TITLE 83: PUBLIC UTILITIES
CHAPTER I: ILLINOIS COMMERCE COMMISSION SUBCHAPTER c: ELECTRIC UTILITIES PART 466 ELECTRIC INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES FACILITIES SECTION 466.APPENDIX C LEVELS 2 TO 4 APPLICATION Section 466.APPENDIX C Levels 2 to 4 Application
Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kW to 10 MVA or less)
Interconnection Customer Contact Information
Equipment Contractor
Electrical Contractor (if different from Equipment Contractor)
Electric Service Information for Customer Facility Where Generator Will Be Interconnected
Intent of Generation
Offset Load (Unit will operate in parallel, but will not export power to EDC)
Net Meter (Unit will operate in parallel and will export power pursuant to Illinois Net Metering or other filed tariffs)
Wholesale Market Transaction (Unit will operate in parallel and participate in PJM or MISO markets pursuant to a PJM Wholesale Market Participation Agreement or MISO equivalent)
Back-up Generation (Units that temporarily operate in parallel with the electric distribution system for more than 100 milliseconds)
Note: Backup units that do not operate in parallel for more than 100 milliseconds do not need an interconnection agreement.
Generator & Prime Mover Information
Requested Procedure Under Which to Evaluate Interconnection Request1
Please indicate below which review procedure applies to the interconnection request. The review procedure used is subject to confirmation by the EDC.
Level 2 – Lab-certified interconnection equipment with an aggregate electric nameplate capacity not exceeding the specifications in Section 466.90(b)(2). Lab-certified is defined in Section 466.20. (Application fee is $100 plus $1.00 per kVA.)
Level 3 – Distributed energy resource facility does not export power. Nameplate capacity rating is less than or equal to 50 kW if connecting to area network or less than or equal to 10 MW if connecting to a radial distribution feeder. (Application fee amount is $500 plus $2.00 per kVA.)
Level 4 – Nameplate capacity rating is less than or equal to 10 MVA and the distributed energy resource facility does not qualify for a Level 1, Level 2 or Level 3 review, or the distributed energy resource facility has been reviewed but not approved under a Level 1, Level 2 or Level 3 review. (Application fee amount is $1,000 plus $2.00 per kVA, to be applied toward any subsequent studies related to this application.)
1 Note: Descriptions for interconnection review categories do not list all criteria that must be satisfied. For a complete list of criteria, please refer to 83 Ill. Adm. Code 466, Electric Interconnection of Distributed Energy Resource Facilities.
Distributed Energy Resource Facility Information
Commissioning Date: _________________________________
List interconnection components/systems to be used in the DER facility that are lab-certified.
Please provide copies of manufacturer brochures or technical specifications.
Energy Production Equipment/Inverter Information:
For Synchronous Machines:
Note: Contact EDC to determine if all the information requested in this section is required for the proposed DER facility.
For Induction Machines:
Note: Contact EDC to determine if all the information requested in this section is required for the proposed DER facility.
Limited Export and Non-Export Controls Information
Additional Information For Inverter-Based Facilities
Inverter Information:
DC Source / Prime Mover:
Other Facility Information:
One Line Diagram attached: Yes
Plot Plan attached: Yes
Battery Storage Facility Information (If Applicable)
Battery Storage Inverter Information
Battery Operational Information
Backup – allows for partial or whole home transition to off-grid during a grid outage. ☐ Yes ☐ No
Solar Self-Powered – the battery will charge from the renewable energy source during normal operation and discharge to serve loads behind your meter. ☐ Yes ☐ No
Solar Non-Export – limits the export of energy to the grid to zero for both the battery and inverter, even if the battery system is fully charged and there is excess renewable source energy. ☐ Yes ☐ No
Time-Based Control (sometimes called time-of-use or TOU mode) – the battery charges during off-peak hours and discharges to serve onsite loads during on-peak hours. ☐ Yes ☐ No
Customer Signature
I hereby certify that all of the information provided in this Interconnection Request Application Form is true.
An application fee is required before the application can be processed. Please verify that the appropriate fee is included with the application:
Amount: _____________________
EDC Acknowledgement
Receipt of the application fee is acknowledged and this interconnection request is complete.
(Source: Amended at 46 Ill. Reg. 9666, effective May 26, 2022) |