TITLE 44: GOVERNMENT CONTRACTS, GRANTMAKING,
PROCUREMENT AND PROPERTY MANAGEMENT
SUBTITLE B: SUPPLEMENTAL PROCUREMENT CHAPTER XII: CAPITAL DEVELOPMENT BOARD PART 990 PREQUALIFICATION OF CONSTRUCTION MANAGERS SECTION 990.430 DEBARMENT
Section 990.430 Debarment
CDB may debar a CM to exclude it from submitting on CDB projects. CDB will consider debarment in cases so serious and egregious in nature that a permanent loss of submittal privileges may be warranted. In addition to the causes listed in Section 990.310, causes for debarment may include, but not be limited to, multiple or repetitive criminal convictions or multiple non-responsibility determinations. Following a period of debarment, when a CM submits a prequalification application to CDB, the application shall be deemed to be a first-time application rather than an application for renewal. A firm that has been debarred as a contractor or A/E (architectural/engineering) firm will automatically be debarred as a CM firm, and vice versa. |