(55 ILCS 5/5-1043) (from Ch. 34, par. 5-1043)
Sec. 5-1043.
Water and sanitary facilities.
Whenever a county resolution or ordinance requires the
installation of water mains, sanitary sewers, drains, or other facilities
for sewers and drains, the construction of any roadways or the installation
of any traffic signals or other traffic related improvements as a condition
precedent to the approval of a preliminary or final subdivision or plat
described in Section 5-1042, or a preliminary or final planned
unit development plan and where, in the opinion of the county board such
facilities, roadways or improvements may be used for the benefit of
property not in the subdivision or planned unit development, and the water
mains, sanitary sewers, drains or other such facilities, or such roadways
or improvements are to be dedicated to the public, the county board may, by
contract with the subdivider, agree to reimburse and may reimburse
the subdivider for a portion of the cost of such facilities, roadways and
improvements. The county board may also, by contract with the subdivider,
agree to share the cost of installing required facilities. The county board
may in either case recover the cost of those facilities
from fees charged to owners of property not within the
subdivision, or planned unit development when and as collected
from such owners. Such contract shall describe the property outside the
subdivision or planned unit development which may reasonably be
expected to benefit from the facilities, roadways or improvements
which are required to be constructed under the contract and shall specify
the amount or proportion of the cost of such facilities, roadways or
improvements which is to be incurred
primarily for the benefit of that property. Such contract shall provide
that the county shall collect such fees charged to owners of property not
within the subdivision or planned unit development at any time prior to
the connection to and use of the said facilities, roadways or improvements
by the respective properties of each owner. Such contract may provide
for the payment to the subdivider of a reasonable amount of interest on the
amount expended by the subdivider in completing such facilities, roadways
and improvements, with said interest to be calculated from and after the
date of completion of such facilities, roadways and improvements.
(Source: P.A. 86-962; 86-1463.)
|