1 | AMENDMENT TO HOUSE BILL 2865
| ||||||
2 | AMENDMENT NO. ______. Amend House Bill 2865 on page 8, by | ||||||
3 | deleting lines 13 through 15; and | ||||||
4 | on page 17, by replacing lines 8 through 20 with the following:
| ||||||
5 | "Section 35. Procedures for selection. | ||||||
6 | (a) The Transportation Agency shall review, evaluate, | ||||||
7 | score, and rank proposals and determine which proposal offers | ||||||
8 | the best value to the public based on the evaluation criteria | ||||||
9 | set forth in the request for proposals. The Transportation | ||||||
10 | Agency shall award the contract based on this determination. | ||||||
11 | Notwithstanding other provisions of this Section, if for any | ||||||
12 | reason the proposer awarded the contract is unable or unwilling | ||||||
13 | to execute the contract, including the failure of the proposer | ||||||
14 | and the Transportation Agency to successfully complete | ||||||
15 | negotiations, if any, of the contract, the Transportation | ||||||
16 | Agency may award the contract to the proposer whose proposal
|
| |||||||
| |||||||
1 | the Transportation Agency determines offers the public the next | ||||||
2 | best value. | ||||||
3 | (b) After a proposal has been submitted as provided in | ||||||
4 | Section 25, a design-builder shall not replace, remove, or | ||||||
5 | otherwise modify any firm identified as a member of the | ||||||
6 | proposer team unless: | ||||||
7 | (1) the firm is no longer in business; | ||||||
8 | (2) the firm is unable to fulfill its legal, financial, | ||||||
9 | or business obligations; | ||||||
10 | (3) the firm no longer meets the terms of its agreement | ||||||
11 | with the design-builder; | ||||||
12 | (4) the firm voluntarily removes itself from the | ||||||
13 | proposer team; | ||||||
14 | (5) the firm fails to provide a sufficient number of | ||||||
15 | qualified personnel to fulfill the duties identified in the | ||||||
16 | proposal; or | ||||||
17 | (6) the firm fails to negotiate in good faith, in a | ||||||
18 | timely manner, and in accordance with the provisions | ||||||
19 | established in the agreement with the design-builder. | ||||||
20 | (c) If the design-builder modifies the proposer team, any | ||||||
21 | cost savings attributable to the modification shall accrue to
| ||||||
22 | the Department and not to the design-builder.".
|