TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE G: WASTE DISPOSAL
CHAPTER I: POLLUTION CONTROL BOARD
SUBCHAPTER i: SOLID WASTE AND SPECIAL WASTE HAULING
PART 820 STANDARDS FOR GENERAL CONSTRUCTION OR DEMOLITION DEBRIS RECOVERY FACILITIES
SECTION 820.205 AGENCY INITIATED MODIFICATION


 

Section 820.205  Agency Initiated Modification

 

a)         The Agency may modify a permit under the following circumstances:

 

1)         Discovery of a typographical, administrative, or calculation error;

 

2)         Discovery that a determination or condition was based upon false or misleading information;

 

3)         An order of the Board issued in an action brought under Title VII, IX, or X of the Act; or

 

4)         Promulgation of new statutes or regulations affecting the permit.

 

b)         A modification initiated by the Agency becomes effective 45 days after the owner or operator receives notice of the modification unless the modification is stayed during an appeal to the Board.  The owner or operator may file a petition for Board hearing under this Part.  All other time periods and procedures in this Part apply during the Agency's reconsideration and during any appeal to the Board.