(50 ILCS 525/5)
Sec. 5. Change orders; bidding. If a change order for any public works
contract (i) is entered into by
a unit of local government or school district, (ii) is not procured in
accordance with the Illinois Procurement Code and the State Finance Act, and
(iii) authorizes or necessitates any increase in the contract price that is 50%
or more of the
original contract price or that authorizes or necessitates any increase in the price of a subcontract under the contract that is 50% or more of the original subcontract price, then the portion of the contract that is covered by the
change order must be resubmitted
for bidding in the same manner for which the original contract was bid. Bidding
for the portion of the contract covered by the change order is subject to
any requirements to employ females and minorities on the public works project
that existed at the bidding for the original contract, together with any later
requirements imposed by law.
(Source: P.A. 93-656, eff. 6-1-04; 94-460, eff. 8-4-05.) |