TITLE 83: PUBLIC UTILITIES
CHAPTER I: ILLINOIS COMMERCE COMMISSION
SUBCHAPTER c: ELECTRIC UTILITIES
PART 466 ELECTRIC INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES FACILITIES
SECTION 466.APPENDIX A LEVEL 1 APPLICATION AND CONTRACT



Section 466.APPENDIX A   Level 1 Application and Contract

 

Illinois Standard Distributed Energy Resources Interconnection

Level 1

Interconnection Request Application Form and

Conditional Agreement to Interconnect

(Lab-Certified Inverter-Based Distributed Energy Resources Facilities 25 kW and Smaller)

 

An application fee of $50.00 must be submitted with the application.

 

Interconnection Applicant Contact Information

 

Name:

 

Mailing Address:

 

City:

 

State:

 

Zip Code:

 

Telephone (Daytime):

 

(Evening):

 

Facsimile Number:

 

E-Mail Address:

 

 

 

Alternate Contact Information (if different from Applicant)

 

Name:

 

Mailing Address:

 

City:

 

State:

 

Zip Code:

 

Telephone (Daytime):

 

(Evening):

 

Facsimile Number:

 

E-Mail Address:

 

 

 

Equipment Contractor

 

Name:

 

Mailing Address:

 

City:

 

State:

 

Zip Code:

 

Telephone (Daytime):

 

(Evening):

 

Facsimile Number:

 

E-Mail Address:

 

 

 

Electrical Contractor (if Different from Equipment Contractor):

 

Name:

 

Mailing Address:

 

City:

 

State:

 

Zip Code:

 

Telephone (Daytime):

 

(Evening):

 

Facsimile Number:

 

E-Mail Address:

 

License number:

 

 

Active License?

Yes

No

 

 

 

Is the Interconnection Customer requesting Net Metering in accordance with 83 Ill. Adm. Code 465?

 

Yes  No

 

 

Distributed Energy Resources Facility ("Facility") Information

 

Facility Address:

 

City:

 

State:

 

Zip Code:

 

Electric Distribution Company (EDC) serving Facility site:

 

Electric Supplier (if different from EDC):

 

If existing EDC electric service exists at point of interconnection:

Account Number of site:

 

EDC billing meter ID

 

Inverter Manufacturer:

 

Model:

 

Is the inverter lab-certified as that term is defined in the Illinois Distributed Energy Resources Interconnection Standard? Yes  No

(If yes, attach manufacturer's technical specifications and label information from a nationally recognized testing laboratory.)

Generation Facility Nameplate Rating:

 

(kW)

 

(kVA)

 

(AC Volts)

Total Facility Nameplate Capacity:

 

(kW)

 

(kVA)

 

 

Prime Mover:

Photovoltaic

Reciprocating Engine

Fuel Cell

 

 

Turbine

Other

 

 

Energy Source:

Solar

Wind

Hydro

Diesel

 

Storage

Combination

 

 

 

Natural Gas

Fuel Oil

Other

 

Commissioning Date:

 

 

(If the Commissioning Date changes, the interconnection customer must inform the EDC as soon as it is aware of the changed date.)

 

 

Limited Export and Non-Export Controls Information

 

Manufacturer:

 

 

 

Model Number:

 

M

 

 

 

 

Limited Export or Non-Export?

  Limited Export

  Non-Export

 

 

 

Control Type:

 

Reverse Power Protection

 

Minimum Power Protection

 

Relative Distributed Energy Resource Rating

 

Configured Power Rating

 

Limited Export Power Control Systems

 

Limited Export using mutually agreed-upon means

 

 

Directional Power Protection

 

 

Export Capacity Value (in kW):

 

Control Power Setting:

 

Control Power Time Delay (if any):

 

 

 

Battery Storage Facility Information (If Applicable)

 

Do the batteries share an inverter with a renewable energy system?

Yes

No

Does the applicant intend to have the batteries charged by the distribution grid?

Yes

No

System Manufacturer:

 

Model:

 

Battery Type:

 

Battery Charge/Discharge Rating (kW AC):

 

Maximum Battery Charge/Discharge Rate (kW AC per second):

 

Battery Energy Capacity (kWh):

 

Power Factor Settings Range:

 

 

Battery Storage Inverter Information

 

Energy System

Manufacturer:

 

Model:

 

Type: Forced   Commutated

 

Line Commutated Rated Output

Watts:

 

Volts:

 

Efficiency:

____ %

Power Factor:

____ %

 

Inverter IEEE 1547 / UL 1741 Listed:

Yes

No

Number of Inverters:

 

Total Capacity:

kW

 

DC Source / Prime Mover:

 

- Rating:

 

kW Rating:

 

kVA Rated Voltage:

Volts

 

Open Circuit Voltage (If Applicable):

Volts

 

Rated Current:

Amps

 

 

Battery Operational Information

 

Backup – allows for partial or whole home transition to off-grid during a grid outage.  Yes No

 

Solar Self-Powered – the battery will charge from the renewable energy source during normal operation and discharge to serve loads behind your meter.           Yes  No

 

Solar Non-Export – limits the export of energy to the grid to zero for both the battery and inverter, even if the battery system is fully charged and there is excess renewable source energy. Yes  No

 

Time-Based Control (sometimes called time-of-use or TOU mode) – the battery charges during off-peak hours and discharges to serve onsite loads during on-peak hours.   Yes  No

 

Describe any other intended operation of the battery:

 

 

 

 

Insurance Disclosure

 

The attached terms and conditions contain provisions related to liability and indemnification, and should be carefully considered by the interconnection customer.  The interconnection customer shall carry general liability insurance coverage, such as, but not limited to, homeowner's insurance.  Whenever possible, the interconnection customer shall name the EDC as an additional insured on its homeowner's insurance policy, or similar policy covering general liability.

 

 

Customer Signature

 

I hereby certify that:  (1) I have read and understand the terms and conditions which are attached hereto by reference;  (2) I hereby agree to comply with the attached terms and conditions; and (3) to the best of my knowledge, all of the information provided in this application request form is complete and true.

 

Applicant Signature:

 

 

Title:

 

Date:

 

 

 

………………………………………………………………………………………………………

 

 

Conditional Agreement to Interconnect Distributed Energy Resources Facility

 

Receipt of the application fee is acknowledged and, by its signature below, the EDC has determined the interconnection request is complete. Interconnection of the distributed energy resources facility is conditionally approved contingent upon the attached terms and conditions of this Agreement, the return of the attached Certificate of Completion, duly executed verification of electrical inspection and successful witness test.

 

EDC Signature:

 

Date:

 

 

Name:

 

Title:

 

 


Terms and Conditions for Interconnection

 

1)         Construction of the Distributed Energy Resources Facility.  The interconnection customer may proceed to construct (including operational testing not to exceed 2 hours) the distributed energy resources (DER) facility, once the conditional Agreement to interconnect a DER facility has been signed by the EDC.

 

2)         Final Interconnection and Operation.  The interconnection customer may operate the DER facility and interconnect with the EDC's electric distribution system after all of the following have occurred:

 

a)         Electrical Inspection:  Upon completing construction, the interconnection customer shall cause the DER facility to be inspected by the local electrical inspection authority, who shall establish that the DER facility meets local code requirements.

 

b)         Certificate of Completion:  The interconnection customer shall provide the EDC with a copy of the Certificate of Completion with all relevant and necessary information fully completed by the interconnection customer, as well as an inspection form from the local electrical inspection authority demonstrating that the DER facility passed inspection.

 

c)         The EDC has completed its witness test as per the following:

 

i)          Within 10 business days of the commissioning date, the EDC must, upon reasonable notice and at a mutually convenient time, conduct a witness test of the DER facility to ensure that all equipment has been appropriately installed and that all electrical connections have been made in accordance with the applicable codes.

 

ii)         If the EDC does not perform the witness test within the 10 business days after the commissioning date or such other time as is mutually agreed to by the Parties, the witness test is deemed waived unless the EDC cannot do so for good cause.  In these cases, upon EDC request, the interconnection customer shall agree to another date for the test within 10 business days after the original scheduled date.

 

3)         IEEE 1547.  The DER facility shall be installed, operated and tested in accordance with the requirements of The Institute of Electrical and Electronics Engineers, Inc. (IEEE), 3 Park Avenue New York, NY 10016-5997, Standard 1547 (2003) "Standard for Interconnecting Distributed Resources with Electric Power Systems."

 

4)         Access.  The EDC shall have direct, unabated access to the disconnect switch and metering equipment of the DER facility at all times.  The EDC shall provide 5 business days' notice to the customer prior to using its right of access except in emergencies.

 

5)         Metering.  Any required metering shall be installed pursuant to Illinois Commerce Commission approved tariffs.

 

6)         Disconnection.  The EDC may disconnect the DER facility upon any of the following conditions, but must reconnect the DER facility once the condition is cured:

 

a)         For scheduled outages, provided that the DER facility is treated in the same manner as EDC's load customers;

 

b)         For unscheduled outages or emergency conditions;

 

c)         If the DER facility does not operate in the manner consistent with this Agreement;

 

d)         Improper installation or failure to pass the witness test;

 

e)         If the DER facility is creating a safety, reliability or a power quality problem; or

 

f)         The interconnection equipment used by the DER facility is de-listed by the Nationally Recognized Testing Laboratory that provided the listing at the time the interconnection was approved.

 

7)         Indemnification.  The interconnection customer shall indemnify and defend the EDC and the EDC's directors, officers, employees, and agents from all damages and expenses resulting from any third party claim arising out of or based upon the interconnection customer's (a) negligence or willful misconduct or (b) breach of this Agreement.  The EDC shall indemnify and defend the interconnection customer and the interconnection customer's directors, officers, employees, and agents from all damages and expenses resulting from a third party claim arising out of or based upon the EDC's (a) negligence or willful misconduct or (b) breach of this Agreement.

 

8)         Insurance.  The interconnection customer shall provide the EDC with proof that it has a current homeowner's insurance policy, or other general liability policy, and, when possible, the interconnection customer shall name the EDC as an additional insured on its homeowner's insurance policy, or similar policy covering general liability.

 

9)         Limitation of Liability.  Each Party's liability to the other Party for any loss, cost, claim, injury, liability, or expense, including reasonable attorney's fees, relating to or arising from any act or omission in its performance of this Agreement, shall be limited to the amount of direct damage actually incurred.  In no event shall either Party be liable to the other Party for any indirect, incidental, special, consequential, or punitive damages of any kind whatsoever.

 

10)       Termination.  This Agreement may be terminated under the following conditions:

 

a)         By interconnection customer − The interconnection customer may terminate this Agreement by providing written notice to the EDC.  If the interconnection customer ceases operation of the DER facility, the interconnection customer must notify the EDC

 

b)         By the EDC − The EDC may terminate this Agreement if the interconnection customer fails to remedy a violation of terms of this Agreement within 30 calendar days after notice, or such other date as may be mutually agreed to prior to the expiration of the 30 calendar day remedy period.  The termination date may be no less than 30 calendar days after the interconnection customer receives notice of its violation from the EDC.

 

11)       Modification of Distributed Energy Resources Facility.  The interconnection customer must receive written authorization from the EDC before making any changes to the DER facility that could affect the EDC's distribution system.  If the interconnection customer makes such modifications without the EDC's prior written authorization, the EDC shall have the right to disconnect the DER facility.

 

12)       Permanent Disconnection.  In the event the Agreement is terminated, the EDC shall have the right to disconnect its facilities or direct the interconnection customer to disconnect its DER facility.

 

13)       Disputes.  Each Party agrees to attempt to resolve all disputes regarding the provisions of this Agreement that cannot be resolved between the two Parties pursuant to the dispute resolution provisions found in 83 Ill. Adm. Code 466.130.

 

14)       Governing Law, Regulatory Authority, and Rules.  The validity, interpretation and enforcement of this Agreement and each of its provisions shall be governed by the laws of the State of Illinois.  Nothing in this Agreement is intended to affect any other agreement between the EDC and the interconnection customer. 

 

15)       Survival Rights.  This Agreement shall remain in effect after termination to the extent necessary to allow or require either Party to fulfill rights or obligations that arose under the Agreement.

 

16)       Assignment/Transfer of Ownership of the Distributed Energy Resources Facility.  This Agreement shall terminate upon the transfer of ownership of the DER facility to a new owner unless the transferring owner assigns the Agreement to the new owner, the new owner agrees in writing to the terms of this Agreement, and the transferring owner so notifies the EDC in writing prior to the transfer of ownership. 

 

17)       Definitions.  Any term used herein and not defined shall have the same meaning as the defined terms used in 83 Ill. Adm. Code 466 (the Illinois Distributed Energy Resources Interconnection Standard).

 

18)       Notice.  The Parties may mutually agree to provide notices, demands, comments, or requests by electronic means such as e-mail.  Absent agreement to electronic communication, or unless otherwise provided in this Agreement, any written notice, demand, or request required or authorized in connection with this Agreement shall be deemed properly given if delivered in person, delivered by recognized national courier service, or sent by first class mail, postage prepaid, to the person specified below:

 

If to Interconnection Customer:

 

Use the contact information provided in the interconnection customer's application.  The interconnection customer is responsible for notifying the EDC of any change in the contact party information, including change of ownership.

 

If to EDC:

 

Use the contact information provided below.  The EDC is responsible for notifying the interconnection customer of any change in the contact party information.

 

 

Name:

 

Mailing Address:

 

City:

 

State:

 

Zip Code:

 

Telephone (Daytime):

 

(Evening):

 

Facsimile Number:

 

E-Mail Address:

 

 

(Source:  Amended at 46 Ill. Reg. 9666, effective May 26, 2022)