TITLE 83: PUBLIC UTILITIES
CHAPTER I: ILLINOIS COMMERCE COMMISSION SUBCHAPTER c: ELECTRIC UTILITIES PART 466 ELECTRIC INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES FACILITIES SECTION 466.30 WAIVER
Section 466.30 Waiver
a) The Commission may, on application or petition of an EDC, DER applicant or customer, or on its own motion, grant a temporary or permanent waiver from this Part, or any Section or subsection of this Part, in individual cases in which the Commission finds that:
1) the provision from which the waiver is granted is not statutorily mandated;
2) there is good cause for the waiver, and it is in the public interest; and
3) the rule from which the waiver is granted would, as applied to the particular case, be unreasonable or unnecessarily burdensome.
b) The burden of proof in establishing a right to waiver shall be on the party seeking the waiver.
(Source: Former Section 466.35 renumbered to 466.30 and amended at 46 Ill. Reg. 9666, effective May 26, 2022) |