|
Rep. Camille Y. Lilly
Filed: 2/27/2019
| | 10100HB0173ham001 | | LRB101 04717 RJF 56577 a |
|
|
1 | | AMENDMENT TO HOUSE BILL 173
|
2 | | AMENDMENT NO. ______. Amend House Bill 173 by replacing |
3 | | everything after the enacting clause with the following:
|
4 | | "Section 5. The State Prompt Payment Act is amended by |
5 | | changing Section 7 as follows:
|
6 | | (30 ILCS 540/7)
(from Ch. 127, par. 132.407)
|
7 | | Sec. 7. Payments to subcontractors and material suppliers. |
8 | | (a) When a State official or agency responsible for |
9 | | administering a
contract submits a voucher to the Comptroller |
10 | | for
payment to a contractor, that State official or agency |
11 | | shall promptly make
available electronically
the voucher |
12 | | number, the date of the voucher, and
the amount of the voucher , |
13 | | and the names of all subcontractors who are to be paid from |
14 | | that pay period in the voucher .
The State official or agency |
15 | | responsible for administering the contract shall
provide |
16 | | subcontractors and material suppliers, known to the State |
|
| | 10100HB0173ham001 | - 2 - | LRB101 04717 RJF 56577 a |
|
|
1 | | official or
agency, with instructions on how to access the |
2 | | electronic information. |
3 | | (a-5) When a
contractor receives any payment, the |
4 | | contractor shall
pay each subcontractor and material supplier |
5 | | electronically within 72 hours after receiving payment in |
6 | | proportion to the work
completed by each subcontractor and |
7 | | material supplier its application or pay estimate, plus |
8 | | interest received under this Act. When a contractor receives |
9 | | any payment, the contractor shall pay each lower-tiered |
10 | | subcontractor and material supplier and each subcontractor and |
11 | | material supplier shall make payment to its own respective |
12 | | subcontractors and material suppliers. If the contractor |
13 | | receives less than the full payment
due under the public |
14 | | construction contract, the contractor shall be
obligated to |
15 | | disburse on a pro rata basis those funds received, plus |
16 | | interest received under this Act, with the
contractor, |
17 | | subcontractors and material suppliers each receiving a |
18 | | prorated
portion based on the amount of payment each has |
19 | | earned. When, however, the State official or agency
does not |
20 | | release the full payment due under the contract because there |
21 | | are
specific areas of work or materials the State agency or |
22 | | official has determined are not suitable for
payment, then |
23 | | those specific subcontractors or material suppliers involved |
24 | | shall not
be paid for that portion of work rejected or deemed |
25 | | not suitable for
payment and all other subcontractors and |
26 | | suppliers shall be paid based upon the amount of payment each |
|
| | 10100HB0173ham001 | - 3 - | LRB101 04717 RJF 56577 a |
|
|
1 | | has earned, plus interest received under this Act.
|
2 | | (a-10) For construction contracts with the Department of |
3 | | Transportation, the contractor, subcontractor, or material |
4 | | supplier, regardless of tier, shall not offset, decrease, or |
5 | | diminish payment or payments that are due to its subcontractors |
6 | | or material suppliers without reasonable cause. |
7 | | A contractor, who refuses to make prompt payment |
8 | | electronically within 72 hours after receiving payment , in |
9 | | whole or in part, shall provide to the subcontractor or |
10 | | material supplier and the public owner or its agent, a written |
11 | | notice of that refusal. The written notice shall be made by a |
12 | | contractor no later than 5 calendar days after payment is |
13 | | received by the contractor. The written notice shall identify |
14 | | the Department of Transportation's contract, any subcontract |
15 | | or material purchase agreement, a detailed reason for refusal, |
16 | | the value of the payment to be withheld, and the specific |
17 | | remedial actions required of the subcontractor or material |
18 | | supplier so that payment may be made. Written notice of refusal |
19 | | may be given in a form and method which is acceptable to the |
20 | | parties and public owner. |
21 | | (b) If the contractor, without reasonable cause, fails to |
22 | | make full payment of amounts due under subsection (a) to its
|
23 | | subcontractors and material suppliers within 72 hours 15 |
24 | | calendar days after
receipt of
payment from the State official |
25 | | or agency, the contractor shall pay to its
subcontractors and |
26 | | material suppliers, in addition to the payment due
them, |
|
| | 10100HB0173ham001 | - 4 - | LRB101 04717 RJF 56577 a |
|
|
1 | | interest in the amount of
2% per month, calculated from the
|
2 | | expiration of the 72-hour 15-day period until fully paid. This |
3 | | subsection shall further
apply to any payments made by |
4 | | subcontractors and material suppliers to
their subcontractors |
5 | | and material suppliers and to all payments made to
lower tier |
6 | | subcontractors and material suppliers throughout the |
7 | | contracting
chain.
|
8 | | (1) If a contractor, without reasonable cause, fails to |
9 | | make payment in
full as
provided in subsection (a-5) within |
10 | | 72 hours 15 calendar days after receipt of payment under |
11 | | the
public
construction contract, any subcontractor or |
12 | | material supplier to whom payments
are owed
may file a |
13 | | written notice and request for administrative hearing with |
14 | | the State official or agency setting forth the
amount owed |
15 | | by
the contractor and the contractor's failure to timely |
16 | | pay the amount owed. The written notice and request for |
17 | | administrative hearing shall identify the public |
18 | | construction contract, the contractor, and the amount |
19 | | owed, and shall contain a sworn statement or attestation to |
20 | | verify the accuracy of the notice. The notice and request |
21 | | for administrative hearing shall be filed with the State |
22 | | official for the public construction contract, with a copy |
23 | | of the notice concurrently provided to the contractor. |
24 | | Notice to the State official may be made by certified or |
25 | | registered mail, messenger service, or personal service, |
26 | | and must include proof of delivery to the State official.
|
|
| | 10100HB0173ham001 | - 5 - | LRB101 04717 RJF 56577 a |
|
|
1 | | (2) The State official or agency, within 15 calendar |
2 | | days after receipt of a
subcontractor's
or material |
3 | | supplier's written notice and request for administrative |
4 | | hearing,
shall hold a hearing convened by an administrative |
5 | | law judge to determine whether the contractor withheld |
6 | | payment,
without
reasonable cause, from the subcontractors |
7 | | or material suppliers and what
amount, if any,
is due to |
8 | | the subcontractors or material suppliers, and the |
9 | | reasonable cause or causes asserted by the contractor. The |
10 | | State official or
agency shall
provide appropriate notice |
11 | | to the parties of the date, time, and location of
the |
12 | | hearing. Each contractor, subcontractor, or material |
13 | | supplier has the right to be represented by counsel at a |
14 | | hearing and to cross-examine witnesses and challenge |
15 | | documents. Upon the request of the subcontractor or |
16 | | material supplier and a showing of good cause, reasonable |
17 | | continuances may be granted by the administrative law |
18 | | judge.
|
19 | | (3) Upon a finding by the administrative law judge that |
20 | | the contractor failed
to make
payment in full, without |
21 | | reasonable cause, as provided in subsection (a-10), then
|
22 | | the administrative law judge shall, in writing, order the |
23 | | contractor to pay the amount
owed to the
subcontractors or |
24 | | material suppliers plus interest within 15 calendar days |
25 | | after the order.
|
26 | | (4) If a contractor fails to make full payment as |
|
| | 10100HB0173ham001 | - 6 - | LRB101 04717 RJF 56577 a |
|
|
1 | | ordered under paragraph (3) of this subsection (b) within |
2 | | 15 days after the
administrative law judge's order, then |
3 | | the contractor shall be barred from
entering into a State
|
4 | | public construction contract for a period of one year |
5 | | beginning on the date of
the administrative law judge's |
6 | | order.
|
7 | | (5) If, on 2 or more occasions within a 3-calendar-year |
8 | | period, there is a finding by an administrative law judge |
9 | | that the contractor failed to make payment in full, without |
10 | | reasonable cause, and a written order was issued to a |
11 | | contractor under paragraph (3) of this subsection (b), then |
12 | | the contractor shall be barred from entering into a State |
13 | | public construction contract for a period of 6 months |
14 | | beginning on the date of the administrative law judge's |
15 | | second written order, even if the payments required under |
16 | | the orders were made in full. |
17 | | (6) If a contractor fails to make full payment as |
18 | | ordered under paragraph (4) of this subsection (b), the |
19 | | subcontractor or material supplier may, within 30 days of |
20 | | the date of that order, petition the State agency for an |
21 | | order for reasonable attorney's fees and costs incurred in |
22 | | the prosecution of the action under this subsection (b). |
23 | | Upon that petition and taking of additional evidence, as |
24 | | may be required, the administrative law judge may issue a |
25 | | supplemental order directing the contractor to pay those |
26 | | reasonable attorney's fees and costs. |
|
| | 10100HB0173ham001 | - 7 - | LRB101 04717 RJF 56577 a |
|
|
1 | | (7) The written order of the administrative law judge |
2 | | shall be final and appealable under the Administrative |
3 | | Review Law. |
4 | | (c) This Section shall not be construed to in any manner |
5 | | diminish, negate, or interfere with the |
6 | | contractor-subcontractor or contractor-material supplier |
7 | | relationship or commercially useful function. |
8 | | (d) This Section shall not preclude, bar, or stay the |
9 | | rights, remedies, and defenses available to the parties by way |
10 | | of the operation of their contract, purchase agreement, the |
11 | | Mechanics Lien Act, or the Public Construction Bond Act. |
12 | | (e) State officials and agencies may adopt rules as may be |
13 | | deemed necessary in order to establish the formal procedures |
14 | | required under this Section. |
15 | | (f) As used in this Section: |
16 | | "Payment" means the discharge of an obligation in money or |
17 | | other valuable consideration or thing delivered in full or |
18 | | partial satisfaction of an obligation to pay. "Payment" shall |
19 | | include interest paid pursuant to this Act. |
20 | | "Reasonable cause" may include, but is not limited to, |
21 | | unsatisfactory workmanship or materials; failure to provide |
22 | | documentation required by the contract, subcontract, or |
23 | | material purchase agreement; claims made against the |
24 | | Department of Transportation or the subcontractor pursuant to |
25 | | subsection (c) of Section 23 of the Mechanics Lien Act or the |
26 | | Public Construction Bond Act; judgments, levies, garnishments, |
|
| | 10100HB0173ham001 | - 8 - | LRB101 04717 RJF 56577 a |
|
|
1 | | or other court-ordered assessments or offsets in favor of the |
2 | | Department of Transportation or other State agency entered |
3 | | against a subcontractor or material supplier. "Reasonable |
4 | | cause" does not include payments issued to the contractor that |
5 | | create a negative or reduced valuation pay application or pay |
6 | | estimate due to a reduction of contract quantities or work not |
7 | | performed or provided by the subcontractor or material |
8 | | supplier; the interception or withholding of funds for reasons |
9 | | not related to the subcontractor's or material supplier's work |
10 | | on the contract; anticipated claims or assessments of third |
11 | | parties not a party related to the contract or subcontract; |
12 | | asserted claims or assessments of third parties that are not |
13 | | authorized by court order, administrative tribunal, or |
14 | | statute. "Reasonable cause" further does not include the |
15 | | withholding, offset, or reduction of payment, in whole or in |
16 | | part, due to the assessment of liquidated damages or penalties |
17 | | assessed by the Department of Transportation against the |
18 | | contractor, unless the subcontractor's performance or supplied |
19 | | materials were the sole and proximate cause of the liquidated |
20 | | damage or penalty. |
21 | | (Source: P.A. 100-43, eff. 8-9-17; 100-376, eff. 1-1-18; |
22 | | 100-863, eff. 8-14-18.)".
|