expected volume of water, in kiloliters, |
15 | | needed to fulfill 100% of the anticipated water |
16 | | consumption needs of the data center over the course of |
17 | | 12 consecutive months; and |
18 | | (B) the data center's policy for sustainable water |
19 | | use and water conservation. |
20 | | (e) To maintain its certificate of exemption, a qualifying |
21 | | data center shall provide the following to the Department each |
22 | | calendar year by June 1: |
23 | | (1) An energy usage report that provides the following |
24 | | information: |
25 | | (A) the actual quantity of electrical energy, in |
26 | | kilowatt-hours, consumed annually by the qualifying |
|
| | 10100HB3412ham001 | - 3 - | LRB101 08764 HLH 57768 a |
|
|
1 | | data center during the previous calendar year; |
2 | | (B) any alterations the qualifying data center |
3 | | proposes to undertake to improve the facility's |
4 | | electrical energy consumption; and |
5 | | (C) documentation of any energy efficiency |
6 | | upgrades that were completed on the facility. |
7 | | (2) A water resources report that provides the |
8 | | following information: |
9 | | (A) the actual volume of water, in kiloliters, |
10 | | consumed by the qualifying data center over the course |
11 | | of 12 consecutive months during the previous calendar |
12 | | year; and |
13 | | (B) any alterations the qualifying data center |
14 | | will undertake to improve the data center's water |
15 | | consumption. |
16 | | (f) Beginning 180 days after the effective date of this |
17 | | amendatory Act of the 101st General Assembly, all qualifying |
18 | | data centers in the State shall meet or exceed the requirements |
19 | | in the ASHRAE Standard 90.4-2016. The Department may replace |
20 | | the ASHRAE Standard 90.4-2016 identified in this subsection by |
21 | | adopting rules consistent with the requirements of the Illinois |
22 | | Administrative Procedure Act. Whenever the provisions of any |
23 | | energy efficiency standard imposed or adopted by the Department |
24 | | are revised by the standard publishing body, including, but not |
25 | | limited to, ASHRAE, the Department shall, not later than 12 |
26 | | months after the date of such revision, publish a notice of |
|
| | 10100HB3412ham001 | - 4 - | LRB101 08764 HLH 57768 a |
|
|
1 | | determination of whether such revision will improve energy |
2 | | efficiency in data centers in Illinois. If the Department |
3 | | publishes an affirmative determination, then, not later than 6 |
4 | | months after the determination, the Department shall, by rule, |
5 | | adopt the revised energy efficiency standard for qualifying |
6 | | data centers and immediately notify all qualifying data centers |
7 | | in the State. Existing qualifying data centers shall be subject |
8 | | to the revised energy efficiency standard within 24 months |
9 | | after the Department adopts the revised standard. The |
10 | | Department shall provide data centers with technical |
11 | | assistance concerning implementation of the energy efficiency |
12 | | standard under this Section. The Department shall determine |
13 | | procedures for compliance with the energy efficiency standard. |
14 | | These procedures may include, but need not be limited to, |
15 | | certification by a national, State, or local accredited energy |
16 | | conservation program or inspections from private certified |
17 | | inspectors using the ASHRAE Standard 90.4-2016. |
18 | | (g) A qualifying data center shall ensure that renewable |
19 | | energy sources fulfill 100% of the facility's electrical energy |
20 | | consumption. A qualifying data center shall do so through one |
21 | | or more of the following: |
22 | | (1) on-site renewable generation; |
23 | | (2) renewable energy credits purchased by the |
24 | | facility; |
25 | | (3) subscription in a renewable energy program by the |
26 | | provider of electricity to the qualifying facility; or |
|
| | 10100HB3412ham001 | - 5 - | LRB101 08764 HLH 57768 a |
|
|
1 | | (4) any combination of (1), (2) and (3) so that |
2 | | renewable energy sources fulfill 100% of the facility's |
3 | | electrical energy consumption. |
4 | | (h) After the first 12 consecutive months of operation, a |
5 | | qualifying data center shall reuse at least 50% of wastewater |
6 | | generated by the data center. The Department, in consultation |
7 | | with the Illinois Environmental Protection Agency, shall adopt |
8 | | rules to carry out the provisions of this subsection. |
9 | | (i) No later than 2 years after the effective date of this |
10 | | amendatory Act of the 101st General Assembly, and at least |
11 | | every 2 years thereafter, the Department, in consultation with |
12 | | the Illinois Commerce Commission, shall make publicly |
13 | | available a report that contains: |
14 | | (1) an analysis of the state of data centers in |
15 | | Illinois and their expected growth; |
16 | | (2) the total energy usage of qualifying data centers |
17 | | in the State; |
18 | | (3) a comparison of energy efficiency of data centers |
19 | | in the State versus that of data centers in other states; |
20 | | (4) a review of the energy efficiency reporting |
21 | | requirements this Section and a determination of whether |
22 | | the Department will revise the requirements; |
23 | | (5) a review of the energy efficiency standard in this |
24 | | Section and a determination of whether the Department will |
25 | | revise the standard; and |
26 | | (6) other recommendations for improving energy |