(30 ILCS 537/45) (Section scheduled to be repealed on January 1, 2026)
Sec. 45. Award. The State construction agency may award the contract to
the highest
overall ranked entity. Notice of award shall be made in writing. Unsuccessful
entities shall also be notified in writing. The State construction agency may
not request a
best and final offer after the receipt of proposals. The State construction
agency may
negotiate with the selected design-build entity after award but prior to
contract
execution for the purpose of securing better terms than originally proposed,
provided that the salient features of the request for proposal are not
diminished.