|
| | HB2664 Enrolled | | LRB100 08773 MLM 18912 b |
|
|
1 | | AN ACT concerning finance.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | Section 5. The State Prompt Payment Act is amended by |
5 | | changing Section 7 as follows:
|
6 | | (30 ILCS 540/7)
(from Ch. 127, par. 132.407)
|
7 | | Sec. 7. Payments to subcontractors and material suppliers. |
8 | | (a) When a State official or agency responsible for |
9 | | administering a
contract submits a voucher to the Comptroller |
10 | | for
payment to a contractor, that State official or agency |
11 | | shall promptly make
available electronically
the voucher |
12 | | number, the date of the voucher, and
the amount of the voucher.
|
13 | | The State official or agency responsible for administering the |
14 | | contract shall
provide subcontractors and material suppliers, |
15 | | known to the State official or
agency, with instructions on how |
16 | | to access the electronic information. |
17 | | (a-5) When a
contractor receives any payment, the |
18 | | contractor shall
pay each subcontractor and material supplier |
19 | | in proportion to the work
completed by each subcontractor and |
20 | | material supplier its their application or pay estimate , plus |
21 | | interest received under this Act ,
less any retention . When a |
22 | | contractor receives any payment, the contractor shall pay each |
23 | | lower-tiered subcontractor and material supplier and each |
|
| | HB2664 Enrolled | - 2 - | LRB100 08773 MLM 18912 b |
|
|
1 | | subcontractor and material supplier shall make payment to its |
2 | | own respective subcontractors and material suppliers. If the |
3 | | contractor receives less than the full payment
due under the |
4 | | public construction contract, the contractor shall be
|
5 | | obligated to disburse on a pro rata basis those funds received, |
6 | | plus interest received under this Act, with the
contractor, |
7 | | subcontractors and material suppliers each receiving a |
8 | | prorated
portion based on the amount of payment each has |
9 | | earned . When, however, the State official or agency public |
10 | | owner
does not release the full payment due under the contract |
11 | | because there are
specific areas of work or materials the State |
12 | | agency or official has determined contractor is rejecting or |
13 | | because
the contractor has otherwise determined such areas are |
14 | | not suitable for
payment, then those specific subcontractors or |
15 | | material suppliers involved shall not
be paid for that portion |
16 | | of work rejected or deemed not suitable for
payment and all |
17 | | other subcontractors and suppliers shall be paid based upon the |
18 | | amount of payment each has earned in full , plus interest |
19 | | received under this Act.
|
20 | | (a-10) For construction contracts with the Department of |
21 | | Transportation, the contractor, subcontractor, or material |
22 | | supplier, regardless of tier, shall not offset, decrease, or |
23 | | diminish payment or payments that are due to its subcontractors |
24 | | or material suppliers without reasonable cause. |
25 | | A contractor, who refuses to make prompt payment, in whole |
26 | | or in part, shall provide to the subcontractor or material |
|
| | HB2664 Enrolled | - 3 - | LRB100 08773 MLM 18912 b |
|
|
1 | | supplier and the public owner or its agent, a written notice of |
2 | | that refusal. The written notice shall be made by a contractor |
3 | | no later than 5 calendar days after payment is received by the |
4 | | contractor. The written notice shall identify the Department of |
5 | | Transportation's contract, any subcontract or material |
6 | | purchase agreement, a detailed reason for refusal, the value of |
7 | | the payment to be withheld, and the specific remedial actions |
8 | | required of the subcontractor or material supplier so that |
9 | | payment may be made. Written notice of refusal may be given in |
10 | | a form and method which is acceptable to the parties and public |
11 | | owner. |
12 | | (b) If the contractor, without reasonable cause, fails to |
13 | | make full payment of amounts due under subsection (a) to its
|
14 | | his subcontractors and material suppliers within 15 calendar |
15 | | days after
receipt of
payment from the State official or agency |
16 | | under the public construction contract , the contractor shall |
17 | | pay to its
his subcontractors and material suppliers, in |
18 | | addition to the payment due
them, interest in the amount of
2% |
19 | | per month, calculated from the
expiration of the 15-day period |
20 | | until fully paid. This subsection shall further
also apply to |
21 | | any payments made by subcontractors and material suppliers to
|
22 | | their subcontractors and material suppliers and to all payments |
23 | | made to
lower tier subcontractors and material suppliers |
24 | | throughout the contracting
chain.
|
25 | | (1) If a contractor, without reasonable cause, fails to |
26 | | make payment in
full as
provided in subsection (a-5) (a) |
|
| | HB2664 Enrolled | - 4 - | LRB100 08773 MLM 18912 b |
|
|
1 | | within 15 calendar days after receipt of payment under the
|
2 | | public
construction contract, any subcontractor or |
3 | | material supplier to whom payments
are owed
may file a |
4 | | written notice and request for administrative hearing with |
5 | | the State official or agency setting forth the
amount owed |
6 | | by
the contractor and the contractor's failure to timely |
7 | | pay the amount owed. The written notice and request for |
8 | | administrative hearing shall identify the public |
9 | | construction contract, the contractor, and the amount |
10 | | owed, and shall contain a sworn statement or attestation to |
11 | | verify the accuracy of the notice. The notice and request |
12 | | for administrative hearing shall be filed with the State |
13 | | official for the public construction contract, with a copy |
14 | | of the notice concurrently provided to the contractor. |
15 | | Notice to the State official may be made by certified or |
16 | | registered mail, messenger service, or personal service, |
17 | | and must include proof of delivery to the State official.
|
18 | | (2) The State official or agency, within 15 calendar |
19 | | days after receipt of a
subcontractor's
or material |
20 | | supplier's written notice and request for administrative |
21 | | hearing of the failure to receive payment from
the |
22 | | contractor ,
shall hold a hearing convened by an |
23 | | administrative law judge to determine whether the |
24 | | contractor withheld payment,
without
reasonable cause, |
25 | | from the subcontractors or and material suppliers and what
|
26 | | amount, if any,
is due to the subcontractors or and |
|
| | HB2664 Enrolled | - 5 - | LRB100 08773 MLM 18912 b |
|
|
1 | | material suppliers , and the reasonable cause or causes |
2 | | asserted by the contractor . The State official or
agency |
3 | | shall
provide appropriate notice to the parties of the |
4 | | date, time, and location of
the hearing. Each contractor, |
5 | | subcontractor, or and material supplier has the right to be |
6 | | represented by counsel at a the hearing and to |
7 | | cross-examine witnesses and challenge documents. Upon the |
8 | | request of the subcontractor or material supplier and a |
9 | | showing of good cause, reasonable continuances may be |
10 | | granted by the administrative law judge.
|
11 | | (3) Upon If there is a finding by the administrative |
12 | | law judge that the contractor failed
to make
payment in |
13 | | full, without reasonable cause, as provided in subsection |
14 | | (a-10) (a) , then
the administrative law judge shall, in |
15 | | writing, order direct the contractor to pay the amount
owed |
16 | | to the
subcontractors or and material suppliers plus |
17 | | interest within 15 calendar days after the order
finding .
|
18 | | (4) If a contractor fails to make full payment as |
19 | | ordered under paragraph (3) of this subsection (b) within |
20 | | 15 days after the
administrative law judge's order finding , |
21 | | then the contractor shall be barred from
entering into a |
22 | | State
public construction contract for a period of one year |
23 | | beginning on the date of
the administrative law judge's |
24 | | order finding .
|
25 | | (5) If, on 2 or more occasions within a 3-calendar-year |
26 | | period, there is a finding by an administrative law judge |
|
| | HB2664 Enrolled | - 6 - | LRB100 08773 MLM 18912 b |
|
|
1 | | that the contractor failed to make payment in full, without |
2 | | reasonable cause, and a written order was issued to a |
3 | | contractor under paragraph (3) of this subsection (b), then |
4 | | the contractor shall be barred from entering into a State |
5 | | public construction contract for a period of 6 months |
6 | | beginning on the date of the administrative law judge's |
7 | | second written order, even if the payments required under |
8 | | the orders were made in full. |
9 | | (6) If a contractor fails to make full payment as |
10 | | ordered under paragraph (4) of this subsection (b), the |
11 | | subcontractor or material supplier may, within 30 days of |
12 | | the date of that order, petition the State agency for an |
13 | | order for reasonable attorney's fees and costs incurred in |
14 | | the prosecution of the action under this subsection (b). |
15 | | Upon that petition and taking of additional evidence, as |
16 | | may be required, the administrative law judge may issue a |
17 | | supplemental order directing the contractor to pay those |
18 | | reasonable attorney's fees and costs. |
19 | | (7) The written order of the administrative law judge |
20 | | shall be final and appealable under the Administrative |
21 | | Review Law. |
22 | | (c) This Section shall not be construed to in any manner |
23 | | diminish, negate, or interfere with the |
24 | | contractor-subcontractor or contractor-material supplier |
25 | | relationship or commercially useful function. |
26 | | (d) This Section shall not preclude, bar, or stay the |
|
| | HB2664 Enrolled | - 7 - | LRB100 08773 MLM 18912 b |
|
|
1 | | rights, remedies, and defenses available to the parties by way |
2 | | of the operation of their contract, purchase agreement, the |
3 | | Mechanics Lien Act, or the Public Construction Bond Act. |
4 | | (e) State officials and agencies may adopt rules as may be |
5 | | deemed necessary in order to establish the formal procedures |
6 | | required under this Section. |
7 | | (f) As used in this Section, |
8 | | "Payment" means the discharge of an obligation in money or |
9 | | other valuable consideration or thing delivered in full or |
10 | | partial satisfaction of an obligation to pay. "Payment" shall |
11 | | include interest paid pursuant to this Act. |
12 | | "Reasonable cause" may include, but is not limited to, |
13 | | unsatisfactory workmanship or materials; failure to provide |
14 | | documentation required by the contract, subcontract, or |
15 | | material purchase agreement; claims made against the |
16 | | Department of Transportation or the subcontractor pursuant to |
17 | | subsection (c) of Section 23 of the Mechanics Lien Act or the |
18 | | Public Construction Bond Act; judgments, levies, garnishments, |
19 | | or other court-ordered assessments or offsets in favor of the |
20 | | Department of Transportation or other State agency entered |
21 | | against a subcontractor or material supplier. "Reasonable |
22 | | cause" does not include payments issued to the contractor that |
23 | | create a negative or reduced valuation pay application or pay |
24 | | estimate due to a reduction of contract quantities or work not |
25 | | performed or provided by the subcontractor or material |
26 | | supplier; the interception or withholding of funds for reasons |
|
| | HB2664 Enrolled | - 8 - | LRB100 08773 MLM 18912 b |
|
|
1 | | not related to the subcontractor's or material supplier's work |
2 | | on the contract; anticipated claims or assessments of third |
3 | | parties not a party related to the contract or subcontract; |
4 | | asserted claims or assessments of third parties that are not |
5 | | authorized by court order, administrative tribunal, or |
6 | | statute. "Reasonable cause" further does not include the |
7 | | withholding, offset, or reduction of payment, in whole or in |
8 | | part, due to the assessment of liquidated damages or penalties |
9 | | assessed by the Department of Transportation against the |
10 | | contractor, unless the subcontractor's performance or supplied |
11 | | materials were the sole and proximate cause of the liquidated |
12 | | damage or penalty. |
13 | | (Source: P.A. 94-672, eff. 1-1-06; 94-972, eff. 7-1-07 .)
|