ACTION
|
START
DATE
|
END
DATE
|
PLAN OF OPERATION
REFERENCE
SECTION
|
|
|
|
|
Prepare and submit the Start-Up
|
|
|
|
Services proposal to the Agency.
|
|
|
|
|
|
|
|
Construct the treatment facilities.
|
|
|
|
|
|
|
|
Submit the draft O&M Manual to the Agency.
|
|
|
|
|
|
|
|
Submit the final PO to the Agency.
|
|
|
|
|
|
|
|
Publish the new sewer use ordinance to accommodate
industrial discharges.
|
|
|
|
|
|
|
|
Publish the industrial pretreatment ordinance.
|
|
|
|
|
|
|
|
Employ Chief Operator (Superintendent).
|
|
|
|
|
|
|
|
Review user charge and industrial cost recovery systems.
|
|
|
|
|
|
|
|
Employ Senior Operator.
|
|
|
|
|
|
|
|
Employ Chief Chemist.
|
|
|
|
|
|
|
|
Review budget considerations for initial operation.
|
|
|
|
|
|
|
|
Begin influent sampling program.
|
|
|
|
|
|
|
|
Begin development of a detailed emergency procedures plan.
|
|
|
|
|
|
|
|
Begin development of detailed guidance on the employee
safety training program.
|
|
|
|
ACTION
|
START
DATE
|
END
DATE
|
PLAN OF OPERATION
REFERENCE
SECTION
|
|
|
|
|
Identify all of the unusual waste discharges.
|
|
|
|
|
|
|
|
Finalize the system and procedures for notification of
unusual industrial waste discharges.
|
|
|
|
|
|
|
|
Identify actions and assignments to be accomplished by
other city department. Coordinate the action plan.
|
|
|
|
|
|
|
|
Identify and begin acquiring equipment and materials to
implement the emergency operation plan.
|
|
|
|
|
|
|
|
Finalize cooperative assistance agreements with other
agencies.
|
|
|
|
|
|
|
|
Assemble manufacturers' manuals and other equipment
literature.
|
|
|
|
|
|
|
|
Begin development of the action plan for process control
and "fine tuning."
|
|
|
|
|
|
|
|
Employ shift operators.
|
|
|
|
|
|
|
|
Employ maintenance crew.
|
|
|
|
|
|
|
|
Conduct training on equipment maintenance.
|
|
|
|
|
|
|
|
Begin acquiring inventory of tools and spare parts.
|
|
|
|
|
|
|
|
Begin acquiring lubricants for new equipment.
|
|
|
|
|
|
|
|
Review and update the operating budget and revenue
program.
|
|
|
|
|
|
|
|
Begin acquiring laboratory supply inventory including test
reagents.
|
|
|
|
|
|
|
|
Being employee training in emergency procedures.
|
|
|
|
|
|
|
|
ACTION
|
START
DATE
|
END
DATE
|
PLAN OF OPERATION
REFERENCE
SECTION
|
|
|
|
|
Finalize O&M Manual.
|
|
|
|
|
|
|
|
Start review of laboratory analytical and reporting
requirements with operators and laboratory staff.
|
|
|
|
|
|
|
|
Conduct training in heavy metals sample collection and
analysis with laboratory staff.
|
|
|
|
|
|
|
|
Start safety training program.
|
|
|
|
|
|
|
|
Review and approval of final O&M Manual by Chief
Operator.
|
|
|
|
|
|
|
|
Acquire a stock of laboratory records, calculation sheets,
and reporting sheets.
|
|
|
|
|
|
|
|
Start review of process control and detailed start-up
procedures with facility staff.
|
|
|
|
|
|
|
|
Begin training of facility staff on maintenance management
system usage.
|
|
|
|
|
|
|
|
Submit final O&M Manual to the Agency.
|
|
|
|
|
|
|
|
Begin pre-start-up maintenance schedule.
|
|
|
|
|
|
|
|
Conduct "wet" and "dry" testing of all
equipment.
|
|
|
|
|
|
|
|
Move into new laboratory.
|
|
|
|
|
|
|
|
Inventory new equipment and supplies furnished by the
contractor.
|
|
|
|
|
|
|
|
Test new laboratory apparatus.
|
|
|
|
|
|
|
|
File treatment facility design, construction and
operations records, manufacturers' manuals, and as-built drawings.
|
|
|
|
|
|
|
|
Conduct operational start-up of facility.
|
|
|
|
|
|
|
|
ACTION
|
START
DATE
|
END
DATE
|
PLAN OF OPERATION
REFERENCE
SECTION
|
|
|
|
|
Start periodic safety reviews with facility staff.
|
|
|
|
|
|
|
|
Conduct the first annual plant safety review and modify
the safety program, if necessary.
|
|
|
|
|
|
|
|
Initiate annual emergency procedures update and employee
training program.
|
|
|
|
|
|
|
|
Complete first annual facility operation and maintenance
report.
|
|
|
|
|
|
|
|
Update the O&M Manual based on first year of operating
experience.
|
|
|
|