|
Public Act 097-0405 |
HB1703 Enrolled | LRB097 10381 ASK 50596 b |
|
|
AN ACT concerning regulation.
|
Be it enacted by the People of the State of Illinois,
|
represented in the General Assembly:
|
Section 5. The Public Utilities Act is amended by changing |
Section 15-401 as follows:
|
(220 ILCS 5/15-401)
|
Sec. 15-401. Licensing.
|
(a) No person shall operate
as a common carrier by pipeline |
unless the person
possesses a certificate in good standing |
authorizing it to operate as a
common carrier by pipeline. No
|
person shall begin or continue construction of a
pipeline or |
other facility, other than the repair or
replacement of an |
existing pipeline or facility, for use
in operations as a |
common carrier by pipeline unless the
person possesses a |
certificate in good standing.
|
(b) Requirements for issuance. The Commission,
after a |
hearing, shall grant an application for a
certificate |
authorizing operations as a common carrier by
pipeline, in |
whole or in part, to the extent that it
finds that the |
application was properly filed; a public
need for the service |
exists; the applicant is fit,
willing, and able to provide the |
service in compliance
with this Act, Commission regulations, |
and orders; and the
public convenience and necessity requires |
|
issuance of the
certificate. Evidence encompassing
any of the |
factors described in items (1) through (9) of this subsection |
(b) that is
submitted by the applicant, any other party, or the |
Commission's staff shall also be
considered by the Commission |
in determining whether a public need for the service
exists |
under either current or expected conditions. The changes in |
this subsection (b) are
intended to be confirmatory of existing |
law.
|
In its determination of public convenience and necessity |
for a proposed
pipeline or facility designed or intended to |
transport crude oil and any
alternate locations for such |
proposed pipeline or facility,
the Commission shall consider, |
but not be limited to, the following:
|
(1) any evidence presented by the Illinois |
Environmental Protection Agency
regarding the |
environmental impact of the proposed pipeline or other |
facility;
|
(2) any evidence presented by the Illinois Department |
of Transportation
regarding the impact of the proposed |
pipeline or facility on traffic safety,
road construction, |
or other transportation issues;
|
(3) any evidence presented by the Department of Natural |
Resources
regarding
the impact of the proposed pipeline or |
facility on any conservation areas,
forest preserves, |
wildlife preserves, wetlands, or any other natural |
resource;
|
|
(4) any evidence of the effect of the pipeline upon the |
economy,
infrastructure, and public safety presented by |
local governmental units that
will be
affected by the |
proposed pipeline or facility;
|
(5) any evidence of the effect of the pipeline upon |
property values
presented by property owners who will be |
affected by the
proposed pipeline or facility , provided |
that the Commission need not hear evidence as to the actual |
valuation of property such as that
as would be presented to |
and determined by the courts under the Eminent Domain Act ;
|
(6) any evidence presented by the Department of |
Commerce and Economic Opportunity
regarding the current |
and future local, State-wide, or regional economic effect , |
direct or indirect, of the proposed
pipeline or facility |
including, but not limited to, property values, employment
|
rates, and residential and business development; and
|
(7) any evidence addressing the factors described in |
items (1) through (9) of this subsection (b) or other |
relevant factors that is presented by any other State |
agency , the applicant, a party, or other entity that
|
participates in the proceeding , including evidence |
presented by the Commission's staff; .
|
(8) any evidence presented by a State agency or unit of |
State or local government as to the
current and future |
national, State-wide, or regional economic effects of the |
proposed
pipeline, direct or indirect, as they affect |
|
residents or businesses in Illinois, including, but
not |
limited to, such impacts as the ability of manufacturers in |
Illinois to meet public
demand for related services and |
products and to compete in the national and regional
|
economies, improved access of suppliers to regional and |
national shipping grids, the
ability of the State to access |
funds made available for energy infrastructure by the |
federal
government, mitigation of foreseeable spikes in |
price affecting Illinois residents or
businesses due to |
sudden changes in supply or transportation capacity, and |
the likelihood
that the proposed construction will |
substantially encourage related investment in the
State's |
energy infrastructure and the creation of energy related |
jobs; and |
(9) any evidence presented by any State or federal |
governmental entity as to how the proposed
pipeline or |
facility will affect the security, stability, and |
reliability of energy in the State
or in the region. |
In its written order, the Commission shall address all of |
the evidence
presented, and if the order is contrary to any of |
the evidence, the Commission
shall state the reasons for its |
determination with regard to that evidence.
The provisions of |
this amendatory Act of 1996 apply to any certificate granted
or |
denied after the effective date of
this
amendatory Act
of 1996.
|
(c) An application filed pursuant to this Section may |
request either that the Commission review and approve a |
|
specific route for a pipeline, or that the Commission review |
and approve a project route width that identifies the areas in |
which the pipeline would be located, with such width ranging |
from the minimum width required for a pipeline right-of-way up |
to 500 feet in width. The purpose for allowing the option of |
review and approval of a project route width is to provide |
increased flexibility during the construction process to |
accommodate specific landowner requests, avoid environmentally |
sensitive areas, or address special environmental permitting |
requirements. |
(d) A common carrier by pipeline may request any other |
approvals as may be needed from the Commission for completion |
of the pipeline under Article VIII or any other Article or |
Section of this Act at the same time, and as part of the same |
application, as its request for a certificate of good standing |
under this Section. The Commission's rules shall ensure that |
notice of such a consolidated application is provided within 30 |
days after filing to the landowners along a proposed project |
route, or to the potentially affected landowners within a |
proposed project route width, using the notification |
procedures set forth in the Commission's rules. If a |
consolidated application is submitted, then the requests shall |
be heard on a consolidated basis and a decision on all issues |
shall be entered within the time frames stated in subsection |
(e) of this Section. In such a consolidated proceeding, the |
Commission may consider evidence relating to the same factors |
|
identified in items (1) through (9) of subsection (b) of this |
Section in granting authority under Section 8-503 of this Act. |
If the Commission grants approval of a project route width as |
opposed to a specific project route, then the common carrier by |
pipeline must, as it finalizes the actual pipeline alignment |
within the project route width, file its final list of affected |
landowners with the Commission at least 14 days in advance of |
beginning construction on any tract within the project route |
width and also provide the Commission with at least 14 days |
notice before filing a complaint for eminent domain in the |
circuit court with regard to any tract within the project route |
width. |
(e) The Commission shall make its determination on any |
application filed pursuant to this Section and issue its final |
order within one year after the date that the application is |
filed unless an extension is granted as provided in this |
subsection (e). The Commission may extend the one-year time |
period for issuing a final order on an application filed |
pursuant to this Section up to an additional 6 months if it |
finds, following the filing of initial testimony by the parties |
to the proceeding, that due to the number of affected |
landowners and other parties in the proceeding and the |
complexity of the contested issues before it, additional time |
is needed to ensure a complete review of the evidence. If an |
extension is granted, then the schedule for the proceeding |
shall not be further extended beyond this 6-month period, and |
|
the Commission shall issue its final order within the 6-month |
extension period. The Commission shall also have the power to |
establish an expedited schedule for making its determination on |
an application filed pursuant to this Section in less than one |
year if it finds that the public interest requires the setting |
of such an expedited schedule. |
(f) Within 6 months after the Commission's entry of an |
order approving either a specific
route or a project route |
width under this Section, the common carrier by pipeline that
|
receives such order may file supplemental applications for |
minor route deviations outside
the approved project route |
width, allowing for additions or changes to the approved
route |
to address environmental concerns encountered during |
construction or to
accommodate landowner requests. Notice of a |
supplemental application shall be
provided to any State agency |
that appeared in the original proceeding or immediately
|
affected landowner at the time such supplemental application is |
filed. The route
deviations shall be approved by the Commission |
within 45 days, unless a written
objection is filed to the |
supplemental application within 20 days after the date such
|
supplemental application is filed. Hearings on any such |
supplemental application shall
be limited to the |
reasonableness of the specific variance proposed, and the |
issues of
public need or public convenience or necessity for |
the project or fitness of the applicant
shall not be reopened |
in the supplemental proceeding. |
|
(g) The rules of the Commission may include additional |
options for expediting the issuance of permits and certificates |
under this Section. Such rules may provide that, in the event |
that an applicant elects to use an option provided for in such |
rules; (1) the applicant must request the use of the expedited |
process at the time of filing its application for a license or |
permit with the Commission; (2) the Commission may engage |
experts and procure additional administrative resources that |
are reasonably necessary for implementing the expedited |
process; and (3) the applicant must bear any additional costs |
incurred by the Commission as a result of the applicant's use |
of such expedited process. |
(h) (c) Duties and obligations of common carriers by
|
pipeline. Each common carrier by pipeline shall provide
|
adequate service to the public at reasonable rates and
without |
discrimination.
|
(Source: P.A. 94-793, eff. 5-19-06.)
|
Section 99. Effective date. This Act takes effect July 1, |
2011.
|